CN1635224A - Bridge structure and construction method therefor - Google Patents

Bridge structure and construction method therefor Download PDF

Info

Publication number
CN1635224A
CN1635224A CN 200310122999 CN200310122999A CN1635224A CN 1635224 A CN1635224 A CN 1635224A CN 200310122999 CN200310122999 CN 200310122999 CN 200310122999 A CN200310122999 A CN 200310122999A CN 1635224 A CN1635224 A CN 1635224A
Authority
CN
China
Prior art keywords
bridge
construction
pier
case beam
basis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200310122999
Other languages
Chinese (zh)
Inventor
葛竞辉
徐激
林志雄
朱廷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN 200310122999 priority Critical patent/CN1635224A/en
Publication of CN1635224A publication Critical patent/CN1635224A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a bridge structure, mainly comprising: piers arranged on the bases, box girders arranged on the piers. It is characterized in that: the top box girder of the bridge is an arched single-box multi-chamber concrete box girder; the bottom pier cross bridge is arranged with an upward column; the top part of the column is a pier column of abducted curved or straight Y type, I I type and H type; the bottom part of the column is straight or abducted curve. The technical characteristics of the invention are: firstly, the structure of the bridge is harmonious, reasonable and the appearance is elegant; secondly, the bridge span is enlarged, and the arched box girder can be preformed or on-site casting according to the bridge width, span and situations of the construction site, by which the project time can be shortened and the effect to the traffic is reduced.

Description

A kind of bridge construction and job practices thereof
Technical field:
The present invention is the related bridge technology field of civil engineering, and specifically a kind of have arch case beam and add shaped form or the vertically bridge construction and the job practices thereof of shape bridge pier.
Background technology:
The urban traffic viaduct occupies the part that becomes more and more important in the daily traffic in city, at present, the bridge pier of the urban traffic viaduct that China has implemented, in linearly only post of shape or twin columns moulding of direction across bridge, spacing is generally between the 20-30m in the bridge pier, the form of girder has hollow slab beam, T beam or straight abdomen and oblique web box girder, and the whole viaduct Mechanical Builds of composition is single, and long construction period.
Summary of the invention:
The object of the present invention is to provide a kind of improved bridge construction, it can adapt to the requirement of urban modernization, makes viaduct when the footpath is striden in increasing, further satisfies the demand of view, construction.
To achieve these goals, technical scheme of the present invention is: a kind of bridge construction, it mainly comprises the basis, be arranged on the bridge pier on the basis, place the case beam on the bridge pier, it is characterized in that: the case beam on described bridge top is an arch single-box multi-cell concrete case beam, and the bridge pier cross-bridges of bridge bottom is provided with column, this column top is II type, the H type pier stud of the curved Y type of abduction, II type, H type pier stud or vertical shape, and the bottom is vertical shape or abduction shaped form.
The tangible technical characterstic that the present invention constitutes by the such scheme feature, one, column on arch case beam and the bridge pier direction across bridge is II type, the H type pier stud of the curved Y type of abduction, II type, H type pier stud or vertical shape, the column at place, bottom is vertical shape or abduction shaped form, the bridge construction that is constituted is more coordinated rationally, new Ying is attractive in appearance, embodies the breath in a kind of overtime generation; Its two, strengthened the footpath of striding of bridge, and wide according to bridge, stride the arch case beam that footpath and job site situation implement and can prefabricatedly also can water construction in the scene, make the form of construction work variation of bridge, thereby accelerated construction progress, shortened the duration, reduced influence the environment traffic.
Description of drawings:
Fig. 1 is the structural representation of one embodiment of the invention
Fig. 2 is the lateral view of Fig. 1
Fig. 3 is the structural representation of another embodiment of the present invention
Fig. 4 is the lateral view of Fig. 3
Fig. 5 is the structural representation of further embodiment of this invention
Fig. 6 is the lateral view of Fig. 5
The specific embodiment:
Below in conjunction with drawings and Examples the present invention is further described.
The present invention is a kind of bridge construction, it mainly comprises basis 4, be arranged on the bridge pier 1 on the basis, place the case beam 2 on the bridge pier 1, it is characterized in that: the case beam on described bridge top is an arch single-box multi-cell concrete case beam, the bridge pier cross-bridges of bridge bottom is provided with to upper pillar stand 6, and this column is II type, the H type pier stud of the curved Y type of abduction, II type, H type pier stud or vertical shape, and the bottom is vertical shape or abduction shaped form.Arch single-box multi-cell concrete case beam is the simply supported beam or the beam structure of steel bar concrete or prestress concrete prefabricated units or cast-in-place member in the enforcement, stride the footpath and be 20-40 rice, the column of bridge pier is the primary structure member that the abduction shaped form is a bridge pier, the angle of its inclination directly influences or controls the force-bearing situation of bridge pier, stressed in consideration, control its shear stress, in the time of principal tensile stress, take into account its facade moulding, shaped form column and horizontal sextant angle are more than or equal to 70 degree in the enforcement, on bridge pier 1, be provided with bearing 3, arch single-box multi-cell concrete case beam 2 places on the bridge pier bearing pad 3, Reference numeral 5 expression stakes.
A kind of job practices of bridge construction is characterized in that: the job practices of described bridge construction may further comprise the steps: drive piles in a, the basis that chooses bridge, stake can be adopted reinforcing bar concrete square pile, PHC pile tube, bored pile; Carry out foundation construction after b, the stake completion; C, on the basis, carry out the construction of bridge pier; After d, Bridge Pier Construction are finished, use bridge fabrication machine or on-the-spot proping that arch case beam is carried out pouring construction; After finishing, e, box girder construction carry out the construction of deck paving, anticollision barrier.
A kind of job practices of bridge construction is characterized in that: the job practices of described bridge construction may further comprise the steps: drive piles in a, the basis that chooses bridge, stake can be adopted reinforcing bar concrete square pile, PHC pile tube, bored pile; Carry out foundation construction after b, the stake completion; C, on the basis, carry out the construction of bridge pier, carry out the prefabricated of arch case beam simultaneously; After d, Bridge Pier Construction are finished and reached intensity, arch case beam is started shipment lifting; Carry out the construction of deck paving, anticollision barrier after e, box girder construction are finished, finally constitute bridge construction.
About the arch single-box multi-cell concrete case beam in the bridge construction is the simply supported beam or the beam structure of steel bar concrete or prestress concrete prefabricated units or cast-in-place member, drive piles in the basis of bridge, reinforcing bar concrete square pile, PHC pile tube, bored pile that stake is adopted, construction to bridge pier, use bridge fabrication machine or on-the-spot proping that arch case beam is carried out pouring construction and be prior art, be not described specifically at this.

Claims (7)

1, a kind of bridge construction, it mainly comprises the basis, be arranged on the bridge pier on the basis, place the case beam on the bridge pier, it is characterized in that: the case beam on described bridge top is an arch single-box multi-cell concrete case beam, the bridge pier cross-bridges of bridge bottom is provided with to upper pillar stand, and this column is II type, the H type pier stud of the curved Y type of abduction, II type, H type pier stud or vertical shape, and the bottom is vertical shape or abduction shaped form.
2, by the described a kind of bridge construction of claim 1, it is characterized in that: arch single-box multi-cell concrete case beam is the simply supported beam or the beam structure of steel bar concrete or prestress concrete prefabricated units or cast-in-place member, strides the footpath and is 20-40 rice.
3, by claim 1 or 2 described a kind of bridge constructions, it is characterized in that: shaped form column and horizontal sextant angle are more than or equal to 70 degree.
4, by the described a kind of bridge construction of claim 1, it is characterized in that: be provided with bearing on bridge pier, arch single-box multi-cell concrete case beam places on the bridge pier bearing pad.
5, by the described a kind of bridge construction of claim 1, it is characterized in that: the basis is made up of steel bar concrete cushion cap and stake, and stake is reinforcing bar concrete square pile, PHC pile tube, bored pile.
6, a kind of job practices of bridge construction is characterized in that: the job practices of described bridge construction may further comprise the steps: drive piles in a, the basis that chooses bridge, stake can be adopted reinforcing bar concrete square pile, PHC pile tube, bored pile; Carry out foundation construction after b, the stake completion; C, on the basis, carry out the construction of bridge pier; After d, Bridge Pier Construction are finished, use bridge fabrication machine or on-the-spot proping that arch case beam is carried out pouring construction; After finishing, e, box girder construction carry out the construction of deck paving, anticollision barrier.
7, a kind of job practices of bridge construction is characterized in that: the job practices of described bridge construction may further comprise the steps: drive piles in a, the basis that chooses bridge, stake can be adopted reinforcing bar concrete square pile, PHC pile tube, bored pile; Carry out foundation construction after b, the stake completion; C, on the basis, carry out the construction of bridge pier, carry out the prefabricated of arch case beam simultaneously; After d, Bridge Pier Construction are finished and reached intensity, arch case beam is started shipment lifting; After finishing, e, box girder construction carry out the construction of deck paving, anticollision barrier.
CN 200310122999 2003-12-30 2003-12-30 Bridge structure and construction method therefor Pending CN1635224A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200310122999 CN1635224A (en) 2003-12-30 2003-12-30 Bridge structure and construction method therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200310122999 CN1635224A (en) 2003-12-30 2003-12-30 Bridge structure and construction method therefor

Publications (1)

Publication Number Publication Date
CN1635224A true CN1635224A (en) 2005-07-06

Family

ID=34844708

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200310122999 Pending CN1635224A (en) 2003-12-30 2003-12-30 Bridge structure and construction method therefor

Country Status (1)

Country Link
CN (1) CN1635224A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101793011A (en) * 2010-03-29 2010-08-04 中煤第三建设(集团)有限责任公司 Construction method for large-span overwater bridge
CN101915558A (en) * 2010-08-09 2010-12-15 重庆交通大学 Geometric linear detection method of bridge member
CN102433841A (en) * 2011-12-28 2012-05-02 中铁二局股份有限公司 Method for installing abnormal-shape curve steel box girder
CN102493349A (en) * 2011-12-16 2012-06-13 中国建筑第六工程局有限公司 Method for prefabricating and erecting box girders by using bailey beam
CN102605709A (en) * 2012-03-12 2012-07-25 北京市市政工程设计研究总院 Structure of simply support and continuous bridge with pier similar to inverted triangle
CN102677563A (en) * 2012-05-31 2012-09-19 徐有平 Modularized direct-moving fast channel system for crossroads of urban main road and construction method
CN103174086A (en) * 2013-03-20 2013-06-26 中铁六局集团天津铁路建设有限公司 Steel web single-box four-chamber combined box girder applied to extradosed cable-stayed bridge equal-height segments
CN103392043A (en) * 2010-09-30 2013-11-13 斯博泰科有限公司 Upper structure for bridge
CN104963279A (en) * 2015-06-25 2015-10-07 华侨大学 Novel box-type steel bridge pier
CN106677056A (en) * 2017-02-16 2017-05-17 上海市城市建设设计研究总院(集团)有限公司 Prefabricated double-column vase bridge pier and assembling construction method thereof
CN110593110A (en) * 2019-09-25 2019-12-20 中交二公局第五工程有限公司 Box girder cast-in-place support suitable for curves and longitudinal and transverse slopes and construction method thereof
CN112376428A (en) * 2020-10-19 2021-02-19 上海市政工程设计研究总院(集团)有限公司 Construction method for public rail integrated double-layer viaduct beam of full precast beam
CN114458059A (en) * 2022-03-09 2022-05-10 中铁二院昆明勘察设计研究院有限责任公司 Airport GTC high-speed rail elevated station bridge in high-intensity seismic area and construction method thereof

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101793011B (en) * 2010-03-29 2011-05-04 中煤第三建设(集团)有限责任公司 Construction method for large-span overwater bridge
CN101793011A (en) * 2010-03-29 2010-08-04 中煤第三建设(集团)有限责任公司 Construction method for large-span overwater bridge
CN101915558A (en) * 2010-08-09 2010-12-15 重庆交通大学 Geometric linear detection method of bridge member
CN101915558B (en) * 2010-08-09 2011-12-14 重庆交通大学 Geometric linear detection method of bridge member
CN103392043A (en) * 2010-09-30 2013-11-13 斯博泰科有限公司 Upper structure for bridge
CN103392043B (en) * 2010-09-30 2015-09-02 斯博泰科有限公司 For the superstructure of bridge
CN102493349A (en) * 2011-12-16 2012-06-13 中国建筑第六工程局有限公司 Method for prefabricating and erecting box girders by using bailey beam
CN102433841A (en) * 2011-12-28 2012-05-02 中铁二局股份有限公司 Method for installing abnormal-shape curve steel box girder
CN102433841B (en) * 2011-12-28 2013-12-25 中铁二局股份有限公司 Method for installing abnormal-shape curve steel box girder
CN102605709B (en) * 2012-03-12 2015-03-18 北京市市政工程设计研究总院有限公司 Structure of simply support and continuous bridge with pier similar to inverted triangle
CN102605709A (en) * 2012-03-12 2012-07-25 北京市市政工程设计研究总院 Structure of simply support and continuous bridge with pier similar to inverted triangle
CN102677563A (en) * 2012-05-31 2012-09-19 徐有平 Modularized direct-moving fast channel system for crossroads of urban main road and construction method
CN103174086A (en) * 2013-03-20 2013-06-26 中铁六局集团天津铁路建设有限公司 Steel web single-box four-chamber combined box girder applied to extradosed cable-stayed bridge equal-height segments
CN103174086B (en) * 2013-03-20 2015-11-11 中铁六局集团天津铁路建设有限公司 Be applicable to the part steel web list case four Room combined box beam of contour section of low-pylon cable-stayed bridge
CN104963279A (en) * 2015-06-25 2015-10-07 华侨大学 Novel box-type steel bridge pier
CN106677056A (en) * 2017-02-16 2017-05-17 上海市城市建设设计研究总院(集团)有限公司 Prefabricated double-column vase bridge pier and assembling construction method thereof
CN110593110A (en) * 2019-09-25 2019-12-20 中交二公局第五工程有限公司 Box girder cast-in-place support suitable for curves and longitudinal and transverse slopes and construction method thereof
CN112376428A (en) * 2020-10-19 2021-02-19 上海市政工程设计研究总院(集团)有限公司 Construction method for public rail integrated double-layer viaduct beam of full precast beam
CN114458059A (en) * 2022-03-09 2022-05-10 中铁二院昆明勘察设计研究院有限责任公司 Airport GTC high-speed rail elevated station bridge in high-intensity seismic area and construction method thereof

Similar Documents

Publication Publication Date Title
Menn Prestressed concrete bridges
CN106894326B (en) The construction method of assembled pretensioned prestressing corrugated steel web plate composite box girder
CN102203346B (en) Construction method of steel composite girder bridge
CN1635224A (en) Bridge structure and construction method therefor
CN1554839A (en) Steel-steel concrete fully prefabricated assembling structure
CN201077951Y (en) Track traffic overhead viaduct interval structure
CN102535327A (en) Through prestress steel truss and concrete combined continuous steel structure bridge and construction method thereof
CN102251488A (en) Stone built old arch bridge reinforcing structure
CN200974956Y (en) Prestressed concrete box girder
CN100427683C (en) Wide pier with canopy beam
CN201786045U (en) House structure with combined steel beam and pretensioning method prestress laminated beam
CN103233537A (en) Heavy-load superimposed overhead terrace and construction method
CN103290777A (en) Prestressed concrete variable-section box girder bridge with internal slant leg rigid frame, and construction method thereof
CN1483896A (en) Overhead bridge interval structure for track traffic
CN203270890U (en) Heavy-load superposed overhead terrace
CN213896714U (en) Prefabricated beam type arch bridge
CN108330808A (en) A kind of cast-in-place Continuous Box arch bridge of Long-span and construction method
CN103669193A (en) Laterally spliced combination T beam with wavy steel webs and construction method thereof
CN111058386B (en) Viaduct construction method for overpass existing ground bridge
JP2000045229A (en) Constructing method of bridge
CN103015304A (en) Prestressed concrete variable-cross-section box girder bridge with internal tilted-leg rigid frame and construction method of prestressed concrete variable-cross-section box girder bridge
JP3394519B2 (en) Viaduct concrete continuous arch structure
Pennells Concrete bridge designer's manual
CN203080399U (en) Pre-stressed concrete variable cross-section box girder bridge with internally-arranged slant legged rigid frame
CN206570674U (en) Assembled pretensioned prestressing corrugated steel web plate composite box girder

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Open date: 20050706