CN117474463A - Site supervision method and system - Google Patents

Site supervision method and system Download PDF

Info

Publication number
CN117474463A
CN117474463A CN202311260003.4A CN202311260003A CN117474463A CN 117474463 A CN117474463 A CN 117474463A CN 202311260003 A CN202311260003 A CN 202311260003A CN 117474463 A CN117474463 A CN 117474463A
Authority
CN
China
Prior art keywords
supervision
site
mobile
construction
terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311260003.4A
Other languages
Chinese (zh)
Inventor
宿良
何非
王江华
操义龙
施通勤
王清波
郑明煌
冯文
赵小斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Zhongchao Power Grid Construction Supervision Co ltd
Original Assignee
Wuhan Zhongchao Power Grid Construction Supervision Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Zhongchao Power Grid Construction Supervision Co ltd filed Critical Wuhan Zhongchao Power Grid Construction Supervision Co ltd
Priority to CN202311260003.4A priority Critical patent/CN117474463A/en
Publication of CN117474463A publication Critical patent/CN117474463A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F11/00Error detection; Error correction; Monitoring
    • G06F11/07Responding to the occurrence of a fault, e.g. fault tolerance
    • G06F11/14Error detection or correction of the data by redundancy in operation
    • G06F11/1402Saving, restoring, recovering or retrying
    • G06F11/1446Point-in-time backing up or restoration of persistent data
    • G06F11/1448Management of the data involved in backup or backup restore
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/21Design, administration or maintenance of databases
    • G06F16/215Improving data quality; Data cleansing, e.g. de-duplication, removing invalid entries or correcting typographical errors
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/28Databases characterised by their database models, e.g. relational or object models
    • G06F16/284Relational databases
    • G06F16/285Clustering or classification
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F21/00Security arrangements for protecting computers, components thereof, programs or data against unauthorised activity
    • G06F21/60Protecting data
    • G06F21/64Protecting data integrity, e.g. using checksums, certificates or signatures
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Databases & Information Systems (AREA)
  • Marketing (AREA)
  • Health & Medical Sciences (AREA)
  • Quality & Reliability (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Engineering & Computer Science (AREA)
  • Data Mining & Analysis (AREA)
  • General Health & Medical Sciences (AREA)
  • Computer Security & Cryptography (AREA)
  • Primary Health Care (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Game Theory and Decision Science (AREA)
  • Bioethics (AREA)
  • Computer Hardware Design (AREA)
  • Software Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the technical field of supervision, in particular to a field supervision method, which comprises the following steps: acquiring an operation plan of a target project; the operation plan comprises construction information of at least one working procedure, and a corresponding supervision form is matched for each working procedure based on the construction information; distributing the supervision form of the corresponding procedure to a specified mobile supervision terminal; acquiring the position information of the mobile supervision terminal in real time, and matching the position information of the mobile supervision terminal with the address information in the construction information; the matching is successful, and the mobile supervision terminal is allowed to operate the supervision form; otherwise, prohibiting the operation of the supervision form by the mobile supervision terminal; filling in a supervision form on the mobile supervision terminal according to the site situation, and uploading and storing the supervision form. The design avoids the problem of inaccurate or distorted data caused by filling errors or misoperation, and improves the quality and the credibility of the supervision data.

Description

Site supervision method and system
[ field of technology ]
The invention relates to the technical field of supervision, in particular to a field supervision method and a field supervision system.
[ background Art ]
Along with the acceleration of the transformation speed of Chinese energy sources, the construction scale of electric power engineering is larger and larger, the technology is more and more complex, the national management is advanced more and more deeply according to law, the traditional management mode of the management is insufficient, and the progress of electric power construction is seriously hindered. The traditional supervision mode of man-sea tactics and experience management is relied on, so that the operation cost is high, the management quality is low, and the development of supervision enterprises is seriously restricted.
Engineering supervision is an industry with high intelligence and high technical content, and various difficulties and opportunities are faced with continuous progress of the age and continuous development of society. The method has the advantages of grasping the time development opportunity, changing the current situation of the supervision industry, effectively playing the supervision role, and changing the urgent demands of the supervision industry.
However, in the current supervision flow, there is a vulnerability in the supervision of first-line supervision personnel.
[ invention ]
In order to solve the problem that the management and control of first-line supervision personnel is easy to have loopholes in the current supervision flow, the invention provides the following technical scheme for solving the technical problems: a method of on-site supervision, comprising the steps of:
acquiring an operation plan of a target project;
the operation plan comprises construction information of at least one working procedure, and a corresponding supervision form is matched for each working procedure based on the construction information;
distributing the supervision form of the corresponding procedure to the mobile supervision terminal;
acquiring the position information of the mobile supervision terminal in real time, and matching the position information of the mobile supervision terminal with the address information in the construction information;
the matching is successful, and the mobile supervision terminal is allowed to operate the supervision form; otherwise, prohibiting the operation of the supervision form by the mobile supervision terminal;
filling in a supervision form on the mobile supervision terminal according to the site situation, and uploading and storing the supervision form.
Preferably, the construction information includes a construction scheme and a construction time of at least one process construction stage.
Preferably, the supervision form is provided with a review content block and a corresponding review result block.
Preferably, in the process of filling in the supervision form, the location of the mobile supervision terminal is continuously acquired, and if the location of the mobile supervision terminal leaves the preset area, the mobile supervision terminal is forbidden to operate the supervision form.
Preferably, the construction information includes position information of the preset area; or the construction information comprises a construction site, and an area in a preset radius direction with the construction site as a center is defined as the preset area.
Preferably, the method further comprises the preliminary steps of: and constructing a form database, wherein the database comprises a plurality of supervision forms required by the engineering at different stages.
Preferably, in the form database, the supervision forms are classified and marked according to the engineering type, the process type and the process stage.
Preferably, when the target project is completed, all the supervision forms uploaded during the execution of the operation plan are called for re-backup.
Preferably, the uploaded form is locked for its filling out content and is not allowed to be modified for subsequent viewing.
The invention provides another technical scheme for solving the technical problems as follows: the on-site supervision system is used for realizing the supervision method, and comprises a platform server, a database and a mobile supervision terminal which are respectively in communication connection with the platform server.
Compared with the prior art, the on-site supervision method and system provided by the invention have the following beneficial effects:
1. the on-site supervision method provided by the embodiment of the invention comprises the following steps: acquiring an operation plan of a target project; the operation plan comprises construction information of at least one working procedure, and a corresponding supervision form is matched for each working procedure based on the construction information; distributing the supervision form of the corresponding procedure to the mobile supervision terminal; acquiring the position information of the mobile supervision terminal in real time, and matching the position information of the mobile supervision terminal with the address information in the construction information; the matching is successful, and the mobile supervision terminal is allowed to operate the supervision form; otherwise, prohibiting the operation of the supervision form by the mobile supervision terminal; filling in a supervision form on the mobile supervision terminal according to the site situation, and uploading and storing the supervision form. It will be appreciated that by matching location information with address information and requiring that the matching be successful before operation is allowed, it is ensured that the proctor will only fill in and submit proctoring forms in the correct procedure. The design avoids the problem of inaccurate or distorted data caused by filling errors or misoperation, and improves the quality and the credibility of the supervision data; meanwhile, the real-time position of the supervision personnel can be monitored. Such a design can provide more accurate supervisor location information and direct, schedule, or emergency response when needed.
2. In the on-site supervision method according to the embodiment of the invention, the construction information includes a construction scheme and a construction time of at least one working procedure construction stage. It will be appreciated that by including construction information for the construction plan and the construction time, the supervisor can better understand the plan and timing of the engineering process. The method is beneficial to effectively controlling and supervising the engineering progress, ensuring that the construction is carried out according to a preset plan, and timely finding and solving the problem that the process progress is possibly affected; meanwhile, the detailed construction information can help a supervision staff to quickly find an applicable supervision form, so that time and energy waste are avoided in selecting and modifying an irrelevant form; the accurate supervision form is matched, which means that the fields and the contents in the form are consistent with the actual requirements of the working procedure, so that the supervision information of the working procedure can be recorded and tracked more accurately; the applicable supervision form can provide clear filling instruction and field requirements, and reduce guesses and errors, so that the working efficiency of supervision staff is improved; by matching an accurate supervision form, the collected data can be ensured to correspond to construction information, and the arrangement, analysis and archiving of the data are facilitated.
3. In the on-site supervision method of the embodiment of the invention, the supervision form is provided with an examination content block and a corresponding examination result block. It will be appreciated that the review content block provides explicit review requirements and guidelines from which a supervisor can conduct review work, avoiding missing or disregarding important review items; meanwhile, the examination result block also provides standardized options or filling fields for the supervision personnel to accurately record examination results and improve examination accuracy.
4. In the on-site supervision method provided by the embodiment of the invention, the position of the mobile supervision terminal is continuously acquired in the process of filling the supervision form, and if the position of the mobile supervision terminal leaves a preset area, the mobile supervision terminal is forbidden to operate the supervision form. It can be understood that by continuously acquiring the position information of the mobile supervision terminal and monitoring, the supervision personnel can be ensured to perform supervision work only in a preset area. The design can avoid the situation that the supervision form is still filled out after the supervision personnel leave the engineering site or the designated area. The method effectively suppresses the non-compliance actions such as remote form filling and the like, and improves the accuracy and the instantaneity of supervision data; the actual observation, inspection and evaluation of the engineering site by the supervision personnel are promoted, and the potential problems and hidden troubles can be found in time; the quality and the safety of engineering are further improved by improving the quality and the actual effect of supervision work.
5. In the on-site supervision method of the embodiment of the invention, the construction information comprises the position information of the preset area; or the construction information comprises a construction site, and an area in a preset radius direction with the construction site as a center is defined as the preset area. It will be appreciated that by incorporating the location information or construction site of the preset area into the construction information, the boundaries and scope of the supervision activities can be clarified. The supervision staff can only fill in and operate the supervision form in the preset area, so that the interference and misoperation of irrelevant areas are avoided. This helps to improve the accuracy and reliability of the proctoring data.
6. The on-site supervision method of the embodiment of the invention further comprises the following steps: and constructing a form database, wherein the database comprises a plurality of supervision forms required by the engineering at different stages. It will be appreciated that the construction of the proctorial forms database may systematically organize and manage proctorial forms required by various engineering processes at different stages. The method is favorable for standardizing the supervision flow, so that supervision personnel can conduct supervision work according to the standard, and the accuracy and consistency of the work are improved. And the supervision requirements and the attention points of different engineering procedures in each stage can be covered through different types of supervision forms. The supervision personnel can check and record the engineering quality condition item by item according to the supervision form in the database, ensure to meet the process requirements, and timely discover and correct potential problems, thereby improving the engineering quality control level.
7. In the on-site supervision method of the embodiment of the invention, supervision forms are classified and marked in a form database according to the engineering types, the process types and the process stages. It can be understood that the form can be more conveniently searched and managed by classifying and marking the supervision form according to the engineering type, the process type and the process stage; the supervision personnel can quickly locate the forms of a specific type or stage, and the forms are more simply arranged and archived, which helps to improve the working efficiency and save time and effort.
8. In the on-site supervision method of the embodiment of the invention, after the target engineering is completed, all the supervision forms uploaded during the execution of the operation plan are called for re-backup. It will be appreciated that this design may ensure the security and integrity of the data. Such a design provides a reliable backup of the proctoring data, preventing data loss or corruption due to accidents or system failures. Meanwhile, the supervision form is archived, so that legal, compliance or audit requirements can be met; moreover, the re-backup supervision form provides an important basis for quality management. The supervision personnel and related stakeholders can check and verify according to the backed up supervision data, so as to ensure that the engineering meets the quality standard and specification requirements. In addition, the re-backed up supervision data is also helpful for overtaking responsibility and identifying responsibility, and investigation and solving of engineering quality problems are also facilitated.
9. In the on-site supervision method of the embodiment of the invention, the filled contents of the uploaded form are locked and are not allowed to be modified in the subsequent check. It can be understood that the uploaded form is locked in content and is not allowed to be modified in subsequent checking, so that the authenticity and reliability of the data can be improved, misoperation and tampering are prevented, the requirements of legal compliance and audit traceability are met, a supervisor and other related parties can trust the data in the form when browsing the form, and correct decisions and judgments are made based on the data, so that the work efficiency is improved and the workload is reduced. The design is helpful for optimizing the on-site supervision flow, guaranteeing the integrity and the credibility of the data, and improving the effect and the reliability of supervision work.
10. The embodiment of the invention also provides a field supervision system for realizing the supervision method, which comprises a platform server, a database and a mobile supervision terminal which are respectively in communication connection with the platform server, and has the same beneficial effects as the field supervision method, and the description is omitted here.
[ description of the drawings ]
Fig. 1 is a flowchart of a method for on-site supervision according to a first embodiment of the present invention.
Fig. 2 is a flowchart of a second method for on-site supervision according to the first embodiment of the present invention.
Fig. 3 is a block diagram of a site supervision system provided in a second embodiment of the present invention.
The attached drawings are used for identifying and describing:
1. a platform server; 2. a database; 3. and the mobile supervision terminal.
[ detailed description ] of the invention
For the purpose of making the technical solution and advantages of the present invention more apparent, the present invention will be further described in detail below with reference to the accompanying drawings and examples of implementation. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the invention.
In the embodiments provided herein, it should be understood that "B corresponding to a" means that B is associated with a, from which B can be determined. It should also be understood that determining B from a does not mean determining B from a alone, but may also determine B from a and/or other information.
It should be appreciated that reference throughout this specification to "one embodiment" or "an embodiment" means that a particular feature, structure or characteristic described in connection with the embodiment is included in at least one embodiment of the present invention. Thus, the appearances of the phrases "in one embodiment" or "in an embodiment" in various places throughout this specification are not necessarily all referring to the same embodiment. Furthermore, the particular features, structures, or characteristics may be combined in any suitable manner in one or more embodiments. Those skilled in the art will also appreciate that the embodiments described in the specification are alternative embodiments and that the acts and modules referred to are not necessarily required for the present invention.
In various embodiments of the present invention, it should be understood that the sequence numbers of the foregoing processes do not imply that the execution sequences of the processes should be determined by the functions and internal logic of the processes, and should not be construed as limiting the implementation of the embodiments of the present invention.
The flowcharts and block diagrams in the figures illustrate the architecture, functionality, and operation of possible implementations of systems, methods and computer program products according to various embodiments of the present application. In this regard, each block in the flowchart or block diagrams may represent a module, segment, or portion of code, which comprises one or more executable instructions for implementing the specified logical function(s). It should also be noted that in some alternative implementations, the functions noted in the block may occur out of the order noted in the figures. For example, two blocks shown in succession may, in fact, be executed substantially concurrently, or the blocks may sometimes be executed in the reverse order, depending upon the functionality involved. It will be noted that each block of the block diagrams and/or flowchart illustration, and combinations of blocks in the block diagrams and/or flowchart illustration, can be implemented by special purpose hardware-based systems which perform the specified functions or acts, or combinations of special purpose hardware and computer instructions.
Proctoring work generally involves four methods: witness, side station, tour and parallel inspection. Each method has its own unique effects and emphasis.
Witness (Witnessing): the supervision personnel personally observe and record the construction process or the test process so as to ensure to meet the standard requirements. This includes participation in critical steps, inspection of materials and equipment, and written recording of the observed situation.
Side station (injection): by side station is meant that real-time observation and inspection is performed at the construction site or at the test site to ensure that the work is performed as planned. The supervisor will check the quality of construction, safety measures, progress, etc., and provide the necessary guidance and advice.
Patrol (Supervision): the inspection is that the inspection staff periodically inspect the construction site to ensure that the construction meets the design and specification requirements. They will check the quality of construction, correctness of the procedure, use of materials, etc., and communicate and coordinate with the relevant parties to solve the problem.
Parallel check (Parallel Inspection): parallel inspection means that the inspection work is independently performed by the inspector, which is the same as or similar to the building unit, to ensure the accuracy and reliability of the result. The method can verify the data and reports provided by the building units, and avoid inaccurate information or fake.
Of these four methods, the bystanders and the patrols typically require more effort because they require the attendant to observe and check in real time on site. The method can help the supervision personnel to ensure that the quality, safety and progress of the construction process meet the specifications, and timely discover and solve the problems.
Referring to fig. 1, a first embodiment of the present invention provides a site supervision method, which includes the following steps:
step S1: acquiring an operation plan of a target project;
step S2: the operation plan comprises construction information of at least one working procedure, and a corresponding supervision form is matched for each working procedure based on the construction information;
step S3: distributing the supervision form of the corresponding procedure to the mobile supervision terminal;
step S4: acquiring the position information of the mobile supervision terminal in real time, and matching the position information of the mobile supervision terminal with the address information in the construction information;
step S5 a: the matching is successful, and the mobile supervision terminal is allowed to operate the supervision form;
step S5 b: otherwise, prohibiting the operation of the supervision form by the mobile supervision terminal;
step S6: filling in a supervision form on the mobile supervision terminal according to the site situation, and uploading and storing the supervision form.
It will be appreciated that by matching location information with address information and requiring that the matching be successful then the operation is allowed, it is ensured that the supervision personnel will only fill in and submit the supervision form in the correct procedure. The design avoids the problem of inaccurate or distorted data caused by filling errors or misoperation, and improves the quality and the credibility of the supervision data; meanwhile, the real-time position of the supervision personnel can be monitored. Such a design can provide more accurate supervisor location information and direct, schedule, or emergency response when needed.
Specifically, for step S1 and step S2, the job planning information is uploaded by the constructor: and the constructor inputs the operation plan file into corresponding information or the relevant files on the machine through the platform App or the platform webpage. These files may be files generated by common planning software (e.g., mi c ro s o ft Proj ec t, prim av era, etc.), or may be files of other formats. The platform receives and stores job planning information uploaded from the constructor. Data is saved using a database or cloud storage. The proctor can view and review the uploaded operation plan information through the corresponding function or interface of the platform. They can select the desired procedure or project and then access the associated work schedule.
In the scheme, the on-site supervision is performed by assigning the supervision personnel, so that witness, side station, inspection and parallel inspection in the supervision method can be correspondingly realized.
Further: the construction information includes a construction plan and a construction time of at least one working procedure construction stage.
It will be appreciated that the construction information includes construction information of the construction scheme and the construction time, and the supervisor can better understand the plan and the time schedule of the engineering process. The method is beneficial to effectively controlling and supervising the engineering progress, ensuring that the construction is carried out according to a preset plan, and timely finding and solving the problem that the process progress is possibly affected; meanwhile, the detailed construction information can help a supervision staff to quickly find an applicable supervision form, so that time and energy waste are avoided in selecting and modifying an irrelevant form; the accurate supervision form is matched, which means that the fields and the contents in the form are consistent with the actual requirements of the working procedure, so that the supervision information of the working procedure can be recorded and tracked more accurately; the applicable supervision form can provide clear filling instruction and field requirements, and reduce guesses and errors, so that the working efficiency of supervision staff is improved; by matching an accurate supervision form, the collected data can be ensured to correspond to construction information, and the arrangement, analysis and archiving of the data are facilitated.
Specifically, the construction information in this embodiment further includes a construction site and a constructor.
Further, the supervision form is provided with an examination content block and a corresponding examination result block.
It will be appreciated that the review content block provides explicit review requirements and guidelines from which a supervisor can conduct review work, avoiding missing or disregarding important review items; meanwhile, the examination result block also provides standardized options or filling fields for the supervision personnel to accurately record examination results and improve examination accuracy.
Further, in step S3, each supervisor has a corresponding mobile supervisor terminal and platform account; the dispatch form can be directly sent to the mobile supervision terminal; or the mobile supervision terminal can be sent to the platform account number, and the supervision personnel logs in the platform to accept the mobile supervision terminal through the mobile supervision terminal.
Specifically, in this embodiment, further, when the sending of the supervision form is performed, the method includes the following steps:
the supervision form comprises a work order and a standardized list;
each work order is correspondingly matched with one or more standardized lists;
the work order allocation is used for definitely allocating the corresponding standardized list to specific executive personnel or account numbers or equipment; the standardized list indicates the specific matters which need to be completed and correspond to the work order.
It can be appreciated that in this design, what is done by doing who is done by the operation of the dispatch bill; the standard of work is realized through the standardized list, so that the whole efficiency and quality of supervision work are ensured.
That is, in step S3, the supervision form is assigned to the specified mobile supervision terminal.
Further, in step S5 a, in the process of filling in the supervision form, the location of the mobile supervision terminal is continuously acquired, and if the location of the mobile supervision terminal leaves the preset area, the mobile supervision terminal is prohibited from operating the supervision form.
It can be understood that by continuously acquiring the position information of the mobile supervision terminal and monitoring, the supervision personnel can be ensured to perform supervision work only in a preset area. The design can avoid the situation that the supervision form is still filled out after the supervision personnel leave the engineering site or the designated area. The method effectively suppresses the non-compliance actions such as remote form filling and the like, and improves the accuracy and the instantaneity of supervision data; the actual observation, inspection and evaluation of the engineering site by the supervision personnel are promoted, and the potential problems and hidden troubles can be found in time; the quality and the safety of engineering are further improved by improving the quality and the actual effect of supervision work.
Further, the construction information includes position information of a preset area; or the construction information includes a construction site, and an area within a preset radius direction centered on the construction site is defined as a preset area.
It will be appreciated that by incorporating the location information or construction site of the preset area into the construction information, the boundaries and scope of the supervision activities can be clarified. The supervision staff can only fill in and operate the supervision form in the preset area, so that the interference and misoperation of irrelevant areas are avoided. This helps to improve the accuracy and reliability of the proctoring data.
Referring to fig. 2, the on-site supervision method further includes the following pre-steps:
step S0: and constructing a form database, wherein the database comprises a plurality of supervision forms required by the engineering at different stages.
It will be appreciated that the construction of the proctorial forms database may systematically organize and manage proctorial forms required by various engineering processes at different stages. The method is favorable for standardizing the supervision flow, so that supervision personnel can conduct supervision work according to the standard, and the accuracy and consistency of the work are improved. And the supervision requirements and the attention points of different engineering procedures in each stage can be covered through different types of supervision forms. The supervision personnel can check and record the engineering quality condition item by item according to the supervision form in the database, ensure to meet the process requirements, and timely discover and correct potential problems, thereby improving the engineering quality control level.
It should be noted that, constructing the database of the supervision form is also a process for realizing standardization of supervision requirements. In the process, the distinguishing standard of each stage of engineering is required to be defined, and the civil engineering of a transformer substation is taken as an example, and can be distinguished through different building stages of a field engineering, a foundation and a foundation, a main body structure, indoor and outdoor auxiliary facilities, a building installation engineering and a decoration engineering; and respectively constructing corresponding standard supervision forms according to different processes and building structures in each stage.
The specific supervision form can be adjusted and supplemented according to the process requirements and actual conditions. The standard supervision form of each stage should contain information such as corresponding inspection procedure, acceptance standard, inspection content and result record, etc. to ensure comprehensive supervision and evaluation of the engineering of each stage. By establishing the standardized supervision form, the standardization and consistency of supervision work can be improved, and construction of engineering according to requirements is ensured to reach the expected quality standard.
As a possible implementation manner, taking the construction stage of the main body structure as an example, at least one corresponding standard supervision form can be respectively constructed aiming at the aspects of concrete engineering, steel structure, construction bracket hoisting, masonry structure, roofing engineering and the like.
Further, the supervision form is provided with an examination content block and a corresponding examination result block. It will be appreciated that the review content block provides explicit review requirements and guidelines from which a supervisor can conduct review work, avoiding missing or disregarding important review items; meanwhile, the examination result block also provides standardized options or filling fields for the supervision personnel to accurately record examination results and improve examination accuracy.
Further, in the form database, the supervision forms are classified and marked according to the engineering type, the process type and the process stage.
It can be understood that the form can be more conveniently searched and managed by classifying and marking the supervision form according to the engineering type, the process type and the process stage; the supervision personnel can quickly locate the forms of a specific type or stage, and the forms are more simply arranged and archived, which helps to improve the working efficiency and save time and effort.
Further, after the target engineering is completed, all the supervision forms uploaded during the execution of the operation plan are called for re-backup.
It will be appreciated that this design may ensure the security and integrity of the data. Such a design provides a reliable backup of the proctoring data, preventing data loss or corruption due to accidents or system failures. Meanwhile, the supervision form is archived, so that legal, compliance or audit requirements can be met; moreover, the re-backup supervision form provides an important basis for quality management. The supervision personnel and related stakeholders can check and verify according to the backed up supervision data, so as to ensure that the engineering meets the quality standard and specification requirements. In addition, the re-backed up supervision data is also helpful for overtaking responsibility and identifying responsibility, and investigation and solving of engineering quality problems are also facilitated.
Further, the uploaded form is locked for filling out content, and modification in subsequent viewing is not allowed.
It can be understood that the uploaded form is locked in content and is not allowed to be modified in subsequent checking, so that the authenticity and reliability of the data can be improved, misoperation and tampering are prevented, the requirements of legal compliance and audit traceability are met, a supervisor and other related parties can trust the data in the form when browsing the form, and correct decisions and judgments are made based on the data, so that the work efficiency is improved and the workload is reduced. The design is helpful for optimizing the on-site supervision flow, guaranteeing the integrity and the credibility of the data, and improving the effect and the reliability of supervision work.
Referring to fig. 3, in order to solve the above technical problems, a second embodiment of the present invention further provides a site supervision system for implementing the supervision method as described above, where the site supervision system includes a platform server 1, and a database 2 and a mobile supervision terminal 3 that are respectively in communication with the platform server.
It can be appreciated that the present embodiment has the same advantages as the above-mentioned on-site supervision method, and will not be described herein.
Furthermore, the constructor and the proctor can log in the platform server 1 through the corresponding account numbers, and can use different functions according to different types of account numbers, for example, the constructor can proctor new engineering procedures on the platform and upload corresponding operation plans; and the supervision party can retrieve the operation plan from the platform and distribute supervision tasks, namely forms, according to the operation plan.
It should be noted that, the allocation of the forms may be performed by the platform according to a set rule, and the proctor may manually retrieve the relevant proctoring form from the database to perform the allocation.
Preferably, the distribution can be performed through the platform, and then whether the modification or the supplementation is performed is confirmed through the proctoring party.
Compared with the prior art, the on-site supervision method and system provided by the invention have the following beneficial effects:
1. the on-site supervision method provided by the embodiment of the invention comprises the following steps: acquiring an operation plan of a target project; the operation plan comprises construction information of at least one working procedure, and a corresponding supervision form is matched for each working procedure based on the construction information; distributing the supervision form of the corresponding procedure to the mobile supervision terminal; acquiring the position information of the mobile supervision terminal in real time, and matching the position information of the mobile supervision terminal with the address information in the construction information; the matching is successful, and the mobile supervision terminal is allowed to operate the supervision form; otherwise, prohibiting the operation of the supervision form by the mobile supervision terminal; filling in a supervision form on the mobile supervision terminal according to the site situation, and uploading and storing the supervision form. It will be appreciated that by matching location information with address information and requiring that the matching be successful before operation is allowed, it is ensured that the proctor will only fill in and submit proctoring forms in the correct procedure. The design avoids the problem of inaccurate or distorted data caused by filling errors or misoperation, and improves the quality and the credibility of the supervision data; meanwhile, the real-time position of the supervision personnel can be monitored. Such a design can provide more accurate supervisor location information and direct, schedule, or emergency response when needed.
2. In the on-site supervision method according to the embodiment of the invention, the construction information includes a construction scheme and a construction time of at least one working procedure construction stage. It will be appreciated that by including construction information for the construction plan and the construction time, the supervisor can better understand the plan and timing of the engineering process. The method is beneficial to effectively controlling and supervising the engineering progress, ensuring that the construction is carried out according to a preset plan, and timely finding and solving the problem that the process progress is possibly affected; meanwhile, the detailed construction information can help a supervision staff to quickly find an applicable supervision form, so that time and energy waste are avoided in selecting and modifying an irrelevant form; the accurate supervision form is matched, which means that the fields and the contents in the form are consistent with the actual requirements of the working procedure, so that the supervision information of the working procedure can be recorded and tracked more accurately; the applicable supervision form can provide clear filling instruction and field requirements, and reduce guesses and errors, so that the working efficiency of supervision staff is improved; by matching an accurate supervision form, the collected data can be ensured to correspond to construction information, and the arrangement, analysis and archiving of the data are facilitated.
3. In the on-site supervision method of the embodiment of the invention, the supervision form is provided with an examination content block and a corresponding examination result block. It will be appreciated that the review content block provides explicit review requirements and guidelines from which a supervisor can conduct review work, avoiding missing or disregarding important review items; meanwhile, the examination result block also provides standardized options or filling fields for the supervision personnel to accurately record examination results and improve examination accuracy.
4. In the on-site supervision method provided by the embodiment of the invention, the position of the mobile supervision terminal is continuously acquired in the process of filling the supervision form, and if the position of the mobile supervision terminal leaves a preset area, the mobile supervision terminal is forbidden to operate the supervision form. It can be understood that by continuously acquiring the position information of the mobile supervision terminal and monitoring, the supervision personnel can be ensured to perform supervision work only in a preset area. The design can avoid the situation that the supervision form is still filled out after the supervision personnel leave the engineering site or the designated area. The method effectively suppresses the non-compliance actions such as remote form filling and the like, and improves the accuracy and the instantaneity of supervision data; the actual observation, inspection and evaluation of the engineering site by the supervision personnel are promoted, and the potential problems and hidden troubles can be found in time; the quality and the safety of engineering are further improved by improving the quality and the actual effect of supervision work.
5. In the on-site supervision method of the embodiment of the invention, the construction information comprises the position information of the preset area; or the construction information comprises a construction site, and an area in a preset radius direction with the construction site as a center is defined as the preset area. It will be appreciated that by incorporating the location information or construction site of the preset area into the construction information, the boundaries and scope of the supervision activities can be clarified. The supervision staff can only fill in and operate the supervision form in the preset area, so that the interference and misoperation of irrelevant areas are avoided. This helps to improve the accuracy and reliability of the proctoring data.
6. The on-site supervision method of the embodiment of the invention further comprises the following steps: and constructing a form database, wherein the database comprises a plurality of supervision forms required by the engineering at different stages. It will be appreciated that the construction of the proctorial forms database may systematically organize and manage proctorial forms required by various engineering processes at different stages. The method is favorable for standardizing the supervision flow, so that supervision personnel can conduct supervision work according to the standard, and the accuracy and consistency of the work are improved. And the supervision requirements and the attention points of different engineering procedures in each stage can be covered through different types of supervision forms. The supervision personnel can check and record the engineering quality condition item by item according to the supervision form in the database, ensure to meet the process requirements, and timely discover and correct potential problems, thereby improving the engineering quality control level.
7. In the on-site supervision method of the embodiment of the invention, supervision forms are classified and marked in a form database according to the engineering types, the process types and the process stages. It can be understood that the form can be more conveniently searched and managed by classifying and marking the supervision form according to the engineering type, the process type and the process stage; the supervision personnel can quickly locate the forms of a specific type or stage, and the forms are more simply arranged and archived, which helps to improve the working efficiency and save time and effort.
8. In the on-site supervision method of the embodiment of the invention, after the target engineering is completed, all the supervision forms uploaded during the execution of the operation plan are called for re-backup. It will be appreciated that this design may ensure the security and integrity of the data. Such a design provides a reliable backup of the proctoring data, preventing data loss or corruption due to accidents or system failures. Meanwhile, the supervision form is archived, so that legal, compliance or audit requirements can be met; moreover, the re-backup supervision form provides an important basis for quality management. The supervision personnel and related stakeholders can check and verify according to the backed up supervision data, so as to ensure that the engineering meets the quality standard and specification requirements. In addition, the re-backed up supervision data is also helpful for overtaking responsibility and identifying responsibility, and investigation and solving of engineering quality problems are also facilitated.
9. In the on-site supervision method of the embodiment of the invention, the filled contents of the uploaded form are locked and are not allowed to be modified in the subsequent check. It can be understood that the uploaded form is locked in content and is not allowed to be modified in subsequent checking, so that the authenticity and reliability of the data can be improved, misoperation and tampering are prevented, the requirements of legal compliance and audit traceability are met, a supervisor and other related parties can trust the data in the form when browsing the form, and correct decisions and judgments are made based on the data, so that the work efficiency is improved and the workload is reduced. The design is helpful for optimizing the on-site supervision flow, guaranteeing the integrity and the credibility of the data, and improving the effect and the reliability of supervision work.
10. The embodiment of the invention also provides a field supervision system for realizing the supervision method, which comprises a platform server, a database and a mobile supervision terminal which are respectively in communication connection with the platform server, and has the same beneficial effects as the field supervision method, and the description is omitted here.
The above describes in detail a method and a system for on-site supervision disclosed in the embodiments of the present invention, and specific examples are applied to describe the principles and embodiments of the present invention, and the description of the above examples is only used to help understand the method and the core idea of the present invention; meanwhile, as for those skilled in the art, according to the idea of the present invention, there are changes in the specific embodiments and the application scope, and in summary, the present disclosure should not be construed as limiting the present invention, and any modifications, equivalent substitutions and improvements made within the principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. The on-site supervision method is characterized by comprising the following steps of:
acquiring an operation plan of a target project;
the operation plan comprises construction information of at least one working procedure, and a corresponding supervision form is matched for each working procedure based on the construction information;
distributing the supervision form of the corresponding procedure to the mobile supervision terminal;
acquiring the position information of the mobile supervision terminal in real time, and matching the position information of the mobile supervision terminal with the address information in the construction information;
the matching is successful, and the mobile supervision terminal is allowed to operate the supervision form; otherwise, prohibiting the operation of the supervision form by the mobile supervision terminal;
filling in a supervision form on the mobile supervision terminal according to the site situation, and uploading and storing the supervision form.
2. The on-site supervision method according to claim 1, wherein: the construction information includes a construction plan and a construction time of at least one working procedure construction stage.
3. The on-site supervision method according to claim 1, wherein: the supervision form is provided with an examination content block and a corresponding examination result block.
4. The on-site supervision method according to claim 1, wherein: and continuously acquiring the position of the mobile supervision terminal in the process of filling the supervision form, and prohibiting the mobile supervision terminal from operating the supervision form if the position of the mobile supervision terminal leaves a preset area.
5. The on-site supervision method according to claim 4, wherein: the construction information comprises the position information of the preset area; or the construction information comprises a construction site, and an area in a preset radius direction with the construction site as a center is defined as the preset area.
6. The on-site proctoring method of claim 1, further comprising the pre-step of: and constructing a form database, wherein the database comprises a plurality of supervision forms required by the engineering at different stages.
7. The on-site supervision method according to claim 6, wherein: in the form database, the supervision forms are classified and marked according to the engineering types, the process types and the process stages.
8. The on-site supervision method according to claim 1, wherein: and after the target engineering is completed, all the supervision forms uploaded during the execution of the operation plan are called for re-backup.
9. The on-site supervision method according to claim 1, wherein: the uploaded form is locked for filling out content and is not allowed to be modified in subsequent viewing.
10. A site supervision system, characterized in that: the on-site supervision system comprises a platform server, a database and a mobile supervision terminal, wherein the database and the mobile supervision terminal are respectively in communication connection with the platform server.
CN202311260003.4A 2023-09-26 2023-09-26 Site supervision method and system Pending CN117474463A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311260003.4A CN117474463A (en) 2023-09-26 2023-09-26 Site supervision method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311260003.4A CN117474463A (en) 2023-09-26 2023-09-26 Site supervision method and system

Publications (1)

Publication Number Publication Date
CN117474463A true CN117474463A (en) 2024-01-30

Family

ID=89630190

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311260003.4A Pending CN117474463A (en) 2023-09-26 2023-09-26 Site supervision method and system

Country Status (1)

Country Link
CN (1) CN117474463A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108460573A (en) * 2018-01-30 2018-08-28 广东建海工程项目管理有限公司 Project supervision manages system
CN109784843A (en) * 2018-12-29 2019-05-21 福建华闽通达信息技术有限公司 A kind of building cost management method and system based on WBS
CN110334942A (en) * 2019-07-04 2019-10-15 四川元丰建设项目管理有限公司 Construction Supervision Work procedure information management system
CN111784172A (en) * 2020-07-06 2020-10-16 贵州电网有限责任公司 Distribution network operation and maintenance management system based on GIS and big data
CN115879728A (en) * 2022-12-27 2023-03-31 武汉中超电网建设监理有限公司 Based on capital construction overall process platform system
CN116542469A (en) * 2023-05-08 2023-08-04 深圳市昊源建设监理有限公司 Building engineering supervision intelligent integrated cloud platform based on BIM technology and supervision method
CN116611667A (en) * 2023-06-19 2023-08-18 武汉中超电网建设监理有限公司 Real-time supervision scheduling method and system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108460573A (en) * 2018-01-30 2018-08-28 广东建海工程项目管理有限公司 Project supervision manages system
CN109784843A (en) * 2018-12-29 2019-05-21 福建华闽通达信息技术有限公司 A kind of building cost management method and system based on WBS
CN110334942A (en) * 2019-07-04 2019-10-15 四川元丰建设项目管理有限公司 Construction Supervision Work procedure information management system
CN111784172A (en) * 2020-07-06 2020-10-16 贵州电网有限责任公司 Distribution network operation and maintenance management system based on GIS and big data
CN115879728A (en) * 2022-12-27 2023-03-31 武汉中超电网建设监理有限公司 Based on capital construction overall process platform system
CN116542469A (en) * 2023-05-08 2023-08-04 深圳市昊源建设监理有限公司 Building engineering supervision intelligent integrated cloud platform based on BIM technology and supervision method
CN116611667A (en) * 2023-06-19 2023-08-18 武汉中超电网建设监理有限公司 Real-time supervision scheduling method and system

Similar Documents

Publication Publication Date Title
CN107222523B (en) Terminal data processing method, device and system
CN107798479B (en) Knowledge management system based on full life cycle integrated knowledge experience information
CN106169131A (en) Project management cloud platform system based on the Internet
CN111860960A (en) Prediction pre-control cloud smart supervision sharing platform based on big data internet and block chain
CN111178709A (en) Full life cycle management system of aluminum electrolysis equipment and repair reporting method thereof
CN107563673A (en) A kind of inspection management method, operation management platform and system
CN110717736A (en) Construction progress intelligent tracking method and system for building
CN105184519A (en) Standardized safety operation tracing management system
CN114639183A (en) Intelligent inspection method, system, computer equipment and medium based on element
CN110619477A (en) Supervision method for construction quality in project supervision
CN112184072B (en) Machine room equipment management method and device
CN117078209A (en) Method, system and device for managing supervision project and computer storage medium
CN117474463A (en) Site supervision method and system
CN112561399A (en) Supervision method for construction quality in project supervision
CN115171236B (en) Inspection management method, inspection management platform and inspection management client
CN114374272B (en) Automatic overhaul method for intelligent substation
CN117408625A (en) Supervision method and system
CN114881596A (en) Automatic management method, device and equipment for field inspection
CN115760493A (en) Investment project land monitoring system
Liu et al. Dynamic analysis of FRAM: A case study of accident investigation
CN115481941A (en) Multifunctional area combined intelligent security management method and system
CN111199391B (en) Maintenance information processing method, system and device for gas pressure regulating equipment and storage medium
RU2755520C1 (en) Automated logistical intelligent information decision-making system in manufacturing and logistical complex
CN114022125A (en) Engineering quantity calculation method, storage medium, and apparatus
CN114358627A (en) Electric power operation and maintenance management system and operation and maintenance method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination