CN1184873A - Pressing cast in position type tech. for making drilling hole piles - Google Patents

Pressing cast in position type tech. for making drilling hole piles Download PDF

Info

Publication number
CN1184873A
CN1184873A CN96117824A CN96117824A CN1184873A CN 1184873 A CN1184873 A CN 1184873A CN 96117824 A CN96117824 A CN 96117824A CN 96117824 A CN96117824 A CN 96117824A CN 1184873 A CN1184873 A CN 1184873A
Authority
CN
China
Prior art keywords
grouting
pile
stake
pressure chamber
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN96117824A
Other languages
Chinese (zh)
Inventor
吴兴序
乔景川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Survey And Design Institute Of Zhengzhou Railway Administration
Southwest Jiaotong University
Original Assignee
Zhengzhou Survey And Design Institute Of Zhengzhou Railway Administration
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Survey And Design Institute Of Zhengzhou Railway Administration, Southwest Jiaotong University filed Critical Zhengzhou Survey And Design Institute Of Zhengzhou Railway Administration
Priority to CN96117824A priority Critical patent/CN1184873A/en
Publication of CN1184873A publication Critical patent/CN1184873A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

In the drilling pile pressure grouting technology we use an extra of a flexible pressure cavity at the pile bottom and preimbedded two grouting pipe, by high pressure grouting aginst pile bottom, the stress condition of the pile base soil can be effectively improved and the bearing strength of pile is enhanced.

Description

Drilled pile pressure grouting technology
The invention belongs to technical field of civil engineering, the pile foundation engineering technique field of various civil engineerings such as particularly traffic, harbour, water conservancy, mine, worker China Democratic National Construction Association, oil.
Castinplace pile is to use extremely general a kind of pile foundation form, be applied in the Foundation Design of all trades and professions at present, this invention technology is to finish on the basis of mature drilling hole bored concrete pile technology, and it is based on, and bearing capacity principle development that grouting can improve ground comes.The stake of castinplace pile is long, the stake footpath can change, and is adapted to all kinds of formation conditions, and has higher capacity.Just construction divides, and bored pile, tube-sinking cast-in-situ pile, hand excavated pile, expanded bore pile, explosion expanded piling etc. are arranged.But these the strengths and weaknesses is and deposits, and is fit to various stratum as bored pile, but behind the pile stake end can exist the extremely disadvantageous loosened soil of bearing capacity; Though hand excavated pile does not have loosened soil, require the stratum strictness, in the stratum of floating cobble is arranged, can't use, and stake can be very not long; Expanded bore pile can increase the load-bearing area of stake, improves bearing capacity, but construction is complicated, and the stratum of requirement is also strict, and as expanding the end with boring, the stake end still can form loosened soil; But explosion expanded piling also form expands the end, but the energy of blast jeopardizes near building sometimes, can make saturated powder fine sand produce liquefaction etc. such as shaking force, and its explosive expansion effect of the difference of strata condition is also different, and pile quality can not guarantee fully.In order to improve the bearing capacity of stake, the technology to being in the milk at the bottom of the stake behind the bored pile piling of using is also arranged at present, but the stake end, be not provided with the pressure grouting chamber, so, the grouting or the densification at the stake end, or infiltration and splitting, the grouting effect at the bottom of it can not direct same grouting pressure, the grouting amount, grouting lasts and connects, effect is extremely unstable, sometimes its grouting effect can be said to be satisfied, can improve 50~70% to the bearing capacity of stake, and is almost like water off a duck's back again sometimes, this explanation, the stake end grouting in no pressure grouting chamber, the discreteness of its effect is very big, and technological parameter is wayward, can only can't include design in as a kind of supplementary means that increases safety.
The purpose of this invention is to provide a kind of drilled pile pressure grouting technology, it can improve the stress condition of a subsoil effectively, thereby has improved the bearing capacity of stake.
The present invention is realized by following technical scheme: before this technology of enforcement, should fully understand character, groundwater table, the natural bearing capacity of soil, fixed history, draining situation etc. and the various the thickness of the layer and the soil nature parameter (modulus E, unit weight=γ, proportion G, void ratio e, mechanical index C, etc.) thereof of force way, foundation soil on bearing capacity of foundation soil, the basis of building requirement, so that select suitable grout pump, make stake bottom pressure grouting chamber that suits and the displacement of in the technology implementation process, controlling grouting pressure, grouting amount, stake etc.Bury the pliable pressure chamber at the bottom of the every pile of the present invention underground and pre-buried two mud jacking pipelines in concrete.Make with resilient rubber materials in the pliable pressure chamber, and its size changes with the size in stake footpath.Behind the pore-forming, pressure chamber is positioned at the stake end of the lower end of reinforcing cage, and grout pipe links to each other with pressure chamber by reinforcing cage, and the other end extends the face of land, before grouting its integral body is put into boring; Grout pipe is steel pipe or plastic pipe, and caliber is by how many decisions of grouting machine model and grouting amount.The specific implementation process is: bury underground at the bottom of pile foundation and the grouting parameter designing → making hole construction → hole and place reinforcing cage and pre-embedment grouting pipe → pour concrete → grouting preparation → grouting construction in pressure chamber → hole.Concrete activities is:
(1) designed length, stake footpath and grouting pressure, the grouting amount etc. of stake by the bearing capacity of single pile that requires, above index will be considered in conjunction with the geology Information integration;
(2) carry out the stake making hole construction, job practices is with general drilled pile construction;
(3) at the bottom of the hole, bury the pressure grouting chamber underground, place in the hole reinforcing cage (if any words) and preset grout pipe by ground to inside, pressure grouting chamber;
(4) carry out the concrete piles cast, this concrete cast with general castinplace pile is identical;
(5) after concrete piles is solidified 7 days, the preparation that can be in the milk.As grout pump, slurries mixer, flushing pressure grouting chamber etc.;
(6) after concrete piles is solidified 7 days, carry out grouting work, in construction, will carry out record, having in the record that grouting lasts, grouting pressure, grouting amount etc.To carry out in case of necessity the stake on lift displacement monitoring;
(7) when reaching the design objective of grouting, (design in advance), can finish grouting, the cleaning grouting equipment.
Adopt the bored pile of this technology to compare with general bored pile, under the same condition in, stake footpath long and stratum in stake, the bearing capacity of pressure grouting stake all will be higher than the bearing capacity of present all types of castinplace piles, in some soil layer (as sandy soil), the former bearing capacity is 2~3 times of the latter.
This technology all will at length be made technical scheme according to the concrete condition of engineering again as other mature engineering, so that make engineering safety and reliability, construction faster, more economical etc. to greatest extent.Key index in this technology is the displacement of, stake footpath long according to stake and geological conditions grouting pressure, grouting amount and the stake of formulating.
The present invention compared with the prior art, its effect and advantage are that it can maximize favourable factors and minimize unfavourable ones, and have both kept the advantage of aforementioned castinplace pile, have got rid of the deficiency of aforementioned castinplace pile again, have all advantages of aforementioned castinplace pile., stake footpath long as stake can change and be adapted to various stratum (this construction machinery by stake is decided); Loosened soil at the bottom of can disposing (as the stake end of hand excavated pile); Can form enlarged footing (as the reaming stake); (as explosion expanded piling, but than the densification better effects if of explosion expanded piling, explosion expanded piling is the moment densification to the soil body at the bottom of can the densification stake, can produce high pore water pressure, and this technology is the densification of pressurizeing gradually, analyzes the densification better effects if of this technology from the consolidation theory of soil); Parameters of construction technology is easy to control, can analyze the bearing capacity that draws stake thus, and can include Base Design in, and this point has difference matter, essence with the stake end grouting technique in no pressure grouting chamber.
In addition, this technology not only can be applied on the bored pile, and is applied on hand excavated pile and the tube-sinking cast-in-situ pile with can having no any modification, goes among can being applied to diaphragm wall after being made amendment in the pressure grouting chamber.
Case history:

Claims (2)

1, a kind of drilled pile pressure grouting technology, mainly forms by burying processes such as placing reinforcing cage and pre-embedment grouting pipe, pour concrete, grouting construction in pliable pressure chamber, the hole at the bottom of grouting parameter designing, making hole construction, the hole underground, it is characterized in that at the bottom of bored piles, burying underground the pliable pressure chamber and pre-buried two by the lead to grouting pipelines of pressure chamber of the face of land.
2, drilled pile pressure grouting technology according to claim 1 is characterized in that the pliable pressure chamber is positioned at the stake end of reinforcing cage lower end, and grout pipe links to each other with the pliable pressure chamber by reinforcing cage.
CN96117824A 1996-12-13 1996-12-13 Pressing cast in position type tech. for making drilling hole piles Pending CN1184873A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN96117824A CN1184873A (en) 1996-12-13 1996-12-13 Pressing cast in position type tech. for making drilling hole piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN96117824A CN1184873A (en) 1996-12-13 1996-12-13 Pressing cast in position type tech. for making drilling hole piles

Publications (1)

Publication Number Publication Date
CN1184873A true CN1184873A (en) 1998-06-17

Family

ID=5124641

Family Applications (1)

Application Number Title Priority Date Filing Date
CN96117824A Pending CN1184873A (en) 1996-12-13 1996-12-13 Pressing cast in position type tech. for making drilling hole piles

Country Status (1)

Country Link
CN (1) CN1184873A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101818957A (en) * 2009-09-17 2010-09-01 邢玉明 System utilizing heat storage of underground aquifer for heating or utilizing cold storage for cooling

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101818957A (en) * 2009-09-17 2010-09-01 邢玉明 System utilizing heat storage of underground aquifer for heating or utilizing cold storage for cooling

Similar Documents

Publication Publication Date Title
Smoltczyk Geotechnical Engineering Handbook, Procedures
CN110230309A (en) Karst region bridge solution cavity pile base construction method
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN104329020B (en) A kind of reinforced long spire embedding rock construction equipment and technique thereof
Bell Methods of treatment of unstable ground
CN110344400A (en) The hard rock pore-forming construction technology of churning driven opportunity
CN106978807A (en) Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area
CN101130991A (en) Caisson cofferdam based on prepacked foundation bed
CN104963346A (en) Support construction method for deep foundation pit in complex geological condition
CN108797618A (en) One kind being used for Urban Underground pipe gallery drainage of foundation pit structure and its construction method
CN103046931A (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN106088099A (en) A kind of subway foundation pit anchor cable processing method
CN105735245A (en) Soil body reinforcement method for trenching construction in stratum of seaside hydraulic fill mud layer
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
CN106677166A (en) Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode
CN209066468U (en) A kind of base pit dewatering device
Munfakh Ground improvement engineering–the state of the US practice: part 1. Methods
CN102296591A (en) Rapid drainage solidifying treatment method of soft soil foundation
CN108570979A (en) A kind of construction method for building antiseepage composite foundation on dolomite stratigraph
Wagener et al. Construction on dolomite in South Africa
CN1184873A (en) Pressing cast in position type tech. for making drilling hole piles
CN208294522U (en) Waterproof of man in a kind of pilot tunnel of rich water sand-pebble layer
CN1042158C (en) Injecting method for steel rod concrete prefabricated pile end
CN205857212U (en) Corrugated steel cofferdam borehole hollow pile
Rowe The potentially latent dominance of groundwater in ground engineering

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication