CN1321798C CNB2004100153183A CN200410015318A CN1321798C CN 1321798 C CN1321798 C CN 1321798C CN B2004100153183 A CNB2004100153183 A CN B2004100153183A CN 200410015318 A CN200410015318 A CN 200410015318A CN 1321798 C CN1321798 C CN 1321798C
Authority
CN
China
Prior art keywords
steel pipe
pipe
steel
internal
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2004100153183A
Other languages
Chinese (zh)
Other versions
CN1557624A (en
Inventor
李志雄
马东生
何永刚
王骧骥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU ADVANCE-TECH Co Ltd
Original Assignee
GUANGZHOU ADVANCE-TECH Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU ADVANCE-TECH Co Ltd filed Critical GUANGZHOU ADVANCE-TECH Co Ltd
Priority to CNB2004100153183A priority Critical patent/CN1321798C/en
Publication of CN1557624A publication Critical patent/CN1557624A/en
Application granted granted Critical
Publication of CN1321798C publication Critical patent/CN1321798C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Application Of Or Painting With Fluid Materials (AREA)

Abstract

The present invention relates to a method and a device for producing a plastic-steel composite pipe of which both the interior and the exterior have anti-corrosive property. The method of the present invention comprises the following procedures that 1) a steel pipe enters a production line via a pipe feeding platform (1); 2) the steel pipe is preheated by a preheating device (2); 3) the steel pipe is conveyed to a derusting device (3) for the interior of the steel pipe, and the inner wall of the steel pipe is derusted; 4) the steel pipe is preheated by a heating device (6); 5) powdery paint is sprayed to the inner wall of the steel pipe by a spray device (7) for the interior of the steel pipe; 6) the outer wall of the steel pipe is derusted by an outer derusting machine set (10); 7) an outer adhesive layer and an outer plastic layer are extruded on the outer wall of the steel pipe continuously in order by an adhesive layer extruding device (15) and a plastic layer extruding device (16); 8) the steel pipe is cooled by a cooling device (17). The device for producing the plastic-steel composite pipe in the present invention comprises the pipe feeding platform (1), the preheating device (2), the derusting device (3), the heating device (6), the spray device (7) for the interior of the steel pipe, the outer derusting machine set (10), the adhesive layer extruding device (15), the plastic layer extruding device (16) and the cooling device (17). The method of the present invention has simple process, low cost and good economic benefit; the device of the present invention has the advantages of simple structure, easy installation and easy use.

Description

A kind of production method of internal and external anti-corrosive steel-plastics composite pipe
1, technical field:
The present invention relates to a kind of production method of internal and external anti-corrosive steel-plastics composite pipe, belong to the innovative technology of the production method of internal and external anti-corrosive steel-plastics composite pipe.
2, background technology:
Steel pipe plays important effect in pipeline is carried, but the etching problem of steel pipe affects the service life of steel pipe always.Steel-plastics composite pipe (patent No. 01257775.8) preferably resolves the etching problem of medium-small diameter steel pipe, its cost is low, corrosion-resistant, easy to connect, obtained more application, but the middle large-diameter pipeline of diameter more than 250mm, the complexity that this kind steel-plastics composite pipe production technology can become, it is very fast that cost is improved, and uses less.In middle large diameter steel pipe is anticorrosion, uses more aseptic technic and be: outer wall of steel pipe adopts 2PE or 3PE anticorrosive coat, and the steel pipe inwall adopts the epoxy powder anti-corrosion layer, and these two kinds of anticorrosive coats all have the technology of comparative maturity.But at present generally can not be to epoxy powder, outer 2PE or 3PE anticorrosive coat in adopting simultaneously inside and outside the steel pipe, also need to adopt two production lines separately to make even adopt, and effect is bad, for example after skin is carried out the 3PE anticorrosive coat, when carrying out the internal layer spraying again, thickness can only reach below the 100 μ m, and the thickness of interior anticorrosive coat just can play antiseptic effect more than will reaching 300 μ m.So at present domestic founded a capital and anticorrosion most of pipeline of building is only done outside do not done interior anticorrosion.Also has a kind of new internal and external anti-corrosive layer process, at the outer 3PE anticorrosion structure that adopts of steel pipe, internal layer has adopted liquid epoxy coating, because of liquid epoxy coating can be constructed at normal temperatures, therefore solved inside and outside can not simultaneously treated problem, but also there is more shortcoming in this aseptic technic: one-pass film-forming thickness has only tens microns, needs repeatedly to spray just can reach desired thickness the technology trouble; Film forming thickness is low, and its antiseptic property is very poor, generally can only use as the drag reduction coating; Still to construct in two steps, promptly carry out outer 3PE anticorrosive coat earlier, remove to spray liquid epoxy again.West-East National Gas Transmission Project adopts this anticorrosion structure and technology exactly, and the outer 3PE anticorrosive coat that is prefabricated in the factory carry out on-the-spot internal layer liquid epoxy spraying application again after pipeline connects, and undercoating also is to use as the drag reduction coating.
3, summary of the invention:
The objective of the invention is to consider the problems referred to above and provide a kind of and on a production line, adopt 2PE or 3PE anticorrosive coat, inwall to adopt the production method of the internal and external anti-corrosive steel-plastics composite pipe that favorable anti-corrosion effect, technology are simple, cost is low of FBE to outer wall of steel pipe simultaneously.
In order to address the above problem, the present invention is achieved through the following technical solutions: production method of the present invention includes the following step:
1) steel pipe with passed examination enters production line by last pipe platform (1);
2) by preheating device (2) steel pipe is carried out preheating;
3) be transported to derusting device in the steel pipe (3) by transmission line after the steel pipe preheating steel pipe inwall is carried out processing of rust removing;
4) by heater (6) steel pipe is carried out preheating again after the steel pipe rust cleaning;
5) steel pipe enters steel pipe inner spray coating device (7) to the pipe inner-wall spraying powdery paints;
6) enter outer rust cleaning unit (10) behind the pipe coating outer wall of steel pipe is carried out outer rust cleaning;
7) by extruding glue-line device (15) and extruding plastic bed device (16) outer wall of steel pipe is pushed outer glue-line and extruding outer plastic layer successively continuously after the outer rust cleaning;
8) by cooling device (17) steel pipe is cooled off, promptly get the internal and external anti-corrosive steel-plastics composite pipe;
Wherein above-mentioned steps 5) behind the pipe inner-wall spraying powdery paints, powdery paints is heating and curing by solidification equipment (8).
Above-mentioned steps 4) after the steel pipe inwall is eliminated rust, also pipeline is carried out internal sweep and the absorption of inner surface micronic dust by interior blow device (4) and inner surface micronic dust adsorbent equipment (5); Step 6) is also carried out internal sweep and the absorption of outer surface micronic dust to pipeline by interior blow device (11) and outer surface micronic dust adsorbent equipment (12) again after outer wall of steel pipe is eliminated rust.
Above-mentioned preheating device (2), heater (6) and heater (13) add thermal recovery Frequency Induction Heating, gas furnace heating, oil burner heating or flame heat to steel pipe, and preheating device (2), heater (6) and heater (13) are provided with automatic temperature control apparatus.
Blow device (4), inner surface micronic dust adsorbent equipment (5), steel pipe inner spray coating device (7) carry out being provided with feedback device (9) behind internal sweep, the absorption of inner surface micronic dust and the pipe inner-wall spraying to pipeline respectively in above-mentioned.
Above-mentioned have the pin hole checkout gear in steel pipe behind the dusty spray, after outer dusty spray and the steel pipe cooling; Above-mentioned steps 8) can carry out the adverse slope mouth by falling beveling machine (18) to the external anti-corrosion layer at cooled steel pipe two ends; Whether the steel pipe behind the adverse slope mouth can qualified by checking that platform (19) detects.
Above-mentioned is 40~80 ℃ to the temperature of carrying out preheating before the rust cleaning of the inside and outside wall of steel pipe; To the temperature of carrying out preheating before the spraying in the steel pipe is 160~250 ℃; To the temperature that heats before the outer spraying of steel pipe is 160~250 ℃; The temperature that is heating and curing behind the above-mentioned pipe inner-wall spraying powdery paints is 160~250 ℃; After the above-mentioned steel pipe surfaces externally and internally rust cleaning pipeline surfaces externally and internally cleannes are reached more than the Sa2 level, depth of abrasion pattern reaches 40~100 μ m.
Compared with prior art, the invention has the beneficial effects as follows: production method of the present invention can realize adopting 2PE or 3PE anticorrosive coat, inwall to adopt FBE to outer wall of steel pipe on a production line simultaneously, the technology of production method of the present invention is simple, cost is low, and is good in economic efficiency.And the inside and outside anticorrosive coating of the steel pipe of producing is best at present inside and outside anticorrosive coating assembled scheme, and its antiseptic effect is splendid.
4, description of drawings:
Fig. 1 is the structural representation of the used production equipment of production method of the present invention.
5, the specific embodiment:
Embodiment:
The production method of internal and external anti-corrosive steel-plastics composite pipe of the present invention, it includes the following step:
1) steel pipe with passed examination enters production line by last pipe platform 1;
2) carry out preheating by 2 pairs of steel pipes of preheating device;
3) be transported to by transmission line after the steel pipe preheating that 3 pairs of steel pipe inwalls of derusting device carry out processing of rust removing in the steel pipe;
4) carry out preheating by 6 pairs of steel pipes of heater again after the steel pipe rust cleaning;
5) steel pipe enters 7 pairs of pipe inner-wall spraying powdery paints of steel pipe inner spray coating device;
6) enter 10 pairs of outer wall of steel pipe of outer rust cleaning unit behind the pipe coating and carry out outer rust cleaning;
7) push outer glue-line and extruding outer plastic layer successively continuously by extruding glue-line device 15 and 16 pairs of outer wall of steel pipe of extruding plastic bed device after the outer rust cleaning;
8) by cooling device 17 steel pipe is cooled off, promptly get the internal and external anti-corrosive steel-plastics composite pipe after the last passed examination, this is the internal and external anti-corrosive steel-plastics composite pipe of outer 2PE, interior epoxy powder.
For obtaining the internal and external anti-corrosive steel-plastics composite pipe of outer 3PE, interior epoxy powder, above-mentioned steps 6) outside to steel pipe the rust cleaning after, also can heat, carry out spray coating powder paint by 14 pairs of steel pipes of outer spray coating device by 13 pairs of steel pipes of heater, carry out the extruding glue-line and the plastic layer of step 7) again, can obtain the anti-corrosive steel tube of outer 3PE, interior epoxy powder.In the present embodiment, above-mentioned preheating device 2, heater 6 and 13 pairs of steel pipe heating of heater can be adopted Frequency Induction Heating, gas furnace heating, oil burner heating or flame heat, and preheating device 2, heater 6 and heater 13 are provided with automatic temperature control apparatus.
For making the inner-wall spraying powder curing effective, above-mentioned steps 5) behind the pipe inner-wall spraying powdery paints, also can be heating and curing by 8 pairs of powdery paints of solidification equipment.In the present embodiment, solidification equipment 8 can be heating furnace.
Above-mentioned steps 4) after the steel pipe inwall is eliminated rust, also can carry out internal sweep and the absorption of inner surface micronic dust by interior blow device 4 and 5 pairs of pipelines of inner surface micronic dust adsorbent equipment; Step 6) also can be carried out internal sweep and the absorption of outer surface micronic dust to pipeline by interior blow device 11 and outer surface micronic dust adsorbent equipment 12 again after outer wall of steel pipe is eliminated rust.
Blow device 4, inner surface micronic dust adsorbent equipment 5, steel pipe inner spray coating device 7 carry out being provided with feedback device 9 behind internal sweep, the absorption of inner surface micronic dust and the pipe inner-wall spraying to pipeline respectively in above-mentioned, reprocess so that the disqualified upon inspection steel pipe is return.
Above-mentioned steel pipe inner spray coating device 7 also is respectively equipped with pin hole checkout gear 20 in to steel pipe behind the dusty spray, after 17 pairs of steel pipes coolings of cooling device, so that coating quality is detected.
Above-mentioned steps 8) can carry out the adverse slope mouth by falling beveling machine 18 to the external anti-corrosion layer at cooled steel pipe two ends, so that pipeline construction.Whether the steel pipe behind the adverse slope mouth can qualified by checking that platform 19 detects.
Above-mentioned is 40~80 ℃ to the temperature of carrying out preheating before the rust cleaning of the inside and outside wall of steel pipe; To the temperature of carrying out preheating before the spraying in the steel pipe is 160~250 ℃; To the temperature that heats before the outer spraying of steel pipe is 160~250 ℃; The temperature that is heating and curing behind the above-mentioned pipe inner-wall spraying powdery paints is 160~250 ℃; After the above-mentioned steel pipe surfaces externally and internally rust cleaning pipeline surfaces externally and internally cleannes are reached more than the Sa2 level, depth of abrasion pattern reaches 50~100 μ m.
The production equipment of internal and external anti-corrosive steel-plastics composite pipe of the present invention, include pipe platform 1, preheating device 2, derusting device 3 in the steel pipe, heater 6, steel pipe inner spray coating device 7, outer rust cleaning unit 10, extruding glue-line device 15, extruding plastic bed device 16, cooling device 17, wherein preheating device 2 places between pipe platform 1 and the interior derusting device 3 of steel pipe, steel pipe inner spray coating device 7 places the side of heater 6, extruding plastic bed device 16 places the side of extruding glue-line device 15, and eliminate rust outward unit 10 and cooling device 17 place extruding glue-line device 15 respectively, the front side of extruding plastic bed device 16 and rear side.
Also be provided with heater 13 that steel pipe is heated and the outer spray coating device 14 that steel pipe is carried out spray coating powder paint between above-mentioned outer rust cleaning unit 10 and the extruding glue-line device 15; The side of steel pipe inner spray coating device 7 also can be provided with the solidification equipment 8 that powdery paints is heating and curing; The side of derusting device 3 also can be provided with interior blow device 4 and the inner surface micronic dust adsorbent equipment 5 that pipeline is carried out internal sweep and the absorption of inner surface micronic dust in the steel pipe; The side of outer rust cleaning unit 10 also can be provided with interior blow device 11 and the outer surface micronic dust adsorbent equipment 12 that pipeline is carried out internal sweep and the absorption of outer surface micronic dust; The side of blow device 4, inner surface micronic dust adsorbent equipment 5, steel pipe inner spray coating device 7 also is provided with feedback device 9 in above-mentioned; Also be respectively equipped with pin hole checkout gear 20 behind above-mentioned steel pipe inner spray coating device 7 backs, the cooling device 17; The side of cooling device 17 also is provided with the inspection platform 19 that falls beveling machine 18 and steel pipe is detected that the external anti-corrosion layer that cools off steel pipe two ends, back is carried out the adverse slope mouth.

Claims (6)

1, a kind of production method of internal and external anti-corrosive steel-plastics composite pipe includes the following step:
1) steel pipe with passed examination enters production line by last pipe platform (1);
2) by preheating device (2) steel pipe is carried out preheating;
3) be transported to derusting device in the steel pipe (3) by transmission line after the steel pipe preheating steel pipe inwall is carried out processing of rust removing;
4) by heater (6) steel pipe is carried out preheating again after the steel pipe rust cleaning;
5) steel pipe enters steel pipe inner spray coating device (7) to the pipe inner-wall spraying powdery paints;
6) enter outer rust cleaning unit (10) behind the pipe coating outer wall of steel pipe is carried out outer rust cleaning;
7) by extruding glue-line device (15) and extruding plastic bed device (16) outer wall of steel pipe is pushed outer glue-line and extruding outer plastic layer successively continuously after the outer rust cleaning;
8) by cooling device (17) steel pipe is cooled off, promptly get the internal and external anti-corrosive steel-plastics composite pipe;
It is characterized in that above-mentioned steps 5) behind the pipe inner-wall spraying powdery paints, powdery paints is heating and curing by solidification equipment (8).
2, the production method of internal and external anti-corrosive steel-plastics composite pipe according to claim 1, it is characterized in that above-mentioned steps 4) after the steel pipe inwall is eliminated rust, also pipeline is carried out internal sweep and the absorption of inner surface micronic dust by interior blow device (4) and inner surface micronic dust adsorbent equipment (5); Step 6) is also carried out internal sweep and the absorption of outer surface micronic dust to pipeline by interior blow device (11) and outer surface micronic dust adsorbent equipment (12) again after outer wall of steel pipe is eliminated rust.
3, the production method of internal and external anti-corrosive steel-plastics composite pipe according to claim 1 and 2, it is characterized in that above-mentioned preheating device (2), heater (6) and heater (13) add thermal recovery Frequency Induction Heating, gas furnace heating, oil burner heating or flame heat to steel pipe, preheating device (2), heater (6) and heater (13) are provided with automatic temperature control apparatus.
4, the production method of internal and external anti-corrosive steel-plastics composite pipe according to claim 3 is characterized in that above-mentioned interior blow device (4), inner surface micronic dust adsorbent equipment (5), steel pipe inner spray coating device (7) carry out being provided with feedback device (9) behind internal sweep, the absorption of inner surface micronic dust and the pipe inner-wall spraying to pipeline respectively.
5, the production method of internal and external anti-corrosive steel-plastics composite pipe according to claim 4 is characterized in that above-mentionedly in steel pipe behind the dusty spray, after outer dusty spray and the steel pipe cooling pin hole checkout gear being arranged; Above-mentioned steps 8) can carry out the adverse slope mouth by falling beveling machine (18) to the external anti-corrosion layer at cooled steel pipe two ends; Whether the steel pipe behind the adverse slope mouth can qualified by checking that platform (19) detects.
6, the production method of internal and external anti-corrosive steel-plastics composite pipe according to claim 4 is characterized in that above-mentioned is 40~80 ℃ to the temperature of carrying out preheating before the rust cleaning of the inside and outside wall of steel pipe; To the temperature of carrying out preheating before the spraying in the steel pipe is 160~250 ℃; To the temperature that heats before the outer spraying of steel pipe is 160~250 ℃; The temperature that is heating and curing behind the above-mentioned pipe inner-wall spraying powdery paints is 160~250 ℃; After the above-mentioned steel pipe surfaces externally and internally rust cleaning pipeline surfaces externally and internally cleannes are reached more than the Sa2 level, depth of abrasion pattern reaches 40~100 μ m.
CNB2004100153183A 2004-02-10 2004-02-10 Method and apparatus for producing inside and outside anticorrosion steel-plastic composite pipe Expired - Fee Related CN1321798C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2004100153183A CN1321798C (en) 2004-02-10 2004-02-10 Method and apparatus for producing inside and outside anticorrosion steel-plastic composite pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2004100153183A CN1321798C (en) 2004-02-10 2004-02-10 Method and apparatus for producing inside and outside anticorrosion steel-plastic composite pipe

Publications (2)

Publication Number Publication Date
CN1557624A CN1557624A (en) 2004-12-29
CN1321798C true CN1321798C (en) 2007-06-20

Family

ID=34351415

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004100153183A Expired - Fee Related CN1321798C (en) 2004-02-10 2004-02-10 Method and apparatus for producing inside and outside anticorrosion steel-plastic composite pipe

Country Status (1)

Country Link
CN (1) CN1321798C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102582165A (en) * 2012-01-18 2012-07-18 绵阳东方特种工程塑料有限公司 Composite steel belt and manufacturing method thereof

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1327979C (en) * 2005-02-28 2007-07-25 王筱均 Method of rust cleaning, scale removing, film coating and corrosion preventing for large and middle sized pipeline inside wall
KR100887710B1 (en) * 2008-10-30 2009-03-11 남궁영 The aluminum tube and process for producing same
CN101862725A (en) * 2010-06-03 2010-10-20 鼎顺钢塑管设备材料(杭州)有限公司 Steel-plastic composite pipe spraying device
CN105457784B (en) * 2014-08-27 2017-12-19 蚌埠市志诚涂装设备科技有限公司 A kind of full-automatic small-bore plastic-coated steel spray-painting production line
CN104500865A (en) * 2014-12-23 2015-04-08 浙江铭仕不锈钢有限公司 Outer weld stainless steel plastic composite pipe
CN104668913B (en) * 2015-03-18 2017-03-01 浙江久立泰祜涂层技术有限公司 The manufacturing equipment of stainless steel tube three-layer polypropylene anti-corrosion pipe and its using method
CN104907239A (en) * 2015-05-26 2015-09-16 成都高普石油工程技术有限公司 Oil pipeline powder inner spraying method
CN106077128B (en) * 2016-06-01 2018-08-17 深圳弘国林科技有限公司 A kind of manufacturing method and its production line of resinous coat aluminum pipe
CN106179806A (en) * 2016-09-13 2016-12-07 天津友发管道科技股份有限公司 A kind of pipe plastic coating apparatus for production line
CN107035756B (en) * 2017-05-19 2023-07-21 江苏中成紧固技术发展股份有限公司 Wind-powered electricity generation crab-bolt antiseptic treatment system based on automatic assembly line

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2038052U (en) * 1988-12-10 1989-05-24 北京市市政工程研究所 Multiunit tube with aluminate concrete and sheet steel
CN1051075A (en) * 1989-10-17 1991-05-01 王理泉 Metal-glass (glaze) heat spray composite anti-corrosive pipeline
CN2489164Y (en) * 2001-08-10 2002-05-01 李志雄 Steel plastic composite pipe with internal external anticorrosive coating
CN1417507A (en) * 2001-11-08 2003-05-14 李志雄 Production process of composite plastic-steel pipe with anti-corrosive coating
CN2681889Y (en) * 2004-02-10 2005-03-02 广州励进新技术有限公司 Device for producing inner/outer anticorrosion steel plastic composite pipe

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2038052U (en) * 1988-12-10 1989-05-24 北京市市政工程研究所 Multiunit tube with aluminate concrete and sheet steel
CN1051075A (en) * 1989-10-17 1991-05-01 王理泉 Metal-glass (glaze) heat spray composite anti-corrosive pipeline
CN2489164Y (en) * 2001-08-10 2002-05-01 李志雄 Steel plastic composite pipe with internal external anticorrosive coating
CN1417507A (en) * 2001-11-08 2003-05-14 李志雄 Production process of composite plastic-steel pipe with anti-corrosive coating
CN2681889Y (en) * 2004-02-10 2005-03-02 广州励进新技术有限公司 Device for producing inner/outer anticorrosion steel plastic composite pipe

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102582165A (en) * 2012-01-18 2012-07-18 绵阳东方特种工程塑料有限公司 Composite steel belt and manufacturing method thereof
CN102582165B (en) * 2012-01-18 2015-07-15 绵阳东方特种工程塑料有限公司 Composite steel belt and manufacturing method thereof

Also Published As

Publication number Publication date
CN1557624A (en) 2004-12-29

Similar Documents

Publication Publication Date Title
CN1321798C (en) Method and apparatus for producing inside and outside anticorrosion steel-plastic composite pipe
CN102698940A (en) Process for machining steel pipe with epoxy and polyester anticorrosive coatings on inner and outer walls
CN102202867A (en) Aluminum tube and method for manufacturing same
US20140147600A1 (en) Method and Apparatus for Lining Pipe and Similar Structures
CN111841987B (en) Continuous processing system and processing method for heat exchange tube with anti-corrosion non-stick coating
CN101637983A (en) Metallurgical bonding composite steel pipe, manufacturing method and manufacturing device thereof
CN109127316A (en) A kind of welded still pipe outer surface epoxy layer antisepsis production line and anticorrosion process
CN106076790A (en) More than DN1400mm large-diameter steel pipe inside and outside wall Anticorrosion measure
CN103418537A (en) Internal powder spraying process for petroleum tubes
CN107186433A (en) Interior surfacing anti-corrosive abrasion-proof oil conduit and processing method, process equipment
CN108787264A (en) Welding epoxy coating antisepsis production line and anticorrosion process in a kind of welded still pipe
CN106077128B (en) A kind of manufacturing method and its production line of resinous coat aluminum pipe
CN101191577A (en) Polyethylene coating steel pipe and its producing method and production line
CN103256435A (en) Double-coating steel tube
CN110976252A (en) Surface treatment process of corrosion-resistant alloy seamless steel pipe
JP5353297B2 (en) Polyolefin powder lining steel pipe
CN202290476U (en) Inner and outer wall spray coating system of fusion bonded epoxy powder steel pipe
CN107511316A (en) A kind of conveyance conduit bend pipe inner coating process
CN101864567B (en) Casting rolling roller surface treatment method of aluminum casting rolling machine
CN103659183B (en) A kind of manufacture method of anti-corrosion concentric reducer pipe fitting
CN2681889Y (en) Device for producing inner/outer anticorrosion steel plastic composite pipe
CN206139380U (en) Large -diameter steel pipe inside and outside wall anticorrosion production line more than DN1400mm
CN102829280B (en) Compound expansion joint capable of resisting strong corrosive medium and preparation method
CN201361597Y (en) Integrated heating, powder-spraying and film-forming device for internal wall of steel tube
CN212603557U (en) Modular skid-mounted 3 PE/epoxy powder anti-corrosion pipe production line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20070620

Termination date: 20150210