CN1640805A - Pretightening method of hoist steel strand for continuous hoist jack - Google Patents

Pretightening method of hoist steel strand for continuous hoist jack Download PDF

Info

Publication number
CN1640805A
CN1640805A CN 200410002193 CN200410002193A CN1640805A CN 1640805 A CN1640805 A CN 1640805A CN 200410002193 CN200410002193 CN 200410002193 CN 200410002193 A CN200410002193 A CN 200410002193A CN 1640805 A CN1640805 A CN 1640805A
Authority
CN
China
Prior art keywords
jack
steel strand
anchor slab
continuous lifting
intermediate plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200410002193
Other languages
Chinese (zh)
Other versions
CN100424003C (en
Inventor
阙潇瑜
刘显晖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HAIWEIMU BUILDING MACHINERY CO Ltd LIUZHOU
Original Assignee
HAIWEIMU BUILDING MACHINERY CO Ltd LIUZHOU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HAIWEIMU BUILDING MACHINERY CO Ltd LIUZHOU filed Critical HAIWEIMU BUILDING MACHINERY CO Ltd LIUZHOU
Priority to CNB2004100021930A priority Critical patent/CN100424003C/en
Publication of CN1640805A publication Critical patent/CN1640805A/en
Application granted granted Critical
Publication of CN100424003C publication Critical patent/CN100424003C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to building construction technology. After completing the primary steps, the press plate on the front end of continuously lifting jack and the clamping sheet on the tie plate are loosened, one secondary clamping sheet is mounted on the tie plate to tighten the twisted steel cables one by one for pre-fastening successively, and loosened press plate and clamping sheet are repositioned to fix the twisted steel cables. Compared with available method, the present invention has high efficiency, and is simpler and safer.

Description

Pre-clamping method to the lifting steel strand in the continuous lifting jack
Technical field
The present invention relates to technical field of building construction, especially a kind of being used for before lifting member carried out pretension to the lifting steel strand in the continuous lifting jack.
Background technology
In the hydraulic pressure lift hoisting engineering, it is to realize by pumping plant and the teamwork of continuous lifting jack that a kind of lifting technology is arranged.In order to lift safely, it is stressed evenly to guarantee to promote continuously each root steel strand that each suspension centre of jack and lifting member is connected.So lifting is gone to toward carrying out pretension to each root steel strand, makes it bear the power of a given data.And existing continuous lifting jack it mainly connect to form by front end jack and rear end jack, one cover anchor slab, intermediate plate all respectively arranged for front end jack and rear end jack and by screw and anchor slab bonded assembly pressing plate, they just are fixed on pressing plate and intermediate plate on the anchor slab of front end jack and rear end jack when dispatching from the factory.When continuous lifting jack loads onto that lifting platform is in place, its oil pipe be connected with its pumping plant finish, promote continuously jack and put on steel strand and many steel strand and lifting member anchoring after, just can begin promoting the pretension operation of steel strand.
Adopt pretension method of operating to be now to promoting steel strand:
1, will promote jack and pumping plant thereof and punching jack and pumping plant thereof continuously and install in that lifting platform is in place, and put on many steel strand being used to promote and be connected anchoring one by one with member to be hoisted with promoting jack continuously;
2, the punching jack is inserted in from the termination of first steel strand to the pressing plate of the front end jack of continuous lifting jack in the upper end that promotes continuously jack, these root steel strand of clamping also are stretched to setting value, grip by the front end jack anchor slab of continuous lifting jack and the intermediate plate on the anchor slab of top, back then, discharge again the punching jack tension force, unclamp clamping, the punching jack is withdrawed from fully from the termination of first steel strand, finish pretension these root steel strand;
3, by the way in above-mentioned the 2nd step remaining each the root steel strand on the continuous lifting jack are carried out pretension one by one.
The shortcoming of above-mentioned this pre-clamping method is: use equipment is various, necessary additive incrementation punching jack and supporting equipment such as pumping plant thereof, the operating sequence complexity, steel strand of every pretension all will penetrate the punching jack with steel strand in the upper end that promotes jack continuously from the termination, and behind these steel strand of stretch-draw pretension, again these steel strand are withdrawed from the punching jack fully, this work fitness for purpose operating personal is many, especially continuously promoting jack often is installed on tens of rice even the up to a hundred meters High Altitude Platforms, to set up operation on the interim and narrow platform on the top that promotes jack continuously, operating difficulties, and very dangerous.
Summary of the invention
The invention provides a kind of pre-clamping method to lifting steel strand in the continuous lifting jack, it mainly is that the existing pre-clamping method efficient of solution is low, production tooling too much and operation inconvenience and the big problem of operational danger.
For addressing the above problem, this to the pre-clamping method that promotes steel strand in the continuous lifting jack is: it includes and will promote jack and pumping plant thereof in place installing on lifting platform continuously, to promote jack continuously and put on many lifting steel strand and be connected these prior steps of anchoring one by one with member to be hoisted, after this:
A, unclamp pressing plate on the front end jack in the continuous lifting jack and the intermediate plate on the anchor slab;
B, be contained on the anchor slab of the front end jack in the continuous lifting jack with a sub-folder sheet, first steel strand of wanting pretension of clamping, be stretched to setting value with these these root steel strand of front end jack pair that promote in the jack continuously, grip this root steel strand by the intermediate plate in the anchor slab of the rear end jack in this continuous lifting jack then, discharge the tension force of described front end jack, pull down the intermediate plate on this front end jack anchor slab, finish pretension these root steel strand;
C, remaining each the root steel strand on the continuous lifting jack are carried out pretension one by one by the way in above-mentioned B step;
D, the pressing plate that above-mentioned A was unclamped in the step and the intermediate plate on the anchor slab put in back in the anchor slab on the front end jack in the continuous lifting jack each root steel strand anchoring.
Owing to adopted such scheme the present invention compared with prior art to have following beneficial effect:
1, construction safety, efficient height.Because not needing to promote steel strand with heavier punching jack pair as existing installation method installs and pulls down from the termination one by one, therefore, not only High Altitude Platform need not many people operation, simple to operate easily and safety, and the comparable existing method of work efficiency improves 400%.
2, equipment is simple.Punching jack and supporting pumping plant thereof have been omitted.
Description of drawings
Fig. 1 is an application example scheme drawing of the present invention.
The specific embodiment
The invention will be further described below in conjunction with Fig. 1 example:
Step to the pre-clamping method of the lifting steel strand in the continuous lifting jack is as follows:
Prior step: will promote jack and pumping plant 9 thereof in place installing on lifting platform 10 continuously, many lifting steel strand that promote continuously on the jack will be connected anchoring with member 11 to be hoisted one by one by ground tackle 12, After this:
A, pull down bolt 3, unclamp pressing plate 4 on the front end jack in the continuous lifting jack and the intermediate plate 2 on the anchor slab 1;
B, be contained in a sub-folder sheet 2 on the anchor slab 1 on the plunger 6 of the front end jack in the continuous lifting jack, the steel strand 5 of pretension are wanted in first of clamping, by pumping plant 9 to the front end jack cylinder body lower end of continuous lifting jack injection pressure oil, allow front end jack plunger 6 rise steel strand 5 are carried out stretch-draw, reflect the front end jack oiling pressurization that stops after the pressure of compressed oil reaches setting value to continuous lifting jack until pumping plant 9, with the intermediate plate 7 of rear end jack in the continuous lifting jack steel strand 5 are clamped on the anchor slab on 8, discharge the front end jack that promotes jack continuously by pumping plant 9 then, plunger 6 is descended, discharge the tension force of 2 pairs of steel strand 5 of intermediate plate, pull down the intermediate plate 2 on this front end jack anchor slab 1, finish pretension steel strand 5;
C, remaining each the root steel strand on the continuous lifting jack are carried out pretension one by one by the way in above-mentioned B step;
D, the pressing plate 4 that above-mentioned A was unclamped in the step and each sub-folder sheet 2 put in back in the anchor slab 1 on the front end jack in the continuous lifting jack, with each root steel strand anchoring.

Claims (1)

1, a kind of to promoting the pre-clamping method of steel strand in the continuous lifting jack, it includes and will promote jack and pumping plant thereof in place installing on lifting platform continuously, to promote jack continuously and put on many lifting steel strand and be connected these prior steps of anchoring one by one, it is characterized in that after finishing described prior step with member to be hoisted:
A, unclamp pressing plate on the front end jack in the continuous lifting jack and the intermediate plate on the anchor slab;
B, be contained on the anchor slab of the front end jack in the continuous lifting jack with a sub-folder sheet, first steel strand of wanting pretension of clamping, be stretched to setting value with these these root steel strand of front end jack pair that promote in the jack continuously, grip this root steel strand by the intermediate plate in the anchor slab of the rear end jack in this continuous lifting jack then, discharge the tension force of described front end jack, pull down the intermediate plate on this front end jack anchor slab, finish pretension these root steel strand;
C, remaining each the root steel strand on the continuous lifting jack are carried out pretension one by one by the way in above-mentioned B step;
D, the pressing plate that above-mentioned A was unclamped in the step and the intermediate plate on the anchor slab put in back in the anchor slab on the front end jack in the continuous lifting jack each root steel strand anchoring.
CNB2004100021930A 2004-01-13 2004-01-13 Pretightening method of hoist steel strand for continuous hoist jack Expired - Fee Related CN100424003C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2004100021930A CN100424003C (en) 2004-01-13 2004-01-13 Pretightening method of hoist steel strand for continuous hoist jack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2004100021930A CN100424003C (en) 2004-01-13 2004-01-13 Pretightening method of hoist steel strand for continuous hoist jack

Publications (2)

Publication Number Publication Date
CN1640805A true CN1640805A (en) 2005-07-20
CN100424003C CN100424003C (en) 2008-10-08

Family

ID=34867314

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004100021930A Expired - Fee Related CN100424003C (en) 2004-01-13 2004-01-13 Pretightening method of hoist steel strand for continuous hoist jack

Country Status (1)

Country Link
CN (1) CN100424003C (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103332637A (en) * 2013-03-06 2013-10-02 中国电力科学研究院 Steel strand pretightening device
CN104058349A (en) * 2013-03-22 2014-09-24 中化二建集团有限公司 Steel strand lifting and clamping device and lifting method
CN104973545A (en) * 2015-07-15 2015-10-14 中铁二十五局第四集团工程有限公司 Tensioning equipment structure
CN105152069A (en) * 2015-09-25 2015-12-16 柳州欧维姆机械股份有限公司 Lifting jack with lifting pre-tightening device and method for lifting jack for pre-tightening lifting steel strands
CN105366598A (en) * 2015-09-28 2016-03-02 中国一冶集团有限公司 Hydraulic lifting method for gas holder top
WO2018072589A1 (en) * 2016-10-18 2018-04-26 柳州黔桥工程材料有限公司 Automated and synchronized control system for bundled steel strand anchoring
CN108002282A (en) * 2017-12-29 2018-05-08 上海市机械施工集团有限公司 A kind of steel construction integral lifting apparatus and its application method
WO2019166025A1 (en) * 2018-02-28 2019-09-06 中国矿业大学 Mechanical constant-resistance single prop continuous prop lifting pre-tightening device and method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2172761Y (en) * 1993-07-23 1994-07-27 郝晋升 Asynchronous traction device
CN2203966Y (en) * 1993-12-04 1995-07-26 郝晋升 Single cylinder multi-head jack
CN2183987Y (en) * 1993-12-04 1994-11-30 郝晋升 Asynchronous lifter with single cylinder and muti-rod
CN2224833Y (en) * 1994-12-30 1996-04-17 郝晋升 Straining jack
JP2937310B2 (en) * 1995-02-14 1999-08-23 紀二 替場 Anchor steel wire tension jack
CN2399366Y (en) * 1999-12-31 2000-10-04 开封科英预应力锚具厂 Four-action tension jack

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103332637A (en) * 2013-03-06 2013-10-02 中国电力科学研究院 Steel strand pretightening device
CN103332637B (en) * 2013-03-06 2015-07-08 中国电力科学研究院 Steel strand pretightening device
CN104058349A (en) * 2013-03-22 2014-09-24 中化二建集团有限公司 Steel strand lifting and clamping device and lifting method
CN104058349B (en) * 2013-03-22 2016-02-17 中化二建集团有限公司 A kind of steel strand hoisting clamping device and method for improving
CN104973545A (en) * 2015-07-15 2015-10-14 中铁二十五局第四集团工程有限公司 Tensioning equipment structure
CN105152069A (en) * 2015-09-25 2015-12-16 柳州欧维姆机械股份有限公司 Lifting jack with lifting pre-tightening device and method for lifting jack for pre-tightening lifting steel strands
CN105366598A (en) * 2015-09-28 2016-03-02 中国一冶集团有限公司 Hydraulic lifting method for gas holder top
WO2018072589A1 (en) * 2016-10-18 2018-04-26 柳州黔桥工程材料有限公司 Automated and synchronized control system for bundled steel strand anchoring
CN108002282A (en) * 2017-12-29 2018-05-08 上海市机械施工集团有限公司 A kind of steel construction integral lifting apparatus and its application method
WO2019166025A1 (en) * 2018-02-28 2019-09-06 中国矿业大学 Mechanical constant-resistance single prop continuous prop lifting pre-tightening device and method
US10844717B2 (en) 2018-02-28 2020-11-24 China University Of Mining And Technology Mechanical constant-resistance single prop continuous prop lifting pre-tightening device and method

Also Published As

Publication number Publication date
CN100424003C (en) 2008-10-08

Similar Documents

Publication Publication Date Title
CN1640805A (en) Pretightening method of hoist steel strand for continuous hoist jack
CN2866450Y (en) Feed-through hydraulic lifter
CN102198914A (en) Working platform for installing wind generating set
CN114180456A (en) Hoisting posture adjusting method for giant laterally inclined truss structure
CN201269792Y (en) Pulling force and static settlement hydraulic test device for raiser of tractor
CN107651594B (en) Support load testing device for winch and testing method thereof
CN216413741U (en) Overhead ground wire lifter
CN202046833U (en) Lifting jack
CN1686757A (en) Method of salvaging applying ship loading and unloading and its device
CN211444835U (en) Tower body tile holding mounting and dismounting device of tower crane
CN2695428Y (en) Front clamp type low expansion lifting jack
CN221027144U (en) Tool for quickly releasing steel cable under no-load condition of hydraulic lifting device
CN201704035U (en) Lifting device of large-sized gas holder top
CN208747537U (en) A kind of combined bay that lifting jack detachable load is combined with guiding
CN209364522U (en) A kind of generator upper spider jack sleeve dial-out utility
CN202011709U (en) Installation work platform for wind turbine generator set
CN116865184B (en) Large-span pipe nut suspension construction method
CN220684422U (en) Lifting tool for removing blocking valve holding plate
CN220033742U (en) Vertical lifting device for reinforcing steel bars
CN103332637A (en) Steel strand pretightening device
CN221796747U (en) High-efficient wallboard hoist device
CN219489432U (en) Variable-magnification lifting hook pulley block structure
CN201952092U (en) Guide rope tensioning device for temporarily changing winch in mine
CN209131948U (en) A kind of low level reaction frame vertical stability test device for multifunctional
CN215855016U (en) Core-through hydraulic lifter

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081008