CN117488804A - Construction method for cleaning and controlling sediment of large-diameter pier foundation - Google Patents

Construction method for cleaning and controlling sediment of large-diameter pier foundation Download PDF

Info

Publication number
CN117488804A
CN117488804A CN202311488401.1A CN202311488401A CN117488804A CN 117488804 A CN117488804 A CN 117488804A CN 202311488401 A CN202311488401 A CN 202311488401A CN 117488804 A CN117488804 A CN 117488804A
Authority
CN
China
Prior art keywords
sediment
steel
rock
pile
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311488401.1A
Other languages
Chinese (zh)
Inventor
陈瑞
李雷
陈琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Construction Engineering Co ltd
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Construction Engineering Co ltd
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Construction Engineering Co ltd, Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Construction Engineering Co ltd
Priority to CN202311488401.1A priority Critical patent/CN117488804A/en
Publication of CN117488804A publication Critical patent/CN117488804A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/08Removing obstacles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/68Mould-pipes or other moulds for making bulkheads or elements thereof

Abstract

The invention relates to a construction method for cleaning and controlling sediment of a foundation of a large-diameter pier; before pile foundation construction, a rotary drilling rig and a drilling and pulling machine matched with project rock entering strength are selected, and lofting is measured: each pile position is fixed and placed by a GPS according to the design requirement; burying a steel pile casing, wherein the buried steel pile casing penetrates through the crushed pebble layer to enter strong wind for at least 2 meters, and the steel pile casing is constructed by adopting a beating-pulling-level vibrating hammer; when the drilling machine is in place, the ground is flattened, compacted and paved with steel plates, the drill rod is adjusted to be vertical, and the center of the drilling hole is ensured to meet the design requirement. The method is based on the existing technological process, and the pile casing method is added before pier foundation punching, so that the hole forming efficiency is effectively improved, hole wall soil disturbance is reduced, and sediment control effect is improved.

Description

Construction method for cleaning and controlling sediment of large-diameter pier foundation
Technical Field
The invention relates to the technical field of foundation construction, in particular to a large-diameter pier foundation construction technology, and specifically relates to a large-diameter pier foundation sediment cleaning control construction method.
Background
Nowadays, pile foundation design of house building engineering generally adopts bored concrete piles or precast piles, the diameter of precast pile is generally different between 300 mm-1000 mm, the diameter of bored concrete piles is generally 600 mm-1500 mm (more than 1500mm is generally used for municipal bridge engineering piles). Aiming at the conventional pile foundation engineering, the current construction process is mature, the construction quality also has good guarantee measures, but the effective quality guarantee measures of the large-diameter cast-in-place pile with the diameter of 1600mm are few under the working condition that the geology is complex and the rock stratum has large fluctuation. The current method is consistent with the common 600-1500 mm bored pile construction process, and by adopting the method, the risk of hole collapse is increased, and the hole forming and hole cleaning efficiency is low.
Disclosure of Invention
The invention aims to overcome the defects, and provides a pier foundation construction process with large diameter (1600 mm and above) on the premise of harder rock aiming at complex geology (large fluctuation of underground rock stratum, maximum height difference of 10m, and pile foundation bearing layer of 10-3B layer: apoplexy granite, and standard value of rock saturated uniaxial compressive strength of 53.2 MPa).
In order to achieve the above object, the present invention is achieved by:
a construction method for cleaning and controlling sediment of a large-diameter pier foundation comprises the following steps of
Step 1, mechanical type selection: before pile foundation construction, a rotary drilling rig matched with the rock entering strength of the project is selected, and a drilling and pulling machine matched with a rock stratum is selected because a steel casing is needed to be arranged in the follow-up process, and the 450-type drilling and pulling machine is selected in the project;
step 2, measuring and lofting: each pile position is fixed by GPS according to the design requirement, and is implemented after rechecking by the measurement of the relevant unit;
step 3, embedding a steel pile casing: in order to improve the pore-forming effect, a method of embedding a steel casing is adopted, and a thickened steel ring is adopted for welding a top ring of the casing, so that the casing is prevented from deforming during the beating and drawing; when the underground water level is higher, the buried steel casing penetrates through the crushed pebble layer to enter strong weathered for at least 2 meters, so that hole collapse is reduced; because the pier foundation piles are short, the steel pile casings with sufficient lengths are configured on site in combination with the land survey report until the steel pile casings are driven to the top surface of the bedrock; the steel pile casing is rolled by adopting a steel plate with the thickness of 18mm, and the diameter is the same as the designed pile diameter; the top ring of the protective cylinder is welded by a thickened steel ring, so that the protective cylinder and the edge cannot deform when the protective cylinder is pulled out; the steel pile casing is constructed by adopting a beating-pulling-level vibrating hammer;
step 4: and (3) positioning a drilling machine: firstly, ensuring that the foundation under the drilling machine does not sink, when the drilling machine is in place, firstly leveling, compacting and paving a steel plate on the ground, adjusting a drill rod vertically, then checking whether the pile center newly defined after the pile casing is embedded coincides with the drill bit center, and if the deviation is larger, adjusting the position of the drilling machine, so as to ensure that the center of the drilled hole meets the design requirement.
The construction method for cleaning and controlling the sediment of the foundation of the large-diameter pier is characterized by comprising the following steps of: it comprises a bottom plate connecting part, a rock sediment crushing part and a rock sediment collecting part. The bottom plate connecting part is connected with the bottom plate of the sediment collecting barrel through welding, and the rock sediment crushing part is welded on two sides of the bottom plate connecting part in a mutually perpendicular mode by 2 high-strength steel plates. The rock sediment collecting part consists of 2 pentagonal steel plates, and 2 right-angle sides of the pentagonal steel plates are respectively connected with the sediment collecting barrel bottom plate and the rock sediment crushing part by welding;
when the drill bit rotates, firstly, the rock sediment breaking part breaks the rock for the first time, and as the drill bit continuously descends, the rock sediment breaking part breaks the rock for the second time, and meanwhile, the drill bit rotates to collect the broken rock sediment into the sediment collecting barrel.
The construction method for cleaning and controlling the sediment of the foundation of the large-diameter pier is characterized by comprising the following steps of: the rock sediment crushing part adopts a blade made of high-strength steel.
According to the invention, on the basis of the existing technological process, a pile casing method is added before the pier foundation is perforated, and drilling is carried out within the range of the steel pile casing, so that soil body can be prevented from moving around, then the bottom of a hole is cleaned in the pile casing, then the pile casing is pulled out, the hole forming efficiency is effectively improved, hole wall soil disturbance is reduced, and the sediment control effect is improved; then, by a method of leading holes and then drilling holes, the drilling speed is improved, the disturbance of soil mass on the hole wall is reduced, and the sediment control effect is improved; and finally, a drilling sediment crushing and collecting synchronous method is utilized, so that sediment collecting efficiency and effect are greatly improved.
The series of methods adopted by the invention have remarkable improvement effect in improving the hole opening efficiency, controlling the fine sediment and cleaning the sediment efficiently. And a new construction process is developed by utilizing the existing partial process foundation, so that the construction efficiency is high, the construction quality is also greatly ensured, and the pile forming quality of the whole pier foundation is well ensured.
Drawings
FIG. 1 is a schematic view of a sediment removal assembly.
Detailed Description
The invention is further illustrated by the following specific examples.
A construction method for cleaning and controlling sediment of a large-diameter pier foundation comprises the following steps of
Step 1, mechanical type selection: before pile foundation construction, a rotary drilling rig matched with the rock entering strength of the project is selected, and a drilling and pulling machine matched with a rock stratum is selected because a steel casing is needed to be arranged in the follow-up process, and the 450-type drilling and pulling machine is selected in the project;
step 2, measuring and lofting: each pile position is fixed by GPS according to the design requirement, and is implemented after rechecking by the measurement of the relevant unit;
step 3, embedding a steel pile casing: in order to improve the pore-forming effect, a method of embedding a steel casing is adopted, and a thickened steel ring is adopted for welding a top ring of the casing, so that the casing is prevented from deforming during the beating and drawing; when the underground water level is higher, the buried steel casing penetrates through the crushed pebble layer to enter strong weathered for at least 2 meters, so that hole collapse is reduced; because the pier foundation piles are short, the steel pile casings with sufficient lengths are configured on site in combination with the land survey report until the steel pile casings are driven to the top surface of the bedrock; the steel pile casing is rolled by adopting a steel plate with the thickness of 18mm, and the diameter is the same as the designed pile diameter; the top ring of the protective cylinder is welded by a thickened steel ring, so that the protective cylinder and the edge cannot deform when the protective cylinder is pulled out; the steel pile casing is constructed by adopting a beating-pulling-level vibrating hammer;
step 4: and (3) positioning a drilling machine: firstly, ensuring that the foundation under the drilling machine does not sink, when the drilling machine is in place, firstly leveling, compacting and paving a steel plate on the ground, adjusting a drill rod vertically, then checking whether the pile center newly defined after the pile casing is embedded coincides with the drill bit center, and if the deviation is larger, adjusting the position of the drilling machine, so as to ensure that the center of the drilled hole meets the design requirement.
The sediment cleaning device in the bored pile construction method of the large straight pier comprises a bottom plate connecting part 1, a rock sediment crushing part 2 and a rock sediment collecting part. The bottom plate connecting part 1 is connected with the bottom plate of the sediment collecting barrel through welding, and the rock sediment crushing part is welded on two sides of the bottom plate connecting part 1 in a mutually perpendicular mode by 2 high-strength steel plates. The rock sediment collecting part 3 consists of 2 pentagonal steel plates, and the 2 right-angle sides of the pentagonal steel plates are respectively connected with the sediment collecting barrel bottom plate and the rock sediment crushing part 2 through welding;
when the drill bit rotates, firstly, the rock sediment breaking part breaks the rock for the first time, and as the drill bit continuously descends, the rock sediment breaking part breaks the rock for the second time, and meanwhile, the drill bit rotates to collect the broken rock sediment into the sediment collecting barrel.
The rock sediment crushing part adopts a blade made of high-strength steel.
The sediment cleaning device can be used for effectively smashing rock and soil sediment for 2 times, so that the volume of the rock sediment is reduced, the smashed rock sediment is pushed into the sediment collecting barrel by means of the thrust of the rotation of the drill bit, the sediment hole cleaning effect of the rock and soil sediment is effectively improved, the sediment thickness of a pile hole is reduced, and the pouring quality is further improved.
According to the invention, on the basis of the existing process flow, the pile casing method is added before pier foundation punching, so that the hole forming efficiency is effectively improved, the hole wall soil disturbance is reduced, and the sediment control effect is improved; then, by a method of leading holes and then drilling holes, the drilling speed is improved, the disturbance of soil mass on the hole wall is reduced, and the sediment control effect is improved; and finally, a drilling sediment crushing and collecting synchronous method is utilized, so that sediment collecting efficiency and effect are greatly improved.
The series of methods adopted by the invention have remarkable improvement effect in improving the hole opening efficiency, controlling the fine sediment and cleaning the sediment efficiently. And a new construction process is developed by utilizing the existing partial process foundation, so that the construction efficiency is high, the construction quality is also greatly ensured, and the pile forming quality of the whole pier foundation is well ensured.

Claims (4)

1. A construction method for cleaning and controlling sediment of a large-diameter pier foundation is characterized by comprising the following steps: comprising
Step 1, mechanical type selection: before pile foundation construction, a rotary drilling rig matched with the rock entering strength of the project is selected, and a drilling and pulling machine matched with a rock stratum is selected because a steel casing is needed to be arranged in the follow-up process, and the 450-type drilling and pulling machine is selected in the project;
step 2, measuring and lofting: each pile position is fixed by GPS according to the design requirement, and is implemented after rechecking by the measurement of the relevant unit;
step 3, embedding a steel pile casing: in order to improve the pore-forming effect, a method of embedding a steel casing is adopted, and a thickened steel ring is adopted for welding a top ring of the casing, so that the casing is prevented from deforming during the beating and drawing; when the underground water level is higher, the buried steel casing penetrates through the crushed pebble layer to enter strong weathered for at least 2 meters, so that hole collapse is reduced; because the pier foundation piles are short, the steel pile casings with sufficient lengths are configured on site in combination with the land survey report until the steel pile casings are driven to the top surface of the bedrock; the steel pile casing is rolled by adopting a steel plate with the thickness of 18mm, and the diameter is the same as the designed pile diameter; the top ring of the protective cylinder is welded by a thickened steel ring, so that the protective cylinder and the edge cannot deform when the protective cylinder is pulled out; the steel pile casing is constructed by adopting a beating-pulling-level vibrating hammer;
step 4: and (3) positioning a drilling machine: firstly, ensuring that the foundation under the drilling machine does not sink, when the drilling machine is in place, firstly leveling, compacting and paving a steel plate on the ground, adjusting a drill rod vertically, then checking whether the pile center newly defined after the pile casing is embedded coincides with the drill bit center, and if the deviation is larger, adjusting the position of the drilling machine, so as to ensure that the center of the drilled hole meets the design requirement.
2. The construction method for cleaning and controlling the sediment of the foundation of the large-diameter pier according to claim 1, which is characterized by comprising the following steps: and cleaning holes through a large-diameter pier foundation sediment cleaning device.
3. The construction method for cleaning and controlling the sediment of the foundation of the large-diameter pier according to claim 2, which is characterized in that: the large-diameter pier foundation sediment cleaning device comprises a bottom plate connecting part (1), a rock sediment crushing part (2) and a rock sediment collecting part. The bottom plate connecting part (1) is connected with the bottom plate of the sediment collecting barrel through welding, and the rock sediment crushing part is welded on two sides of the bottom plate connecting part (1) through 2 high-strength steel plates in a mutually perpendicular mode. The rock sediment collecting part (3) consists of 2 pentagonal steel plates, and 2 right-angle sides of the pentagonal steel plates are respectively connected with a sediment collecting barrel bottom plate and the rock sediment crushing part (2) through welding;
when the drill bit rotates, firstly, the rock sediment breaking part breaks the rock for the first time, and as the drill bit continuously descends, the rock sediment breaking part breaks the rock for the second time, and meanwhile, the drill bit rotates to collect the broken rock sediment into the sediment collecting barrel.
4. A large straight pier bored pile sediment cleaning apparatus according to claim 3, wherein: the rock sediment crushing part adopts a blade made of high-strength steel.
CN202311488401.1A 2023-11-09 2023-11-09 Construction method for cleaning and controlling sediment of large-diameter pier foundation Pending CN117488804A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311488401.1A CN117488804A (en) 2023-11-09 2023-11-09 Construction method for cleaning and controlling sediment of large-diameter pier foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311488401.1A CN117488804A (en) 2023-11-09 2023-11-09 Construction method for cleaning and controlling sediment of large-diameter pier foundation

Publications (1)

Publication Number Publication Date
CN117488804A true CN117488804A (en) 2024-02-02

Family

ID=89684462

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311488401.1A Pending CN117488804A (en) 2023-11-09 2023-11-09 Construction method for cleaning and controlling sediment of large-diameter pier foundation

Country Status (1)

Country Link
CN (1) CN117488804A (en)

Similar Documents

Publication Publication Date Title
CN107938676B (en) Pile foundation construction method for penetrating through full-filling karst cave
CN108589718B (en) Piles in Karst Region base construction method
CN104747088B (en) A kind of leafy hosqe bit of cast-in-situ bored pile list waist and drilling construction method
WO2018210019A1 (en) Pile formation method for down-the-hole impact rotary jet composite piles
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN105780763B (en) Mesoporous vibrates the construction method of casing retaining wall long auger guncreting pile
CN111335306A (en) Rapid construction method for deep and thick hard rock section drilled pile
CN111395330B (en) Construction method for concrete cast-in-situ bored pile complete steel casing penetrating through underground gallery
CN108589707A (en) A kind of full-sleeve long screw auger and churning driven combined type construction
CN109385992B (en) Construction method for forming hole in artificial stone-filling layer
CN112030956A (en) Karst stratum bored pile construction method
CN113550305B (en) Construction method and drill bit for high-pressure water jet stiffening core composite pile of hard soil interlayer foundation
CN110761265A (en) Karst cave disposal method for deep foundation pit pile foundation construction in karst area
CN104329020B (en) A kind of reinforced long spire embedding rock construction equipment and technique thereof
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
CN110735432A (en) Method for clearing pile foundation and controlling parameters in shield tunneling machine over-invasion limit tunnel range
CN103015408A (en) Cast-in-place pile synchronous casing hole-forming constructing method
US10487468B2 (en) Mandrel and a method for soil compaction
CN108071110A (en) Rotary drilling rig Pile method under complex geological condition
CN111910634A (en) Karst geological impact pore-forming construction method
CN110512594B (en) Simple method for forming hole and pile in cavity of rotary drilling rig
CN204225100U (en) The construction equipment of concrete pile
CN109113054A (en) A kind of reclaimation area complex geological condition cast-in-situ bored pile multimachine combined construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination