CN1464151A - Construction method for curtain wall - Google Patents

Construction method for curtain wall Download PDF

Info

Publication number
CN1464151A
CN1464151A CN 02111962 CN02111962A CN1464151A CN 1464151 A CN1464151 A CN 1464151A CN 02111962 CN02111962 CN 02111962 CN 02111962 A CN02111962 A CN 02111962A CN 1464151 A CN1464151 A CN 1464151A
Authority
CN
China
Prior art keywords
hole
curtain wall
wall
fixture
stone material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 02111962
Other languages
Chinese (zh)
Inventor
陈克俭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Simike Building Ceramics Co Ltd
Original Assignee
Shanghai Simike Building Ceramics Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Simike Building Ceramics Co Ltd filed Critical Shanghai Simike Building Ceramics Co Ltd
Priority to CN 02111962 priority Critical patent/CN1464151A/en
Publication of CN1464151A publication Critical patent/CN1464151A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The curtain wall constructing process includes drilling holes in the back side of porcelain board or stone material, making back bolt pass through fixing and hanging rod, fixing the hanging rod with nuts onto the back side of porcelain board or stone material, drilling holes on wall in corresponding positions, cleaning the holes on wall, grouting anchoring agent into the holes and inserting the unions into the holes. Compared with available curtain wall constructing processes, the said one needs no installation of keel, and this can simplify the construction and lower the cost greatly.

Description

A kind of job practices of curtain wall
Technical field:
The present invention relates to the technical field of construction techniques, specifically a kind of being mainly used in carried out cladding job practices with porcelain plate or stone material as curtain wall.
Background technology:
At present, along with developing rapidly of Building Trade in China, curtain wall in architectural use also more and more widely but now domesticly need be installed keel when carrying out curtain wall construction, and it is complicated to exist construction, and the shortcoming that cost is high has brought certain degree of difficulty for the popularization of curtain wall
Summary of the invention:
The object of the present invention is to provide a kind of simple and reliable curtain wall construction method.
To achieve these goals, technical scheme of the present invention is: a kind of job practices of curtain wall, it is characterized in that: earlier in the boring of the behind of porcelain plate or stone material, back of the body bolt is passed the fixture of peg spare, adopt nut peg spare to be fixed on the back side of porcelain plate or stone material by this fixture, in the corresponding position boring of body of wall and peg spare, then foreign material in the hole of body of wall are cleaned out the back and in the hole, injected the anchoring agent and pipe connecting piece is inserted in the hole.
The present invention compares with existing curtain wall construction method does not need to install keel, thereby has simplified the operation of curtain wall construction greatly, and the construction cost of curtain wall is reduced significantly, has very big economic benefit, help the popularization of curtain wall, and construction safety is reliable.
Description of drawings:
Fig. 1 is the structural representation of the present invention one peg spare embodiment
Fig. 2 is the right view of Fig. 1
Fig. 3 is for being fixed on peg spare in the schematic diagram on porcelain plate or the stone material
Fig. 4 is the schematic diagram in the boring of body of wall relevant position
The schematic diagram of Fig. 5 for the hole of body of wall is cleared up
Fig. 6 is the schematic diagram that injects the anchoring agent in the hole of body of wall
Fig. 7 inserts in the body of wall hole schematic diagram that porcelain plate or stone material are fixed for peg spare
The specific embodiment:
The invention will be further described below in conjunction with drawings and Examples.
The present invention is a kind of job practices of curtain wall, it is different from prior art and is: bore a hole at least in the behind of porcelain plate or stone material 6 earlier, back of the body bolt 3 is passed the fixture 2 of peg spare 1, adopt nut peg spare to be fixed on the back side of porcelain plate or stone material by this fixture, in body of wall 8 and peg spare corresponding position boring 9, then foreign material in the hole of body of wall being cleaned out the back injects the anchoring agent and pipe connecting piece is inserted in the hole in the hole, one end of the peg spare in the enforcement 1 is fixedlyed connected with a fixture 2, being provided with on fixture 2 can be for carrying on the back hole or the opening 4 that bolt 3 passes, generally on fixture 2, be provided with opening upwards in the enforcement, back of the body bolt 3 passes the hole or the opening 4 of fixture during use, to be fixed on the back side of porcelain plate 6 or stone material with the fixture 2 that peg spare is connected as a single entity by nut 5, the anchoring agent can be adopted the epoxy resin of selling on the market.
Embodiment 1
Bore two holes in the behind of porcelain plate by 80 centimetres spacing earlier, each Kong Jun will carry on the back the opening that bolt passes the fixture of peg spare, adopt nut peg spare to be fixed on the back side of porcelain plate by this fixture, then by the requirement of curtain wall construction, bore two holes at body of wall and the corresponding position of peg spare, again with wire brush and dust catcher with after foreign material are cleaned out in the hole of body of wall, adopt syringe in each hole of being bored, to inject commercially available anchoring agent epoxy resin, after two minutes, will pipe connecting piece be inserted in each hole porcelain plate can be fixed on the body of wall respectively.
Embodiment 2
Bore four holes in the behind of stone material by 150 centimetres spacing earlier, each Kong Jun will carry on the back the hole that bolt passes the fixture of peg spare, adopt nut peg spare to be fixed on the back side of stone material by this fixture, then by the requirement of curtain wall construction, bore four holes at body of wall and the corresponding position of peg spare, again with wire brush and dust catcher with after foreign material are cleaned out in the hole of body of wall, adopt syringe in each hole of being bored, to inject the anchoring agent, after one minute respectively just pipe connecting piece insert in each hole and porcelain plate can be fixed on the body of wall.

Claims (3)

1, a kind of job practices of curtain wall, it is characterized in that: earlier in the boring of the behind of porcelain plate or stone material, back of the body bolt is passed the fixture of peg spare, adopt nut peg spare to be fixed on the back side of porcelain plate or stone material by this fixture, in the corresponding position boring of body of wall and peg spare, then foreign material in the hole of body of wall are cleaned out the back and in the hole, injected the anchoring agent and pipe connecting piece is inserted in the hole.
2, by the job practices of the described a kind of curtain wall of claim 1, it is characterized by: an end of peg spare is fixedlyed connected with a fixture, and being provided with on fixture can be for carrying on the back hole or the opening that bolt passes.
3, by the job practices of the described a kind of curtain wall of claim 1, it is characterized by: the blind hole that a back taper is arranged in the bottom in porcelain plate or hole, stone material behind.
CN 02111962 2002-06-06 2002-06-06 Construction method for curtain wall Pending CN1464151A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 02111962 CN1464151A (en) 2002-06-06 2002-06-06 Construction method for curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 02111962 CN1464151A (en) 2002-06-06 2002-06-06 Construction method for curtain wall

Publications (1)

Publication Number Publication Date
CN1464151A true CN1464151A (en) 2003-12-31

Family

ID=29741974

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 02111962 Pending CN1464151A (en) 2002-06-06 2002-06-06 Construction method for curtain wall

Country Status (1)

Country Link
CN (1) CN1464151A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105952086A (en) * 2016-04-27 2016-09-21 张家口家诚首佳新型建材股份有限公司 Assembly-type energy-saving hanging plate

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105952086A (en) * 2016-04-27 2016-09-21 张家口家诚首佳新型建材股份有限公司 Assembly-type energy-saving hanging plate

Similar Documents

Publication Publication Date Title
CN200978477Y (en) Mounting structure of china clay plate curtain wall
CN206090859U (en) Novel embedding slot
CN101899868A (en) Construction method for rear planted wall steel tie
CN1464151A (en) Construction method for curtain wall
CN205712561U (en) A kind of prefabricated panel
CN109898852B (en) Building template fastening device and fastening method
CN200968042Y (en) Ceramic tile for architectural decoration
CN1464150A (en) Construction method for curtain wall
CN111852528A (en) Sectional recoverable high-strength prestressed anchor cable and its construction method
CN2697217Y (en) Connector for multi-section flagpole
CN210482589U (en) Novel prefabricated shear wall
CN204326565U (en) Face frontier defense guardrail
CN209799349U (en) Easily-installed and easily-disassembled building template
CN220791122U (en) Profile steel step
JP4404430B2 (en) Method of attaching a building decoration material and the attachment device
CN203174835U (en) Combination hanging piece and beam-free ceramic gravel curtain wall system
CN207302492U (en) A kind of gardens direction board being easily installed
CN206731644U (en) A kind of convenient cleaning equipment of chemical anchor bolts
CN207177744U (en) Drilling tool cleaning nozzle mounting bracket
CN220167558U (en) Safety protection net
CN203174834U (en) Combination hanging piece and ceramic gravel curtain wall with beams
CN206468003U (en) A kind of Xin Jiamo guard bar structures
CN205444959U (en) Safety protection device for building
CN220066708U (en) Steel pipe clamp for bridge laying
CN105220837B (en) A kind of installation method of ornamental sets of brackets on top of the columns

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication