CN1331365A - Pile-forming method by perforating with long screw and pumping concrete - Google Patents

Pile-forming method by perforating with long screw and pumping concrete Download PDF

Info

Publication number
CN1331365A
CN1331365A CN 00110560 CN00110560A CN1331365A CN 1331365 A CN1331365 A CN 1331365A CN 00110560 CN00110560 CN 00110560 CN 00110560 A CN00110560 A CN 00110560A CN 1331365 A CN1331365 A CN 1331365A
Authority
CN
China
Prior art keywords
concrete
pile
long
central tube
spiral
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 00110560
Other languages
Chinese (zh)
Inventor
胡永福
孙恒战
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHANGCHUN ARCHITECTURAL FOUNDATION ENGINEERING GROUP Co
Original Assignee
CHANGCHUN ARCHITECTURAL FOUNDATION ENGINEERING GROUP Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHANGCHUN ARCHITECTURAL FOUNDATION ENGINEERING GROUP Co filed Critical CHANGCHUN ARCHITECTURAL FOUNDATION ENGINEERING GROUP Co
Priority to CN 00110560 priority Critical patent/CN1331365A/en
Publication of CN1331365A publication Critical patent/CN1331365A/en
Pending legal-status Critical Current

Links

Abstract

A pile-forming technology for the saturated or unsaturated clay or sandy stratum features that a long-screw drill with central tube is used to drill hole until the destination stratum, a high-pressure pump is then used to pump concrete into the drilled hole via the said central tube, and the drill rod is lifted up while the concrete is pumped into the hole to form a pile. Its advantages include no collapse and diameter decreasing, low noise, no pollution, high efficiency and high pile integrity.

Description

A kind of long spiral pore-forming---pumping of concrete piling method
The invention belongs to technical field of buildings, is concrete piling method in a kind of Foundation Design.
At present, a large amount of employing hammerings or vibrating type tube-sinking cast-in-situ pile in the pile foundation engineering of general load, but in saturated soft clay, because immersed tube soil compaction stress to the negative effect of adjacent studs phenomenons such as undergauge, broken pile takes place very easily.Though and common long screw auger drilling deposited pile is a kind of non-soil compaction stake, in the saturated soft soil of phreatic high drilling rod hole wall behind the hole easily cave in, shrinkage cavity, its application is subjected to certain limitation.Improve and next secondary making pile by grouting into technology by long auger, though solved this problem, complex process, work efficiency is lower, is difficult to apply.
The objective of the invention is to provide a kind of undergauge, broken pile, hole wall collapse and shrinkage cavity situation in construction, can avoided to take place, and the simply long spiral pore-forming of technology---pumping of concrete piling method.
The present invention is realized by following steps:
Employing has the long-spiral drilling machine of central tube to carry out drilling construction, and behind the layer of waiting to achieve the goal, with in the central tube injection hole of concrete by long-spiral drilling machine that mixes, the limit is carried and bored the limit infusion up to finishing pile then with the high pressure concrete delivery pump.
Wherein, the rate of penetration 1-2m/min of rig, the hoisting velocity 1-1.5m/min of rig, concrete transporting velocity 1-1.5m/min, the concrete slump is 180-220mm, the maximum particle diameter<32mm of concrete coarse aggregate.
The inventive method suits to construct under saturated, unsaturation clay and geological conditionss such as loam or sand bed, has low noise, pollution-free, high efficiency and the complete characteristics of pile body.Through 10 meters noise measuring maximum noises less than 50 decibels.Because of it does not use mud, environmentally safe, comparing with the high-pressure slip-casting stake has its unique advantage.This process is to pour into disposable finishing from creeping into to, and the mechanization degree height can improve efficiency of construction greatly.As the construction of non-soil compaction stake, fully guaranteed the integrality of pile body, and can construct general foundation pile, lagging pile, compound foundation pile or the like.
Below provide the specific embodiment of the invention:
Adopt ZKL800 type super large stride long-spiral drilling machine, be transported to and specify the stake position, centering makes equipment maintenance level, and drilling tool is the vertical state.Start rig, loosening hoist rope begins to creep into, speed remains 1.5m/min, when being drilled into 8 meters of desired depths, stop to bore, and on carry 0.2 meter of drilling tool, start concrete pump, in the central tube injection hole of concrete with the maximum particle diameter<32mm of the coarse aggregate that mixes, carry drilling tool limit pumping of concrete on the limit, wherein the hoisting velocity 1.2m/nin of rig by long-spiral drilling machine, concrete transporting velocity 1.2m/min, concrete spouting finishes to remove drilling tool.If pile foundation need be provided with reinforcing cage, reinforcing cage can be inserted down in the concrete after the perfusion, if when situation not in place down occurring, available cover-plate type vibrator will reinforcing cage down to assigned address.

Claims (1)

1, a kind of long spiral pore-forming---pumping of concrete piling method, it is characterized in that: adopting has the long-spiral drilling machine of central tube to carry out drilling construction, wait to achieve the goal behind the layer, with the high pressure concrete delivery pump with in the central tube injection hole of concrete that mixes by long-spiral drilling machine, the limit is carried and is bored the limit infusion up to finishing pile then, wherein, rate of penetration 1-the 2m/min of rig, hoisting velocity 1-the 1.5m/min of rig, concrete transporting velocity 1-1.5m/min, the concrete slump is 180-220mm, the maximum particle diameter<32mm of concrete coarse aggregate.
CN 00110560 2000-06-22 2000-06-22 Pile-forming method by perforating with long screw and pumping concrete Pending CN1331365A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 00110560 CN1331365A (en) 2000-06-22 2000-06-22 Pile-forming method by perforating with long screw and pumping concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 00110560 CN1331365A (en) 2000-06-22 2000-06-22 Pile-forming method by perforating with long screw and pumping concrete

Publications (1)

Publication Number Publication Date
CN1331365A true CN1331365A (en) 2002-01-16

Family

ID=4580548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 00110560 Pending CN1331365A (en) 2000-06-22 2000-06-22 Pile-forming method by perforating with long screw and pumping concrete

Country Status (1)

Country Link
CN (1) CN1331365A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102444116A (en) * 2011-10-31 2012-05-09 山东鸿泰建设集团有限公司 Construction waste regenerated aggregate concrete pile and soil foundation treatment method thereof
CN102535445A (en) * 2012-02-07 2012-07-04 陕西桩鑫建设工程有限公司 Molding device and molding method for long spiral extruding rock-entering cast-in-place pile

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102444116A (en) * 2011-10-31 2012-05-09 山东鸿泰建设集团有限公司 Construction waste regenerated aggregate concrete pile and soil foundation treatment method thereof
CN102535445A (en) * 2012-02-07 2012-07-04 陕西桩鑫建设工程有限公司 Molding device and molding method for long spiral extruding rock-entering cast-in-place pile
CN102535445B (en) * 2012-02-07 2013-09-04 陕西桩鑫建设工程有限公司 Molding device and molding method for long spiral extruding rock-entering cast-in-place pile

Similar Documents

Publication Publication Date Title
CN1193141C (en) Combined grouting construction process of reinforcing foundation
WO2018210019A1 (en) Pile formation method for down-the-hole impact rotary jet composite piles
AU2020376449B2 (en) Construction method of pressurized grouting pile based on reinforcing fiber and metakaolin
CN100501011C (en) Hole drilling mudjack pile construction method
CN105780763B (en) Mesoporous vibrates the construction method of casing retaining wall long auger guncreting pile
CN112609673B (en) Device and method for deep resonance compaction and reinforcement of miscellaneous fill foundation
KR100762991B1 (en) Precast piling method injected with high-strength mortar
CN1657711A (en) Rotary spray anchoring pile construction process
CN111058443B (en) Precast pile composite foundation construction method for eliminating loess collapsibility
CN105714834B (en) A kind of construction technology of hardpan preexisting hole grouting behind shaft or drift lining H profile steel stake
CN100532733C (en) Diving casting cast-in-place pile construction method for constructing in scree layer and sand layer
CN106812149A (en) A kind of construction method of pile foundation
CN108643214B (en) Backfill mixed soil composite foundation structure and construction method thereof
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
CN109736313A (en) Drill-pouring end-bearing pile handles pile bottom sediment technique using coring hole grouting behind shaft or drift lining
CN1548661A (en) Method of supporting foundation pit in soft layer with brad
CN101245597A (en) Breast wall type cast-in-situ bored pile construction method and pile machine
CN203594023U (en) Enhanced type long auger drilling pressure-grouting concrete pile
CN108316288A (en) Half casing guncreting pile construction equipment and construction method
CN205776209U (en) The construction equipment of concrete-pile
CN1331365A (en) Pile-forming method by perforating with long screw and pumping concrete
CN1078282A (en) Pile shoe pouring process and special reinforcing steel cage thereof
CN208088287U (en) Half casing guncreting pile construction equipment
CN101629470B (en) Drilling construction method for dry rock-socketed bored pile
CN214832540U (en) Device for densely reinforcing miscellaneous filling foundation by deep layer resonance

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication