CN117211476A - Construction process of metal roof skylight - Google Patents

Construction process of metal roof skylight Download PDF

Info

Publication number
CN117211476A
CN117211476A CN202311186372.3A CN202311186372A CN117211476A CN 117211476 A CN117211476 A CN 117211476A CN 202311186372 A CN202311186372 A CN 202311186372A CN 117211476 A CN117211476 A CN 117211476A
Authority
CN
China
Prior art keywords
skylight
glass
framework
metal roof
glue
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311186372.3A
Other languages
Chinese (zh)
Inventor
卞可磊
王洋
郑成立
曹明
田乾
代会浮
杨新禄
徐雅儒
高文光
韩建成
张兰芳
杨程鹏
李刚
张威
蔡田园
马海川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban Construction Sixth Group Co Ltd
Original Assignee
Beijing Urban Construction Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban Construction Sixth Group Co Ltd filed Critical Beijing Urban Construction Sixth Group Co Ltd
Priority to CN202311186372.3A priority Critical patent/CN117211476A/en
Publication of CN117211476A publication Critical patent/CN117211476A/en
Pending legal-status Critical Current

Links

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The application discloses a construction process of a metal roof skylight, and relates to the technical field of steel structure buildings. In order to solve the sealing problem, the metal roof skylight comprises a skylight framework, a skylight bottom plate, skylight glass, a skylight sunshade curtain and a sealing component, and the metal roof skylight construction process comprises the following steps: measuring and paying-off and working face arrangement, measuring and paying-off according to a design drawing and an installed roof structure, determining installation positions of all parts of the skylight, and determining a working face when the skylight is installed according to the roof structure; installing a skylight structure; and the skylight framework is arranged on the metal roof according to the paying-off position. According to the application, the sealing assembly is added for sealing the gap, and the water spraying test is carried out after the sealing, so that the running water position can be detected and repaired, the sealing performance of the gap of the skylight is ensured, and the sunshade curtain is installed for acceptance after the test, so that the sunshade curtain can be prevented from absorbing water and wetting during the test.

Description

Construction process of metal roof skylight
Technical Field
The application relates to the technical field of steel structure buildings, in particular to a construction process of a metal roof skylight.
Background
Compared with the traditional concrete building, the steel structure building is a novel building system, and steel plates or section steel are used for replacing reinforced concrete, so that the steel structure building is higher in strength and better in shock resistance. The steel has high strength and high flexibility, and compared with the traditional reinforced concrete building, the reinforced concrete building has high strength, light dead weight, good rigidity of the whole rigid frame and strong forming capability. The building dead weight is only one fifth of that of a brick-concrete structure, typhoons of 70 meters per second can be resisted, the life and property can be maintained powerfully, and the building dead weight is widely applied to fields of large gymnasiums, meeting places, exhibition halls and the like.
In the metal roof of a steel structure building, in order to meet lighting, ventilation and the like of the building, a skylight needs to be arranged on the roof.
Because the metal roofing is different with traditional concrete structure roofing, the roof of metal roofing is the steel constitution that does not have fluidity, and its relative concrete structure roofing can't utilize the fluidity of concrete to fill the building gap to can make after the skylight is installed, can exist the gap because of installation, processing, design error etc. between skylight and the roofing, thereby can lead to the building to leak.
Therefore, the application provides a construction process of the metal roof skylight.
Disclosure of Invention
The application aims to solve the defects in the prior art, and provides a metal roof skylight construction process.
In order to achieve the above purpose, the present application adopts the following technical scheme:
a construction process of a metal roof skylight comprises a skylight framework, a skylight bottom plate, skylight glass, a skylight sunshade curtain and a sealing component,
the construction process of the metal roof skylight comprises the following steps:
s1: measuring and paying-off and working face arrangement, measuring and paying-off according to a design drawing and an installed roof structure, determining installation positions of all parts of the skylight, and determining a working face when the skylight is installed according to the roof structure;
s2: installing a skylight structure;
s21: the skylight framework is installed, and the skylight framework is installed on the metal roof according to the paying-off position;
s22: the skylight bottom plate is installed, buckled and fixed on the skylight framework;
s23: the skylight glass is installed, and the skylight glass is installed on the framework by using a pressing block;
s3: the installation of the sealing component comprises the steps of installing the sealing component between glass and a framework, between the framework and a metal roof, and between a bottom plate and the framework;
s4: the water spraying test is carried out, the skylight is closed, the spray gun or the spray head is used for spraying water on the skylight, whether the skylight leaks or not is observed, and if the skylight leaks, the leakage is repaired until the sealing effect is achieved;
s5: and (3) installing the sunshade curtain, namely installing the sunshade curtain on the framework, and checking and accepting the technological requirements of the drawing.
Preferably: the skylight skeleton adopts the structure of main, secondary fossil fragments.
Further: the main keels and the secondary keels are galvanized square tubes.
Based on the scheme: when the main keels and the secondary keels are installed, the main keels and the secondary keels are lifted to a discharging platform of a working face by using a tower crane or an automobile crane and then manually carried to an installation position.
Among the foregoing, the preferred one is: when the skylight glass is transported, the tower crane is firstly used for hoisting the skylight glass to the unloading platform, then the skylight glass is transported to the installation position for installation by workers, and after the installation is finished, the next piece of glass is hoisted by the tower crane, so that only one piece of glass is guaranteed to be processed and installed each time.
As a further scheme of the application: and S23, after the glass is installed, a gap between the glass and the framework is plugged into a foam rod, and then glue fixing is carried out.
Meanwhile, in the step S23, the specific steps are as follows:
s231: cleaning and drying the sealing part; cleaning and drying the part where the glass is installed and the periphery of the glass by using gauze;
s232: installing glass, namely installing the glass, and inserting a foam rod into the gap;
s233: attaching a masking tape, namely attaching the masking tape on the junction of the sealing glue line and the surface material;
s234: glue is applied, and glue is applied and fixed at the gaps, so that the glue is uniformly, compactly and fully applied;
s235: after the gap is corrected and the glue is beaten, the glue line is forced to be pressed by a small shovel along the glue injection direction, redundant glue is scraped off, and the glue line is scraped into a designed shape, so that the glue line is smooth and fluent;
s236: paper tape removal: after finishing the glue line, timely removing the protective tape, and tearing the tape off to prevent the glass surface or the aluminum plate surface from being polluted; and cleaning glue marks stuck on the construction surface.
As a preferred embodiment of the present application: the sealing component adopts the combined design of a waterproof coiled material, a waterproof coiled material additional layer and a trimming plate.
Meanwhile, the edge folding plate is a profiled steel plate.
The beneficial effects of the application are as follows:
1. according to the application, the sealing assembly is added for sealing the gap, and the water spraying test is performed after the sealing assembly is used for detecting and repairing the running water, so that the sealing performance of the gap of the skylight is ensured, and the sunshade curtain is installed for acceptance after the test, so that the sunshade curtain can be prevented from absorbing water and wetting during the test.
2. According to the application, the framework of the skylight adopts the main keel and the secondary keel, so that the whole framework is split in a unitized mode, the size and the weight of structural members which are installed at one time in high-altitude operation can be reduced, the construction difficulty is effectively reduced, and the construction efficiency is improved.
3. According to the application, for the transportation and installation processes of glass, the processes of lifting, transferring, installing and lifting are adopted, so that only one piece of glass is ensured to be processed and installed, the situation that the glass is fragile under the condition of cross construction is prevented, and the construction safety is increased.
4. According to the application, the steps of cleaning, installing and correcting the gap are adopted for installing the glass, and the paper adhesive tape is used during the installation, so that on one hand, the influence of dirt on the installation firmness can be prevented, and on the other hand, the overall attractive appearance after the installation is ensured to be higher.
5. According to the application, the waterproof coiled material, the additional layer of the waterproof coiled material and the edge folding plate are combined for the sealing assembly, so that the gaps are filled by using the flexibility of the coiled material and the additional layer of the coiled material, the sealing effect is improved, the edge folding plate is utilized for folding edges, the protection effect on the flexible material is achieved, and meanwhile, the overall attractiveness is also improved.
Drawings
The accompanying drawings, which are included to provide a further understanding of the application, are incorporated in and constitute a part of this specification. The drawings and their description are illustrative of the application and are not to be construed as unduly limiting the application. In the drawings:
fig. 1 is a schematic flow chart of a construction process of a metal roof skylight provided by the application.
Detailed Description
In order that those skilled in the art will better understand the present application, a technical solution in the embodiments of the present application will be clearly and completely described below with reference to the accompanying drawings in which it is apparent that the described embodiments are only some embodiments of the present application, not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the present application without making any inventive effort, shall fall within the scope of the present application.
It should be noted that the terms "first," "second," and the like in the description and the claims of the present application and the above figures are used for distinguishing between similar objects and not necessarily for describing a particular sequential or chronological order. It is to be understood that the data so used may be interchanged where appropriate in order to describe the embodiments of the application herein. Furthermore, the terms "comprises," "comprising," and "having," and any variations thereof, are intended to cover a non-exclusive inclusion, such that a process, method, system, article, or apparatus that comprises a list of steps or elements is not necessarily limited to those steps or elements expressly listed but may include other steps or elements not expressly listed or inherent to such process, method, article, or apparatus.
In the present application, the terms "upper", "lower", "left", "right", "front", "rear", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like indicate an azimuth or a positional relationship based on that shown in the drawings. These terms are only used to better describe the present application and its embodiments and are not intended to limit the scope of the indicated devices, elements or components to the particular orientations or to configure and operate in the particular orientations.
Also, some of the terms described above may be used to indicate other meanings in addition to orientation or positional relationships, for example, the term "upper" may also be used to indicate some sort of attachment or connection in some cases. The specific meaning of these terms in the present application will be understood by those of ordinary skill in the art according to the specific circumstances.
In addition, the term "plurality" shall mean two as well as more than two.
It should be noted that, without conflict, the embodiments of the present application and features of the embodiments may be combined with each other. The application will be described in detail below with reference to the drawings in connection with embodiments.
Example 1:
the construction process of the metal roof skylight is shown in fig. 1, and comprises the following steps of:
s1: measuring and paying-off and working face arrangement, measuring and paying-off according to a design drawing and an installed roof structure, determining installation positions of all parts of the skylight, and determining a working face when the skylight is installed according to the roof structure;
s2: installing a skylight structure;
s21: the skylight framework is installed, and the skylight framework is installed on the metal roof according to the paying-off position;
s22: the skylight bottom plate is installed, buckled and fixed on the skylight framework;
s23: the skylight glass is installed, and the skylight glass is installed on the framework by using a pressing block;
s3: the installation of the sealing component comprises the steps of installing the sealing component between glass and a framework, between the framework and a metal roof, and between a bottom plate and the framework;
s4: the water spraying test is carried out, the skylight is closed, the spray gun or the spray head is used for spraying water on the skylight, whether the skylight leaks or not is observed, and if the skylight leaks, the leakage is repaired until the sealing effect is achieved;
s5: and (3) installing the sunshade curtain, namely installing the sunshade curtain on the framework, and checking and accepting the technological requirements of the drawing.
In this embodiment, through increasing seal assembly for to the seam is sealed, and carry out the drenching test again after sealed, can detect and repair flowing water department, thereby guaranteed the leakproofness in skylight seam, and install the sunshade screen again after the test and accept, thereby can prevent that the sunshade screen from absorbing water when testing from wetting.
Example 2:
the construction process of the metal roof skylight is shown in fig. 1, and comprises the following steps of:
s1: measuring and paying-off and working face arrangement, measuring and paying-off according to a design drawing and an installed roof structure, determining installation positions of all parts of the skylight, and determining a working face when the skylight is installed according to the roof structure;
s2: installing a skylight structure;
s21: the skylight framework is installed, and the skylight framework is installed on the metal roof according to the paying-off position;
s22: the skylight bottom plate is installed, buckled and fixed on the skylight framework;
s23: the skylight glass is installed, and the skylight glass is installed on the framework by using a pressing block;
s3: the installation of the sealing component comprises the steps of installing the sealing component between glass and a framework, between the framework and a metal roof, and between a bottom plate and the framework;
s4: the water spraying test is carried out, the skylight is closed, the spray gun or the spray head is used for spraying water on the skylight, whether the skylight leaks or not is observed, and if the skylight leaks, the leakage is repaired until the sealing effect is achieved;
s5: and (3) installing the sunshade curtain, namely installing the sunshade curtain on the framework, and checking and accepting the technological requirements of the drawing.
The skylight skeleton adopts the structure of main, secondary joist, and main, secondary joist are zinc-plated side's pipe, and preferred: the specification of galvanized square pipe is 100 x 4mm, and when main, secondary fossil fragments are installed, use tower crane or automobile crane to promote it to the discharge platform of working face, carry to the mounted position by the manual work again.
In this embodiment, adopt the structure of main, secondary fossil fragments to the skeleton of skylight to carry out "unitization" split with whole skeleton, thereby reducible high altitude construction single installation's structure size and weight, follow effectual reduction construction degree of difficulty, improvement efficiency of construction.
Example 3:
the construction process of the metal roof skylight is shown in fig. 1, and comprises the following steps of:
s1: measuring and paying-off and working face arrangement, measuring and paying-off according to a design drawing and an installed roof structure, determining installation positions of all parts of the skylight, and determining a working face when the skylight is installed according to the roof structure;
s2: installing a skylight structure;
s21: the skylight framework is installed, and the skylight framework is installed on the metal roof according to the paying-off position;
s22: the skylight bottom plate is installed, buckled and fixed on the skylight framework;
s23: the skylight glass is installed, and the skylight glass is installed on the framework by using a pressing block;
s3: the installation of the sealing component comprises the steps of installing the sealing component between glass and a framework, between the framework and a metal roof, and between a bottom plate and the framework;
s4: the water spraying test is carried out, the skylight is closed, the spray gun or the spray head is used for spraying water on the skylight, whether the skylight leaks or not is observed, and if the skylight leaks, the leakage is repaired until the sealing effect is achieved;
s5: and (3) installing the sunshade curtain, namely installing the sunshade curtain on the framework, and checking and accepting the technological requirements of the drawing.
The skylight skeleton adopts the structure of main, secondary joist, and main, secondary joist are zinc-plated side's pipe, and preferred: the specification of galvanized square pipe is 100 x 4mm, and when main, secondary fossil fragments are installed, use tower crane or automobile crane to promote it to the discharge platform of working face, carry to the mounted position by the manual work again.
When the skylight glass is transported, the tower crane is firstly used for hoisting the skylight glass to the unloading platform, then the skylight glass is transported to the installation position for installation by workers, and after the installation is finished, the next piece of glass is hoisted by the tower crane, so that only one piece of glass is guaranteed to be processed and installed each time.
When the skylight glass is transported, the tower crane is firstly used for hoisting the skylight glass to the unloading platform, then the skylight glass is transported to the installation position for installation by workers, and after the installation is finished, the next piece of glass is hoisted by the tower crane, so that only one piece of glass is guaranteed to be processed and installed each time.
And S23, after the glass is installed, a gap between the glass and the framework is plugged into a foam rod, and then glue fixing is carried out.
In the step S23, the specific steps are as follows:
s231: cleaning and drying the sealing part; cleaning and drying the part where the glass is installed and the periphery of the glass by using gauze;
s232: installing glass, namely installing the glass, and inserting a foam rod into the gap;
s233: attaching a masking tape, namely attaching the masking tape on the junction of the sealing glue line and the surface material;
s234: glue is applied, and glue is applied and fixed at the gaps, so that the glue is uniformly, compactly and fully applied;
s235: after the gap is corrected and the glue is beaten, the glue line is forced to be pressed by a small shovel along the glue injection direction, redundant glue is scraped off, and the glue line is scraped into a designed shape, so that the glue line is smooth and fluent;
s236: paper tape removal: after finishing the glue line, timely removing the protective tape, and tearing the tape off to prevent the glass surface or the aluminum plate surface from being polluted; and cleaning glue marks stuck on the construction surface.
In the embodiment, for the transportation and installation processes of glass, the processes of lifting, transferring, installing and lifting are adopted, so that only one piece of glass is ensured to be processed and installed, the situation that the glass is fragile under the condition of cross construction is prevented, and the construction safety is improved.
In addition, the steps of cleaning, installing and correcting gaps are adopted for installing the glass, and a paper adhesive tape is used during installation, so that on one hand, the firmness of installation can be prevented from being influenced by dirt, and on the other hand, the overall attractive appearance after installation is ensured to be higher.
Example 4:
the construction process of the metal roof skylight is shown in fig. 1, and comprises the following steps of:
s1: measuring and paying-off and working face arrangement, measuring and paying-off according to a design drawing and an installed roof structure, determining installation positions of all parts of the skylight, and determining a working face when the skylight is installed according to the roof structure;
s2: installing a skylight structure;
s21: the skylight framework is installed, and the skylight framework is installed on the metal roof according to the paying-off position;
s22: the skylight bottom plate is installed, buckled and fixed on the skylight framework;
s23: the skylight glass is installed, and the skylight glass is installed on the framework by using a pressing block;
s3: the installation of the sealing component comprises the steps of installing the sealing component between glass and a framework, between the framework and a metal roof, and between a bottom plate and the framework;
s4: the water spraying test is carried out, the skylight is closed, the spray gun or the spray head is used for spraying water on the skylight, whether the skylight leaks or not is observed, and if the skylight leaks, the leakage is repaired until the sealing effect is achieved;
s5: and (3) installing the sunshade curtain, namely installing the sunshade curtain on the framework, and checking and accepting the technological requirements of the drawing.
The skylight skeleton adopts the structure of main, secondary joist, and main, secondary joist are zinc-plated side's pipe, and preferred: the specification of galvanized square pipe is 100 x 4mm, and when main, secondary fossil fragments are installed, use tower crane or automobile crane to promote it to the discharge platform of working face, carry to the mounted position by the manual work again.
When the skylight glass is transported, the tower crane is firstly used for hoisting the skylight glass to the unloading platform, then the skylight glass is transported to the installation position for installation by workers, and after the installation is finished, the next piece of glass is hoisted by the tower crane, so that only one piece of glass is guaranteed to be processed and installed each time.
When the skylight glass is transported, the tower crane is firstly used for hoisting the skylight glass to the unloading platform, then the skylight glass is transported to the installation position for installation by workers, and after the installation is finished, the next piece of glass is hoisted by the tower crane, so that only one piece of glass is guaranteed to be processed and installed each time.
And S23, after the glass is installed, a gap between the glass and the framework is plugged into a foam rod, and then glue fixing is carried out.
In the step S23, the specific steps are as follows:
s231: cleaning and drying the sealing part; cleaning and drying the part where the glass is installed and the periphery of the glass by using gauze;
s232: installing glass, namely installing the glass, and inserting a foam rod into the gap;
s233: attaching a masking tape, namely attaching the masking tape on the junction of the sealing glue line and the surface material;
s234: glue is applied, and glue is applied and fixed at the gaps, so that the glue is uniformly, compactly and fully applied;
s235: after the gap is corrected and the glue is beaten, the glue line is forced to be pressed by a small shovel along the glue injection direction, redundant glue is scraped off, and the glue line is scraped into a designed shape, so that the glue line is smooth and fluent;
s236: paper tape removal: after finishing the glue line, timely removing the protective tape, and tearing the tape off to prevent the glass surface or the aluminum plate surface from being polluted; and cleaning glue marks stuck on the construction surface.
The sealing component adopts the combined design of a waterproof coiled material, a waterproof coiled material additional layer and a trimming plate.
The edge folding plate is a profiled steel plate.
In this embodiment, adopt the combined type design of waterproofing membrane, waterproofing membrane additional layer and receipts limit board to seal assembly, both utilized the flexibility of coiled material and coiled material additional layer to pack the gap, increased sealed effect, utilized the receipts limit board to receive the limit again, played the protection effect to flexible material and also increased holistic aesthetic property simultaneously.
The above description is only of the preferred embodiments of the present application and is not intended to limit the present application, but various modifications and variations can be made to the present application by those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included in the protection scope of the present application.

Claims (9)

1. The construction process of the metal roof skylight comprises a skylight framework, a skylight bottom plate, skylight glass, a skylight sunshade curtain and a sealing component, and is characterized in that,
the construction process of the metal roof skylight comprises the following steps of:
s1: measuring and paying-off and working face arrangement, measuring and paying-off according to a design drawing and an installed roof structure, determining installation positions of all parts of the skylight, and determining a working face when the skylight is installed according to the roof structure;
s2: installing a skylight structure;
s21: the skylight framework is installed, and the skylight framework is installed on the metal roof according to the paying-off position;
s22: the skylight bottom plate is installed, buckled and fixed on the skylight framework;
s23: the skylight glass is installed, and the skylight glass is installed on the framework by using a pressing block;
s3: the installation of the sealing component comprises the steps of installing the sealing component between glass and a framework, between the framework and a metal roof, and between a bottom plate and the framework;
s4: the water spraying test is carried out, the skylight is closed, the spray gun or the spray head is used for spraying water on the skylight, whether the skylight leaks or not is observed, and if the skylight leaks, the leakage is repaired until the sealing effect is achieved;
s5: and (3) installing the sunshade curtain, namely installing the sunshade curtain on the framework, and checking and accepting the technological requirements of the drawing.
2. The construction process of the metal roof skylight of claim 1, wherein the skylight framework adopts a main keel structure and an auxiliary keel structure.
3. The construction process of the metal roof skylight of claim 2, wherein the main keels and the secondary keels are galvanized square tubes.
4. A metal roof skylight construction process according to claim 3, wherein when the main keels and the secondary keels are installed, the main keels and the secondary keels are lifted to a discharging platform of a working surface by using a tower crane or an automobile crane and then manually conveyed to an installation position.
5. The construction process of the metal roof skylight according to claim 1, wherein when the skylight glass is transported, the skylight glass is firstly hoisted to a discharging platform by using a tower crane, then is transported to a mounting position by a worker for mounting, and after the mounting is finished, the next piece of glass is hoisted by using the tower crane, so that only one piece of glass is guaranteed to be processed and mounted each time.
6. The construction process of the metal roof skylight according to claim 1, wherein in the step S23, after the glass is installed, a gap between the glass and the framework is plugged into a foam rod, and then glue is applied for fixing.
7. The metal roof skylight construction process according to claim 6, wherein in the step S23, the specific steps are as follows:
s231: cleaning and drying the sealing part; cleaning and drying the part where the glass is installed and the periphery of the glass by using gauze;
s232: installing glass, namely installing the glass, and inserting a foam rod into the gap;
s233: attaching a masking tape, namely attaching the masking tape on the junction of the sealing glue line and the surface material;
s234: glue is applied, and glue is applied and fixed at the gaps, so that the glue is uniformly, compactly and fully applied;
s235: after the gap is corrected and the glue is beaten, the glue line is forced to be pressed by a small shovel along the glue injection direction, redundant glue is scraped off, and the glue line is scraped into a designed shape, so that the glue line is smooth and fluent;
s236: paper tape removal: after finishing the glue line, timely removing the protective tape, and tearing the tape off to prevent the glass surface or the aluminum plate surface from being polluted; and cleaning glue marks stuck on the construction surface.
8. The metal roof skylight construction process according to claim 1, wherein the sealing assembly is a combined design of a waterproof roll, an additional layer of the waterproof roll and a edging plate.
9. The metal roof skylight construction process according to claim 8, wherein the edge trimming plate is a profiled steel plate.
CN202311186372.3A 2023-09-14 2023-09-14 Construction process of metal roof skylight Pending CN117211476A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311186372.3A CN117211476A (en) 2023-09-14 2023-09-14 Construction process of metal roof skylight

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311186372.3A CN117211476A (en) 2023-09-14 2023-09-14 Construction process of metal roof skylight

Publications (1)

Publication Number Publication Date
CN117211476A true CN117211476A (en) 2023-12-12

Family

ID=89038354

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311186372.3A Pending CN117211476A (en) 2023-09-14 2023-09-14 Construction process of metal roof skylight

Country Status (1)

Country Link
CN (1) CN117211476A (en)

Similar Documents

Publication Publication Date Title
CN106760560B (en) Complicated arc list construction of Pyramid engineering method
CN113982198B (en) Lotus leaf molding roof
CN104631668A (en) Connection construction method for composite keel double-layer decorative curtain wall
CN110552450A (en) Construction method of large-span short-vertical-edge vertical double-lock-edge titanium-zinc alloy metal roof
CN105672656A (en) Construction method of exterior hidden frame supported glass curtain wall
CN216475513U (en) Metal roof
CN212977217U (en) Support tarpaulin for welding steel box girder
CN117211476A (en) Construction process of metal roof skylight
CN202115527U (en) Roof structure of rail car
CN116988604A (en) Construction method of open hyperboloid overlapping metal curtain wall mounting structure
CN216276498U (en) Gutter structure arranged on metal roof
CN206888607U (en) A kind of rail type mobile workshop for the assembling of water-storage formula generator unit
CN108177731B (en) Method for building main pipe platform of liquid cargo ship
KR101780988B1 (en) Waterproofing method of building wall
CN115787937A (en) Light photovoltaic module building integrated structure and construction method
CN111593887B (en) Outsourcing waterproof construction method for penetrating metal roof plate component
CN211850290U (en) Integrally-detachable large-scale roof access opening structure
CN110778036B (en) Combined roof system of metal tiles and metal eaves rafters
CN104088481A (en) Sandwich composite glass fiber reinforced plastic plenum chamber for auditorium and construction method thereof
CN210530092U (en) Profiled steel sheet longitudinal lap joint node structure
CN110778035B (en) Construction method of combined roof of metal tiles and metal eaves rafters
CN107419857A (en) Built-up roofing Durchgangshohle node and its construction method
CN216516085U (en) Daylighting roof construction joint
CN219622105U (en) Integral truss roof board keel structure
CN214272685U (en) Go out roofing air shaft mounting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication