CN1259606A - Deep base pit sand pebble layer casing pipe hole forming technique - Google Patents

Deep base pit sand pebble layer casing pipe hole forming technique Download PDF

Info

Publication number
CN1259606A
CN1259606A CN 99116304 CN99116304A CN1259606A CN 1259606 A CN1259606 A CN 1259606A CN 99116304 CN99116304 CN 99116304 CN 99116304 A CN99116304 A CN 99116304A CN 1259606 A CN1259606 A CN 1259606A
Authority
CN
China
Prior art keywords
casing pipe
pipe hole
hole forming
forming technique
pebble layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 99116304
Other languages
Chinese (zh)
Inventor
陈永昌
黄文洲
欧阳霞
陈玉渊
张立松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
1st Engineering Co China Non-Ferrous Metal 15th Metallurgical Construction
Original Assignee
1st Engineering Co China Non-Ferrous Metal 15th Metallurgical Construction
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 1st Engineering Co China Non-Ferrous Metal 15th Metallurgical Construction filed Critical 1st Engineering Co China Non-Ferrous Metal 15th Metallurgical Construction
Priority to CN 99116304 priority Critical patent/CN1259606A/en
Publication of CN1259606A publication Critical patent/CN1259606A/en
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The present invention relates to new technology of forming hole used in architectural industry for deep foundation pit in gril pebble gravel layer by using casing pipe, the hole formation method is to use vibrating machine and drill to the deepest position, pull out the drilling rod, sink in steal casing pipe, then use geological drilling machine to drill hole to position, high pressure sealing and blocking underground water. It is quick in construction and advance in technology.

Description

A kind of deep base pit sand pebble layer casing pipe hole forming technique
The present invention relates to construction industry, is a kind of deep base pit sand pebble layer casing pipe hole forming technique.
The job practices that is used for antiseepage during present domestic ground is handled is impervious wall, high-pressure rotary-spray and grouting basically.High-pressure rotary-spray is since invention in the latter stage sixties, through constantly improving characteristics such as having possessed speed of application is fast, good seepage-proof property, construction safety; Grouting construction, domestic all is to use the geological drilling rig pore-forming, it can strengthen is irritated the body density, reduces the permeability of ground.
But the required expense costliness of impervious wall construction, and at K=10 -1Still there is not the successfully example of construction in the sand gravel stratum of CM/S; High-pressure rotary-spray is holed in sand gravel stratum as the employing geological drilling rig and is used the certain material retaining wall, then required long in time limit, expense is high, as adopt the swell soil retaining wall hole of then easily collapsing, influence the duration, as to adopt behind the vibrodrill pore-forming be churning, but be difficult to break through 20M again in the degree of depth that sand gravel stratum is holed; The geological drilling rig well cementing, its rate of penetration in sand gravel stratum is slow, and easily blocks drilling rod and be difficult to retaining wall.
The present invention will provide a kind of speed of application fast, reduces construction cost, is suitable for the casing pipe hole forming technique that deep base pit sand pebble layer is used.
Concrete scheme of the present invention is: at first adopt vibrodrill to be drilled into depth capacity, extract drilling rod then, sink to steel sleeve, re-use geological drilling rig boring and put in place, adopt existing high-pressure slip-casting blocking technology at last, shutoff underground water.
Speed of application of the present invention is fast, and technology advanced person has solved the difficult problem that single use vibrodrill can not be finished the deep foundation ditch pore-forming, and is faster than single use geological drilling rig progress again, improves work efficiency more than 60 times, saved a large amount of engineering times, reduced construction cost.
The utility model is described in further detail below in conjunction with accompanying drawing:
Accompanying drawing is a construction technology key diagram of the present invention.
Embodiment: at first according to the position, design arrangement hole, position, hole in the constructure scheme, begin dead man after adopting vibrodrill pore-forming to 20 meter then, in the dead man process, inject suitable quantity of water mud, being beneficial to down the step sinks between seamless steel sleeve pipe and the sand ovum gravel hole in and combines tightly, sink to steel sleeve (referring to accompanying drawing, its label is 1) and build the mouth of pipe with thing, do mark and be beneficial to the next procedure construction.The cement paste of stationary steel bushing pipe can begin with the punching of geology machine after certain intensity has been arranged.The geological drilling rig drilling rod is lowered in steel sleeve, and it is dark to be drilled into required mark, protects hole wall with swell soil, descend Grouting Pipe at the bottom of the hole then, again flushing liquor is changed into the cement paste that will irritate, return out from sleeve opening until low amounts of water mud, build the aperture sealer then, begin the slip casting that circulates, after the overfall amount is greater than 20L/min, begin to pressurize with pressure regulator valve, having under the condition of overfall, add to design pressure as early as possible, if do not reach design pressure for a long time, then calculate grout consumption, the slip casting ending standard is:
1. when overfall pressure reaches 1.5MPa (design pressure) and double reading less than 3L/min;
2. when overfall thickens;
3. when not reaching design pressure, when grout consumption reached 3l/m, grouting finished back tube drawing rapidly, and in filling process, Grouting Pipe will often be rotated, otherwise plugging easily, pipe laying.
Master operation of the present invention is: the cloth hole---vibrodrill pore-forming------geological drilling rig pore-forming---high-pressure slip-casting of imbedding steel sleeve.

Claims (1)

1. adopting a kind of deep base pit sand pebble layer casing pipe hole forming technique in construction industry, is to use earlier rig pore-forming, back high-pressure slip-casting shutoff, it is characterized in that: the rig pore-forming is to adopt vibrodrill to be drilled into depth capacity earlier, extract drilling rod then, sink to steel sleeve, re-use geological drilling rig boring and put in place.
CN 99116304 1999-01-01 1999-01-01 Deep base pit sand pebble layer casing pipe hole forming technique Pending CN1259606A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 99116304 CN1259606A (en) 1999-01-01 1999-01-01 Deep base pit sand pebble layer casing pipe hole forming technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 99116304 CN1259606A (en) 1999-01-01 1999-01-01 Deep base pit sand pebble layer casing pipe hole forming technique

Publications (1)

Publication Number Publication Date
CN1259606A true CN1259606A (en) 2000-07-12

Family

ID=5279134

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 99116304 Pending CN1259606A (en) 1999-01-01 1999-01-01 Deep base pit sand pebble layer casing pipe hole forming technique

Country Status (1)

Country Link
CN (1) CN1259606A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101985836A (en) * 2010-09-10 2011-03-16 广东省基础工程公司 Processing method of pile-wall type deep base pit supporting structure in case of encountering large boulder stone
CN102162335A (en) * 2011-02-10 2011-08-24 中煤矿山建设集团有限责任公司 A hole-forming method of drilling through an underground structure in an aquifer sand layer from the ground
CN103556645A (en) * 2013-09-29 2014-02-05 河北钢铁集团矿业有限公司 Method for forming grouting space in sand gravel layer
CN105649098A (en) * 2016-01-21 2016-06-08 中国能源建设集团安徽电力建设第工程有限公司 Multi-stage casing tube sand getting and boring method suitable for light well point precipitation of medium-coarse sand geology

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101985836A (en) * 2010-09-10 2011-03-16 广东省基础工程公司 Processing method of pile-wall type deep base pit supporting structure in case of encountering large boulder stone
CN101985836B (en) * 2010-09-10 2012-03-28 广东省基础工程公司 Processing method of pile-wall type deep base pit supporting structure in case of encountering large boulder stone
CN102162335A (en) * 2011-02-10 2011-08-24 中煤矿山建设集团有限责任公司 A hole-forming method of drilling through an underground structure in an aquifer sand layer from the ground
CN103556645A (en) * 2013-09-29 2014-02-05 河北钢铁集团矿业有限公司 Method for forming grouting space in sand gravel layer
CN103556645B (en) * 2013-09-29 2015-06-17 河北钢铁集团矿业有限公司 Method for forming grouting space in sand gravel layer
CN105649098A (en) * 2016-01-21 2016-06-08 中国能源建设集团安徽电力建设第工程有限公司 Multi-stage casing tube sand getting and boring method suitable for light well point precipitation of medium-coarse sand geology

Similar Documents

Publication Publication Date Title
US11214938B2 (en) Construction method for pouring concrete in karst cave
CN110230309B (en) Karst area bridge karst cave pile foundation construction method
CN100591866C (en) Drifting sand layer and gravel stratum water-moving double-liquid high pressure slip-casting water-blocking construction method
WO2018210019A1 (en) Pile formation method for down-the-hole impact rotary jet composite piles
CN103184734B (en) A kind of construction method implanting slip casting compound pile
CN100462507C (en) Construction method for pulling-resistant and pressure-resistant slip casting pipe pile
CN101525881B (en) Structure of karst strata pile holes protecting wall and method for constructing pile holes
CN102787602A (en) Curtain grouting technique
CN101270576A (en) Secondary segmenting slip casting method for miniature pile
CN101307695A (en) Coal mine gas pre-draining borehole sealing method adopting aerated capsule as temporary hole bottom
CN106320354A (en) Anti-seepage construction method for karst cave development stratum under overburden
CN102011399A (en) PHC pile-based multiple high jet pedestal pile construction method
CN107747312A (en) A kind of method of sand and gravel stratum well cementing construction
CN103088836A (en) Sedimentation control method for pumping water and performing reinjection in well casing simultaneously
CN112482364A (en) Construction process of rotary digging cast-in-place pile under strong corrosive soft geological conditions in coastal region
CN104762981A (en) Hole forming method of precipitation well
CN102011591A (en) Grouting process for working surface of deep well
CN101225740A (en) Annular filling method for space between freezing pipe and surrounding rock
CN107587502B (en) Construction method for rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile
CN104711973A (en) Construction method for small-diameter pile composite foundation
CN102418337A (en) New grouting method
CN101985836B (en) Processing method of pile-wall type deep base pit supporting structure in case of encountering large boulder stone
CN107653889A (en) A kind of shaped steel pressure is poured water the construction method of soil curtain support pile
CN102817361B (en) Double bushing top cover for broken rock curtain grouting and construction method of double bushing top cover
CN203960941U (en) A kind of artesian water water intake well

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication