CN1193065A - Method of alternatively taking out soil for construction of underground engineering - Google Patents

Method of alternatively taking out soil for construction of underground engineering Download PDF

Info

Publication number
CN1193065A
CN1193065A CN97100623A CN97100623A CN1193065A CN 1193065 A CN1193065 A CN 1193065A CN 97100623 A CN97100623 A CN 97100623A CN 97100623 A CN97100623 A CN 97100623A CN 1193065 A CN1193065 A CN 1193065A
Authority
CN
China
Prior art keywords
post
construction
underground
excavation
tops
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN97100623A
Other languages
Chinese (zh)
Inventor
贾恩福
张斌
王振华
梁喜顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHIJIAZHUANG CITY CONSTRUCTION COMMITTEE
Original Assignee
SHIJIAZHUANG CITY CONSTRUCTION COMMITTEE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHIJIAZHUANG CITY CONSTRUCTION COMMITTEE filed Critical SHIJIAZHUANG CITY CONSTRUCTION COMMITTEE
Priority to CN97100623A priority Critical patent/CN1193065A/en
Publication of CN1193065A publication Critical patent/CN1193065A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to an inverse-operation earth-cutting new process for underground engineering. It is characterized by that in the course of underground construction, after the top plate is poured, under the covering action of said top plat said invention fully uses the undisturbed earth body and formed column body as temporary support of the top plate, and in underground first floor, it uses four columns as support around every column and alternatively excavates earth around said column (i.e. "using four to support one"), and after the internal structure of underground first floor is completed, and uses eight columns to support around every column in underground second floor (i.e. "using eight to support one") and alternatively excavates earth and makes the constructions of gusset treatment, etc..

Description

Reverse construction underground construction " four tops one ", " eight tops one " staggered soil digging method
The invention belongs to a kind of building foundation construction technology, the new technology of particularly a kind of underground construction contrary sequence method soil digging.
In the underground building in reverse construction, cubic metre of earth excavation be after top board and post are finished, under top board covers, carry out soil digging and make lower floor's cap (or interim basis), at this moment the earthwork is in case excavation, top board and post begin carrying, and therefore, whether the shoveling scheme is suitable, to the inhomogeneous structure crack that produces of control structure load-bearing, even destruction is very important.Adopt lower joint pin channel-type soil digging method before, only make top board earlier, connect behind the pillar, draw by root by mast axis and dig soil on every side, the soil excavation around any single-column often need be set up a lot of interim supports, the expense costliness, and technology is loaded down with trivial details; Add interim support load-bearing inequality, structure is easy to crack, and can only construct by the root pillar in same passage, and speed is slow, and is very uneconomical.
The purpose of this invention is to provide a kind of under covering, can drawing continuously and dig the earthwork on every side of several posts with the reverse construction underground construction, utilize post, soil body acting in conjunction to form support system and no longer set up interim support, and can control a kind of soil digging method of structure crack that differential settlement causes.
Main technical schemes of the present invention is: earlier with the method one-step pore-creating of double-layer structure post with drill-pouring, an install reinforcing cage, a pour-shaping, but by (slightly) sand in highly in the hole, filling up the post concrete is divided into two sections at plate-girder post node place, so that node is constructed later on.After having watered top board, under top board covers, make full use of and be undisturbed the interim support of the soil body and molded post as plate, the maximum of utilizing finite element theory to calculate plate according to two-layer load difference allows unsettled span, around each post of B1, do to support (i.e. " four tops one ") with four posts, the earthwork around the staggered excavation post, processing node, construction cap etc.After the completion of B1 internal construction, around underground two layers of each post, make to support (i.e. " eight tops one "), the earthwork around the staggered excavation post, job practicess such as processing node again with eight posts.
Adopt constructure scheme of the present invention, technology is simple, practical, not as any interim support, can be in construction simultaneously between the different posts with one deck, draw continuously and dig the earthwork on every side of some posts, improved speed of application, reduced cost, excessive differential settlement be can not occur, structural safety and construction safety guaranteed.
Below in conjunction with accompanying drawing the present invention is further described.
Accompanying drawing 1 is " four tops one " schematic diagram.
Accompanying drawing 2 is " four tops one " soil digging scheme schematic diagram.
Accompanying drawing 3 is " eight tops one " schematic diagram.
Accompanying drawing 4 is " eight tops one " shoveling cell schematics.
Arabic numerals in the accompanying drawing are the numbering of post.
First with the method one-step pore-creating of double-layer structure post with drill-pouring, an install reinforcing cage, a pour-shaping, but by (slightly) sand in highly in the hole, filling up the post concrete is divided into two sections at plate-girder post node place, so that node is constructed later on.Underground first floor structural load is top board and deadweight of top earthing and live load, through checking computations and force analysis, if excavate a certain single-column surrounding soil, four pillar utilizations on every side are undisturbed the soil body and post as support, span according to the excavation passage is calculated, unsettled span can satisfy the unsettled of this single-column fully, forms " four tops one ", referring to accompanying drawing 1.Therefore, after having excavated around this root pillar cubic metre of earth, the disposable plates bean column node forms overall structure and reaches supporting role rapidly.Other pillar therewith roughly the same, adopt " four tops one " staggered shoveling scheme, referring to accompanying drawing 2, specific implementation method is: (1) excavates a unearthed work ditch earlier in bigger place in a side place of building, the bottom of trench absolute altitude is with the first floor ground level, put a muck haulage ramp in ditch, purpose is to transport outside the venue for the earthwork that will draw out; Or utilizing top board hole to be provided such as daylight opening, wind passage mouth etc., the installation vertical transportation machinery is put on soil and is transported outside the venue on mouth.(2) every interval two organ timbering dig a passage earlier at span centre, passage is communicated with unearthed work ditch or top board hole to be provided, in passage, excavate the post earthwork on every side by 1,2,3,4 orders, processing node, construction cap, the pillar of same sequence number can be constructed simultaneously, the sequence number of having constructed is for behind the post of " 1 ", and the preface of constructing again is the post of " 2 ", by that analogy.(3) all caps are all finished, and after the formation integrated support system, the excavation interlayer remains all cubic metres of earth, forms large space, carry out construction of first floor internal construction and equipment installation.
Subbasement structural load, force mechanism and mode of transfer force are different with first floor, take into full account first floor space rigidity through stressed analysis, utilize cap, post and around be undisturbed the soil body and calculate maximum as the interim support of upper load and fill and permitted unsettled span, consequently around being in when unsettled, a certain single-column need eight pillars and the soil body to bear jointly, form " eight tops one ", see accompanying drawing 3." eight tops one " the staggered soil digging method of specifically implementing in a shoveling unit is referring to accompanying drawing 4, that is: (1) reduces to second layer ground level place with original work bottom of trench absolute altitude, put a muck haulage ramp in the ditch, or same at the reserved opening place along the following vertical transportation machinery second layer.(2) arrange earlier and dig,, handle by the root pillar along mast axis excavation passage from A, treat that A arranges " 3 " root base for post and watered after, excavate C and arrange " 1 " root base for post; After A arranges " 6 " root base for post and waters, excavate B then and arrange " 1 " root base for post; After B arranges " 3 " root base for post and waters, excavate D again and arrange " 1 " root base for post,, carry out forward in proper order according to arranging about unit form shown in Figure 4.(3) all pattens are finished the back and are formed the overall structure system, and the excavation interlayer remains all cubic metres of earth, and the formation large space carries out the construction of second layer internal construction and equipment is installed.
The present invention tests in certain construction work, achieves success, and 44155 square metres of this project building areas, 18600 square metres of its top board areas, underground two-layer.Adopt technical scheme of the present invention, reduce earth excavation 2.3 ten thousand steres; Make full use of clay model and reduce more than 40,000 square metre of formwork area, save timber one over thousands of cubic meter, reduce investment outlay more than 1,000 ten thousand yuan altogether, only just recovered traffic above-ground, afforest, the degree that minimizes is disturbed in traffic with 6 months.

Claims (1)

1. a reverse construction underground construction " four tops one ", " eight tops one " staggered soil digging method, earlier with the method one-step pore-creating of double-layer structure post with drill-pouring, install reinforcing cage, fill up sand post concrete at plate-girder post node place by height in the hole and be divided into two sections, a pour-shaping is then at the same high work ditch with first floor ground of building one side excavation, put a muck haulage ramp in the ditch, or utilize the top board hole to be provided, vertical transport mechanism is installed on the hole, its feature:
The underground first floor of a adopts " four tops one " staggered soil digging method, that is: (1) every interval two organ timbering dig a passage earlier at span centre, press 1 in the passage, 2,3, No. 4 orders are excavated the post earthwork on every side, processing node, construction cap, the pillar of same sequence number can be constructed simultaneously, the sequence number of having constructed is for behind the post of " 1 ", and the sequence number of constructing again is the post of " 2 ", by that analogy; (2) all caps are all finished, and after the formation integrated support system, the excavation interlayer remains all cubic metres of earth, forms large space, carry out underground first floor internal construction construction and equipment installation;
The b subbasement adopts " eight tops one " staggered soil digging method, promptly; (1) original work bottom of trench absolute altitude is reduced to second layer ground level place, put a muck haulage ramp in the ditch, or same suitable vertical transport is down reduced to the second layer at the reserved opening place; (2) in a shoveling unit, earlier arrange the beginning from A, along mast axis excavation passage, handle by the root pillar, treat that A arranges " 3 " individual base for post and watered after, excavation C arranges " 1 " individual base for post, after A arranges " 6 " individual base for post and watered, excavate B then and arrange " 1 " base for post, B arranges and excavates D again after " 3 " individual base for post waters and arrange " 1 " individual base for post, according to arranging about this unit form, carry out forward in proper order; (3) all base for posts finish forming the overall structure system, and the excavation interlayer remains all cubic metres of earth, form large space and carry out construction of second layer internal construction and equipment installation.
CN97100623A 1997-03-07 1997-03-07 Method of alternatively taking out soil for construction of underground engineering Pending CN1193065A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN97100623A CN1193065A (en) 1997-03-07 1997-03-07 Method of alternatively taking out soil for construction of underground engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN97100623A CN1193065A (en) 1997-03-07 1997-03-07 Method of alternatively taking out soil for construction of underground engineering

Publications (1)

Publication Number Publication Date
CN1193065A true CN1193065A (en) 1998-09-16

Family

ID=5165189

Family Applications (1)

Application Number Title Priority Date Filing Date
CN97100623A Pending CN1193065A (en) 1997-03-07 1997-03-07 Method of alternatively taking out soil for construction of underground engineering

Country Status (1)

Country Link
CN (1) CN1193065A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100348835C (en) * 2005-06-07 2007-11-14 上海市城市建设设计研究院 Construction method of subsurface excavation and layer added by using top layer of existed basement as native cover board
CN100443673C (en) * 2002-03-07 2008-12-17 P·布拉热维奇 Method of construction
CN103161167A (en) * 2011-12-14 2013-06-19 中国二十冶集团有限公司 Earth excavation method under condition of imperfect vertical supporting system in reverse building method construction
CN106284411A (en) * 2016-08-30 2017-01-04 河南城建学院 The excavation method of sunk type subway station

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100443673C (en) * 2002-03-07 2008-12-17 P·布拉热维奇 Method of construction
CN100348835C (en) * 2005-06-07 2007-11-14 上海市城市建设设计研究院 Construction method of subsurface excavation and layer added by using top layer of existed basement as native cover board
CN103161167A (en) * 2011-12-14 2013-06-19 中国二十冶集团有限公司 Earth excavation method under condition of imperfect vertical supporting system in reverse building method construction
CN103161167B (en) * 2011-12-14 2015-03-04 中国二十冶集团有限公司 Earth excavation method under condition of imperfect vertical supporting system in reverse building method construction
CN106284411A (en) * 2016-08-30 2017-01-04 河南城建学院 The excavation method of sunk type subway station

Similar Documents

Publication Publication Date Title
CN107558494B (en) Underground station structure for rail transit and construction method thereof
CN101914925B (en) Basement by using optimized composite prefabricated arch wall as external wall
CN105862910B (en) A kind of the inverse of assembled stereoscopic underground garage makees formula method of construction
CN100348835C (en) Construction method of subsurface excavation and layer added by using top layer of existed basement as native cover board
CN107119711B (en) Connecting structure for large-range adjacent existing transfer station and construction method
CN101092850A (en) Method and installation for rising building or historical building / cluster of historical building integrally
CN105926669A (en) Construction method of subway station
CN108589771B (en) Construction method for layer-adding transfer node of operated underground station
CN110578339B (en) Construction method of shaft type underground stereo garage
CN110469341B (en) Subway underground excavation station assembling and pouring combined integrated structure and construction method
CN104453274A (en) Method for supporting underground layer increasing of existing building by supporting structure and underpinning structure
CN111851509A (en) Temporary channel construction method based on deep foundation pit inner support structure
CN104234082A (en) Jump-layer reversed construction method for deep foundation pit
CN115324366A (en) Hoisting method for overlong and overweight truss of framed bent structure system
CN1279319A (en) Full-reverse construction technology for basement
CN105386779A (en) Arch column method for building large-scale underground structure in shallow buried rock stratums
CN112681376A (en) Construction method of shaft type underground stereo garage
CN1193065A (en) Method of alternatively taking out soil for construction of underground engineering
CN111305220A (en) Concrete support and structural top plate combined building system based on permanent and temporary combination and construction method thereof
CN105840216A (en) Underground space exploitation excavation construction method
CN217053493U (en) Anti-floating system for crossing section of existing subway on open-cut tunnel
CN203066083U (en) Supporting structure for two adjacent foundation pits
CN115748735A (en) Foundation pit support system with umbrella-shaped ring beam support and construction method
CN105625184A (en) Subway station building method using bridge and station combined building mode
CN210797573U (en) Underground structure internal transportation system based on under-board sliding groove

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication