CN117952552A - Project management method, system, equipment and medium for street engineering construction - Google Patents

Project management method, system, equipment and medium for street engineering construction Download PDF

Info

Publication number
CN117952552A
CN117952552A CN202410115173.1A CN202410115173A CN117952552A CN 117952552 A CN117952552 A CN 117952552A CN 202410115173 A CN202410115173 A CN 202410115173A CN 117952552 A CN117952552 A CN 117952552A
Authority
CN
China
Prior art keywords
project
node
data
project management
street
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202410115173.1A
Other languages
Chinese (zh)
Inventor
付巍巍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Yuanzun Engineering Management Consulting Co ltd
Original Assignee
Beijing Yuanzun Engineering Management Consulting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Yuanzun Engineering Management Consulting Co ltd filed Critical Beijing Yuanzun Engineering Management Consulting Co ltd
Priority to CN202410115173.1A priority Critical patent/CN117952552A/en
Publication of CN117952552A publication Critical patent/CN117952552A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A project management method, system, equipment and medium for street engineering construction relates to the engineering construction field. In the method, street engineering construction project management flow chart data are acquired and analyzed, and association relations among project management nodes are determined; generating project management task execution time sequences corresponding to each project management node according to the association relation; carrying out node task calculation on each project management node in turn according to the project management task execution time sequence to obtain a calculation result; and correlating the calculation result with the street engineering construction project management flow chart data. By implementing the technical scheme provided by the application, the effect of automatically managing the projects in the street engineering construction is realized.

Description

Project management method, system, equipment and medium for street engineering construction
Technical Field
The application relates to the technical field of engineering construction, in particular to a project management method, system, equipment and medium for street engineering construction.
Background
With the development of science and technology, the population of cities is continuously increased, and the original road traffic cannot meet the development requirements of the cities, so that large-scale street engineering construction is required.
At present, the project management method for street engineering construction generally depends on manual execution of corresponding tasks in each management link, lacks an automatic unified management mechanism, cannot perform all-round project management from each management dimension of each management link, and has the problem of poor project management effect.
Thus, there is a need for an automated project management method for street engineering construction.
Disclosure of Invention
The application provides a project management method, system, equipment and medium for street engineering construction, which are used for automatically managing projects in the street engineering construction, carrying out all-round project management from each link of the projects by combining different management dimensions, and improving project management effects.
In a first aspect of the present application, there is provided a project management method for street engineering construction, applied to a project management platform, the method comprising:
Acquiring and analyzing data of a street engineering construction project management flow chart, and determining association relations among project management nodes;
Generating project management task execution time sequences corresponding to each project management node according to the association relation;
carrying out node task calculation on each project management node in turn according to the project management task execution time sequence to obtain a calculation result;
and correlating the calculation result with the street engineering construction project management flow chart data.
By adopting the technical scheme, the corresponding project management task execution time sequence is generated according to the association relation among the project management nodes, so that the sequential execution of the project management tasks is ensured, the confusion and omission of task execution are avoided, and the project management efficiency and quality are improved. By carrying out node task calculation on each project management node and obtaining a calculation result and associating the calculation result with the street engineering construction project management flow chart data, the tight combination of node task calculation and flow is realized, and more comprehensive and accurate project management information is provided for project management staff.
Optionally, the acquiring and analyzing the street engineering construction project management flowchart data includes:
analyzing the management document of the street engineering project uploaded by the user to locate the document position corresponding to the street engineering project management flow chart data, and intercepting the street engineering project management flow chart data in a specified format from the document position.
By adopting the technical scheme, the management document of the street engineering construction project uploaded by the user is analyzed, the document position where the flow chart data are located can be automatically positioned, the time for manual searching and positioning is reduced, and the accuracy and efficiency of data acquisition are improved. And intercepting the street engineering construction project management flow chart data in the specified format from the document position, ensuring that the acquired data is correct in format and complete in content, and providing accurate basic data for the subsequent node association relation determination and task execution time sequence generation. By intercepting the data in the appointed format, the standardized processing of the data is realized, the unified processing and analysis of the data are convenient for the system, and the normalization and reliability of the data processing are improved. By intercepting the data from the document, the integrity of the data is ensured, errors or omission caused by manual input or copy and paste are avoided, and the accuracy and reliability of the data are improved.
Optionally, the obtaining and analyzing the street engineering construction project management flowchart data further includes:
node attribute data of the project management node is acquired,
The project management node comprises a project design node, a budget review node, a project bid-inviting node, a contract processing node, a project implementation node and a project settlement node;
The node attribute data of the project design node includes: project design drawings, project design schemes and street project site investigation record tables;
The node attribute data of the budget review node comprises: project budget files and project design drawings;
The node attribute data of the project bid-inviting node comprises: purchasing platform information, project schedule registration form, purchasing project execution notice, project bidding agreement data and winning bid unit data corresponding to different budget intervals;
The node attribute data of the contract processing node includes: project contract auditing opinion documents and construction contract documents;
the node attribute data of the project implementation node includes: project supervision week report data and construction problem notification data;
The node attribute data of the item settlement node includes: project acceptance data, settlement audit data.
By adopting the technical scheme, the node attribute data of each project management node is acquired, the specific work content and the required data related to each node can be known in detail, and more accurate and comprehensive basic data is provided for subsequent task execution time sequence generation and node task calculation. By acquiring and analyzing the street engineering construction project management flow chart data and the node attribute data, the specific condition and the requirement of the project can be known more comprehensively and accurately, the project management efficiency and quality can be improved, the project period can be shortened, the project cost can be reduced, and the project success rate can be improved.
Optionally, the step of sequentially performing node task calculation on each project management node according to the project management task execution sequence and obtaining a calculation result includes:
Checking the budget file and the construction drawing file, and determining the budget amount according to the checked budget file;
determining an amount interval according to the budget amount to call a corresponding platform for initial project data entry;
determining an item bidding category according to the initial item data, and determining a winning unit according to the item bidding category;
And generating a project contract by combining the unit data of the winning unit.
By adopting the technical scheme, the accuracy and the integrity of the data are ensured by checking the budget file and the construction drawing file, and a reliable basis is provided for the subsequent budget amount determination and project data entry. And determining an amount interval according to the budget amount and automatically calling a corresponding platform to perform initial project data entry, so that automatic processing of tasks is realized, and the working efficiency is improved. The method can automatically determine the project bid category and bid unit according to the initial project data, and has intelligent data processing and analysis capability. And the project contract is generated by combining the unit data of the winning unit, so that the contract making flow is simplified, and the efficiency and standardization of contract management are improved. By means of automatic and intelligent data processing and analysis, human errors and omission are reduced, and efficiency and quality of project management are improved.
Optionally, the checking the budget file and the construction image file includes:
checking stamping of the project design drawing through image recognition;
Carrying out integrity check on the project design scheme through key field verification;
Carrying out integrity check on the on-site investigation record table of the street project through key field check;
and carrying out integrity check on the project budget file through key field verification.
By adopting the technical scheme, the stamping of the project design drawing is inspected based on the image recognition technology, so that the automatic recognition and verification of the stamping are realized, the efficiency and accuracy of inspection are improved, and the errors and omission of manual inspection are avoided. And the project design scheme, the street project site investigation record table and the project budget file are subjected to integrity check through key field check, so that the integrity and the accuracy of data are ensured, and management errors or omission caused by data missing or incomplete data are avoided. Through automatic and intelligent data processing and analysis, the possibility of human errors and omission is reduced, and the accuracy and reliability of project management are improved.
Optionally, the generating the project contract by combining the unit data of the winning unit includes:
and the unit data of the winning bid unit is summarized, and project contract auditing opinion documents and construction contract documents are generated according to the summarized unit data.
By adopting the technical scheme, the unit data of the winning bid unit are summarized and arranged, so that the situation of the winning bid unit can be better known, and accurate basic data is provided for subsequent project contract auditing and construction contract formulation. And generating project contract auditing opinion documents and construction contract documents according to the unit data after induction, simplifying the production flow of the contract documents, and improving the efficiency and standardization of contract management.
Optionally, the associating the calculation result with the street engineering construction project management flowchart data includes:
And integrating the node tasks and the calculation results of each project management node, and filling the street engineering construction project management flow chart data according to the integrated data.
By adopting the technical scheme, the tasks and the calculation results of all the nodes are integrated, unified management and integration of data are realized, and project management personnel can know the project comprehensively and accurately conveniently. And filling the data of the street engineering construction project management flow chart according to the integrated data, so that the flow chart data is more complete and accurate, and project management personnel can better know the project progress condition and the existing problems.
In a second aspect of the present application, a project management system for street engineering construction is provided, including an parsing module, a timing module, an executing module, and an associating module, where:
the analysis module is configured to acquire and analyze the street engineering construction project management flow chart data and determine the association relation among each project management node;
The time sequence module is configured to generate a project management task execution time sequence corresponding to each project management node according to the association relation;
the execution module is configured to sequentially perform node task calculation on each project management node according to the project management task execution time sequence and obtain a calculation result;
and the association module is configured to associate the calculation result with the street engineering construction project management flow chart data.
In a third aspect the application provides an electronic device comprising a processor, a memory for storing instructions, a user interface and a network interface, both for communicating with other devices, the processor being for executing instructions stored in the memory to cause the electronic device to perform a method as claimed in any one of the preceding claims.
In a fourth aspect of the application there is provided a computer readable storage medium storing instructions which, when executed, perform a method as claimed in any one of the preceding claims.
In summary, one or more technical solutions provided in the embodiments of the present application at least have the following technical effects or advantages:
1. By analyzing the data of the street engineering construction project management flow chart, the association relation among each project management node can be obtained, and the automatic processing and standardized management of the data are realized; according to the association relation between the nodes, project management task execution time sequences corresponding to each project management node can be generated, and accurate time sequence references are provided for subsequent task execution; according to the project management task execution time sequence, node task calculation can be carried out on each project management node, a calculation result is obtained, and accurate basic data is provided for subsequent data association;
2. the calculation result is associated with the street engineering construction project management flow chart data, so that unified management and dynamic monitoring of the data are realized, and project management personnel can conveniently and comprehensively know the project progress condition and existing problems;
3. The dynamic monitoring and management of the project can be realized through the data association, so that the problem in the project execution process can be found and solved in time, and the project can be ensured to be carried out smoothly.
Drawings
FIG. 1 is a flow chart of a project management method for street engineering construction according to an embodiment of the present application;
FIG. 2 is a block diagram of a project management system for street engineering construction in accordance with an embodiment of the present application;
fig. 3 is a schematic structural diagram of an electronic device according to an embodiment of the present application.
Reference numerals illustrate: 201. an analysis module; 202. a timing module; 203. an execution module; 204. an association module; 301. a processor; 302. a communication bus; 303. a user interface; 304. a network interface; 305. a memory.
Detailed Description
In order that those skilled in the art will better understand the technical solutions in the present specification, the technical solutions in the embodiments of the present specification will be clearly and completely described below with reference to the drawings in the embodiments of the present specification, and it is apparent that the described embodiments are only some embodiments of the present application, not all embodiments.
In describing embodiments of the present application, words such as "for example" or "for example" are used to mean serving as examples, illustrations, or descriptions. Any embodiment or design described herein as "such as" or "for example" in embodiments of the application should not be construed as preferred or advantageous over other embodiments or designs. Rather, the use of words such as "or" for example "is intended to present related concepts in a concrete fashion.
In the description of embodiments of the application, the term "plurality" means two or more. For example, a plurality of systems means two or more systems, and a plurality of screen terminals means two or more screen terminals. Furthermore, the terms "first," "second," and the like, are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating an indicated technical feature. Thus, a feature defining "a first" or "a second" may explicitly or implicitly include one or more such feature. The terms "comprising," "including," "having," and variations thereof mean "including but not limited to," unless expressly specified otherwise.
The embodiment discloses a project management method for street engineering construction, which is applied to a project management platform, and fig. 1 is a flow chart of the project management method for street engineering construction disclosed by the embodiment of the application, as shown in fig. 1, the project management method comprises the following steps:
s110, acquiring and analyzing street engineering construction project management flow chart data, and determining association relations among project management nodes;
And uploading a document containing the data of the street engineering construction project management flow chart by a user through the uploading function of the project management platform. The street engineering construction project management flow chart data is analyzed by using a specific analysis algorithm and a specific rule, for example, each project management node can be identified, and the connection line between the nodes is extracted to represent the association relationship between the nodes. The association relationship is determined based on the drawing rule of the flow chart and project management practice, for example, a certain node can start the next node after finishing, or parallel relationship exists among a plurality of nodes. Through the determination of the association relationship, the platform can know the logic sequence and the interdependence relationship of each node in the project management process.
Optionally, the acquiring and analyzing the street engineering construction project management flowchart data includes:
analyzing the management document of the street engineering project uploaded by the user to locate the document position corresponding to the street engineering project management flow chart data, and intercepting the street engineering project management flow chart data in a specified format from the document position.
The project management platform can receive the street project management documents uploaded by the user, different projects have different management documents, when the target street project management documents are needed, the document catalogue can be analyzed, the document positions of the target street project management flow chart data are located, and street project management flow chart data in a specified format are intercepted from the document positions.
The method and the device can automatically locate the position of the flow chart data by automatically analyzing the document uploaded by the user, save the steps of manual searching and screening and improve the data processing efficiency. Intercepting the data in the specified format ensures standardization and normalization of the data, making subsequent data processing and analysis more accurate and reliable. The automatic data acquisition and analysis process simplifies the operation flow of the user, reduces the difficulty of data processing, and enables the user to concentrate on project management. By automatically intercepting the data in the specified format, the integrity of the data in the flow chart can be ensured, and the problems of data omission or error importing are avoided. The automatic data processing process greatly improves the efficiency of data processing, reduces the manual intervention and error rate, and improves the efficiency and quality of project management.
Optionally, the obtaining and analyzing the street engineering construction project management flowchart data further includes:
node attribute data of the project management node is acquired,
The project management node comprises a project design node, a budget review node, a project bid-inviting node, a contract processing node, a project implementation node and a project settlement node;
The node attribute data of the project design node includes: project design drawings, project design schemes and street project site investigation record tables;
The node attribute data of the budget review node comprises: project budget files and project design drawings;
The node attribute data of the project bid-inviting node comprises: purchasing platform information, project schedule registration form, purchasing project execution notice, project bidding agreement data and winning bid unit data corresponding to different budget intervals;
The node attribute data of the contract processing node includes: project contract auditing opinion documents and construction contract documents;
the node attribute data of the project implementation node includes: project supervision week report data and construction problem notification data;
The node attribute data of the item settlement node includes: project acceptance data, settlement audit data.
The node attribute data of the project design nodes comprise project design drawings, project design schemes and a street project site investigation record table. This data is the core content of the project design, providing the basis for subsequent budgeting, bidding and implementation. The node attribute data of the budget review node comprises a project budget file and a project design drawing. The budget file is used for verifying project cost, and the design drawing is the basis of budget calculation. The node attribute data of the project bidding node comprises purchasing platform information, project progress registration forms, purchasing project execution notice books, project bidding protocol data and winning bid unit data corresponding to different budget intervals. These data ensure the fairness and disclosure of the bidding process and provide basis for subsequent contract processing. The node attribute data of the contract processing node includes project contract audit opinion documents and construction contract documents. The treaty document is a legal basis for ensuring the enforcement and management of projects. The node attribute data of the project implementation node includes project supervision report data and construction problem notification data. These data reflect the actual execution of the project, helping to find problems and take action in time. The node attribute data of the item settlement node includes item acceptance data and settlement audit data. These data are used to confirm the final cost of the item, ensuring complete settlement of the item.
By acquiring node attribute data of each project management node, such as project design drawings, budget files, contract documents and the like, the integrity and the elaboration of the project data are ensured. These data provide comprehensive information support for project management, helping to reduce information omission or errors. The node attribute data provides key information for project management, so that project management personnel can make more scientific and reasonable decisions based on the data. The acquisition of the node attribute data provides convenience for monitoring and auditing of the project. The project manager can track the state and data change of each node in real time, discover problems in time and take measures. Meanwhile, the data also provides important basis for auditing after the project is completed. The automatic acquisition and analysis of the data reduce the need for manual intervention and improve the efficiency and accuracy of data processing. This helps the project management team manage projects more efficiently, shortens project cycles, and reduces costs.
S120, generating project management task execution time sequences corresponding to each project management node according to the association relation;
The following association relationship between the project management nodes may be sequentially performed: project design node-budget review node-project bid node-contract processing node-project implementation node-project settlement node. For each project management node, the corresponding project management task execution time sequence is as follows: project design node-budget review node-project bid node-contract processing node-project implementation node-project settlement node.
S130, carrying out node task calculation on each project management node in turn according to the project management task execution time sequence, and obtaining a calculation result;
And carrying out corresponding node task calculation on each project management node in turn according to the project management task execution time sequence, entering a task calculation link corresponding to the next project management node after the calculation is passed until the node tasks corresponding to all the project management nodes are calculated, and reading the document data corresponding to each project management node.
Optionally, the step of sequentially performing node task calculation on each project management node according to the project management task execution sequence and obtaining a calculation result includes:
Checking the budget file and the construction drawing file, and determining the budget amount according to the checked budget file;
determining an amount interval according to the budget amount to call a corresponding platform for initial project data entry;
determining an item bidding category according to the initial item data, and determining a winning unit according to the item bidding category;
And generating a project contract by combining the unit data of the winning unit.
Acquiring a budget file and a construction drawing file of an electronic version; performing seal checking on the budget file and the construction image file, and if the seal is confirmed to be correct, warehousing and storing; determining a budget amount based on the budget file inspected for no errors; determining an amount interval in which the budget amount is located, calling a system or platform corresponding to the amount interval, and recording initial project data; after the initial project data is successfully input, returning electronic version notification data; determining a corresponding project bid category by combining the electronic version notification data; and bidding is carried out according to the item bidding category, corresponding winning bid units are determined, and item contracts are generated by combining unit data of the winning bid units.
By checking the budget file and the construction drawing file, the accuracy of the budget amount is ensured. This helps to prevent problems of project cost hyperbranched or insufficient funds due to budget errors. The project bidding category is determined according to the initial project data, and the bidding unit is determined according to the project bidding category, so that fairness, disclosure and transparency of the bidding process are ensured. This helps to prevent unfair conduct in the bidding process and improve the integrity of the project. And generating the project contract by combining the unit data of the winning unit, so that compliance and integrity of the contract are ensured. This helps reduce the risk of contract disputes, ensuring the successful implementation of the project. And by means of automatic and standardized node task calculation, project management efficiency is improved. This helps to shorten the project period, reduce the management cost, and improve the economic benefit of the project. By strictly controlling key links such as budget, bid and contract, the risk in project management is reduced. This helps to ensure smooth progress of the project, reducing unnecessary losses.
Optionally, the checking the budget file and the construction image file includes:
checking stamping of the project design drawing through image recognition;
Carrying out integrity check on the project design scheme through key field verification;
Carrying out integrity check on the on-site investigation record table of the street project through key field check;
and carrying out integrity check on the project budget file through key field verification.
For project design nodes, the node calculation tasks are: and performing stamping checking of the project design drawing through image recognition, performing integrity checking of the project design scheme through key field checking, and performing integrity checking of the street project on-site investigation record table through key field checking. The node calculation result is: whether to seal; whether the project design scheme is complete; the street project site survey records are complete.
For budget review nodes, the node computing tasks are: and carrying out integrity check on the project budget file through key field verification, mapping the interval to which the budget amount belongs, and carrying out seal check on the project design drawing through image identification. The node calculation result is: whether the project budget file is complete, the interval to which the budget amount belongs, and whether to seal.
And checking the stamping on the project design drawing through an image recognition technology, so as to ensure the authenticity and effectiveness of the stamping. Specifically, an image recognition algorithm is used for scanning a project design drawing, a stamping area on the drawing is recognized, feature extraction is carried out on stamping, such as fonts, colors, shapes and the like, and the feature extraction is compared with a known legal stamping template to judge the authenticity of stamping. And carrying out integrity check on the key fields in the project design scheme, the street project site investigation record table and the project budget file through key field check, so as to ensure the integrity and accuracy of the key information. Specifically, key fields needing to be checked in each file, such as project names, budget amounts, construction dates and the like, are determined, extracted, compared with preset standards or specifications, and whether the fields are missed or wrong is checked.
And the stamping of the project design drawing is checked through image recognition, so that the recognition and the prevention of counterfeiting or fraudulent conduct are facilitated, and the legitimacy and benefits of the project are protected. And the project design scheme, the street project site investigation record table and the project budget file are subjected to integrity check through key field check, so that the integrity and the accuracy of data are ensured, and reliable data support is provided for project management. By means of an automatic and standardized checking flow, project management efficiency is improved, manual intervention and errors are reduced, and management cost is lowered.
Optionally, the generating the project contract by combining the unit data of the winning unit includes:
and the unit data of the winning bid unit is summarized, and project contract auditing opinion documents and construction contract documents are generated according to the summarized unit data.
For project bidding nodes, the node calculation tasks are: project bid-winning data extraction and bid-winning unit data induction. The node calculation result is: item bid data in the form of key value pairs and bid unit data.
For contract processing nodes, the node computation tasks are: and generating project contract auditing opinion book documents and construction contract documents. The node calculation result is: project contract auditing opinion documents and construction contract documents.
For project implementation nodes, the node computation tasks are: and calculating an early warning event. The node calculation result is: and outputting an early warning.
For an item settlement node, the node calculation tasks are: and (5) checking and accepting score calculation and settlement audit calculation. The node calculation result is: acceptance scoring and result auditing.
And carrying out induction arrangement on the related data of the winning bid unit so as to facilitate the generation of subsequent project contract documents. Specific: collecting unit data of winning units, including but not limited to qualification, performance, technical strength, financial status, etc. of winning units; sorting and summarizing the collected data, and extracting key information; formatting the summarized data to make the data suitable for subsequent contract document generation. And generating a project contract auditing opinion book document for reference of contract auditing personnel based on the summarized winning bid unit data. Specific: and writing a project contract auditing opinion book document according to the summarized winning bid unit data, clearly listing key information such as qualification, technical strength, financial condition and the like of the winning bid unit in the document, organizing contract auditors to audit, ensuring the accuracy and the integrity of the document, and revising and perfecting the document according to the audit result. And generating a construction contract document based on the summarized winning unit data, and taking the construction contract document as a formal document of the project construction contract. Specific: and writing a construction contract document according to the summarized winning unit data, clearly defining key terms such as construction range, construction period, quality requirement, payment mode and the like of the project in the document, negotiating and negotiating with the winning unit, revising and perfecting the same terms, and finally signing the construction contract document to ensure that rights and interests of both sides are ensured.
By summarizing and sorting the data of the winning bid unit, the integrity and consistency of the data can be ensured. The process is helpful for integrating data with different sources and formats, so that the data is in a standardized format, and the subsequent generation of contract documents is facilitated. And generating a project contract based on the unit data after induction, so that the accuracy of contract terms can be ensured. Because the data is derived from the winning unit, the generated contract is closer to the actual situation, and unnecessary disputes caused by misunderstanding or mistakes are reduced. And generating project contract auditing opinion book documents, so that the auditing flow of the contract is more perfect. The document provides detailed reference information for auditors, helps the auditors to better understand contract contents, and improves auditing efficiency and accuracy. The generated construction contract document provides a formal contract document for project management. The project management process is more standard, and the parties can conveniently review, execute and supervise the same content.
And S140, associating the calculation result with the street engineering construction project management flow chart data.
Optionally, the associating the calculation result with the street engineering construction project management flowchart data includes:
And integrating the node tasks and the calculation results of each project management node, and filling the street engineering construction project management flow chart data according to the integrated data.
And archiving the document data corresponding to each project management node, and storing the integrated document data and the street engineering construction project management flow chart data in an associated mode. And the initial street engineering project management flow chart can be filled with information according to the keywords in the integrated document data, so that a final version of street engineering project management flow chart is obtained. The street engineering construction project management flow chart of the final version comprises node tasks corresponding to each project management node and node task calculation results.
By associating the calculation result with the flow chart data, the originally abstract data can be displayed in an intuitive way. The method is beneficial to project management personnel to better understand data, quickly identify project states and progress, and improve decision-making efficiency. By integrating the node tasks and the calculation results of each project management node, a complete data stream can be formed. This helps to find bottlenecks and problems in the process, optimize the project management process, and improve the project execution efficiency. By updating the flow chart data in real time, real-time monitoring of project progress can be realized. When the data is abnormal or not in line with expectations, early warning can be sent out in time to remind project management personnel to take corresponding measures, and project delay or other risks are prevented. The visualized project management flow chart can enhance communication and collaboration between teams. Team members can view, understand and analyze the flow chart data together, so that information sharing and collaborative work are promoted, and team collaborative efficiency is improved.
The embodiment also discloses a project management system for street engineering construction, and fig. 2 is a schematic block diagram of the project management system for street engineering construction disclosed in the embodiment of the application, as shown in fig. 2, the project management system includes an analysis module 201, a timing module 202, an execution module 203 and an association module 204, where:
The analysis module 201 is configured to acquire and analyze the street engineering construction project management flow chart data, and determine the association relationship between each project management node;
a time sequence module 202, configured to generate a project management task execution time sequence corresponding to each project management node according to the association relationship;
the execution module 203 is configured to sequentially perform node task calculation on each project management node according to the project management task execution time sequence and obtain a calculation result;
an association module 204 is configured to associate the calculation result with the street engineering construction project management flowchart data.
Optionally, the parsing module 201 is further configured to:
analyzing the management document of the street engineering project uploaded by the user to locate the document position corresponding to the street engineering project management flow chart data, and intercepting the street engineering project management flow chart data in a specified format from the document position.
Optionally, the parsing module 201 is further configured to:
node attribute data of the project management node is acquired,
The project management node comprises a project design node, a budget review node, a project bid-inviting node, a contract processing node, a project implementation node and a project settlement node;
The node attribute data of the project design node includes: project design drawings, project design schemes and street project site investigation record tables;
The node attribute data of the budget review node comprises: project budget files and project design drawings;
The node attribute data of the project bid-inviting node comprises: purchasing platform information, project schedule registration form, purchasing project execution notice, project bidding agreement data and winning bid unit data corresponding to different budget intervals;
The node attribute data of the contract processing node includes: project contract auditing opinion documents and construction contract documents;
the node attribute data of the project implementation node includes: project supervision week report data and construction problem notification data;
The node attribute data of the item settlement node includes: project acceptance data, settlement audit data.
Optionally, the execution module 203 is further configured to:
Checking the budget file and the construction drawing file, and determining the budget amount according to the checked budget file;
determining an amount interval according to the budget amount to call a corresponding platform for initial project data entry;
determining an item bidding category according to the initial item data, and determining a winning unit according to the item bidding category;
And generating a project contract by combining the unit data of the winning unit.
Optionally, the execution module 203 is further configured to:
checking stamping of the project design drawing through image recognition;
Carrying out integrity check on the project design scheme through key field verification;
Carrying out integrity check on the on-site investigation record table of the street project through key field check;
and carrying out integrity check on the project budget file through key field verification.
Optionally, the execution module 203 is further configured to:
and the unit data of the winning bid unit is summarized, and project contract auditing opinion documents and construction contract documents are generated according to the summarized unit data.
Optionally, the association module 204 is further configured to:
And integrating the node tasks and the calculation results of each project management node, and filling the street engineering construction project management flow chart data according to the integrated data.
It should be noted that: in the device provided in the above embodiment, when implementing the functions thereof, only the division of the above functional modules is used as an example, in practical application, the above functional allocation may be implemented by different functional modules according to needs, that is, the internal structure of the device is divided into different functional modules, so as to implement all or part of the functions described above. In addition, the embodiments of the apparatus and the method provided in the foregoing embodiments belong to the same concept, and specific implementation processes of the embodiments of the method are detailed in the method embodiments, which are not repeated herein.
The embodiment also discloses an electronic device, referring to fig. 3, the electronic device may include: at least one processor 301, at least one communication bus 302, a user interface 303, a network interface 304, at least one memory 305.
Wherein the communication bus 302 is used to enable connected communication between these components.
The user interface 303 may include a Display screen (Display), a Camera (Camera), and the optional user interface 303 may further include a standard wired interface, and a wireless interface.
The network interface 304 may optionally include a standard wired interface, a wireless interface (e.g., WI-FI interface), among others.
Wherein the processor 301 may include one or more processing cores. The processor 301 utilizes various interfaces and lines to connect various portions of the overall server, perform various functions of the server and process data by executing or executing instructions, programs, code sets, or instruction sets stored in the memory 305, and invoking data stored in the memory 305. Alternatively, the processor 301 may be implemented in at least one hardware form of digital signal Processing (DIGITAL SIGNAL Processing, DSP), field-Programmable gate array (Field-Programmable GATE ARRAY, FPGA), programmable logic array (Programmable Logic Array, PLA). The processor 301 may integrate one or a combination of several of a central processor 301 (Central Processing Unit, CPU), an image processor 301 (Graphics Processing Unit, GPU), a modem, etc. The CPU mainly processes an operating system, a user interface, an application program and the like; the GPU is used for rendering and drawing the content required to be displayed by the display screen; the modem is used to handle wireless communications. It will be appreciated that the modem may not be integrated into the processor 301 and may be implemented by a single chip.
The Memory 305 may include a random access Memory 305 (Random Access Memory, RAM), or may include a Read-Only Memory 305 (Read-Only Memory). Optionally, the memory 305 includes a non-transitory computer readable medium (non-transitory computer-readable storage medium). Memory 305 may be used to store instructions, programs, code, sets of codes, or sets of instructions. The memory 305 may include a stored program area and a stored data area, wherein the stored program area may store instructions for implementing an operating system, instructions for at least one function (such as a touch function, a sound playing function, an image playing function, etc.), instructions for implementing the above-described respective method embodiments, etc.; the storage data area may store data or the like involved in the above respective method embodiments. Memory 305 may also optionally be at least one storage device located remotely from the aforementioned processor 301. As shown, the memory 305, which is a type of computer storage medium, may include an operating system, a network communication module, a user interface module, and applications for project management methods for street engineering.
In the electronic device shown in fig. 3, the user interface 303 is mainly used for providing an input interface for a user, and acquiring data input by the user; and the processor 301 may be used to invoke an application in the memory 305 that stores project management methods of street engineering construction, which when executed by the one or more processors 301, causes the electronic device to perform the methods as in one or more of the embodiments described above.
It should be noted that, for simplicity of description, the foregoing method embodiments are all described as a series of acts, but it should be understood by those skilled in the art that the present application is not limited by the order of acts described, as some steps may be performed in other orders or concurrently in accordance with the present application. Further, those skilled in the art will also appreciate that the embodiments described in the specification are all of the preferred embodiments, and that the acts and modules referred to are not necessarily required for the present application.
In the foregoing embodiments, the descriptions of the embodiments are emphasized, and for parts of one embodiment that are not described in detail, reference may be made to related descriptions of other embodiments.
In the several embodiments provided by the present application, it should be understood that the disclosed apparatus may be implemented in other ways. For example, the apparatus embodiments described above are merely illustrative, such as a division of units, merely a division of logic functions, and there may be additional divisions in actual implementation, such as multiple units or components may be combined or integrated into another system, or some features may be omitted, or not performed. Alternatively, the coupling or direct coupling or communication connection shown or discussed with each other may be through some service interface, device or unit indirect coupling or communication connection, electrical or otherwise.
The units described as separate units may or may not be physically separate, and units shown as units may or may not be physical units, may be located in one place, or may be distributed over a plurality of network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
In addition, each functional unit in the embodiments of the present application may be integrated in one processing unit, or each unit may exist alone physically, or two or more units may be integrated in one unit. The integrated units may be implemented in hardware or in software functional units.
The integrated units, if implemented in the form of software functional units and sold or used as stand-alone products, may be stored in a computer readable memory 305. Based on this understanding, the technical solution of the present application may be embodied essentially or partly in the form of a software product, or all or part of the technical solution, which is stored in a memory 305, and includes several instructions for causing a computer device (which may be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method of the embodiments of the present application. And the aforementioned memory 305 includes: various media capable of storing program codes, such as a U disk, a mobile hard disk, a magnetic disk or an optical disk.
The foregoing is merely exemplary embodiments of the present disclosure and is not intended to limit the scope of the present disclosure. That is, equivalent changes and modifications are contemplated by the teachings of this disclosure, which fall within the scope of the present disclosure. Other embodiments of the disclosure will be apparent to those skilled in the art from consideration of the specification and practice of the disclosure. This application is intended to cover any variations, uses, or adaptations of the disclosure following, in general, the principles of the disclosure and including such departures from the present disclosure as come within known or customary practice within the art to which the disclosure pertains. It is intended that the specification and examples be considered as exemplary only, with a scope and spirit of the disclosure being indicated by the claims.

Claims (10)

1. A project management method for street engineering construction, applied to a project management platform, the method comprising:
Acquiring and analyzing data of a street engineering construction project management flow chart, and determining association relations among project management nodes;
Generating project management task execution time sequences corresponding to each project management node according to the association relation;
carrying out node task calculation on each project management node in turn according to the project management task execution time sequence to obtain a calculation result;
and correlating the calculation result with the street engineering construction project management flow chart data.
2. The method of claim 1, wherein the obtaining and parsing the street engineering project management flow chart data comprises:
analyzing the management document of the street engineering project uploaded by the user to locate the document position corresponding to the street engineering project management flow chart data, and intercepting the street engineering project management flow chart data in a specified format from the document position.
3. The method of claim 1, wherein the obtaining and parsing the street engineering project management flow chart data further comprises:
node attribute data of the project management node is acquired,
The project management node comprises a project design node, a budget review node, a project bid-inviting node, a contract processing node, a project implementation node and a project settlement node;
The node attribute data of the project design node includes: project design drawings, project design schemes and street project site investigation record tables;
The node attribute data of the budget review node comprises: project budget files and project design drawings;
The node attribute data of the project bid-inviting node comprises: purchasing platform information, project schedule registration form, purchasing project execution notice, project bidding agreement data and winning bid unit data corresponding to different budget intervals;
The node attribute data of the contract processing node includes: project contract auditing opinion documents and construction contract documents;
the node attribute data of the project implementation node includes: project supervision week report data and construction problem notification data;
The node attribute data of the item settlement node includes: project acceptance data, settlement audit data.
4. A method for project management of street engineering construction according to claim 3, wherein the sequentially performing node task calculation on each project management node according to the project management task execution sequence and obtaining a calculation result includes:
Checking the budget file and the construction drawing file, and determining the budget amount according to the checked budget file;
determining an amount interval according to the budget amount to call a corresponding platform for initial project data entry;
determining an item bidding category according to the initial item data, and determining a winning unit according to the item bidding category;
And generating a project contract by combining the unit data of the winning unit.
5. The method of project management for street engineering construction of claim 4, wherein said checking the budget file and the construction map file comprises:
checking stamping of the project design drawing through image recognition;
Carrying out integrity check on the project design scheme through key field verification;
Carrying out integrity check on the on-site investigation record table of the street project through key field check;
and carrying out integrity check on the project budget file through key field verification.
6. The method of claim 5, wherein generating the project contract in connection with the unit data of the winning unit comprises:
and the unit data of the winning bid unit is summarized, and project contract auditing opinion documents and construction contract documents are generated according to the summarized unit data.
7. The project management method of street construction according to claim 1, wherein the associating the calculation result with the street construction project management flowchart data comprises:
And integrating the node tasks and the calculation results of each project management node, and filling the street engineering construction project management flow chart data according to the integrated data.
8. The project management system for street engineering construction is characterized by comprising an analysis module, a time sequence module, an execution module and a correlation module, wherein:
the analysis module is configured to acquire and analyze the street engineering construction project management flow chart data and determine the association relation among each project management node;
The time sequence module is configured to generate a project management task execution time sequence corresponding to each project management node according to the association relation;
the execution module is configured to sequentially perform node task calculation on each project management node according to the project management task execution time sequence and obtain a calculation result;
and the association module is configured to associate the calculation result with the street engineering construction project management flow chart data.
9. An electronic device comprising a processor, a memory, a user interface, and a network interface, the memory for storing instructions, the user interface and the network interface each for communicating with other devices, the processor for executing instructions stored in the memory to cause the electronic device to perform the method of any of claims 1-7.
10. A computer readable storage medium storing instructions which, when executed, perform the method of any one of claims 1-7.
CN202410115173.1A 2024-01-26 2024-01-26 Project management method, system, equipment and medium for street engineering construction Pending CN117952552A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202410115173.1A CN117952552A (en) 2024-01-26 2024-01-26 Project management method, system, equipment and medium for street engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202410115173.1A CN117952552A (en) 2024-01-26 2024-01-26 Project management method, system, equipment and medium for street engineering construction

Publications (1)

Publication Number Publication Date
CN117952552A true CN117952552A (en) 2024-04-30

Family

ID=90805027

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202410115173.1A Pending CN117952552A (en) 2024-01-26 2024-01-26 Project management method, system, equipment and medium for street engineering construction

Country Status (1)

Country Link
CN (1) CN117952552A (en)

Similar Documents

Publication Publication Date Title
CN108984418B (en) Software test management method and device, electronic equipment and storage medium
CN110457294B (en) Data processing method and device
US8706684B2 (en) System and method for managing enterprise data
CN111062690A (en) User purchase management system based on block chain technology
CN112001586A (en) Enterprise networking big data audit risk control architecture based on block chain consensus mechanism
CN109377282A (en) Real estate Land Appraisal production management method and system, computer equipment and storage medium
Söylemez et al. Challenges of software process and product quality improvement: catalyzing defect root-cause investigation by process enactment data analysis
CN104200324A (en) Business knowledge management based configuration management method
CN109711849B (en) Ether house address portrait generation method and device, electronic equipment and storage medium
CN115221380A (en) Method, system and platform for managing urban construction files in batches
CN111476597A (en) Resource quantity estimation result processing method and related equipment
CN117952552A (en) Project management method, system, equipment and medium for street engineering construction
CN114722789B (en) Data report integrating method, device, electronic equipment and storage medium
CN116051272A (en) Enterprise risk analysis method and related equipment
CN115186025A (en) Automatic configuration method, system and equipment of visual report
CN111933228B (en) Method and device for realizing project distribution and management system in clinical research
CN112465456A (en) Engineering evaluation data information management method, system and electronic equipment
CN112488652B (en) Work order auditing method, system, terminal and storage medium
Jing et al. Research on Data Assets and Their Appraisal Models
CN114596068A (en) Project evaluation method and device, electronic equipment and storage medium
CN114549217A (en) Credit data generation method and device, computer equipment and readable storage medium
CN116909844A (en) Resource interaction information early warning method and device, computer equipment and storage medium
CN116610674A (en) Information processing method, device, equipment and storage medium
CN117951341A (en) Block chain-based service processing method, device, equipment, medium and product
CN115587723A (en) Control method and system for visual quality control process of engineering design

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination