CN1309210A - Technology for constructing drilled and cast-in-situ pile with protective clay wall - Google Patents

Technology for constructing drilled and cast-in-situ pile with protective clay wall Download PDF

Info

Publication number
CN1309210A
CN1309210A CN 01109971 CN01109971A CN1309210A CN 1309210 A CN1309210 A CN 1309210A CN 01109971 CN01109971 CN 01109971 CN 01109971 A CN01109971 A CN 01109971A CN 1309210 A CN1309210 A CN 1309210A
Authority
CN
China
Prior art keywords
constructing
cohesive soil
technology
drilled
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 01109971
Other languages
Chinese (zh)
Inventor
陈文玮
吕广荣
邓树生
肖专文
杨金钟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING UNIV CONSTRUCTION SUBWAY AND FOUNDATION MUNICIPAL ENGINEERING Co Ltd
Original Assignee
BEIJING UNIV CONSTRUCTION SUBWAY AND FOUNDATION MUNICIPAL ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING UNIV CONSTRUCTION SUBWAY AND FOUNDATION MUNICIPAL ENGINEERING Co Ltd filed Critical BEIJING UNIV CONSTRUCTION SUBWAY AND FOUNDATION MUNICIPAL ENGINEERING Co Ltd
Priority to CN 01109971 priority Critical patent/CN1309210A/en
Publication of CN1309210A publication Critical patent/CN1309210A/en
Pending legal-status Critical Current

Links

Abstract

A technology for constructing the drilled and cast-in-situ pile with protecting clay wall includes drilling, pulling up drilling rod, constructing the protecting wall, drilling again, and repeating said steps several times. Said constructing the protecting wall is to load clay into hole. Its advantages are preventing collapse of hole wall, high hole quality, low cost, and high construction speed.

Description

Technology for constructing drilled and cast-in-situ pile with protective clay wall
The present invention relates to a kind of drill-pouring pile forming technology.
Construction drill castinplace pile in sand pebble layer, its construction Difficulties is the pore-forming difficulty, is easy to generate the hole of collapsing.Though can creep into spiral drilling machine, if do not adopt wall protecting method, then drilling rod is proposed after because sand ovum layer is inviscid, boring can be caved in immediately.Existing construction technology adopts cement paste dado, wet work, cause the job site dirty and messy easily, cement material cost height need be acquired again and stir and conveying machinery, has not only improved construction costs, but also delayed the duration, it is excessive that human and material resources are dropped into, and causes waste, and this technical barrier is badly in need of solving.
The purpose of this invention is to provide a kind of technology for constructing drilled and cast-in-situ pile with protective clay wall, prevent hole wall collapse, and reduce construction costs, the reduction of erection time, improve construction environment, improve hole quality.
Technology for constructing drilled and cast-in-situ pile with protective clay wall method of the present invention is: hole, extract under drilling rod, retaining wall, the original position and bore, creep into, extract drilling rod, retaining wall, circulation several times, pore-forming again, it is characterized in that: its retaining wall and again retaining wall be to throw the cohesive soil hand-hole.
Above-mentioned cohesive soil comprises: cohesive soil, inferior cohesive soil or mix the cohesive soil of waste residue.
Above-mentioned cohesive soil is the plasticity state.
The method of above-mentioned input cohesive soil hand-hole is with manually or with machinery dropping into.
The technology for constructing drilled and cast-in-situ pile with protective clay wall step:
(1), boring;
(2), extract drilling rod;
(3), throw the cohesive soil hand-hole;
(4), bore under the original position;
(5), creep into again;
(6), extract drilling rod;
(7), throw the cohesive soil hand-hole again;
(8), the circulation several times, pore-forming.
Mechanism of the present invention: after clay dropped into, the drilling rod rotation drove the bit blades rotation, and cohesive soil is extruded, form the mud wall at hole wall, in the drilling rod rotary course, the granule sandy gravel is formed extruding simultaneously, thereby press to hole wall and make hole Zhou Mishi, reach the pore-forming purpose.
Advantage of the present invention: prevent hole wall collapse, dry construction, method is easy, and material is inexpensive, be easy to get, and need not acquire equipment, improves construction environment, improves hole quality, reduces construction costs, both saves money, and is laborsaving again, and speed of application is fast, the reduction of erection time.This technology is applicable in the hole depth scope to be the geological conditions of the sand pebble layer of few water.
Below in conjunction with embodiment the present invention is done detailed description:
Embodiment: after march into the arena earlier during construction unwrapping wire, the levelling, the displaced spirals rig, the drilling rod verticality is adjusted in drill bit stake position, finishes technology in place; In the rod boring process, because boring is in the sand pebble layer all the time, drilling rod is easily beated, shaking phenomenon, influences into hole perpendicularity, and therefore, this process must tightly be monitored with transit, and sets up control system, accomplishes in time to be controlled to hole perpendicularity.Creep into about 5 meters, extract drilling rod, Xiang Kongzhong drops into fat clay, and cohesive soil perusal hand is pinched into piece, lands and scatters.Then drilling rod is moved and move, restart to creep into, be drilled into about 7 meters to the foramen primum position.Extract drilling rod again, in the hole, drop into fat clay again, creep into again.The circulation several times reach designing requirement until hole depth.
During construction, produce when preventing that drilling rod from running into big particle diameter beat, stake biased from, the drilling rod of common spiral drilling machine needs to transform, and drilling rod is increased the weight of.Cohesive soil can comprise: cohesive soil, inferior cohesive soil or mix the cohesive soil of flyash equal industrial residue.The water content of retaining wall cohesive soil should be in the plasticity scope, and the perusal hand is pinched into piece, and landing scatters gets final product.

Claims (4)

1, a kind of technology for constructing drilled and cast-in-situ pile with protective clay wall, its technological process is: hole, extract under drilling rod, retaining wall, the original position and bore, creep into, extract drilling rod, retaining wall, circulation several times, pore-forming again, it is characterized in that: its retaining wall and again retaining wall be to throw the cohesive soil hand-hole.
2, technology for constructing drilled and cast-in-situ pile with protective clay wall according to claim 1 is characterized in that: described cohesive soil comprises: cohesive soil, inferior cohesive soil or mix the cohesive soil of waste residue.
3, technology for constructing drilled and cast-in-situ pile with protective clay wall according to claim 1 is characterized in that: described cohesive soil is the plasticity state.
4, technology for constructing drilled and cast-in-situ pile with protective clay wall according to claim 1 is characterized in that: the method for described input cohesive soil hand-hole is with manually or with machinery dropping into.
CN 01109971 2001-03-28 2001-03-28 Technology for constructing drilled and cast-in-situ pile with protective clay wall Pending CN1309210A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 01109971 CN1309210A (en) 2001-03-28 2001-03-28 Technology for constructing drilled and cast-in-situ pile with protective clay wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 01109971 CN1309210A (en) 2001-03-28 2001-03-28 Technology for constructing drilled and cast-in-situ pile with protective clay wall

Publications (1)

Publication Number Publication Date
CN1309210A true CN1309210A (en) 2001-08-22

Family

ID=4658252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 01109971 Pending CN1309210A (en) 2001-03-28 2001-03-28 Technology for constructing drilled and cast-in-situ pile with protective clay wall

Country Status (1)

Country Link
CN (1) CN1309210A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103061670A (en) * 2013-01-06 2013-04-24 中国建筑第六工程局有限公司 Structure for preventing collapse of boreholes in pebble bed and construction method thereof
CN108035340A (en) * 2017-12-19 2018-05-15 中冶成都勘察研究总院有限公司 A kind of sandy silt soil stratum construction process of bored concrete pile of low temperature high-moisture percentage
CN108797566A (en) * 2018-06-20 2018-11-13 河南竣祥岩土工程有限公司 Bored concrete pile retaining wall material and preparation method thereof and pouring pile hole construction technology in a kind of miscellaneous fill

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103061670A (en) * 2013-01-06 2013-04-24 中国建筑第六工程局有限公司 Structure for preventing collapse of boreholes in pebble bed and construction method thereof
CN103061670B (en) * 2013-01-06 2015-03-25 中国建筑第六工程局有限公司 Structure for preventing collapse of boreholes in pebble bed and construction method thereof
CN108035340A (en) * 2017-12-19 2018-05-15 中冶成都勘察研究总院有限公司 A kind of sandy silt soil stratum construction process of bored concrete pile of low temperature high-moisture percentage
CN108797566A (en) * 2018-06-20 2018-11-13 河南竣祥岩土工程有限公司 Bored concrete pile retaining wall material and preparation method thereof and pouring pile hole construction technology in a kind of miscellaneous fill

Similar Documents

Publication Publication Date Title
US4958962A (en) Methods of modifying the structural integrity of subterranean earth situs
CN1088283A (en) The grouting equipment of drifter drill for underground
CN103556628B (en) Spiral conical soil compaction pile construction method
CN105239561A (en) Long spiral mix spray pre-grouting press concrete post-inserted steel reinforcement cage cast-in-place pile construction process
US6183166B1 (en) Method of centrifugally forming a subterranean soil-cement casing
CN105297710A (en) High-pressure-jetting cement soil twist drill and reamed reinforced concrete grouting combined pile and manufacturing method
US6079906A (en) Method for making foundation piling with drilling machines
CN1173097C (en) Impervious wall construction and soilslip-resisting and leakage-blocking process
CN1309210A (en) Technology for constructing drilled and cast-in-situ pile with protective clay wall
US3191390A (en) Method of preparing subsurface and forming concrete column therein
CN1206417C (en) Forming method for water-proof pile fender and screw drill therefor
CN101914915A (en) Construction method for anti-floating anchor rod and special long auger
US3097492A (en) Method of forming concrete piles in situ
CN100374657C (en) Construction method employing threaded stirring shaft to decrease ambient foundation deformation
RU2054502C1 (en) Method for making cement/soil piles in caved-in soils
CN205100208U (en) Crowded, reaming reinforced concrete bored concrete pile composite pile of high water spray earth anger
JP3920974B2 (en) Earth auger excavator and construction method of deep underground column wall in collapsible gravel layer
JP4074198B2 (en) How to remove existing piles
KR100907275B1 (en) Process of Single Slab Deep Cement Mixing and Apparatus therefor
CN204023594U (en) A kind of water-stop curtain stake and water-stop curtain
CN2160679Y (en) Screw pipe-sinking base enlarging slurryinjector
CN205242418U (en) A campshed grafting stake board combining frame water blockoff diaphragm wall
CN2934354Y (en) Construction device for drill center pumping concrete to stake end and mortar intrusion for concrete perfusion stake
CN1127819A (en) Internal thread bored and cast-in-place pile series and construction method and equipment thereof
CN1115819A (en) Serial pile of screw drilling pouring pile of and their construction process and apparatus

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
AD01 Patent right deemed abandoned
C20 Patent right or utility model deemed to be abandoned or is abandoned