CN1233695A - Process for producing seepage control bulk head by using mould vibrosinking method - Google Patents

Process for producing seepage control bulk head by using mould vibrosinking method Download PDF

Info

Publication number
CN1233695A
CN1233695A CN 99112187 CN99112187A CN1233695A CN 1233695 A CN1233695 A CN 1233695A CN 99112187 CN99112187 CN 99112187 CN 99112187 A CN99112187 A CN 99112187A CN 1233695 A CN1233695 A CN 1233695A
Authority
CN
China
Prior art keywords
limit
vibration
slurry
vibration template
vibrosinking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 99112187
Other languages
Chinese (zh)
Other versions
CN1101881C (en
Inventor
张灿峰
白永年
彭国强
王文秀
关德斌
杜希明
张圣国
姜宏勇
赵建民
张爱民
赵延龙
潘维宗
赵春和
赵春富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Huashui Hydroelectric Engineering Co., Ltd.
Original Assignee
SHANDONG BRANCH OF HUASHUI HYDROPOWER DEVELOPMENT GEN CORP CHINA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=5275516&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN1233695(A) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by SHANDONG BRANCH OF HUASHUI HYDROPOWER DEVELOPMENT GEN CORP CHINA filed Critical SHANDONG BRANCH OF HUASHUI HYDROPOWER DEVELOPMENT GEN CORP CHINA
Priority to CN 99112187 priority Critical patent/CN1101881C/en
Publication of CN1233695A publication Critical patent/CN1233695A/en
Application granted granted Critical
Publication of CN1101881C publication Critical patent/CN1101881C/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The processing technology of impervious siding wall by adopting vibrating and form-sinking processes is as follows: two vibrating forms are sunk underground, then fill slurry body mortar into the cavity of first form, the first form is vibrated, pulled with filling slurry body mortar at the same time until the form is drawn out of the ground surface, the slurry body mortar remains in the cavity underground; then sink the first form at the other side of the second form, and fill the cavity of second form with slurry body mortar the second form is vibrated pulled with filling slurry body mortar at the same time until the form is drawn out of the ground surface, the slurry body mortar remains in the cavity underground and connected together with the slurry body mortar remained before, continue to proceed the said process until the whole impervious siding wall is constructed.

Description

Process for producing seepage control bulk head by using mould vibrosinking
The present invention relates to the process for producing seepage control bulk head by using mould vibrosinking technical field.
Being used for the major defect that the technology of dykes and dams vertical seepage control exists at present is: the manufacturing process complexity, equipment investment is big, the construction costs height, stock utilization is low, in the construction energy consumption big, the project seepage controlling effect of making is undesirable, seam is not tight, speed of application is slow.
The objective of the invention is to invent a kind of process for producing seepage control bulk head by using mould vibrosinking, it makes two vibration templates be driven underground earlier, then cement injection mortar in first vibration template, then first vibromold edges of boards shake, pull out on the limit and limit grouting body, up to extracting ground, slurry stays in underground slotted eye, then first vibration template is sunk to the opposite side of second vibration template, and so successively back and forth said process is made the antiseepage board wall one.
The present invention is achieved in that earlier two vibration templates is assigned projected depth along the construction axis with sinking to, cement injection mortar in first vibration template immediately, then first vibromold edges of boards are shaken, pull out and limit grouting body on the limit, up to extracting ground, slurry stays in underground slotted eye, then first vibration template is sunk to the opposite side of second vibration template, again second vibration template filled with slurry, same limit shakes, the limit is pulled out with the limit and is in the milk body up to extracting ground, slurry stays in underground slotted eye and stays the slurry in underground slotted eye to couple together with last, then second vibration template sunk to first vibration template opposite side again, so successively back and forth said process is made seepage control bulk head by using mould vibrosinking one.
Advantage of the present invention is: construction technology is reliable, good engineering quality, the engineering unit price is cheap, and manufacturing process is simple, the construction equipment small investment, energy consumption is low, has improved work efficiency, has reduced construction cost, be connected reliable between plate and the plate, barrier performance improves greatly, short construction period, and antiseepage wallboard cost reduces greatly.
Below in conjunction with embodiment, the present invention will be further described:
Clamp first vibration template by the chuck on the stake machine assign projected depth with sinking at vibrating hammer effect lower edge construction axis, chuck clamps second vibration template after locating with first vibration template then, assign projected depth in the vibrating hammer effect with being lowered into, by grouting system cement mortar is filled with in first vibration template then, then first vibration template is shaken in stake machine vibration hammer effect bottom, pull out and limit grouting body on the limit, up to extracting ground, slurry stays in underground slotted eye, sink to the opposite side of second vibration template after then first vibration template being located, second vibration template filled with slurry, same limit shakes, the limit is pulled out with the limit and is in the milk body up to extracting ground, slurry stays in underground slotted eye and stays the slurry in underground slotted eye to couple together with last, then second vibration template sunk to first vibration template opposite side again, so successively back and forth said process is made seepage control bulk head by using mould vibrosinking one.

Claims (1)

1, process for producing seepage control bulk head by using mould vibrosinking, it is characterized in that: earlier two vibration templates are assigned projected depth along the construction axis with sinking to, cement injection mortar in first vibration template immediately, then first vibromold edges of boards are shaken, pull out and limit grouting body on the limit, up to extracting ground, slurry stays in underground slotted eye, then first vibration template is sunk to the opposite side of second vibration template, again second vibration template filled with slurry, same limit shakes, the limit is pulled out with the limit and is in the milk body up to extracting ground, slurry stays in underground slotted eye and stays the slurry in underground slotted eye to couple together with last, then second vibration template sunk to first vibration template opposite side again, so successively back and forth said process is made seepage control bulk head by using mould vibrosinking one.
CN 99112187 1999-04-22 1999-04-22 Process for producing seepage control bulk head by using mould vibrosinking method Expired - Lifetime CN1101881C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 99112187 CN1101881C (en) 1999-04-22 1999-04-22 Process for producing seepage control bulk head by using mould vibrosinking method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 99112187 CN1101881C (en) 1999-04-22 1999-04-22 Process for producing seepage control bulk head by using mould vibrosinking method

Publications (2)

Publication Number Publication Date
CN1233695A true CN1233695A (en) 1999-11-03
CN1101881C CN1101881C (en) 2003-02-19

Family

ID=5275516

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 99112187 Expired - Lifetime CN1101881C (en) 1999-04-22 1999-04-22 Process for producing seepage control bulk head by using mould vibrosinking method

Country Status (1)

Country Link
CN (1) CN1101881C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102174811A (en) * 2010-12-14 2011-09-07 张永忠 Wedge-shaped pile plate

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102174811A (en) * 2010-12-14 2011-09-07 张永忠 Wedge-shaped pile plate

Also Published As

Publication number Publication date
CN1101881C (en) 2003-02-19

Similar Documents

Publication Publication Date Title
CN106760546B (en) Pouring vibration method and vibration device for large-volume concrete structure construction
CN108999421A (en) A kind of wall body structure seepage treatment method
CN209207732U (en) Precast concrete overlaps board mold
CN202430997U (en) Reinforcing device for template of sump or elevator shaft
CN105839850A (en) Basement reverse-construction scape post-casting pre-stressed construction method
CN106930277A (en) A kind of construction of manual-excavation cast-in-place pile method
CN101446073A (en) Reinforced concrete pier stud with capping beam or irregular Y-shaped reinforced concrete pier stud once-forming construction method
CN105780726A (en) Brick and method for building dam on water with bricks
CN202925561U (en) Bearing platform template structure
CN107964946A (en) The construction method of stiff composite pile based on pump drainage water precipitation
CN1101881C (en) Process for producing seepage control bulk head by using mould vibrosinking method
CN202247938U (en) Wedge-shaped foundation bolt preformed hole core formwork device
CN203654317U (en) Guide wall structure of basement exterior wall
CN106381999A (en) Fair-faced concrete wall intaglio character die plate construction method
CN2234463Y (en) Vibration grouting device
CN109972632A (en) Recoverable soil nail pin-connected panel flexible cladding wall construction method
CN102966089B (en) Plate plug method capable of realizing vibratory compaction
CN214575093U (en) Environment-friendly precast concrete board's processingequipment
CN108049524B (en) Wall reinforcement structure
RU2097489C1 (en) Process of placing concrete into cast-in-place piles and installation for its implementation
EP1520936A3 (en) Boring method and apparatus
CN102477737A (en) Construction method of cement fly-ash gravel (CFG) pile on collapsible loess foundation of highway
CN209114471U (en) A kind of grout hole comes to nothing a section rapid hole sealing device
CN110512642A (en) Soft clay area drainage pipeline concrete pack punching block board construction method
CN1069093A (en) Stabilization method for concrete structure pressed and filled by expanded agent cement paste

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANDONG HUASHUI HYDROELECTRIC ENGINEERING CO., L

Free format text: FORMER OWNER: HUASHUI ENGINEERING CO., LTD., SHANDONG

Effective date: 20060908

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20060908

Address after: 250100, Shandong, Ji'nan hi tech Development Zone, Qilu Ring Road No. 1588, golden age 1, building 1, Room 502

Patentee after: Shandong Huashui Hydroelectric Engineering Co., Ltd.

Address before: 250013 No. 39, Jiefang Road, Shandong, Ji'nan

Patentee before: Huashui Engineering Co Ltd, Shandong

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20030219