CN116677436A - A multi-hole yielding pressure bolt device capable of segmental grouting and its application method - Google Patents

A multi-hole yielding pressure bolt device capable of segmental grouting and its application method Download PDF

Info

Publication number
CN116677436A
CN116677436A CN202310755034.0A CN202310755034A CN116677436A CN 116677436 A CN116677436 A CN 116677436A CN 202310755034 A CN202310755034 A CN 202310755034A CN 116677436 A CN116677436 A CN 116677436A
Authority
CN
China
Prior art keywords
anchor rod
grouting
hole
section
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310755034.0A
Other languages
Chinese (zh)
Inventor
孟庆彬
辛学奎
吴疆宇
申海龙
郝阳
肖猛
曹悦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology Beijing CUMTB
Original Assignee
China University of Mining and Technology Beijing CUMTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology Beijing CUMTB filed Critical China University of Mining and Technology Beijing CUMTB
Priority to CN202310755034.0A priority Critical patent/CN116677436A/en
Publication of CN116677436A publication Critical patent/CN116677436A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/025Grouting with organic components, e.g. resin
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/028Devices or accesories for injecting a grouting liquid in a bore-hole
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • E21D21/0033Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts having a jacket or outer tube
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a porous yielding anchor rod device capable of grouting in a segmented mode and a use method thereof, and belongs to the field of underground engineering support of roadways, tunnels and the like. The device comprises an anchor rod and a sleeve, wherein plastic teeth are arranged in the sleeve, and the plastic teeth on the inner wall of the sleeve are extruded by utilizing a high-strength nut at the end part of the anchor rod, so that plastic damage is generated to realize the yielding characteristic of the anchor rod device; when the surrounding rock is deformed greatly, the device can synchronously realize constant resistance large deformation, and the anchor rod device is ensured not to be damaged; the device can also realize sectional grouting, and the sectional grouting reinforcement is realized by pulling the sectional grouting stop plug inside the anchor rod through the circular isolation disc and the steel wire which are inherent outside the anchor rod. The structure of the invention can realize the constant resistance yielding effect, can partially and sectionally grouting, and has the advantages of various functions, constant resistance, reasonable structure, economy and applicability.

Description

一种可分段注浆的多孔让压锚杆装置及其使用方法A multi-hole yielding pressure bolt device capable of segmental grouting and its application method

技术领域technical field

本发明涉及巷道、隧道、隧洞等地下工程支护领域,是一种可分段注浆的多孔让压锚杆装置及其使用方法。The invention relates to the field of underground engineering support such as roadways, tunnels, tunnels, etc., and relates to a multi-hole yielding pressure bolt device capable of segmented grouting and a method for using the same.

背景技术Background technique

随着我国铁路和公路隧道、矿山巷道、水利水电及输水隧洞等地下工程建设的飞速发展,随着固体矿产开采深度和隧道、隧洞埋深的不断加大,面临的开采环境与工程地质条件愈加复杂。深部围岩巷道受“三高一扰动”影响易发生变形破坏,其支护问题成了深部开采及隧道工程建设的重要任务。With the rapid development of underground engineering construction such as railway and highway tunnels, mine roadways, water conservancy and hydropower and water transmission tunnels in my country, as the mining depth of solid minerals and the burial depth of tunnels and tunnels continue to increase, the mining environment and engineering geological conditions faced more and more complicated. Deep surrounding rock roadways are prone to deformation and failure due to the influence of "three highs and one disturbance". The support problem has become an important task for deep mining and tunnel engineering construction.

锚杆是一种广泛高效应用于地下工程支护领域的支护形式,为解决破碎围岩大变形的支护难题,就要求锚杆不仅能提供恒定的支护力,而且能产生较大的伸长变形以满足破碎围岩大变形的要求;除此之外,为解决破碎围岩强度低的问题,现有方法是使用注浆的方法来加固破碎围岩使之提高强度。但是在现场施工作业时,大量工程注浆后往往不知浆液流向何段、流向何处,即无法对局部破碎围岩进行精准加固,这便使注浆修复加固围岩的效益不佳;并且,施工现场常用的端部注浆加固方法受其注浆位置和设备的限制,注浆后需要预留钻孔,等待浆液固化后甚至需要二次钻孔才可使用锚杆进行加强锚固以保证锚杆对围岩的支护效果,时间过长、工序复杂且工作效率低,不仅影响了锚固效果而且现场的可行性极低。相比之下树脂锚固剂锚固固化时间短,锚固效果更优,能够克服以上不足。基于上述问题,亟需研制一种既能够提供恒定的支护力以有效控制围岩变形,又能够分段注浆以精准修复围岩裂隙、加固破碎围岩,还能够结合锚固剂锚固、注浆加固,使之作业同时进行的锚杆装置,即一种集功能多样、恒定阻力、结构合理、经济适用、变形让压功能于一身的锚杆装置以解决存在的工程技术难题,以实现破碎围岩“锚固—注浆”一体化作业。Bolt is a support form widely and efficiently used in the field of underground engineering support. In order to solve the support problem of large deformation of broken surrounding rock, it is required that the bolt can not only provide a constant support force, but also generate a large The elongation deformation meets the requirement of large deformation of the broken surrounding rock; in addition, in order to solve the problem of low strength of the broken surrounding rock, the existing method is to use the method of grouting to reinforce the broken surrounding rock to increase its strength. However, during on-site construction work, after grouting a large number of projects, it is often not known where the grout flows and where it flows, that is, it is impossible to accurately reinforce the partially broken surrounding rock, which makes the benefit of grouting repair and reinforcement of the surrounding rock poor; and, The commonly used end grouting reinforcement method on the construction site is limited by the grouting position and equipment. After the grouting, it is necessary to reserve a drill hole. After the grout solidifies, even a second drill is required before the anchor rod can be used to strengthen the anchorage to ensure the anchorage. The supporting effect of the rod on the surrounding rock is too long, the process is complicated and the work efficiency is low, which not only affects the anchoring effect but also has extremely low feasibility on site. In contrast, the resin anchoring agent has a shorter anchoring and curing time and better anchoring effect, which can overcome the above shortcomings. Based on the above problems, it is urgent to develop a method that can not only provide a constant support force to effectively control the deformation of the surrounding rock, but also allow segmental grouting to accurately repair the cracks in the surrounding rock and reinforce the broken surrounding rock. Slurry reinforcement, so that the anchor device can be operated at the same time, that is, a kind of anchor device that integrates multiple functions, constant resistance, reasonable structure, economical application, and deformation and compression functions to solve the existing engineering technical problems and achieve crushing. Surrounding rock "anchor-grouting" integrated operation.

发明内容Contents of the invention

技术问题:本发明的目的是要克服现有技术中的不足之处,提供一种可分段注浆的多孔让压锚杆装置及其使用方法,其不但能够提供恒定的支护力以有效控制围岩变形,又能够分段注浆以精准修复围岩裂隙、加固破碎围岩,还能够结合锚固剂锚固、注浆加固,使之作业同时进行。Technical problem: The purpose of this invention is to overcome the deficiencies in the prior art, to provide a multi-hole yielding pressure bolt device that can be grouted in sections and its use method, which can not only provide constant supporting force to effectively It can control the deformation of the surrounding rock, and can inject grouting in sections to accurately repair the cracks in the surrounding rock and reinforce the broken surrounding rock. It can also be combined with anchoring agent for anchoring and grouting reinforcement, so that the operations can be carried out at the same time.

技术方案:本发明的一种可分段注浆的多孔让压锚杆装置及其使用方法,包括锚杆,锚杆上设有套筒;锚杆包括一体结构且外径相同的锚杆螺纹段、锚杆中空段和锚杆实心段,其中锚杆实心段设置在锚杆中空段的端部,锚杆螺纹段设置在锚杆中空段的尾部,锚杆螺纹段上设有用以安装托盘和防滑丝螺母的螺纹,锚杆中空段内轴向设有贯通锚杆螺纹段的通孔,通孔内设有能够在通孔中移动并封堵通孔的分段止浆塞、限位器和注浆钢管,其中分段止浆塞和注浆钢管分别设置在限位器两端,分段止浆塞上设有延伸至通孔外侧的钢丝线,锚杆中空段上间隔设有与通孔沟通的多个注浆孔,锚杆中空段的外侧间隔设有三个圆形隔绝盘,圆形隔绝盘的尺寸与锚孔匹配,从而将锚孔内的空间分割为区域I、区域II、区域III和区域IV,其中区域I内为锚杆螺纹段所在空间,区域II、区域III为锚杆中空段所在空间,区域IV为锚杆实心段所在空间,并根据需要对区域II或者区域III分段注浆;锚杆实心段的端部通过螺纹设有高强度螺母,套筒套设在整个锚杆实心段,套筒前端设有防止岩土碎渣及尘土进入的密封盘,套筒内侧间隔距离设有多圈与配合高强度螺母实现让压的塑性齿。Technical solution: A multi-hole yielding pressure bolt device capable of segmental grouting and its use method according to the present invention, including a bolt on which a sleeve is arranged; the bolt includes bolt threads with an integral structure and the same outer diameter section, the hollow section of the anchor and the solid section of the anchor, wherein the solid section of the anchor is set at the end of the hollow section of the anchor, the threaded section of the anchor is set at the tail of the hollow section of the anchor, and the threaded section of the anchor is provided with a and the thread of the anti-skid wire nut, the hollow section of the anchor rod is axially provided with a through hole through the threaded section of the anchor rod, and the through hole is provided with a segmented grout stopper and a stopper that can move in the through hole and block the through hole and grouting steel pipes, wherein the segmented grout stoppers and grouting steel pipes are respectively arranged at both ends of the limiter, the segmental grout stoppers are provided with steel wires extending to the outside of the through hole, and the hollow section of the anchor rod is provided with There are multiple grouting holes communicated by through holes, and three circular isolation discs are arranged on the outer side of the hollow section of the anchor rod. The size of the circular isolation discs matches the anchor hole, so that the space in the anchor hole is divided into area I and area II , area III and area IV, where area I is the space where the threaded section of the anchor rod is located, area II and area III are the space where the hollow section of the anchor rod is located, area IV is the space where the solid section of the anchor rod is located, and area II or area III Segmented grouting; the end of the solid section of the anchor rod is threaded with a high-strength nut, and the sleeve is sleeved on the entire solid section of the anchor rod. The inner side of the cylinder is provided with plastic teeth with multi-turns and high-strength nuts at intervals to achieve pressure relief.

进一步,锚杆中空段上设置的注浆孔共有8~12个,等间距布置在三个圆形隔绝盘之间的锚杆中空段侧壁上。Further, there are 8 to 12 grouting holes arranged on the hollow section of the anchor rod, which are equally spaced on the side wall of the hollow section of the anchor rod between the three circular insulating plates.

进一步,圆形隔绝的外缘处设有用以提高密封效果的膨胀剂或者环形塞,膨胀剂用高弹性薄膜包裹并设有延时膨胀启动装置。Further, the outer edge of the circular insulation is provided with an expansion agent or an annular plug to improve the sealing effect, and the expansion agent is wrapped with a high elastic film and provided with a delay expansion start device.

进一步,套筒内壁各断面均匀布置4~6个塑性齿,塑性齿材料具有一定的塑性,并在在高强度螺母的挤压下发生变形。Further, 4 to 6 plastic teeth are uniformly arranged on each section of the inner wall of the sleeve, and the material of the plastic teeth has certain plasticity and deforms under the extrusion of the high-strength nut.

进一步,三个圆形隔绝盘中最靠近锚杆实心段的圆形隔绝盘设置在锚杆实心段与锚杆中空段连接处,该圆形隔绝盘端面开有用以与套筒连接并联动的圆柱形凸起,圆柱形凸起卡在圆形隔绝盘的预留孔中,可保证套筒随锚杆一起转动。Further, among the three circular insulating discs, the circular insulating disc closest to the solid section of the anchor rod is set at the joint between the solid section of the anchor rod and the hollow section of the anchor rod, and the end surface of the circular insulating disc is provided with a ring for connecting and interlocking with the sleeve. Cylindrical protrusion, the cylindrical protrusion is stuck in the reserved hole of the circular isolation disc, which can ensure that the sleeve rotates together with the anchor rod.

进一步,限位器为设置在锚杆中空段上位于区域II和区域III接连处的螺栓,螺栓径向插入锚杆中空段并利用螺母紧固,其能够限制分段止浆塞和注浆钢管移动范围。Further, the limiter is a bolt arranged on the hollow section of the anchor rod at the junction of area II and area III. The bolt is radially inserted into the hollow section of the anchor rod and tightened with a nut, which can limit the segmented grout stopper and the grouted steel pipe. range of movement.

进一步,注浆钢管口处设有环形止浆塞,环形止浆塞可在注浆时防止浆液回流。Further, an annular grout stopper is provided at the mouth of the grouting steel pipe, and the annular grout stopper can prevent the grout from flowing back during grouting.

一种可分段注浆的多孔让压锚杆装置的使用方法,其步骤如下:A method for using a multi-hole yielding pressure bolt device that can be grouted in sections, the steps are as follows:

在围岩预先标定的位置施工钻锚孔,将锚杆的锚杆实心段滑入套筒中,打开套筒端部的密封盘,在该侧将高强度螺母按螺纹添加到锚杆实心段上;Drill the anchor hole in the pre-marked position of the surrounding rock, slide the solid section of the anchor rod into the sleeve, open the sealing disc at the end of the sleeve, and add high-strength nuts to the solid section of the anchor rod by thread on this side superior;

在圆形隔绝盘外周凹槽中环绕上包裹膨胀剂的高弹性薄膜;Surround the high elastic film wrapped with expansion agent in the outer peripheral groove of the circular insulating disc;

用注浆钢管将连接有钢丝线的分段止浆塞推送到锚杆中空段底部,然后安装上螺栓和螺母;Use the grouted steel pipe to push the segmented grout plug connected with the steel wire to the bottom of the hollow section of the anchor rod, and then install the bolts and nuts;

将锚固剂胶泥药卷、固化剂药卷和锚杆送入锚孔之中;Send the anchoring agent cement roll, curing agent roll and anchor rod into the anchor hole;

启动搅拌器带动锚杆旋转搅拌锚固剂胶泥药卷、固化剂药卷充分搅拌形成锚固剂胶结体,套筒通过圆柱形凸起与圆形隔绝盘联动;等待锚固剂固化后,在锚孔孔外露的锚杆螺纹段上依次套装托盘和防滑丝螺母,通过预紧防滑丝螺母沿螺纹升角提供预紧力;Start the agitator to drive the anchor rod to rotate and stir the anchoring agent cement roll and curing agent roll to form an anchoring agent cemented body. The sleeve is linked with the circular isolation plate through the cylindrical protrusion; The exposed threaded section of the anchor rod is fitted with a tray and an anti-slip wire nut in sequence, and the pre-tightening force is provided along the thread lead angle by pre-tightening the anti-slip wire nut;

当检测到被圆形隔绝盘分割出来的区域III部分由于裂隙过多或者处于岩层交错带,即判断需要对区域III部分注浆加固;将注浆钢管推入锚杆中空段中设有螺栓的位置,由于螺栓的阻挡,将限制注浆钢管的进一步推送,在注浆钢管外露尾端通过橡胶导管与高压注浆泵连接,启动高压注浆泵,浆液通过注浆孔注入锚孔区域III部分,将对区域III部分围岩裂隙进行修复加固;When it is detected that the area III part divided by the circular isolation plate has too many cracks or is in the interlaced zone of rock strata, it is judged that the area III part needs to be reinforced by grouting; push the grouted steel pipe into the hollow section of the anchor rod and set the bolt Due to the blocking of the bolts, the further pushing of the grouting steel pipe will be restricted. The exposed end of the grouting steel pipe is connected to the high-pressure grouting pump through a rubber conduit, and the high-pressure grouting pump is started. The grout is injected into the anchor hole area III through the grouting hole , will repair and strengthen part of the surrounding rock cracks in Area III;

与上述同理,当需要对区域II部分注浆加固时,则拉动钢丝线牵拉分段止浆塞(26)运动,由于锚杆中空段中设有螺栓的阻挡,分段止浆塞(26)将在螺栓处停下,此时将注浆钢管推入到锚杆螺纹段注浆即可保证只修复加固区域II部分围岩裂隙。In the same way as above, when the grouting of the region II part needs to be reinforced, the steel wire is pulled to pull the segmental grout stopper (26) to move, and the segmental grout stopper (26) is blocked by bolts in the hollow section of the bolt. 26) It will stop at the bolt. At this time, push the grouted steel pipe into the threaded section of the bolt and inject grout to ensure that only the cracks in the surrounding rock in the reinforcement area II will be repaired.

当围岩发生大变形时,锚杆实心段端部的高强度螺母挤压套筒内壁上的塑性齿,塑性齿产生塑性变形,此时高强度螺母滑移接触下一个断面的塑性齿,以此来实现该装置的恒阻大变形。When the surrounding rock undergoes large deformation, the high-strength nut at the end of the solid section of the anchor squeezes the plastic teeth on the inner wall of the sleeve, and the plastic teeth produce plastic deformation. This is to realize the constant resistance and large deformation of the device.

有益效果:由于采用了上述技术方案,本发明兼具有提供恒定的支护力,产生较大的伸长变形以满足围岩大变形的要求和分段注浆以精准修复围岩裂隙、加固破碎围岩的功能,弥补了现有传统锚杆无法随围岩发生变形的缺点,弥补了大量注浆后浆液流失不知去向无法精准加固围岩的缺点。通过高强度螺母对塑性齿的挤压变形来提供恒定阻力,进而可在允许范围之内随围岩一起变形来满足围岩大变形的要求;通过圆形隔绝盘可在浆液注入锚孔时将浆液隔离开和拉动分段止浆塞来实现选择性分段注浆的效果。所述锚杆装置集多种功能于一身,解决了普通锚杆无法满足围岩大变形的问题,解决了现有让压锚杆造价过高的问题,解决了现有注浆方法难以精准加固围岩和修复裂隙、加固围岩效果差的问题,实现了破碎围岩“锚固—注浆”一体化作业。本发明结构简单,造价低廉,功能稳定,工序简单,可极大得工作效率,且锚杆的变形让压功能又可有效减少事故的发生,保证工作人员的生命安全。Beneficial effects: due to the adoption of the above-mentioned technical scheme, the present invention can provide constant supporting force, generate larger elongation deformation to meet the requirement of large deformation of surrounding rock and segmental grouting to accurately repair surrounding rock fissures and reinforce The function of breaking the surrounding rock makes up for the shortcomings of the existing traditional anchor bolts that cannot deform with the surrounding rock, and makes up for the shortcomings of the loss of grout after a large amount of grouting and the inability to accurately reinforce the surrounding rock. The extrusion deformation of the plastic tooth by the high-strength nut provides constant resistance, and then it can deform together with the surrounding rock within the allowable range to meet the requirements of large deformation of the surrounding rock; through the circular isolation disc, the grout can be used when the grout is injected into the anchor hole. The grout isolates and pulls the segmented stop plugs to achieve the effect of selective segmented grouting. The bolt device integrates multiple functions, solves the problem that ordinary bolts cannot meet the large deformation of surrounding rock, solves the problem of high cost of existing pressure bolts, and solves the problem that the existing grouting method is difficult to accurately reinforce The problems of surrounding rock and poor effect of repairing cracks and reinforcing surrounding rock have realized the integrated operation of "anchor-grouting" for breaking surrounding rock. The invention has the advantages of simple structure, low cost, stable function and simple process, which can greatly improve work efficiency, and the deformation and compression function of the anchor rod can effectively reduce the occurrence of accidents and ensure the safety of workers.

附图说明Description of drawings

图1为本发明的实施例中锚孔示意图;Fig. 1 is the anchor hole schematic diagram in the embodiment of the present invention;

图2为本发明实施例中锚固装置示意图;Fig. 2 is the schematic diagram of anchoring device in the embodiment of the present invention;

图3为本发明实施例中锚固装置的安装示意图;Fig. 3 is the schematic diagram of the installation of the anchoring device in the embodiment of the present invention;

图4为本发明实施例中套筒装置的让压示意图;Fig. 4 is a schematic diagram of yielding pressure of the sleeve device in the embodiment of the present invention;

图5(a)为本发明实施例中围岩区域III部分注浆加固示意图;Fig. 5 (a) is a schematic diagram of grouting reinforcement of the surrounding rock area III part in the embodiment of the present invention;

图5(b)为本发明实施例中围岩区域II部分注浆加固示意图;Fig. 5 (b) is a schematic diagram of the grouting reinforcement of the surrounding rock area II part in the embodiment of the present invention;

图6为本发明实施例中注浆钢管和橡胶导管放大示意图;6 is an enlarged schematic view of a grouted steel pipe and a rubber conduit in an embodiment of the present invention;

图7(a)为本发明实施例中螺栓所在横截面示意图;Fig. 7 (a) is the schematic diagram of the cross section where the bolt is located in the embodiment of the present invention;

图7(b)为本发明实施例中注浆孔所在横截面示意图;Fig. 7 (b) is the schematic diagram of the cross section where the grouting hole is located in the embodiment of the present invention;

图7(c)为本发明实施例中套筒内塑性齿所在横截面示意图;Figure 7(c) is a schematic cross-sectional view of where the plastic teeth in the sleeve are located in the embodiment of the present invention;

图8(a)为本发明实施例中圆形隔绝盘正视示意图;Fig. 8(a) is a schematic front view of a circular insulating disk in an embodiment of the present invention;

图8(b)为本发明实施例中圆形隔绝盘立体图。Fig. 8(b) is a perspective view of a circular insulating disk in an embodiment of the present invention.

图中:1-围岩,2-锚杆,3-防滑丝螺母,4-托盘,5-裂隙,6-锚杆螺纹段,7-锚杆中空段,8-锚杆实心段,9-高强度螺母,10-圆形隔绝盘,11-膨胀剂,12-套筒,13-圆柱形凸起,14-塑性齿,15-锚固剂胶结体,16-密封盘,17-注浆孔,18-钢丝线,19-螺栓,20-螺母,21-注浆钢管,22-橡胶导管,23-锚孔,24-高弹性薄膜,25-环形止浆塞,26-分段止浆塞。In the figure: 1-surrounding rock, 2-bolt, 3-anti-slip wire nut, 4-tray, 5-crack, 6-threaded section of bolt, 7-hollow section of bolt, 8-solid section of bolt, 9- High-strength nut, 10-circular isolation disc, 11-expansion agent, 12-sleeve, 13-cylindrical protrusion, 14-plastic tooth, 15-anchor cement, 16-sealing disc, 17-grouting hole , 18-steel wire, 19-bolt, 20-nut, 21-grouting steel pipe, 22-rubber conduit, 23-anchor hole, 24-high elastic film, 25-annular grout stopper, 26-segmented grout stopper .

具体实施方式Detailed ways

下面结合附图中的实施例对本发明作进一步的描述:The present invention will be further described below in conjunction with the embodiment in the accompanying drawings:

如图1和图2所示,一种可分段注浆的多孔让压锚杆装置,包括锚杆2和套筒12,所述锚杆2分为锚杆螺纹段6、锚杆中空段7和锚杆实心段8。所述锚杆螺纹段6设有螺纹,螺纹上顺序设置的托盘4和防滑丝螺母3;锚杆中空段7上固有圆形隔绝盘10,围岩1通过圆形隔绝盘10可分为区域I、区域II、区域III和区域IV;锚杆实心段8深入套筒12当中。所述锚杆螺纹段6、锚杆中空段7和锚杆实心段8为一体结构且外径相同;所述锚杆中空段7各断面沿圆周间隔设有4个注浆孔17,如图7(b)所示,各断面间距布置合理,注浆时浆液可从注浆孔17注入锚孔23中,进而修复裂隙5,加固围岩1;在锚杆中空段7与锚杆实心段8交接结合处设有分段止浆塞26,用以阻绝浆液,分段止浆塞26上连有钢丝线18,在锚孔23孔外拉动钢丝线18可拉动分段止浆塞26运动。锚杆中空段7在区域II和区域III接连处附近设有螺栓19和螺母20,当通过钢丝线18拉动分段止浆塞26时,分段止浆塞26滑移到螺栓19处将会被卡住;锚杆中空段7上还设有圆形隔绝盘10,其周身环绕膨胀剂11,膨胀剂11用高弹性薄膜24包裹。圆形隔绝盘10可在浆液注入锚孔23时将浆液隔离开,以实现选择性分段注浆的效果所述锚杆实心段8深入套筒12之中,其端部通过螺纹设置有高强度螺母9,所选高强度螺母9的强度和刚度应足够大。通过高强度螺母9对套筒12内壁上设置的塑性齿14的挤压破坏来实现让压功能。As shown in Figures 1 and 2, a multi-hole yielding anchor device that can be grouted in sections includes an anchor 2 and a sleeve 12, and the anchor 2 is divided into an anchor threaded section 6, an anchor hollow section 7 and anchor rod solid section 8. The bolt threaded section 6 is provided with a thread, and the tray 4 and the anti-skid wire nut 3 are arranged in sequence on the thread; the hollow section 7 of the anchor bolt has a circular isolation plate 10, and the surrounding rock 1 can be divided into regions through the circular isolation plate 10. I, area II, area III and area IV; the solid section 8 of the anchor rod goes deep into the middle of the sleeve 12 . The threaded section 6 of the anchor rod, the hollow section 7 of the anchor rod and the solid section 8 of the anchor rod have an integral structure and the same outer diameter; each section of the hollow section of the anchor rod 7 is provided with four grouting holes 17 at intervals along the circumference, as shown in the figure As shown in Fig. 7(b), the spacing of each section is reasonable. During grouting, the grout can be injected into the anchor hole 23 from the grouting hole 17, thereby repairing the crack 5 and strengthening the surrounding rock 1; 8. Segmented grout stopper 26 is provided at the junction to block the slurry. Steel wire 18 is connected to the segmented grout stopper 26. Pull the steel wire 18 outside the anchor hole 23 to pull the segmented grout stopper 26 to move. . Bolts 19 and nuts 20 are provided in the hollow section 7 of the anchor rod near the junction of area II and area III. When the segmented grout stopper 26 is pulled by the steel wire 18, the segmented grout stopper 26 slides to the bolt 19 and will It is stuck; the hollow section 7 of the anchor rod is also provided with a circular insulating disc 10, which surrounds the expansion agent 11, and the expansion agent 11 is wrapped with a high elastic film 24. The circular isolation disc 10 can isolate the grout when the grout is injected into the anchor hole 23, so as to realize the effect of selective segmental grouting. Strength nut 9, the strength and rigidity of selected high-strength nut 9 should be large enough. The pressure relief function is realized by the high-strength nut 9 crushing and destroying the plastic teeth 14 provided on the inner wall of the sleeve 12 .

如图3所示,将锚固剂胶泥药卷、固化剂药卷和锚杆2送入锚孔23之中。启动搅拌器带动锚杆2旋转搅拌锚固剂胶泥药卷、固化剂药卷充分搅拌形成锚固剂胶体,套筒12通过圆柱形凸起13与圆形隔绝盘10联动;等待锚固剂固化后,在锚孔23孔外露的锚杆螺纹段6上依次套装托盘4和防滑丝螺母3,通过预紧防滑丝螺母3沿螺纹升角提供预紧力。As shown in FIG. 3 , the anchoring agent mastic roll, the curing agent roll and the anchor rod 2 are sent into the anchor hole 23 . Start the agitator to drive the anchor rod 2 to rotate and stir the anchoring agent glue roll and the curing agent roll to fully stir to form the anchoring agent colloid, and the sleeve 12 is linked with the circular isolation plate 10 through the cylindrical protrusion 13; after the anchoring agent is solidified, the The anchor rod threaded section 6 exposed in the anchor hole 23 is sequentially set with the tray 4 and the anti-skid wire nut 3, and the pre-tightening force is provided along the thread lead angle by pre-tightening the anti-skid wire nut 3.

如图4所示,所述套筒12内壁各断面均匀布置4~6个塑性齿14,所选塑性齿14材料应具有一定的塑性,可在高强度螺母9的挤压下发生变形,如图7c所示。套筒12在靠近锚孔23孔底一侧设有密封盘16,以防止岩土碎渣及尘土的进入;其另一侧设有圆柱形凸起13,圆柱形凸起13卡在圆形隔绝盘10的预留孔中,可保证套筒12随锚杆2一起转动;所述围岩1发生变形时,锚杆实心段8端部的高强度螺母9挤压套筒12内壁上的塑性齿14,塑性齿14产生塑性变形,此时高强度螺母9滑移接触下一个断面的塑性齿14,以此来实现该装置的恒阻大变形;As shown in Figure 4, 4 to 6 plastic teeth 14 are evenly arranged on each section of the inner wall of the sleeve 12, and the selected plastic teeth 14 materials should have certain plasticity and can be deformed under the extrusion of the high-strength nut 9, such as Figure 7c shows. The sleeve 12 is provided with a sealing disc 16 on one side near the bottom of the anchor hole 23 to prevent the entry of rock debris and dust; the other side is provided with a cylindrical protrusion 13, which is stuck in the circular In the reserved hole of the insulating disc 10, the sleeve 12 can be guaranteed to rotate together with the anchor rod 2; when the surrounding rock 1 is deformed, the high-strength nut 9 at the end of the solid section 8 of the anchor rod squeezes the nut 9 on the inner wall of the sleeve 12. Plastic tooth 14, the plastic tooth 14 produces plastic deformation, at this time, the high-strength nut 9 slides to contact the plastic tooth 14 of the next section, so as to realize the constant resistance and large deformation of the device;

如图5(a)和图5(b)所示,所述围岩1和锚孔23按圆形隔绝盘10所在位置可分为区域I、区域II、区域III和区域IV。当检测到区域III部分裂隙较多时或该部分处于岩层交错带,即需要对区域III部分注浆加固时,可将注浆钢管21推入锚杆中空段7中设有螺栓19的位置,由于螺栓19的阻挡,将限制注浆钢管21的进一步推送,如图7(a)所示;当需要对区域II部分注浆加固时,可拉动钢丝线18进而牵拉分段止浆塞26运动,由于锚杆中空段7中设有螺栓19的阻挡,分段止浆塞26将在螺栓19处停下。此时将注浆钢管21推入到锚杆螺纹段6注浆即可加固区域II部分围岩裂隙5;所述注浆钢管21由各段钢管拼接而成,亦可以与橡胶导管22接连。如图6所示,注浆钢管21口处设有环形止浆塞25,环形止浆塞25可在注浆时防止浆液回流。As shown in Fig. 5(a) and Fig. 5(b), the surrounding rock 1 and the anchor hole 23 can be divided into area I, area II, area III and area IV according to the position of the circular insulating disk 10. When it is detected that there are many cracks in the area III part or the part is in the interlaced zone of the rock formation, that is, when the part of the area III needs to be grouted and reinforced, the grouted steel pipe 21 can be pushed into the position where the bolt 19 is provided in the hollow section 7 of the anchor rod, because The blocking of the bolt 19 will limit the further pushing of the grouted steel pipe 21, as shown in Figure 7(a); when it is necessary to grout the area II and reinforce it, the steel wire 18 can be pulled and then the segmented grout stopper 26 can be pulled to move , because the hollow section 7 of the bolt is provided with the blocking of the bolt 19, the segmented grout stopper 26 will stop at the bolt 19. At this time, push the grouting steel pipe 21 into the threaded section 6 of the anchor rod and inject grout to reinforce the surrounding rock fissure 5 in the region II; As shown in Fig. 6, an annular grout stopper 25 is provided at the mouth of the grouting steel pipe 21, and the annular grout stopper 25 can prevent the grout from flowing back during grouting.

如图8(a)和图8(b)所示,锚杆中空段7上还设有圆形隔绝盘10,其周身环绕膨胀剂11,膨胀剂11用高弹性薄膜24包裹。圆形隔绝盘10外径略小于锚孔23孔径,当环绕的膨胀剂11膨胀后,可在浆液注入锚孔23时将浆液隔离开,以实现选择性分段注浆的效果。As shown in Figure 8(a) and Figure 8(b), the hollow section 7 of the anchor rod is also provided with a circular insulating disk 10, which is surrounded by an expansion agent 11, and the expansion agent 11 is wrapped with a high elastic film 24. The outer diameter of the circular insulating disc 10 is slightly smaller than the diameter of the anchor hole 23. When the surrounding expansion agent 11 expands, the grout can be isolated when the grout is injected into the anchor hole 23, so as to achieve the effect of selective segmental grouting.

Claims (9)

1.一种可分段注浆的多孔让压锚杆装置,其特征在于:包括锚杆(2),锚杆(2)上设有套筒(12);锚杆(2)包括一体结构且外径相同的锚杆螺纹段(6)、锚杆中空段(7)和锚杆实心段(8),其中锚杆实心段(8)设置在锚杆中空段(7)的端部,锚杆螺纹段(6)设置在锚杆中空段(7)的尾部,锚杆螺纹段(6)上设有用以安装托盘(4)和防滑丝螺母(3)的螺纹,锚杆中空段(7)内轴向设有贯通锚杆螺纹段(6)的通孔,通孔内设有能够在通孔中移动并封堵通孔的分段止浆塞(26)、限位器和注浆钢管(21),其中分段止浆塞(26)和注浆钢管(21)分别设置在限位器前后侧,分段止浆塞(26)上设有延伸至通孔外侧的钢丝线(18),锚杆中空段(7)上间隔设有与通孔沟通的多个注浆孔(17),锚杆中空段(7)的外侧间隔设有三个圆形隔绝盘(10),圆形隔绝盘(10)的尺寸与锚孔(23)匹配,从而将锚孔(23)内的空间分割为区域I、区域II、区域III和区域IV,其中区域I内为锚杆螺纹段(6)所在空间,区域II、区域III为锚杆中空段(7)所在空间,区域IV为锚杆实心段(8)所在空间,根据需要对区域II或者区域III分段注浆;锚杆实心段(8)的端部通过螺纹设有高强度螺母(9),套筒(12)套设在整个锚杆实心段(8),套筒(12)前端设有防止岩土碎渣及尘土进入的密封盘(16),套筒(12)内侧间隔距离设有多圈与配合高强度螺母(9)实现让压的塑性齿(14)。1. A multi-hole pressure-yielding bolt device capable of segmented grouting, characterized in that: it comprises a bolt (2), and the bolt (2) is provided with a sleeve (12); the bolt (2) includes an integral structure Anchor rod threaded section (6), anchor rod hollow section (7) and anchor rod solid section (8) with the same outer diameter, wherein the anchor rod solid section (8) is arranged at the end of the anchor rod hollow section (7), The anchor rod threaded section (6) is arranged on the afterbody of the anchor rod hollow section (7), and the anchor rod threaded section (6) is provided with threads for installing the tray (4) and the anti-skid wire nut (3), and the anchor rod hollow section ( 7) There is a through hole through the threaded section (6) of the anchor rod in the inner axial direction, and a segmented grout stopper (26), stopper and grouting plug (26) capable of moving in the through hole and sealing the through hole are arranged in the through hole. Steel pipes (21), wherein the segmented grout stoppers (26) and the grouting steel pipes (21) are respectively arranged on the front and rear sides of the limiter, and the segmental grout stoppers (26) are provided with steel wires extending to the outside of the through hole ( 18), a plurality of grouting holes (17) communicating with the through holes are arranged at intervals on the hollow section of the anchor rod (7), and three circular isolation discs (10) are arranged at intervals on the outer side of the hollow section of the anchor rod (7). The size of the shaped insulating disc (10) matches the anchor hole (23), thereby dividing the space in the anchor hole (23) into area I, area II, area III and area IV, wherein in area I is the threaded section of the anchor rod ( 6) Space, area II and area III are the space where the hollow section of the anchor rod (7) is located, area IV is the space where the solid section of the anchor rod (8) is located, and the area II or area III is segmented grouting according to the needs; the solid anchor rod The end of the section (8) is threaded with a high-strength nut (9), the sleeve (12) is sleeved on the entire solid section (8) of the anchor rod, and the front end of the sleeve (12) is provided with an anti-rock and soil slag and dust The sealing disc (16) that enters is provided with multi-turn plastic teeth (14) that cooperate with high-strength nuts (9) to realize pressure-releasing at the inner side of the sleeve (12). 2.根据权利要求1所述的可分段注浆的多孔让压锚杆装置,其特征在于:锚杆中空段(7)上设置的注浆孔(17)共有8~12个,等间距布置在三个圆形隔绝盘(10)之间的锚杆中空段(7)侧壁上。2. The multi-hole yielding pressure bolt device capable of segmented grouting according to claim 1, characterized in that: there are 8 to 12 grouting holes (17) arranged on the hollow section (7) of the bolt, with equal intervals It is arranged on the side wall of the anchor rod hollow section (7) between the three circular insulating discs (10). 3.根据权利要求1所述的可分段注浆的多孔让压锚杆装置,其特征在于:圆形隔绝的外缘处设有用以提高密封效果的膨胀剂(11)或者环形塞,膨胀剂(11)用高弹性薄膜(24)包裹并设有延时膨胀启动装置。3. The multi-hole pressure-yield bolt device capable of segmented grouting according to claim 1, characterized in that: the outer edge of the circular insulation is provided with an expansion agent (11) or an annular plug to improve the sealing effect, and the expansion The agent (11) is wrapped with a high-elastic film (24) and is provided with a delayed expansion starting device. 4.根据权利要求1所述的可分段注浆的多孔让压锚杆装置,其特征在于:套筒(12)内壁各断面均匀布置4~6个塑性齿(14),塑性齿(14)材料具有一定的塑性,并在在高强度螺母(9)的挤压下发生变形。4. The multi-hole yielding pressure bolt device capable of segmented grouting according to claim 1, characterized in that: 4 to 6 plastic teeth (14) are evenly arranged on each section of the inner wall of the sleeve (12), and the plastic teeth (14 ) material has a certain degree of plasticity and is deformed under the extrusion of the high-strength nut (9). 5.根据权利要求1所述的可分段注浆的多孔让压锚杆装置,其特征在于:三个圆形隔绝盘(10)中最靠近锚杆实心段(8)的圆形隔绝盘(10)设置在锚杆实心段(8)与锚杆中空段(7)连接处,该圆形隔绝盘(10)端面开有用以与套筒(12)连接并联动的圆柱形凸起(13),圆柱形凸起(13)卡在圆形隔绝盘(10)的预留孔中,可保证套筒(12)随锚杆(2)一起转动。5. The multi-hole yielding pressure bolt device capable of segmented grouting according to claim 1, characterized in that: among the three circular insulating disks (10), the circular insulating disk closest to the solid section of the anchor rod (8) (10) is arranged at the connection between the solid section (8) of the anchor rod and the hollow section (7) of the anchor rod, and the end surface of the circular insulating disc (10) is provided with a cylindrical protrusion for connecting and interlocking with the sleeve (12) ( 13), the cylindrical protrusion (13) is stuck in the reserved hole of the circular insulating disc (10), which can ensure that the sleeve (12) rotates together with the anchor rod (2). 6.根据权利要求1所述的可分段注浆的多孔让压锚杆装置,其特征在于:限位器为设置在锚杆中空段(7)上位于区域II和区域III接连处的螺栓(19),螺栓(19)径向插入锚杆中空段(7)并利用螺母(20)紧固,其能够限制分段止浆塞(26)和注浆钢管(21)移动范围。6. The segmental grouting multi-hole yielding anchor device according to claim 1, characterized in that: the limiter is a bolt arranged on the hollow section (7) of the anchor rod at the junction of area II and area III (19), bolts (19) are radially inserted into the anchor rod hollow section (7) and tightened with nuts (20), which can limit the range of movement of the segmented grout stopper (26) and the grouted steel pipe (21). 7.根据权利要求1所述的可分段注浆的多孔让压锚杆装置,其特征在于:注浆钢管(21)口处设有环形止浆塞(25),环形止浆塞(25)可在注浆时防止浆液回流。7. The multi-hole pressure-yielding bolt device capable of segmented grouting according to claim 1, characterized in that: an annular grout stopper (25) is provided at the mouth of the grouting steel pipe (21), and the annular grout stopper (25 ) can prevent grout backflow during grouting. 8.一种使用上述1~7权利要求所述的一种可分段注浆的多孔让压锚杆装置的使用方法,其特征在于步骤如下:8. A method for using the segmented grouting porous yielding anchor device described in claims 1 to 7 above, characterized in that the steps are as follows: 在围岩(1)预先标定的位置施工钻锚孔(23),将锚杆(2)的锚杆实心段(8)滑入套筒(12)中,打开套筒(12)端部的密封盘(16),在该侧将高强度螺母(9)按螺纹添加到锚杆实心段(8)上;Drill the anchor hole (23) at the pre-marked position of the surrounding rock (1), slide the anchor rod solid section (8) of the anchor rod (2) into the sleeve (12), and open the end of the sleeve (12) A sealing disc (16), on which side a high-strength nut (9) is threaded onto the solid section (8) of the bolt; 在圆形隔绝盘(10)外周凹槽中环绕上包裹膨胀剂(11)的高弹性薄膜(24);Surround the high elastic film (24) of the expansion agent (11) in the peripheral groove of the circular insulating disc (10); 用注浆钢管(21)将连接有钢丝线(18)的分段止浆塞(26)推送到锚杆中空段(7)底部,然后安装上螺栓(19)和螺母(20);Use the grouting steel pipe (21) to push the segmented grout stopper (26) connected with the steel wire (18) to the bottom of the anchor rod hollow section (7), and then install the bolt (19) and nut (20); 将锚固剂胶泥药卷、固化剂药卷和锚杆(2)送入锚孔(23)之中;Send the anchoring agent mastic roll, curing agent roll and anchor rod (2) into the anchor hole (23); 启动搅拌器带动锚杆(2)旋转搅拌锚固剂胶泥药卷、固化剂药卷充分搅拌形成锚固剂胶结体(15),套筒(12)通过圆柱形凸起(13)与圆形隔绝盘(10)联动;等待锚固剂固化后,在锚孔(23)孔外露的锚杆螺纹段(6)上依次套装托盘(4)和防滑丝螺母(3),通过预紧防滑丝螺母(3)沿螺纹升角提供预紧力;Start the agitator to drive the anchor rod (2) to rotate and stir the anchoring agent cement roll and curing agent roll to form an anchoring agent cement (15), and the sleeve (12) passes through the cylindrical protrusion (13) and the circular isolation plate (10) linkage; after waiting for the anchoring agent to solidify, set the tray (4) and the anti-slip wire nut (3) on the exposed anchor rod threaded section (6) of the anchor hole (23) in sequence, and pre-tighten the anti-slip wire nut (3) ) provides pre-tightening force along the thread lead angle; 当检测到被圆形隔绝盘(10)分割出来的区域III部分由于裂隙(5)过多或者处于岩层交错带,即判断需要对区域III部分注浆加固;将注浆钢管(21)推入锚杆中空段(7)中设有螺栓(19)的位置,由于螺栓(19)的阻挡,将限制注浆钢管(21)的进一步推送,在注浆钢管(21)外露尾端通过橡胶导管(22)与高压注浆泵连接,启动高压注浆泵,浆液通过注浆孔(17)注入锚孔(23)区域III部分,将对区域III部分围岩裂隙(5)进行修复加固;When it is detected that the area III part divided by the circular isolation disc (10) has too many cracks (5) or is in the interlaced zone of rock formations, it is judged that the area III part needs to be reinforced by grouting; the grouting steel pipe (21) is pushed into The position of the bolt (19) is set in the hollow section (7) of the anchor rod. Due to the obstruction of the bolt (19), the further pushing of the grouted steel pipe (21) will be restricted, and the exposed end of the grouted steel pipe (21) will pass through the rubber conduit (22) Connect with the high-pressure grouting pump, start the high-pressure grouting pump, and inject the grout into the III part of the anchor hole (23) area through the grouting hole (17), and repair and reinforce the surrounding rock fissure (5) of the area III part; 与上述同理,当需要对区域II部分注浆加固时,则拉动钢丝线(18)牵拉分段止浆塞(26)运动,由于锚杆中空段(7)中设有螺栓(19)的阻挡,分段止浆塞(26)将在螺栓(19)处停下,此时将注浆钢管(21)推入到锚杆螺纹段(6)注浆即可保证只修复加固区域II部分围岩裂隙(5)。In the same way as above, when it is necessary to grout reinforcement to the area II part, the steel wire (18) is pulled to pull the segmented grout stopper (26) to move, because the bolt (19) is provided in the hollow section (7) of the bolt block, the segmented grout stopper (26) will stop at the bolt (19), and at this time, push the grouted steel pipe (21) into the threaded section of the anchor rod (6) and inject grout to ensure that only the reinforcement area II will be repaired Part of the surrounding rock fissures (5). 9.根据权利要求8所述的使用方法,其特征在于:当围岩(1)发生大变形时,锚杆实心段(8)端部的高强度螺母(9)挤压套筒(12)内壁上的塑性齿(14),塑性齿(14)产生塑性变形,此时高强度螺母(9)滑移接触下一个断面的塑性齿(14),以此来实现该装置的恒阻大变形。9. The use method according to claim 8, characterized in that: when the surrounding rock (1) undergoes large deformation, the high-strength nut (9) at the end of the solid section (8) of the anchor rod squeezes the sleeve (12) The plastic tooth (14) on the inner wall produces plastic deformation. At this time, the high-strength nut (9) slides to contact the plastic tooth (14) of the next section, so as to realize the constant resistance and large deformation of the device .
CN202310755034.0A 2023-06-25 2023-06-25 A multi-hole yielding pressure bolt device capable of segmental grouting and its application method Pending CN116677436A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310755034.0A CN116677436A (en) 2023-06-25 2023-06-25 A multi-hole yielding pressure bolt device capable of segmental grouting and its application method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310755034.0A CN116677436A (en) 2023-06-25 2023-06-25 A multi-hole yielding pressure bolt device capable of segmental grouting and its application method

Publications (1)

Publication Number Publication Date
CN116677436A true CN116677436A (en) 2023-09-01

Family

ID=87790864

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310755034.0A Pending CN116677436A (en) 2023-06-25 2023-06-25 A multi-hole yielding pressure bolt device capable of segmental grouting and its application method

Country Status (1)

Country Link
CN (1) CN116677436A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116733515A (en) * 2023-06-30 2023-09-12 中国矿业大学 Self-adjusting shearing-resistant yielding anchor rod device and application method thereof
CN116988825A (en) * 2023-09-25 2023-11-03 中国矿业大学(北京) Resistance-increasing large-deformation grouting anchor rod and application method
CN118959059A (en) * 2024-09-29 2024-11-15 中国矿业大学 A self-advancing graded pressure-releasing anchor device and its use method
CN119244218A (en) * 2024-09-30 2025-01-03 中国矿业大学 A water-induced vibration measuring device for drilling cracks and a method of using the same
CN119933760A (en) * 2025-01-23 2025-05-06 鹤壁煤电股份有限公司 A shear-resistant variable resistance pressure-yielding measuring anchor rod and its use method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207004554U (en) * 2017-08-02 2018-02-13 中铁十四局集团第二工程有限公司 A kind of multistage allows pressure grouting anchor pole
CN109162743A (en) * 2018-09-26 2019-01-08 西南交通大学 A kind of quasi- constant resistance and large deformation anchor cable of friction-shearing combined type
US20200056479A1 (en) * 2017-09-12 2020-02-20 China University Of Mining And Technology Self-drilling differential grouting combined bolt and anchoring method therefor
CN111946375A (en) * 2020-07-27 2020-11-17 黄锋 Sectional type slip casting stock
CN113236251A (en) * 2021-06-09 2021-08-10 临沂矿业集团菏泽煤电有限公司 Deep well supporting-unloading-sealing-injecting multi-stage cooperative control method and device along empty crossheading
CN114542144A (en) * 2022-02-22 2022-05-27 中国矿业大学 Broken surrounding rock enlarged type end anchoring multi-stage yielding constant-resistance large-deformation anchor rod and method
US20230094882A1 (en) * 2021-09-24 2023-03-30 Wuhan Center, China Geological Survey (Central South China Innovation Center For Geosciences) Basalt fiber anchoring system with accurate sectioned grouting and mounting method thereof
WO2023061044A1 (en) * 2021-10-14 2023-04-20 中铁隧道集团二处有限公司 Expansion shell yielding anchor cable and construction method thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207004554U (en) * 2017-08-02 2018-02-13 中铁十四局集团第二工程有限公司 A kind of multistage allows pressure grouting anchor pole
US20200056479A1 (en) * 2017-09-12 2020-02-20 China University Of Mining And Technology Self-drilling differential grouting combined bolt and anchoring method therefor
CN109162743A (en) * 2018-09-26 2019-01-08 西南交通大学 A kind of quasi- constant resistance and large deformation anchor cable of friction-shearing combined type
CN111946375A (en) * 2020-07-27 2020-11-17 黄锋 Sectional type slip casting stock
CN113236251A (en) * 2021-06-09 2021-08-10 临沂矿业集团菏泽煤电有限公司 Deep well supporting-unloading-sealing-injecting multi-stage cooperative control method and device along empty crossheading
US20230094882A1 (en) * 2021-09-24 2023-03-30 Wuhan Center, China Geological Survey (Central South China Innovation Center For Geosciences) Basalt fiber anchoring system with accurate sectioned grouting and mounting method thereof
WO2023061044A1 (en) * 2021-10-14 2023-04-20 中铁隧道集团二处有限公司 Expansion shell yielding anchor cable and construction method thereof
CN114542144A (en) * 2022-02-22 2022-05-27 中国矿业大学 Broken surrounding rock enlarged type end anchoring multi-stage yielding constant-resistance large-deformation anchor rod and method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116733515A (en) * 2023-06-30 2023-09-12 中国矿业大学 Self-adjusting shearing-resistant yielding anchor rod device and application method thereof
CN116733515B (en) * 2023-06-30 2025-12-12 中国矿业大学 A self-adjusting anti-shear pressure anchor bolt device and its application method
CN116988825A (en) * 2023-09-25 2023-11-03 中国矿业大学(北京) Resistance-increasing large-deformation grouting anchor rod and application method
CN116988825B (en) * 2023-09-25 2023-12-05 中国矿业大学(北京) Grouting anchors with increased resistance and large deformation and application methods
CN118959059A (en) * 2024-09-29 2024-11-15 中国矿业大学 A self-advancing graded pressure-releasing anchor device and its use method
CN119244218A (en) * 2024-09-30 2025-01-03 中国矿业大学 A water-induced vibration measuring device for drilling cracks and a method of using the same
CN119933760A (en) * 2025-01-23 2025-05-06 鹤壁煤电股份有限公司 A shear-resistant variable resistance pressure-yielding measuring anchor rod and its use method

Similar Documents

Publication Publication Date Title
CN116677436A (en) A multi-hole yielding pressure bolt device capable of segmental grouting and its application method
CN102278130B (en) Process method for reinforcing and grouting of high-pressure water-rich solution cavity of tunnel
CN101251017B (en) Subsection retrusive slip-casting method for porthole slurry-stop jackrod
CN103410161B (en) Oblique control slip casting steel anchor tube framework and construction method thereof
CN105350519A (en) Advanced pre-grouting device suitable for shallow-buried tunnel construction in sand soil layer and construction process
CN110185484A (en) The combined anchor device and construction method that tunnel wall rock deformation quickly controls
CN103161484B (en) A kind of lotion fixed length anchoring support method
CN102051880B (en) Detachable anchor
CN206092038U (en) Slip casting anchor bar
WO2023142654A1 (en) Large-deformation and constant-resistance support grouting anchor cable
CN103557012B (en) A kind of roadway with large deformation wall rock grouting fastening carrying structure and construction method
CN113738423B (en) Coal mine tunnel ultrahigh-strength anti-bending shear anchor cable supporting device and supporting method
CN103089276A (en) Deep-shallow hole and high-low pressure coupling grouting technology
CN101994315B (en) Full-length bonded prestressed anchor rod and its construction method
CN116733515B (en) A self-adjusting anti-shear pressure anchor bolt device and its application method
CN204703159U (en) Prefabricated anchor head pressure anchor wire structure
CN109798140A (en) Km Deep Soft Rock fracture grouting support reinforcement method
CN203230443U (en) Novel case expanding reverse wedging type slip casting anchor rod
CN109026101A (en) A kind of mining anchor dispensing device and its application method
CN209838457U (en) Combined Bolt Device for Rapid Control of Tunnel Surrounding Rock Deformation
CN102748048A (en) Hole wall grouting anchor cable
CN116792132B (en) A recyclable spray-type segmented grouting pressure-relieving anchor bolt device and its application method
CN208136918U (en) A kind of tubular type Soil-Nailing Wall Structure
CN205858371U (en) A kind of colliery big cross section digging laneway combined support structure
CN108842792A (en) A kind of layering is interior to draw anchor pole and construction method with being lifted discharging type

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination