CN212603557U CN201921102138.7U CN201921102138U CN212603557U CN 212603557 U CN212603557 U CN 212603557U CN 201921102138 U CN201921102138 U CN 201921102138U CN 212603557 U CN212603557 U CN 212603557U
Authority
CN
China
Prior art keywords
module
pipe
transmission line
spiral transmission
production line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921102138.7U
Other languages
Chinese (zh)
Inventor
孙旭东
王峰宾
孟宪俐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Xudong Dingsheng Pipeline Equipment Manufacturing Co ltd
Langfang Dingsheng Mechanical Equipment Co ltd
Original Assignee
Tianjin Xudong Dingsheng Pipeline Equipment Manufacturing Co ltd
Langfang Dingsheng Mechanical Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Xudong Dingsheng Pipeline Equipment Manufacturing Co ltd, Langfang Dingsheng Mechanical Equipment Co ltd filed Critical Tianjin Xudong Dingsheng Pipeline Equipment Manufacturing Co ltd
Priority to CN201921102138.7U priority Critical patent/CN212603557U/en
Application granted granted Critical
Publication of CN212603557U publication Critical patent/CN212603557U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Application Of Or Painting With Fluid Materials (AREA)

Abstract

A modularized skid-mounted 3 PE/epoxy powder anti-corrosion pipe production line relates to the field of anti-corrosion pipe production. The modularized skid-mounted 3 PE/epoxy powder anti-corrosion pipe production line comprises a first spiral transmission line module, a pipe inlet rack module, a second spiral transmission line module, a flame preheating furnace module, a steel pipe outer wall shot blasting deruster module, a dust remover module, a trolley module blown in the pipe, a dust recovery trolley module blown in the pipe, a medium-frequency heating module, a spraying extruder module, a cooling module, a pipe end processing module, an electronic control module, a water cooling processing module, the medium-frequency heating module and the spraying extrusion module are connected, the cooling module is arranged on one side if the water cooling processing module is arranged, the pipe end processing module is arranged on one side of the water cooling processing module, and the electronic control module is arranged on the side of the dust. After the technical scheme is adopted, the beneficial effects of the utility model are that: the device has the advantages of reasonable design, rapid and quick field installation, direct service on construction sites, high efficiency, investment saving, high quality and the like.

Description

Modular skid-mounted 3 PE/epoxy powder anti-corrosion pipe production line
Technical Field
The utility model relates to an anticorrosive pipe production field, concretely relates to modularization sled dress 3PE epoxy anticorrosion pipe production line.
Background
In order to prevent corrosion, the outer wall of the oil and gas transmission pipeline is usually coated with an epoxy powder + adhesive + polyethylene (3PE) or epoxy powder (single-layer or multi-layer) anticorrosive coating. In the transportation of the anti-corrosion pipe, the steel pipe after corrosion prevention needs to be protected, and the anti-corrosion layer of the steel pipe is prevented from being damaged. When the anticorrosion pipes produced in factories are transported to a construction site, the anticorrosion pipes need to be lifted and placed by various transportation means, so that the surfaces of the anticorrosion pipes are difficult to damage, the on-site repair quantity of the anticorrosion pipes on the site is overlarge, and the anticorrosion quality of the anticorrosion pipes is reduced. In the operation process of the conveying pipeline, the corrosion-resistant pipe is partially corroded due to the reduction of the corrosion-resistant quality, and the pipeline leakage is caused. The service life of the pipeline is greatly reduced, unpredictable harm is caused, and the maintenance cost of the pipeline is increased.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to prior art's defect and not enough, provide a modularization sled dress 3PE epoxy powder anti-corrosion pipe production line, its reasonable in design through the modularization mode, makes up into one set of complete equipment according to technology order with the integration of a whole set of 3PE epoxy powder anti-corrosion pipe production line, and the field installation is swift rapidly, can directly serve construction site, has characteristics such as efficient, the investment is economized, the quality is excellent.
In order to achieve the above purpose, the utility model adopts the following technical scheme: the device comprises a first spiral transmission line module 1, a pipe inlet rack module 2, a second spiral transmission line module 3, a flame preheating furnace module 4, a steel pipe outer wall shot blasting deruster module 5, a dust remover module 6, an in-pipe sweeping trolley module 7, an in-pipe sweeping dust recovery trolley module 8, a medium-frequency heating module 9, a spraying extruder module 10, a cooling module 11, a pipe end processing module 12, an electric control module 13 and a water cooling processing module 14, wherein the first spiral transmission line module 1 and the second spiral transmission line module 3 are consistent in structure, the first spiral transmission line module 1 or the second spiral transmission line module 3 is fixedly connected with the pipe inlet rack module 2, one side of the flame preheating furnace module 4 is provided with the steel pipe outer wall shot blasting deruster module 5, the other side of the flame preheating furnace module 4 is provided with the dust remover module 6, the pipe inlet rack module 2 is arranged between the in-pipe sweeping trolley module 7 and the in-pipe sweeping dust recovery, the medium-frequency heating module 9 is connected with the spraying extruder module 10, one side of the cooling module 11 is provided with a water cooling processing module 14, the pipe end processing module 12 is arranged on one side of the water cooling processing module 14, and the electric control module 13 is arranged on the side of the dust remover module 6.
The electric control module 13 is an electric control system of the production line.
The utility model discloses a theory of operation: the whole set of anti-corrosion production line adopts a container form, the anti-corrosion pipe production line is modularly installed inside the container according to the functions of the anti-corrosion pipe production line, the anti-corrosion pipe production line can be quickly installed on site and can be used for producing the anti-corrosion pipes, the adaptive pipe diameter is DN100-DN1000, and the pipe length is 8m-12 m. The steel pipe enters an anticorrosive pipe production line from the pipe inlet rack module after passing through the first spiral transmission line module, and is conveyed to the steel pipe outer wall shot blasting derusting machine module through the flame preheating furnace module after passing through the second spiral transmission line module to carry out shot blasting derusting operation and surface dust treatment on the outer wall of the steel pipe; after the outer wall of the steel pipe is derusted, the steel pipe is conveyed to a sweeping rack through a second spiral transmission line module, the interior of the derusted steel pipe is cleaned through two in-pipe sweeping trolley modules, and the cleaned steel pipe is subjected to derusting inspection and pipe end pasting on the subsequent rack; conveying the cleaned steel pipe to a medium-frequency heating module through a spiral transmission line module to heat the steel pipe, conveying the steel pipe to a spraying extruder module to spray epoxy powder on the surface of the pipe body, extruding and winding the AD adhesive and PE on the surface of the steel pipe, and cooling the steel pipe coated with an anticorrosive layer through a cooling module to finish coating the anticorrosive layer on the surface of the steel pipe; the steel pipe after the anticorrosion is finished is processed through the pipe end processing module, harmful substances of the steel pipe are processed through the dust remover module, and a finished product pipe is formed after the operation is finished.
After the technical scheme is adopted, the utility model discloses beneficial effect does: 1. the system consists of independent functional modules, and the modules can be adjusted and decreased randomly according to production requirements; 2. the field installation is rapid and convenient, only a flat hardened terrace is needed, and foundation pits and ground feet are not needed to be installed; 3. because no factory building and foundation treatment are needed, the field installation is rapid and quick, the anti-corrosion pipe can be rapidly produced, the investment is saved, and better economic benefit is achieved. The utility model relates to a rationally, through the modularization mode, make up into one set of complete equipment according to the technology order with the integration of a whole set of 3PE epoxy powder anticorrosive pipe production line, the field installation is swift rapidly, can directly serve construction site, has characteristics such as efficient, the investment is economized, the quality is excellent.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without inventive exercise.
Fig. 1 is a functional block diagram of the present invention;
fig. 2 is a process flow diagram of the present invention.
Description of reference numerals: the device comprises a first spiral transmission line module 1, a pipe inlet rack module 2, a second spiral transmission line module 3, a flame preheating furnace module 4, a steel pipe outer wall shot blasting deruster module 5, a dust remover module 6, an in-pipe sweeping trolley module 7, an in-pipe sweeping dust recovery trolley module 8, a medium-frequency heating module 9, a spraying extruder module 10, a cooling module 11, a pipe end processing module 12, an electric control module 13 and a water cooling processing module 14.
Detailed Description
Referring to fig. 1 to 2, the technical solution adopted by the present embodiment is: the device comprises a first spiral transmission line module 1, a pipe inlet rack module 2, a second spiral transmission line module 3, a flame preheating furnace module 4, a steel pipe outer wall shot blasting deruster module 5, a dust remover module 6, an in-pipe sweeping trolley module 7, an in-pipe sweeping dust recycling trolley module 8, a medium-frequency heating module 9, a spraying extruder module 10, a cooling module 11, a pipe end processing module 12, an electric control module 13 and a water cooling processing module 14, wherein the pipe inlet rack module 2 is connected beside the first spiral transmission line module 1, the first spiral transmission line module 1 and the second spiral transmission line module 2 are consistent in structure, the first spiral transmission line module 1, the second spiral transmission line module 3 and the pipe inlet rack module 2 are arranged in the whole production line in a penetrating manner, the steel pipe outer wall shot blasting deruster module 5 is arranged on the left side of the flame preheating furnace module 4, the dust remover module 6 is arranged on the other side of the flame preheating furnace module 4, an inlet pipe rack module 2 is arranged between the in-pipe sweeping trolley module 7 and the in-pipe sweeping dust recovery trolley module 8, the intermediate frequency heating module 9 is connected with the spraying extruder module 10, a water cooling processing module 14 is arranged beside the cooling module 11, a pipe end processing module 12 is arranged beside the inlet pipe rack module 2, and an electric control module 13 is arranged beside the dust remover module 6. The whole set of anti-corrosion production line consists of containers with independent functional modules, has the advantage of convenient transportation, and can add or replace part of the functional modules if the production has special requirements. The field installation only needs to carry out plane hardening to the opposite face can, equipment connection is fixed with the bolt, and the electrical apparatus is connected with the form of pegging graft, and the installation is convenient rapidly.
The electric control module 13 is an electric control system of the production line, and the electric control module 13 provides electric power for the whole production line.
The utility model discloses a theory of operation: the whole set of anti-corrosion production line adopts a container form, the anti-corrosion pipe production line is modularly installed inside the container according to the functions of the anti-corrosion pipe production line, the anti-corrosion pipe production line can be quickly installed on site and can be used for producing the anti-corrosion pipes, the adaptive pipe diameter is DN100-DN1000, and the pipe length is 8m-12 m. After the steel pipe outer wall is derusted, the steel pipe is conveyed to a purging rack through the second spiral transmission line module, the steel pipe after derusting is internally cleaned through two in-pipe purging trolley modules, and the cleaned steel pipe is subjected to derusting inspection and pipe end pasting on the subsequent rack; conveying the cleaned steel pipe to a medium-frequency heating module through a spiral transmission line module to heat the steel pipe, conveying the steel pipe to a spraying extruder module to spray epoxy powder on the surface of the pipe body, extruding and winding the AD adhesive and PE on the surface of the steel pipe, and cooling the steel pipe coated with an anticorrosive layer through a cooling module to finish coating the anticorrosive layer on the surface of the steel pipe; the steel pipe after the anticorrosion is finished is processed through the pipe end processing module, harmful substances of the steel pipe are processed through the dust remover module, and a finished product pipe is formed after the operation is finished.
After the technical scheme is adopted, the utility model discloses beneficial effect does: 1. the device consists of independent functional modules, and can randomly adjust and decrease the modules according to production requirements: 2. the field installation is convenient rapidly, only needs smooth sclerosis terrace, does not need foundation ditch and lower margin installation: 3. because no factory building and foundation treatment are needed, the field installation is rapid and quick, the anti-corrosion pipe can be rapidly produced, the investment is saved, and better economic benefit is achieved. The utility model relates to a rationally, through the modularization mode, make up into one set of complete equipment according to the technology order with the integration of a whole set of 3PE epoxy powder anticorrosive pipe production line, the field installation is swift rapidly, can directly serve construction site, has characteristics such as efficient, the investment is economized, the quality is excellent.
The above description is only for the purpose of illustrating the technical solutions of the present invention and not for the purpose of limiting the same, and other modifications or equivalent replacements made by those of ordinary skill in the art to the technical solutions of the present invention should be covered within the scope of the claims of the present invention as long as they do not depart from the spirit and scope of the technical solutions of the present invention.

Claims (2)

1. Modularization sled dress 3PE epoxy powder anticorrosive pipe production line, its characterized in that: the device comprises a first spiral transmission line module (1), a pipe inlet rack module (2), a second spiral transmission line module (3), a flame preheating furnace module (4), a steel pipe outer wall shot blasting deruster module (5), a dust remover module (6), an in-pipe sweeping trolley module (7), an in-pipe sweeping dust recovery trolley module (8), an intermediate frequency heating module (9), a spraying extruder module (10), a cooling module (1), a pipe end processing module (12), an electric control module (13) and a water cooling processing module (14), wherein the first spiral transmission line module (1) and the second spiral transmission line module (3) are consistent in structure, the first spiral transmission line module (1) or the second spiral transmission line module (3) is fixedly connected with the pipe inlet rack module (2), the steel pipe outer wall shot blasting deruster module (5) is arranged on one side of the flame preheating furnace module (4), the other side of the flame preheating furnace module (4) is provided with a dust remover module (6), a pipe inlet rack module (2) is arranged between the in-pipe sweeping trolley module (7) and the in-pipe sweeping dust recovery trolley module (8), the intermediate frequency heating module (9) is connected with the spraying extruder module (10), one side of the cooling module (11) is provided with a water cooling processing module (14), the pipe end processing module (12) is arranged on one side of the water cooling processing module (14), and the electric control module (13) is arranged on the side of the dust remover module (6).
2. The modular skid-mounted 3 PE/epoxy powder corrosion-resistant pipe production line according to claim 1, wherein: the electric control module (13) is an electric control system of the production line.
CN201921102138.7U 2019-07-15 2019-07-15 Modular skid-mounted 3 PE/epoxy powder anti-corrosion pipe production line Active CN212603557U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921102138.7U CN212603557U (en) 2019-07-15 2019-07-15 Modular skid-mounted 3 PE/epoxy powder anti-corrosion pipe production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921102138.7U CN212603557U (en) 2019-07-15 2019-07-15 Modular skid-mounted 3 PE/epoxy powder anti-corrosion pipe production line

Publications (1)

Publication Number Publication Date
CN212603557U true CN212603557U (en) 2021-02-26

Family

ID=74728915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921102138.7U Active CN212603557U (en) 2019-07-15 2019-07-15 Modular skid-mounted 3 PE/epoxy powder anti-corrosion pipe production line

Country Status (1)

Country Link
CN (1) CN212603557U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110216906A (en) * 2019-07-15 2019-09-10 廊坊市鼎盛机械设备有限公司 Modularization skid 3PE/ epoxy powder anti-corrosion pipe production line

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110216906A (en) * 2019-07-15 2019-09-10 廊坊市鼎盛机械设备有限公司 Modularization skid 3PE/ epoxy powder anti-corrosion pipe production line

Similar Documents

Publication Publication Date Title
CN105413978B (en) A kind of parallel arrangement of tunnel synchronization spraying and cured processing method
CN103542197A (en) Anticorrosive coating production line and process for steel pipes
KR20110010571U (en) Automatic anti-corrosion coating process and production line for large size steel pipe
CN212603557U (en) Modular skid-mounted 3 PE/epoxy powder anti-corrosion pipe production line
CN102240630A (en) Process for coating small-diameter 3-polyurethane (PE) antiseptic steel tube
CN101823044A (en) Integration method of steel tube inner wall and outer wall powder spraying, curing and film-forming and device thereof
CN202911022U (en) Automatic production line for pipe fitting with plastic-coated inner and outer parts
CN202290476U (en) Inner and outer wall spray coating system of fusion bonded epoxy powder steel pipe
CN103256435A (en) Double-coating steel tube
CN105114708B (en) The processing method of anti-corrosion uvioresistant airbreak steel gas pipeline
CN110976252A (en) Surface treatment process of corrosion-resistant alloy seamless steel pipe
CN109248842A (en) Single layer, outer dual-layer epoxy powder spraying method in steel pipe
CN1321798C (en) Method and apparatus for producing inside and outside anticorrosion steel-plastic composite pipe
CN110216906A (en) Modularization skid 3PE/ epoxy powder anti-corrosion pipe production line
CN108187993A (en) Composite anti-corrosive coating process based on stainless steel
CN201361597Y (en) Integrated heating, powder-spraying and film-forming device for internal wall of steel tube
CN207266960U (en) Produce pond product ore deposit cleaning and recovery system
CN1704639A (en) Three-layer structured polypropylene anticorrosive technology for steel buried transportation pipe
CN203585589U (en) Coating production line preventing steel pipe from corrosion
CN215141187U (en) Double-layer epoxy powder spraying device for pipe fitting
CN112113040B (en) Anti-corrosion alloy pipe for fluid transportation and production method thereof
CN114653513A (en) Universal production process for epoxy resin plastic-coated steel pipe and petroleum special-purpose internal coating
CN104889040A (en) Integrated technology for anticorrosive coatings of steel pipelines
CN206855964U (en) A kind of plastic pipe cools down qualitative conveying device
CN201997447U (en) Full automatic inside and outside autophoresis treatment spraying assembly line

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant