CN206570674U - Assembled pretensioned prestressing corrugated steel web plate composite box girder - Google Patents

Assembled pretensioned prestressing corrugated steel web plate composite box girder Download PDF

Info

Publication number
CN206570674U
CN206570674U CN201720222065.XU CN201720222065U CN206570674U CN 206570674 U CN206570674 U CN 206570674U CN 201720222065 U CN201720222065 U CN 201720222065U CN 206570674 U CN206570674 U CN 206570674U
Authority
CN
China
Prior art keywords
prestressed
concrete
corrugated steel
steel web
box girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720222065.XU
Other languages
Chinese (zh)
Inventor
李斐然
张士红
袁波
贾亚光
马捷
卢彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Zhongding Zhijian Technology Co ltd
Original Assignee
Henan Provincial Communication Planning and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Provincial Communication Planning and Design Institute Co Ltd filed Critical Henan Provincial Communication Planning and Design Institute Co Ltd
Priority to CN201720222065.XU priority Critical patent/CN206570674U/en
Application granted granted Critical
Publication of CN206570674U publication Critical patent/CN206570674U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of assembled pretensioned prestressing corrugated steel web plate composite box girder, including by the longitudinally connected combination beam of multiple precast beam body units, precast beam body unit includes individually prefabricated concrete roof, prestressed concrete bottom plate and Wavelike steel webplate, and precast beam body unit is that concrete roof width is more than the inverted trapezoidal structure that prestressed concrete baseplate width and Wavelike steel webplate are obliquely installed;Concrete roof is built-in with longitudinally connected muscle and prestressed pore passage, and its both sides is longitudinally spaced to offer multiple upper peg notches;Prestressed concrete bottom plate is built-in with longitudinally connected muscle and pretensioning steel beam, and its both sides is longitudinally spaced to offer multiple lower peg notches;Wavelike steel webplate upper and lower ends are welded with the flange plate with peg group.The utility model carries out beam body erection using the assembled structure type of precast block, and the volume and weight of each part are all corresponding smaller, and transport is stable, Hoisting Security, beneficial to construction.

Description

装配式先张法预应力波形钢腹板组合箱梁Assembled Pretensioned Prestressed Corrugated Steel Web Composite Box Girder

技术领域technical field

本实用新型涉及桥梁建筑技术领域,尤其是涉及一种适于大型桥梁的装配式先张法预应力波形钢腹板组合箱梁。The utility model relates to the technical field of bridge construction, in particular to an assembled pretensioned prestressed corrugated steel web composite box girder suitable for large bridges.

背景技术Background technique

传统预制箱梁腹板多为混凝土材质,不仅重量大且易开裂,故混凝土箱梁只适合应用于小跨径(40m以下)的公路桥梁。波形钢腹板PC组合箱梁桥是20世纪80年代出现的一种新型桥梁结构,其所使用的波形钢腹板具有优良的稳定性和不抵抗轴向力的特性,使预应力能有效地加载于混凝土顶板和预应力混凝土底板上;此外,波形钢腹板PC组合箱梁桥施工简便,能够有效缩短工期,因此在大中型桥梁(50m以上跨径)中得到了广泛的应用。Traditional prefabricated box girder webs are mostly made of concrete, which is heavy and easy to crack. Therefore, concrete box girders are only suitable for highway bridges with small spans (less than 40m). Corrugated steel web PC composite box girder bridge is a new type of bridge structure that appeared in the 1980s. The corrugated steel web used in it has excellent stability and the characteristics of not resisting axial force, so that the prestress can be effectively Loaded on the concrete roof and prestressed concrete floor; in addition, corrugated steel web PC composite box girder bridges are easy to construct and can effectively shorten the construction period, so they are widely used in large and medium-sized bridges (spans above 50m).

波形钢腹板PC组合箱梁在施工时,一般先在预制场内预制一体化结构的包括顶板、底板和波形钢腹板的工字型梁体单元,再在现场将上述拼接单元进行横向和纵向拼接后完成桥梁施工,如中国专利“二次张拉预应力装配式波形钢腹板组合梁及其施工方法”(申请号201510255113.0)就公开了上述结构的工字形预制件,并于相应的时机施加二次预应力,实现工字形预制件的横向拼装。上述工字型拼装单元自身稳定性差,且体积大,吨位重(例如单个预制工字形单元每延米的重量即可达5t左右),其运输成本和吊装成本较高,吊装安全性较低;同时,由于波形钢腹板与顶板和底板之间采用固定连接方式,因此该预制拼装单元内的各部件不可调整、不可替换,增加了后期维护的难度。During the construction of PC composite box girder with corrugated steel web, the I-shaped beam unit with integrated structure including top plate, bottom plate and corrugated steel web is generally prefabricated in the prefabrication site first, and then the above spliced units are horizontally and vertically integrated on site. The bridge construction is completed after longitudinal splicing. For example, the Chinese patent "Secondary tension prestressed assembled corrugated steel web composite beam and its construction method" (application number 201510255113.0) discloses the I-shaped prefabricated parts of the above structure, and in the corresponding The secondary prestress is applied at the right time to realize the horizontal assembly of the I-shaped prefabricated parts. The above-mentioned I-shaped assembly unit itself has poor stability, large volume, and heavy tonnage (for example, the weight of a single prefabricated I-shaped unit can reach about 5 tons per linear meter), and its transportation and hoisting costs are high, and hoisting safety is low; At the same time, due to the fixed connection between the corrugated steel web, the top plate and the bottom plate, the components in the prefabricated assembly unit cannot be adjusted or replaced, which increases the difficulty of later maintenance.

中国专利“拼装式预应力混凝土组合箱梁”(申请号200620126505.3)公开了一种组合箱梁的拼装单元,即将钢筋预制混凝土顶板、钢筋预应力混凝土底板和波形钢腹板分为三个部分分别进行整体预制,吊装就位后,在桥位处对三者进行竖向拼接,通过螺栓连接后形成箱梁梁体单元。相对于一体式结构,这种分开预制的箱梁顶板、底板和腹板体积小、重量轻,便于运输和吊装,适用于小跨径的、整孔架设的桥梁。对于大型桥梁,例如桥宽为16.75m的波形钢腹板箱梁桥,其每延米的重量高达10t以上,因此即便采用这种结构,各预制件的体积、重量仍然较大,运输及吊装优势不明显;同时,由于钢腹板竖直设置,具有以下缺点:Ⅰ.抗扭性能较差;Ⅱ.箱梁底板宽度及自重较大;Ⅲ.美观性较差;Ⅳ.直腹板日照面积大,受温度力影响大;此外,该专利没有考虑实际施工时预应力钢束的施加时机和预留孔道等情况,且对于负弯矩区的处理措施也未加论述,缺乏应对梁体荷载变形的措施和具体施工工艺方面的详细考虑,施工可行性较差。The Chinese patent "Assembled Prestressed Concrete Composite Box Girder" (Application No. 200620126505.3) discloses an assembly unit of a composite box girder, which divides the reinforced precast concrete roof, reinforced prestressed concrete bottom and corrugated steel web into three parts respectively. The overall prefabrication is carried out, and after being hoisted in place, the three are vertically spliced at the bridge position, and connected by bolts to form a box girder girder unit. Compared with the integrated structure, the separately prefabricated box girder top plate, bottom plate and web plate are small in size and light in weight, which is convenient for transportation and hoisting, and is suitable for small-span bridges erected with whole holes. For large bridges, such as corrugated steel web box girder bridges with a bridge width of 16.75m, the weight per linear meter is as high as 10t or more. Therefore, even if this structure is adopted, the volume and weight of each prefabricated part are still relatively large. The advantage is not obvious; at the same time, due to the vertical setting of the steel web, it has the following disadvantages: Ⅰ. Poor torsional performance; Ⅱ. Large width and self-weight of the bottom plate of the box girder; Ⅲ. Poor aesthetics; The area is large and is greatly affected by temperature forces; in addition, the patent does not consider the timing of applying prestressed steel beams and reserved holes during actual construction, and does not discuss the treatment measures for the negative bending moment area, lacking to deal with the beam body. The measures of load deformation and the detailed consideration of the specific construction technology make the construction feasibility poor.

发明内容Contents of the invention

本实用新型提供一种装配式先张法预应力波形钢腹板组合箱梁,目的在于解决现有波形钢腹板PC 组合箱梁应用于大型桥梁时容易出现运输、吊装和后期维护等方面的问题。The utility model provides an assembled pretensioned prestressed corrugated steel web composite box girder, which aims to solve the problems of transportation, hoisting and later maintenance when the existing corrugated steel web PC composite box girder is applied to large bridges. question.

为实现上述目的,本实用新型可采取下述技术方案:In order to achieve the above object, the utility model can take the following technical solutions:

本实用新型所述的装配式先张法预应力波形钢腹板组合箱梁,包括由多个预制梁体单元纵向连接而成的组合梁,所述预制梁体单元包括单独预制的混凝土顶板、预应力混凝土底板和波形钢腹板,预制梁体单元为混凝土顶板宽度大于预应力混凝土底板宽度、且波形钢腹板倾斜设置的倒梯形结构;所述混凝土顶板内置有纵向连接筋和用于穿设墩顶负弯矩张拉钢束的预应力孔道,混凝土顶板两侧沿纵向间隔开设有多个上栓钉槽口;所述预应力混凝土底板内置有纵向连接筋和先张拉预应力钢束,预应力混凝土底板两侧沿纵向间隔开设有多个下栓钉槽口;所述波形钢腹板上下两端均焊接有翼缘板,所述翼缘板上焊接有与所述上、下栓钉槽口相配合的栓钉群。The assembled pretensioned prestressed corrugated steel web composite box girder of the utility model includes a composite beam formed by longitudinal connection of a plurality of prefabricated beam units, and the prefabricated beam units include a separate prefabricated concrete roof, Prestressed concrete floor and corrugated steel web, the prefabricated beam unit is an inverted trapezoidal structure with the width of the concrete roof greater than the width of the prestressed concrete floor, and the corrugated steel web is inclined; The prestressed channel for the negative bending moment tension steel beam at the top of the pier is set, and a plurality of upper stud notches are arranged longitudinally on both sides of the concrete top plate; The two sides of the prestressed concrete floor are longitudinally spaced with a plurality of lower stud notches; the upper and lower ends of the corrugated steel web are welded with flange plates, and the flange plates are welded with the upper and lower The peg cluster fits in the lower peg notch.

所述波形钢腹板的倾斜角度为25°-40°,此时,倒梯形预制梁体单元结构最稳固。The inclination angle of the corrugated steel web is 25°-40°, at this time, the inverted trapezoidal prefabricated beam unit structure is the most stable.

本实用新型提供的装配式先张法预应力波形钢腹板组合箱梁,采用单独预制的混凝土顶板、预应力混凝土底板和波形钢腹板,并在现场将波形钢腹板倾斜插装在混凝土顶板和预应力混凝土底板之间,从而形成外型美观、整体抗扭能力较强的倒梯形预制梁体单元,之后再进行纵向拼接浇筑。上述倒梯形的预制梁体单元结构一方面充分利用了波形钢腹板的“褶皱效应”实现箱梁化整为零,实现在竖向上的进一步分块,将预制构件体积充分减小,特别是预应力混凝土底板的体积、重量减小,更加易于运输和吊装,有利于桥梁的快速架设,同时避免了整体预制的工字形构件自身稳定性差的问题;另一方面利用了波形钢腹板特有的弱“梁端效应”,在顶板内设置有后张拉预应力钢束,底板内设置先张拉预应力钢束,用于抵抗混凝土收缩徐变产生的应力,与施工过程完美配合,减少了现场钢束张拉工程量,实现施工的最大便捷。此外,倾斜设置的波形钢腹板由于日照面积小,受温度影响较小,有利于延长桥梁寿命。上述腹板通过端部栓钉群插装在顶、底板栓钉槽口内的方式进行连接,连接牢固、施工便捷。由此可见,本实用新型的优点可以体现在以下几点:The pre-tensioned prestressed corrugated steel web composite box girder provided by the utility model adopts a separate prefabricated concrete roof, prestressed concrete bottom plate and corrugated steel web, and obliquely inserts the corrugated steel web into the concrete on site. Between the top slab and the prestressed concrete bottom slab, an inverted trapezoidal prefabricated beam unit with beautiful appearance and strong overall torsional resistance is formed, and then longitudinally spliced and poured. On the one hand, the inverted trapezoidal prefabricated beam unit structure makes full use of the "fold effect" of the corrugated steel web to realize the box girder into parts, realize further division in the vertical direction, and fully reduce the volume of prefabricated components, especially The volume and weight of the prestressed concrete floor are reduced, and it is easier to transport and hoist, which is conducive to the rapid erection of bridges, and at the same time avoids the problem of poor stability of the overall prefabricated I-shaped components; Weak "beam end effect", post-tensioned prestressed steel beams are installed in the roof, and pre-tensioned prestressed steel beams are installed in the bottom plate to resist the stress caused by concrete shrinkage and creep, which perfectly cooperates with the construction process and reduces On-site steel beam tensioning engineering volume, to achieve the maximum convenience of construction. In addition, the inclined corrugated steel web is less affected by temperature due to the small sunlight area, which is beneficial to prolong the service life of the bridge. The above-mentioned webs are connected by inserting groups of studs at the ends into the notches of the studs on the top and bottom plates, so the connection is firm and the construction is convenient. This shows that the advantage of the utility model can be embodied in the following points:

(1)本实用新型采用倒梯形的预制拼装单元,各部件、特别是预应力混凝土底板的体积及重量都相应较小,不仅能有效保证预制件在运输过程中的稳定性,而且容易保证吊装过程中构件的安全性,利于施工。(1) The utility model adopts an inverted trapezoidal prefabricated assembly unit, and the volume and weight of each component, especially the prestressed concrete floor, are relatively small, which can not only effectively ensure the stability of the prefabricated parts during transportation, but also easily ensure the hoisting The safety of components in the process is conducive to construction.

(2)本实用新型的组合箱梁全部采用体内预应力钢束,利用弱“梁端效应”的特点,大部分先张法预应力钢束,仅在相邻跨径的梁体间张拉少量顶板墩顶负弯矩预应力钢束,现场预应力钢束张拉作业量少,预应力施加效果稳定。(2) The composite box girder of this utility model all adopts prestressed steel tendons in the body, and utilizes the characteristics of the weak "beam end effect", most of the pretensioned prestressed steel tendons are only stretched between beams with adjacent spans A small number of negative moment prestressed steel tendons on the top of the roof pier, less tensioning work on site, and stable prestressing effects.

(3)本实用新型的混凝土构件均为标准件,可规模化进行预制,现场预应力钢束张拉和现浇作业量较小,便于桥梁的快速施工。(3) The concrete components of the utility model are all standard parts, which can be prefabricated on a large scale, and the on-site prestressed steel beam tensioning and cast-in-place operations are relatively small, which facilitates the rapid construction of the bridge.

附图说明Description of drawings

图1是本实用新型中倒梯形预制梁体单元的结构示意图。Fig. 1 is a structural schematic diagram of an inverted trapezoidal prefabricated beam unit in the utility model.

图2是图1中混凝土顶板的结构示意图(省略纵向连接筋)。Fig. 2 is a schematic structural diagram of the concrete roof in Fig. 1 (the longitudinal connecting bars are omitted).

图3是图1中预应力混凝土底板的结构示意图(省略纵向连接筋)。Fig. 3 is a structural schematic diagram of the prestressed concrete floor in Fig. 1 (the longitudinal connecting ribs are omitted).

图4是图1中波形钢腹板的结构示意图。Fig. 4 is a structural schematic diagram of the corrugated steel web in Fig. 1 .

图5、图6是本实用新型的施工过程示意图。Fig. 5 and Fig. 6 are schematic diagrams of the construction process of the present utility model.

图7-12是对本实用新型进行原理性说明的相关附图。Figures 7-12 are related drawings for explaining the principle of the utility model.

具体实施方式detailed description

本实用新型所述的装配式先张法预应力波形钢腹板组合箱梁,包括由多个预制梁体单元纵向连接而成的组合梁,所述预制梁体单元包括单独预制的混凝土顶板1、预应力混凝土底板2和波形钢腹板3,如图1所示,预制梁体单元为混凝土顶板1宽度大于预应力混凝土底板2宽度、且波形钢腹板3倾斜设置的倒梯形结构;如图2所示,混凝土顶板1内置有纵向连接筋和用于穿设墩顶负弯矩张拉钢束的预应力孔道1.1,混凝土顶板1两侧沿纵向间隔开设有多个上栓钉槽口1.2;如图3所示,预应力混凝土底板2内置有纵向连接筋和先张拉预应力钢束2.1,预应力混凝土底板2两侧沿纵向间隔开设有多个下栓钉槽口2.2;如图4所示,波形钢腹板3上下两端均焊接有翼缘板3.1,翼缘板3.1上焊接有与上、下栓钉槽口1.2、2.2相配合的栓钉群3.2。The assembled pretensioned prestressed corrugated steel web composite box girder of the utility model includes a composite beam composed of a plurality of prefabricated beam units longitudinally connected, and the prefabricated beam units include a separate prefabricated concrete roof 1 , prestressed concrete floor 2 and corrugated steel web 3, as shown in Figure 1, the prefabricated beam unit is an inverted trapezoidal structure whose width of the concrete roof 1 is greater than the width of the prestressed concrete floor 2, and the corrugated steel web 3 is inclined; As shown in Figure 2, the concrete roof 1 has built-in longitudinal connecting ribs and prestressed tunnels 1.1 for piercing negative moment tension steel beams on the top of the pier. The two sides of the concrete roof 1 are longitudinally spaced with a plurality of upper stud slots. 1.2; as shown in Figure 3, the prestressed concrete floor 2 is built with longitudinal connecting ribs and pre-tensioned prestressed steel beams 2.1, and the two sides of the prestressed concrete floor 2 are provided with a plurality of lower bolt notches 2.2 along the longitudinal interval; As shown in Figure 4, the upper and lower ends of the corrugated steel web 3 are welded with flange plates 3.1, and the flange plate 3.1 is welded with stud groups 3.2 matching the upper and lower stud notches 1.2, 2.2.

上述波形钢腹板的倾斜角度为25°-40°,此时,倒梯形预制梁体单元结构最稳固。The inclination angle of the corrugated steel web is 25°-40°, at this time, the inverted trapezoidal prefabricated beam unit structure is the most stable.

本实用新型所述的装配式先张法预应力波形钢腹板组合箱梁施工时,按下述步骤进行:During the construction of the assembled pretensioned prestressed corrugated steel web composite box girder described in the utility model, the following steps are carried out:

第一步,在预制场内预制预应力混凝土底板2,首先在张拉台座上的预定位置固定先张拉预应力钢束并张拉至设计值,然后绑扎钢筋网,再安装模板,浇筑混凝土,待混凝土达到设计强度后,拆除模板,放松先张拉预应力钢束,完成先张法预应力混凝土底板2的预制,大大减少现场钢束张拉工程量;同时,预制混凝土顶板1,按照常规方法绑扎钢筋网,安装预应力孔道1.1,然后浇筑成型;波形钢腹板3在整体加工完成后,在两端焊接,之后按照上、下栓钉槽口1.2、2.2的位置焊接相应的栓钉群3.2。The first step is to prefabricate the prestressed concrete bottom slab 2 in the prefabrication site. First, fix the prestressed steel tendon at the predetermined position on the tensioning platform and stretch it to the design value, then bind the steel mesh, install the formwork, and pour the concrete , after the concrete reaches the design strength, the formwork is removed, the pre-tensioned prestressed steel tendons are loosened, and the prefabrication of the pre-tensioned prestressed concrete floor 2 is completed, which greatly reduces the amount of on-site steel tendon tensioning; at the same time, the prefabricated concrete roof 1, according to The conventional method binds the steel mesh, installs the prestressed channel 1.1, and then casts it into shape; after the corrugated steel web 3 is processed as a whole, it is welded at both ends, and then the corresponding bolts are welded according to the positions of the upper and lower peg notches 1.2 and 2.2. Nail Group 3.2.

第二步,如图5所示,在完成施工的相邻桥台或桥墩之间设置移动支撑装置4作为辅助施工平台,同时将预制完成的预应力混凝土底板2、波形钢腹板3和混凝土顶板1运送至施工现场。In the second step, as shown in Figure 5, a mobile support device 4 is set between the adjacent abutments or piers that have been constructed as an auxiliary construction platform, and the prefabricated prestressed concrete floor 2, corrugated steel web 3 and concrete The roof 1 is transported to the construction site.

第三步,使用吊装设备将预应力混凝土底板2吊装至移动支撑装置4上,将波形钢腹板3吊至预应力混凝土底板2上方,并将钢腹板3底部栓钉群3.2准确插装在预应力混凝土底板2的下栓钉槽口2.2中;之后,再起吊混凝土顶板1,同样将钢腹板3顶部栓钉群3.2准确插装到混凝土顶板1的上栓钉槽口1.2中。The third step is to use hoisting equipment to hoist the prestressed concrete floor 2 onto the mobile support device 4, hoist the corrugated steel web 3 above the prestressed concrete floor 2, and accurately insert the bolt group 3.2 at the bottom of the steel web 3 In the lower stud notch 2.2 of the prestressed concrete floor 2; after that, the concrete roof 1 is lifted, and the top stud group 3.2 of the steel web 3 is also accurately inserted into the upper stud notch 1.2 of the concrete roof 1.

第四步,如图6所示,将移动支撑装置4转移至下一桥跨位置,重复第三步作业;绑扎相邻桥跨顶板、底板之间的纵向连接筋,并浇筑混凝土形成横向湿接缝5;当混凝土达到一定强度时,张拉位于相邻桥跨的墩顶负弯矩区顶板预应力孔道1.1内的预应力钢束,用以抵抗墩顶负弯矩。The fourth step, as shown in Figure 6, is to transfer the mobile support device 4 to the position of the next bridge span, and repeat the third step; bind the longitudinal connecting ribs between the top and bottom plates of adjacent bridge spans, and pour concrete to form a horizontal wet bridge. Joint 5: when the concrete reaches a certain strength, stretch the prestressed steel strands located in the prestressed channel 1.1 of the top plate prestressed channel 1.1 in the negative bending moment area of the adjacent bridge span to resist the negative bending moment at the top of the pier.

第五步,重复第四步作业,形成多跨的连续梁结构,完成附属设施的架设后,结束施工。The fifth step is to repeat the fourth step to form a multi-span continuous beam structure. After completing the erection of auxiliary facilities, the construction ends.

以下是对本实用新型的预应力混凝土底板采用先张法预应力,并将波形钢腹板倾斜设置的倒梯形结构组合梁(近似于工字形波形钢腹板组合梁)进行竖向拼接这种施工方法的可行性、合理性所做出的具体原理性说明:The following is the construction of vertically splicing the inverted trapezoidal structure composite beam (similar to the I-shaped corrugated steel web composite beam) of the prestressed concrete floor of the present utility model using pretensioning prestressing and obliquely setting the corrugated steel web. Specific rationale for the feasibility and rationality of the method:

首先分析预制混凝土底板在两种状态下的受力。Firstly, the force of the precast concrete floor under two states is analyzed.

1.第1状态:1. The first state:

如图7所示的预应力混凝土底板,其内设置的张拉预应力钢束所施加的预应力为N,则预应力混凝土底板上的截面上应力为:For the prestressed concrete floor as shown in Figure 7, the prestress applied by the tensioned prestressed steel beams arranged in it is N, then the stress on the cross section of the prestressed concrete floor is:

2.第2状态:2. Second state:

当上述预应力混凝土底板组合成为波形钢腹板倾斜设置的倒梯形结构组合梁时,其断面结构(部分)如图8所示。When the above-mentioned prestressed concrete floor is combined into an inverted trapezoidal composite beam with corrugated steel webs inclined, its cross-sectional structure (part) is shown in Figure 8.

在预应力混凝土底板上施加预应力N,对组合截面中性轴的弯矩为:The prestress N is applied on the prestressed concrete floor, and the bending moment on the neutral axis of the composite section is:

由上下截面的面积矩相等可得:The area moments of the upper and lower sections are equal:

组合梁全截面的面积为:The area of the full cross-section of the composite beam is:

整个截面的惯性矩为:The moment of inertia of the entire section is:

波形钢腹板组合梁由于腹板的不抵抗轴力,在抗弯承载力计算时可不考虑腹板的作用,相当于无腹板截面,因此设定:Since the web of corrugated steel web composite beam does not resist the axial force, the effect of the web may not be considered in the calculation of the flexural bearing capacity, which is equivalent to a section without a web, so it is set as:

则: but:

顶板的应力: Stress on top plate:

令高厚比 height to thickness ratio

则顶板的应力: Then the stress on the top plate is:

底板的应力: The stress of the bottom plate:

对于一般的组合梁断面有,可得For general composite beam sections there are ,Available

以30m跨径的波形钢腹板组合梁为例。若,此时,带入式(9)和(10)得:Take a corrugated steel web composite beam with a span of 30m as an example. like ,at this time , into equations (9) and (10) to get:

当桥梁的跨径进一步增大时,和进一步增大,式(10)满足When the span of the bridge is further increased, with Further increase, formula (10) satisfies

由此可见,第1状态和第2状态下,预应力混凝土底板的应力近似相等。也就是说,先期在预制底板阶段施加的预应力,在叠合成波形钢腹板组合梁后仍基本保持不变。因此称波形钢腹板组合梁采取竖向分层拼装前后受力可基本保持不变的这种力学特征为叠合受力不变性。这种特性为波形钢腹板组合梁的竖向分层拼接提供了基础。It can be seen that in the first state and the second state, the stress of the prestressed concrete floor is approximately equal. That is to say, the prestress applied in the prefabricated floor stage remains basically unchanged after being laminated into a corrugated steel web composite beam. Therefore, the mechanical characteristic that the force of corrugated steel web composite beams can basically remain unchanged before and after vertical layered assembly is called superposition force invariance. This characteristic provides the basis for the vertical layered splicing of corrugated steel web composite beams.

在上述分析的基础上,再来讨论普通钢-混组合工字梁和波形钢腹板组合工字梁的竖向拆分与拼装过程中应力的变化。其中,将预应力作为唯一考虑的外力:On the basis of the above analysis, the stress changes in the process of vertical splitting and assembly of ordinary steel-concrete composite I-beams and corrugated steel web composite I-beams are discussed. Among them, the prestress is considered as the only external force:

1. 竖向拆分过程:1. Vertical split process:

图9为普通钢-混组合工字梁(倒梯形结构)进行竖向拆分的示意图。Figure 9 is a schematic diagram of vertical splitting of ordinary steel-concrete composite I-beams (inverted trapezoidal structure).

图10为波形钢腹板倾斜设置的倒梯形结构组合梁进行竖向拆分的示意图。Fig. 10 is a schematic diagram of vertical splitting of an inverted trapezoidal structural composite beam with a corrugated steel web obliquely arranged.

2.先张法预应力+竖向拼接过程:2. Pretensioning prestressing + vertical splicing process:

图11为普通钢-混组合工字梁(倒梯形结构)采用先张法预应力及进行竖向拼接时的示意图。Figure 11 is a schematic diagram of an ordinary steel-concrete composite I-beam (inverted trapezoidal structure) prestressed by pretensioning and vertically spliced.

图12为波形钢腹板倾斜设置的倒梯形结构组合梁采用先张法预应力及进行竖向拼接时的示意图。Fig. 12 is a schematic diagram of an inverted trapezoidal structural composite beam with corrugated steel webs inclined and prestressed by pretensioning and vertically spliced.

对比上述图例可以看出,对于波形钢腹板倾斜设置的倒梯形结构组合梁来说,在底板施加预应力就好像是一个独立的过程;但是普通钢-混组合的情况是完全不同的。 因此,施工中可在预制混凝土底板时施加全部或部分预应力,然后将预制混凝土底板、波形钢腹板和预制混凝土顶板竖向分层拼装,这样能大大减少现场的钢束张拉工作量,提高工厂预制化程度。Comparing the above illustrations, it can be seen that for the inverted trapezoidal composite beam with corrugated steel web inclined, applying prestress on the bottom plate seems to be an independent process; but the situation of ordinary steel-concrete composite is completely different. Therefore, during construction, all or part of the prestress can be applied to the prefabricated concrete floor, and then the precast concrete floor, corrugated steel web and precast concrete roof are vertically assembled in layers, which can greatly reduce the workload of steel beam tension on site. Increase the degree of factory prefabrication.

Claims (2)

1. a kind of assembled pretensioned prestressing corrugated steel web plate composite box girder, including it is longitudinally connected by multiple precast beam body units Combination beam, the precast beam body unit include individually prefabricated precast concrete top plate, prestressed concrete bottom plate and Wavelike steel webplate, it is characterised in that:Precast beam body unit be concrete roof width be more than prestressed concrete baseplate width and The inverted trapezoidal structure that Wavelike steel webplate is obliquely installed;The concrete roof is built-in with longitudinally connected muscle and born for wearing pier top The prestressed pore passage of moment of flexure tensioning steel beam, concrete roof both sides are longitudinally spaced to offer multiple upper peg notches;It is described pre- Prestressed concrete bottom plate is built-in with longitudinally connected muscle and pretensioning steel beam, and prestressed concrete bottom plate both sides are along between longitudinal direction Separate provided with multiple lower peg notches;The Wavelike steel webplate upper and lower ends are welded with flange plate, the flange plate and welded There is the peg group being engaged with the upper and lower peg notch.
2. assembled pretensioned prestressing corrugated steel web plate composite box girder according to claim 1, it is characterised in that:It is described The angle of inclination of Wavelike steel webplate is 25 ° -40 °.
CN201720222065.XU 2017-03-09 2017-03-09 Assembled pretensioned prestressing corrugated steel web plate composite box girder Active CN206570674U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720222065.XU CN206570674U (en) 2017-03-09 2017-03-09 Assembled pretensioned prestressing corrugated steel web plate composite box girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720222065.XU CN206570674U (en) 2017-03-09 2017-03-09 Assembled pretensioned prestressing corrugated steel web plate composite box girder

Publications (1)

Publication Number Publication Date
CN206570674U true CN206570674U (en) 2017-10-20

Family

ID=60057472

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720222065.XU Active CN206570674U (en) 2017-03-09 2017-03-09 Assembled pretensioned prestressing corrugated steel web plate composite box girder

Country Status (1)

Country Link
CN (1) CN206570674U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111893884A (en) * 2020-07-06 2020-11-06 湖北工业大学 An asynchronous construction method for a fully prefabricated and assembled corrugated steel web bridge
CN114239180A (en) * 2021-12-22 2022-03-25 广西科技大学 Equivalent calculation model of I-beam of corrugated steel web
CN116837709A (en) * 2023-07-18 2023-10-03 上海市城市建设设计研究总院(集团)有限公司 Combined box girder of UHPC plate, corrugated steel plate and concrete plate and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111893884A (en) * 2020-07-06 2020-11-06 湖北工业大学 An asynchronous construction method for a fully prefabricated and assembled corrugated steel web bridge
CN114239180A (en) * 2021-12-22 2022-03-25 广西科技大学 Equivalent calculation model of I-beam of corrugated steel web
CN116837709A (en) * 2023-07-18 2023-10-03 上海市城市建设设计研究总院(集团)有限公司 Combined box girder of UHPC plate, corrugated steel plate and concrete plate and construction method

Similar Documents

Publication Publication Date Title
CN106894326B (en) The construction method of assembled pretensioned prestressing corrugated steel web plate composite box girder
CN101550675B (en) A pre-bent composite beam with corrugated steel web and its construction method
CN204282199U (en) Pile-column concrete hollow pile bridge pier structure
CN106906748A (en) Construction method of prefabricated corrugated steel web composite box girder based on mixed prestress
CN206570671U (en) Based on the prestressed assembled corrugated steel web plate composite box girder of mixing
CN108677685A (en) A kind of ultra-high performance concrete-part girder steel combination bent cap and its construction method
CN101775775B (en) Combined bridge with self-anti-cracking function and construction method thereof
CN106638265B (en) A kind of steel reinforced concrete beam rigid framed structure arch bridge
CN108978434A (en) A kind of Novel steel-is mixed to be combined Continuous Box Girder Bridge and its industrializes construction method without bracket
CN108193607B (en) Fabricated prestressed truss for reinforcement and construction method thereof
CN104988844A (en) Secondary tensioning prestressed assembly-type corrugated steel web composite beam and construction method thereof
CN103498533A (en) Prestressed H-shaped steel reinforced concrete superposed beam
CN103410102A (en) H-shaped double column pier wide-bridge-surface cantilever temporary consolidation structure and construction method thereof
CN102535327A (en) Through prestress steel truss and concrete combined continuous steel structure bridge and construction method thereof
CN208293400U (en) A kind of ultra-high performance concrete-part girder steel combination bent cap
CN208933811U (en) A kind of novel steel-concrete combination Continuous Box Girder Bridge of erection without scaffolding
CN202990196U (en) Partially prestressed prefabricated thin plate
CN106869317B (en) The beam column edge of a wing is the group frame system and construction method of concrete-filled rectangular steel tube
CN106012806B (en) Cored slab hinge seam Shear connection construction and construction technology
CN114182620A (en) Partial cable-stayed bridge structure system and construction method with large cantilever core steel box
CN106906749B (en) The construction method of full assembled steel-concrete combined structure box beam
CN109930469B (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail
CN215051984U (en) Wide-width large-span hybrid beam short-tower cable-stayed bridge system
CN203547019U (en) Prestressed H-shaped steel reinforced concrete superposed beam
CN202830741U (en) Semi-assembled type bamboo-concrete combined bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230116

Address after: Southwest corner of the intersection of New 107 National Road and 327 National Road, Yuanyang County, Xinxiang City, Henan Province 453500

Patentee after: Henan Zhongding Zhijian Technology Co.,Ltd.

Address before: 450052 No. 70 Longhai Middle Road, Erqi District, Zhengzhou City, Henan Province

Patentee before: HENAN PROVINCIAL COMMUNICATIONS PLANNING & DESIGN INSTITUTE Co.,Ltd.

Patentee before: Li Feiran

TR01 Transfer of patent right