CN116485585A - Digital concrete management system - Google Patents

Digital concrete management system Download PDF

Info

Publication number
CN116485585A
CN116485585A CN202310454846.1A CN202310454846A CN116485585A CN 116485585 A CN116485585 A CN 116485585A CN 202310454846 A CN202310454846 A CN 202310454846A CN 116485585 A CN116485585 A CN 116485585A
Authority
CN
China
Prior art keywords
concrete
management
business
node
task
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310454846.1A
Other languages
Chinese (zh)
Inventor
叶有相
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Zhonghai Building Materials Co ltd
Original Assignee
Ningbo Zhonghai Building Materials Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Zhonghai Building Materials Co ltd filed Critical Ningbo Zhonghai Building Materials Co ltd
Priority to CN202310454846.1A priority Critical patent/CN116485585A/en
Publication of CN116485585A publication Critical patent/CN116485585A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/083Shipping
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The utility model relates to a concrete digital management system, which is characterized in that a professional business concrete management system is built based on an ERP management platform, each business concrete management node in the whole business concrete supply chain orderly executes respective management tasks through the business concrete management system, and the business concrete management tasks are classified and executed according to business attributes, so that the business concrete management nodes can be timely and effectively managed and timely communicated with each other in the business concrete management system of the same management dimension. The scheme can also enable a background manager to comprehensively manage task execution results of business concrete management nodes of each module under each business attribute, trace back each link of business concrete according to a task chain, thereby realizing specific business concrete management responsibility and enabling each management link/node on the whole business concrete supply chain to be orderly and circulated.

Description

Digital concrete management system
Technical Field
The disclosure relates to the technical field of digital management, in particular to a concrete digital management method, a concrete digital management system and electronic equipment.
Background
The concrete is prepared and transported through a concrete mixing station, and in the early, middle and later transportation processes of the concrete preparation, the concrete mixing station needs to effectively manage each link to acquire the state of each link, each department and responsible persons need to participate in time, and the departments and responsible persons cooperate with each other to execute the concrete tasks of each business.
In the process of managing each link of concrete in a concrete mixing plant, the general mode of the existing concrete mixing plant is basically the traditional mode: after receiving the commercial concrete demand of the first party, analyzing the commercial concrete demand information and giving out a corresponding commercial concrete proportioning list, and after confirming the two parties of the commercial concrete proportioning list, carrying out commercial concrete preparation and transportation according to the commercial concrete proportioning list. In each business concrete link, the participation main body of each link is basically an independent business concrete management node, after the last business concrete management node transmits business concrete data of the link to the next business concrete management node, the next business concrete management node is basically used for management, the last business concrete management node basically does not monitor the management process of the next business concrete management node, and the like, and in case of the superior business concrete management node, management connection is lacking.
After the business concrete management problem occurs, the investigation can only be started from the bottom business concrete nodes one by one, but because of the business property of the concrete, after the business concrete has a problem in a certain link, the link or the last link can be basically traced, and the whole business concrete supply chain cannot be traced, so that the problems of unclear responsibility and fuzzy management of the supply problem exist.
Although in reality, the social tools of the third party may be used for communication, the business concrete management nodes cannot communicate effectively and timely in the same management dimension in time, and unified and effective communication in the business concrete management dimension is lacking.
Disclosure of Invention
In order to solve the problems, the application provides a concrete digital management method, a concrete digital management system and electronic equipment.
In one aspect of the application, a concrete digital management method is provided, which comprises the following steps:
presetting a business concrete supply chain, and configuring corresponding node numbers for each business concrete management node of the business concrete supply chain;
based on an ERP management platform, constructing a corresponding concrete digital management system, and configuring the business concrete supply chain on the concrete digital management system;
establishing corresponding business concrete management tasks on the concrete digital management system according to the node numbers of all business concrete management nodes;
and issuing the business concrete management task to the corresponding business concrete management node, and waiting for the response of the corresponding business concrete management node.
As an optional embodiment of the present application, optionally, constructing a corresponding concrete digital management system based on an ERP management platform, and configuring the commercial concrete supply chain on the concrete digital management system includes:
constructing corresponding concrete digital management rules according to the commercial concrete supply chain and configuring the concrete digital management rules on an ERP management platform;
according to the concrete digital management rule, constructing concrete digital management modules with different service attributes in each business concrete management link on an ERP management platform;
and adding each business concrete management node in the business concrete supply chain into the corresponding concrete digital management module according to the business attribute.
As an optional embodiment of the present application, optionally, constructing a corresponding concrete digital management system based on an ERP management platform, and configuring the commercial concrete supply chain on the concrete digital management system, further includes:
constructing a background manager for carrying out background management on the business concrete supply chain on an ERP management platform;
the background manager is associated with each concrete digital management module, and the node numbers of the business concrete management nodes in the business concrete supply chain are sent to the background manager;
and storing the node numbers in the background manager to generate the concrete digital management system.
As an optional embodiment of the present application, optionally, according to the node number of each business concrete management node, establishing a corresponding business concrete management task on the concrete digital management system, including:
initiating a business concrete task creation request to the background manager;
the background manager receives the business concrete task creation request and acquires node numbers of business concrete management nodes which need to execute business concrete management tasks in the business concrete task creation request;
and creating a corresponding business concrete management flow according to the business concrete task creation request, adding the node number of each business concrete management node into each business concrete management link in the business concrete management flow, and generating a current business concrete management task.
As an optional embodiment of the present application, optionally, according to the node number of each business concrete management node, a corresponding business concrete management task is established on the concrete digital management system, and further includes:
acquiring a business concrete management flow of the current business concrete management task;
and the background manager issues and circulates the business concrete management tasks among the corresponding concrete digital management modules according to the business concrete management flow of the current business concrete management tasks.
As an optional embodiment of the present application, optionally, issuing the business concrete management task to a corresponding business concrete management node, waiting for a response from the corresponding business concrete management node includes:
the current concrete digital management module receives the business concrete management task issued by the background manager;
analyzing the business concrete management task to obtain a task execution node and a task execution list in the business concrete management task;
in the current concrete digital management module, identifying node numbers of all the business concrete management nodes, and finding out node numbers matched with the task execution nodes;
and issuing the task execution list to the business concrete management node serving as a target node corresponding to the node number.
As an optional embodiment of the present application, optionally, issuing the business concrete management task to a corresponding business concrete management node, waiting for a response from the corresponding business concrete management node, further includes:
the business concrete management node serving as a target node receives the task execution list issued by the concrete digital management module at present and starts to respond to the business concrete task of the current link;
after the business concrete task of the current link is executed, reporting an execution result to the current concrete digital management module by the business concrete management node serving as a target node;
and the current concrete digital management module receives and records the execution result, and reports the execution result and the node number of the corresponding business concrete management node to the background manager.
As an optional embodiment of the present application, optionally, after the response of the merchant concrete management node, the method further includes:
the background manager receives all execution results reported by the concrete digital management modules;
checking all execution results reported by each concrete digital management module through the background manager, and judging whether the execution results with errors exist in all the execution results or not:
if so, finding out the execution result with errors and the node number of the corresponding business concrete management node, and notifying;
if not, recording and storing the execution result.
In another aspect of the present application, a concrete digital management system is provided, configured to implement the concrete digital management method, including:
the function management unit is configured with a plurality of concrete digital management modules with different service attributes;
the business concrete task management unit is used for creating and issuing business concrete management tasks to the function management unit by the background manager and auditing the execution results reported by the response;
the scheduling unit is used for scheduling the corresponding concrete digital management module in the function management unit according to the business concrete management flow of the current business concrete management task, and executing the business concrete management task in a circulating way;
and the application terminal is used for receiving and responding to the task execution list and reporting the execution result.
In another aspect of the present application, an electronic device is also provided, including:
a processor;
a memory for storing processor-executable instructions;
wherein the processor is configured to implement the concrete digital management method when executing the executable instructions.
The invention has the technical effects that:
according to the method, a corresponding concrete digital management system is built based on an ERP management platform, and a business concrete supply chain is configured on the concrete digital management system; establishing corresponding business concrete management tasks on the concrete digital management system according to the node numbers of all business concrete management nodes; and issuing the business concrete management task to the corresponding business concrete management node, and waiting for the response of the corresponding business concrete management node. The method realizes the construction of a professional business concrete management system based on the ERP management platform, each business concrete management node in the whole business concrete supply chain orderly executes respective management tasks through the business concrete management system, and the business concrete management tasks are classified and executed according to business attributes, so that the business concrete management systems of the same management dimension can be used for effective and timely task management and timely communication among the business concrete management nodes. The scheme can also enable a background manager to comprehensively manage task execution results of business concrete management nodes of each module under each business attribute, trace back each link of business concrete according to a task chain, thereby realizing specific business concrete management responsibility and enabling each management link/node on the whole business concrete supply chain to be orderly and circulated.
Other features and aspects of the present disclosure will become apparent from the following detailed description of exemplary embodiments, which proceeds with reference to the accompanying drawings.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate exemplary embodiments, features and aspects of the present disclosure and together with the description, serve to explain the principles of the disclosure.
FIG. 1 is a schematic diagram showing the implementation flow of the concrete digital management method of the invention;
FIG. 2 is a schematic diagram illustrating the design of a concrete digital management module on an ERP management platform according to the present invention;
FIG. 3 is a schematic diagram showing the application composition of the concrete digital management system constructed on the ERP management platform according to the present invention;
FIG. 4 is a flow chart illustrating the process of the concrete digital management module of the present invention after receiving a corresponding business concrete management task;
fig. 5 shows a schematic application diagram of the electronic device of the present invention.
Detailed Description
Various exemplary embodiments, features and aspects of the disclosure will be described in detail below with reference to the drawings. In the drawings, like reference numbers indicate identical or functionally similar elements. Although various aspects of the embodiments are illustrated in the accompanying drawings, the drawings are not necessarily drawn to scale unless specifically indicated.
The word "exemplary" is used herein to mean "serving as an example, embodiment, or illustration. Any embodiment described herein as "exemplary" is not necessarily to be construed as preferred or advantageous over other embodiments.
In addition, numerous specific details are set forth in the following detailed description in order to provide a better understanding of the present disclosure. It will be understood by those skilled in the art that the present disclosure may be practiced without some of these specific details. In some instances, well known means, elements, and circuits have not been described in detail so as not to obscure the present disclosure.
Example 1
As shown in fig. 1, in one aspect of the present application, a concrete digitalized management method is provided, including the following steps:
s1, presetting a business concrete supply chain, and configuring corresponding node numbers for each business concrete management node of the business concrete supply chain;
s2, constructing a corresponding concrete digital management system based on an ERP management platform, and configuring the business concrete supply chain on the concrete digital management system;
s3, establishing corresponding business concrete management tasks on the concrete digital management system according to the node numbers of the business concrete management nodes;
s4, the business concrete management task is issued to the corresponding business concrete management node, and the corresponding business concrete management node waits for response.
The ERP management platform, namely open ERP management software, can enable a user to execute and comprehensively manage each management task on the ERP management platform, and realizes the full-chain management of enterprise generation and supply.
In this embodiment, the specific selection of the ERP management software is performed by a commercial concrete provider or an ERP server according to the commercial concrete supply chain of a certain commercial concrete enterprise (concrete mixing plant), so that a professional commercial concrete management system, that is, a concrete digital management system, is created based on the ERP management platform.
According to the concrete digital management system constructed based on the ERP management platform, each business concrete management node in the whole business concrete supply chain orderly executes respective management tasks through the business concrete management system, and the business concrete management tasks are classified and executed according to business attributes, so that the business concrete management systems in the same management dimension can be used for effectively and timely managing tasks and communicating in time. The scheme can also enable a background manager to comprehensively manage task execution results of business concrete management nodes of each module under each business attribute, trace back each link of business concrete according to a task chain, thereby realizing specific business concrete management responsibility and enabling each management link/node on the whole business concrete supply chain to be orderly and circulated.
The background manager can create a corresponding business concrete management task on the concrete digital management system, issue the business concrete management task to each business concrete management node on a corresponding business concrete supply chain according to the business attribute, and simultaneously obtain a response execution result of the basic business concrete management node in the process of executing the business concrete management task, and finally check the execution result by the background manager to screen error nodes so as to realize the traceability and responsibility checking of task execution.
The respective steps will be specifically described below.
S1, presetting a business concrete supply chain, and configuring corresponding node numbers for each business concrete management node of the business concrete supply chain;
the flow chart of concrete supply by a business concrete supply chain, i.e. a business concrete enterprise, can be provided by a business concrete enterprise. Each business concrete management node in the business concrete supply chain, namely the execution main body of the concrete in the current link, such as a certain primary mixing station, a transport station and the like, is provided with an application terminal for interacting with a concrete digital management system of a business concrete enterprise, such as receiving business concrete management tasks issued by the enterprise background, reporting task execution results and the like. The application terminal may be a PC or the like.
If a certain business concrete management node needs to execute a plurality of continuous tasks, the configured application terminal can be utilized for multitask receiving and responding; if different types of business concrete tasks need to be executed, application terminals with different attributes can be configured, and communication with a concrete digital management system is established.
The node numbers are configured for the concrete management nodes of each business, such as a second transport station No. twenty-five-000250, so that the subsequent background can manage each execution body comprehensively through the node numbers, and the problems of management confusion and the like of names, management attributes and the like of the concrete management nodes of each business are avoided. When the concrete business concrete management task is executed later, the task is issued according to the node number.
As an optional embodiment of the present application, optionally, constructing a corresponding concrete digital management system based on an ERP management platform, and configuring the commercial concrete supply chain on the concrete digital management system includes:
constructing corresponding concrete digital management rules according to the commercial concrete supply chain and configuring the concrete digital management rules on an ERP management platform;
according to the concrete digital management rule, constructing concrete digital management modules with different service attributes in each business concrete management link on an ERP management platform;
and adding each business concrete management node in the business concrete supply chain into the corresponding concrete digital management module according to the business attribute.
Each business concrete enterprise is provided with a concrete digitalized management rule according to a business concrete supply chain, the concrete digitalized management rule can be known from a concrete supply flow chart provided by each business concrete enterprise, the concrete digitalized management rule is configured on an ERP management platform and is waited to be utilized on the ERP management platform, and a concrete digitalized management system matched with the concrete supply flow chart is established.
As shown in fig. 2, the business concrete enterprise may register on the ERP management platform, and upload the concrete supply flow chart to the service provider management system of the ERP management platform, and a background person of the ERP management platform may obtain information of the business concrete enterprise and the concrete supply flow chart from the service provider management system. And constructing concrete digital management modules with different service attributes on each business concrete management link on an ERP management platform by carrying out functional analysis, classification and the like on the concrete supply flow chart.
Background personnel of the ERP management platform construct concrete digital management modules with different service attributes on each business concrete management link on the digital design platform according to the analyzed and classified business concrete management services. For example, the digital concrete management module for "commercial concrete transportation" is mainly used for managing each commercial concrete management node of "commercial concrete transportation", and the commercial concrete management task related to "commercial concrete transportation" is implemented by the digital concrete management module for "commercial concrete transportation" and the corresponding node, so long as the digital concrete management module is the node for "commercial concrete transportation", the digital concrete management module for "commercial concrete transportation" is under the management of the digital concrete management module for "commercial concrete transportation".
As an optional embodiment of the present application, optionally, constructing a corresponding concrete digital management system based on an ERP management platform, and configuring the commercial concrete supply chain on the concrete digital management system, further includes:
constructing a background manager for carrying out background management on the business concrete supply chain on an ERP management platform;
the background manager is associated with each concrete digital management module, and the node numbers of the business concrete management nodes in the business concrete supply chain are sent to the background manager;
and storing the node numbers in the background manager to generate the concrete digital management system.
In order to uniformly manage each concrete digital management module, a business concrete enterprise needs to have a background manager to comprehensively manage the concrete digital management modules with each business attribute. The background manager is a comprehensive business processing terminal, after the design is finished, the program package can be compressed and sent to a background server of a business concrete enterprise, and the business concrete enterprise logs in the background manager (background management software) on the background server to uniformly manage each concrete digital management module. As to how to uniformly deploy the concrete digital management system on the background of the concrete enterprise in the following, the embodiment is not limited. The business concrete enterprises can further realize unified management of each business concrete management node in the supply chain by means of the ERP management platform, and the business concrete enterprises specifically need to combine with server lease rules of the ERP management platform to carry out butt joint management.
In this embodiment, unified management of each business concrete management node in the self-supply chain is preferably implemented by means of an ERP management platform.
As shown in fig. 3, the concrete digital management system is constructed on the ERP management platform. The concrete digital management system mainly comprises:
the function management unit is configured with a plurality of concrete digital management modules with different service attributes;
the business concrete task management unit is used for creating and issuing business concrete management tasks to the function management unit by the background manager and auditing the execution results reported by the response;
and the scheduling unit is used for scheduling the corresponding concrete digital management module in the function management unit according to the business concrete management flow of the current business concrete management task, and executing the business concrete management task in a circulating way.
And each concrete digital management module with different service attributes is uniformly deployed in the function management unit, and a specific module is scheduled to execute a corresponding task under the scheduling of the scheduling unit. When a concrete digital management module executes tasks, the corresponding business concrete management nodes are scheduled to execute and issue the tasks.
In the process of executing the business concrete tasks, the generated task execution logs and the like can be stored in a database which is not distributed by the business concrete enterprises of the ERP management platform.
As an optional embodiment of the present application, optionally, according to the node number of each business concrete management node, establishing a corresponding business concrete management task on the concrete digital management system, including:
initiating a business concrete task creation request to the background manager;
the background manager receives the business concrete task creation request and acquires node numbers of business concrete management nodes which need to execute business concrete management tasks in the business concrete task creation request;
and creating a corresponding business concrete management flow according to the business concrete task creation request, adding the node number of each business concrete management node into each business concrete management link in the business concrete management flow, and generating a current business concrete management task.
The business concrete enterprises can send business concrete task creation requests to business concrete task management units in the concrete digital management system through a background server or authorized business concrete management nodes; after receiving the business concrete task creation request, a background manager in the business concrete task management unit creates a corresponding business concrete management flow according to the business concrete requirement in the request and the node number corresponding to the needed business concrete management node, wherein each implementation subject and implementation flow of the business concrete are determined, and the background can respond and manage each business concrete management node through the node number of each business concrete management node.
As an optional embodiment of the present application, optionally, according to the node number of each business concrete management node, a corresponding business concrete management task is established on the concrete digital management system, and further includes:
acquiring a business concrete management flow of the current business concrete management task;
and the background manager issues and circulates the business concrete management tasks among the corresponding concrete digital management modules according to the business concrete management flow of the current business concrete management tasks.
After the business concrete management task is established, a background manager is required to issue to the corresponding concrete digital management module according to the business concrete management flow of the business concrete management task, and issue to the corresponding execution main body according to the front-back sequence of the business concrete management flow. At this time, the corresponding execution body "concrete digitalized management module" in the scheduling function management unit needs to be scheduled by the scheduling unit, and the current business concrete management task (parent task) is executed in circulation.
As an optional embodiment of the present application, optionally, issuing the business concrete management task to a corresponding business concrete management node, waiting for a response from the corresponding business concrete management node includes:
the current concrete digital management module receives the business concrete management task issued by the background manager;
analyzing the business concrete management task to obtain a task execution node and a task execution list in the business concrete management task;
in the current concrete digital management module, identifying node numbers of all the business concrete management nodes, and finding out node numbers matched with the task execution nodes;
and issuing the task execution list to the business concrete management node serving as a target node corresponding to the node number.
After each concrete digitalized management module receives the corresponding business concrete management tasks, each business concrete management node under self management is determined, and each concrete task (sub-level task) received by the module is executed according to the flow.
As shown in fig. 4, a process flow diagram is shown after each concrete digitalized management module receives a corresponding business concrete management task.
The method comprises the steps of receiving a current concrete digital management module of a task, firstly analyzing the business concrete management task, and obtaining a task execution node and a task execution list in the business concrete management task. And the current concrete digital management module is used for obtaining a task execution list to be executed by the current concrete digital management module and corresponding task execution nodes, wherein the task execution nodes are all business concrete management nodes under the management of the current concrete digital management module, and the corresponding business concrete management nodes can be allocated after task analysis, so that the task execution list is executed specifically.
Therefore, the current concrete digitalized management module needs to identify and find the node number matched with the task execution node in all the business concrete management nodes under the management of the current concrete digitalized management module, so as to determine the execution main body, namely the target node, for actually executing the task execution list. And issuing the task execution list to the target node, and enabling the target node to execute the corresponding task on the task execution list. The scheduling unit may be used for task scheduling.
As an optional embodiment of the present application, optionally, issuing the business concrete management task to a corresponding business concrete management node, waiting for a response from the corresponding business concrete management node, further includes:
the business concrete management node serving as a target node receives the task execution list issued by the concrete digital management module at present and starts to respond to the business concrete task of the current link;
after the business concrete task of the current link is executed, reporting an execution result to the current concrete digital management module by the business concrete management node serving as a target node;
and the current concrete digital management module receives and records the execution result, and reports the execution result and the node number of the corresponding business concrete management node to the background manager.
The task is issued to the application terminal of the target node, which starts to execute specific sub-level tasks, such as "business concrete transportation". After the execution of the task of 'business concrete transportation', the target node reports the transportation destination and other waybill information to the system through the application terminal, and the upper management module of the target node receives the execution results. The upper management module of the target node records and saves the execution result of the target node, and meanwhile, the execution result of the target node and the node number of the corresponding target node are reported to the background manager, so that the background manager records and saves all the execution results and the corresponding numbers of the execution main body, and the tracing and checking of the basic task execution are facilitated. When an execution error occurs in a certain execution node, the execution main body of the task of the upper and lower stages and the corresponding task execution result can be traced through the business concrete task flow.
As an optional embodiment of the present application, optionally, after the response of the merchant concrete management node, the method further includes:
the background manager receives all execution results reported by the concrete digital management modules;
checking all execution results reported by each concrete digital management module through the background manager, and judging whether the execution results with errors exist in all the execution results or not:
if so, finding out the execution result with errors and the node number of the corresponding business concrete management node, and notifying;
if not, recording and storing the execution result.
And a background manager, such as a project general engineer, checks all the reported execution results and judges whether the execution results with errors exist in all the execution results. The project master engineering engineer checks and judges, if the project master engineering engineer has errors, the project master engineering engineer can check and trace through the execution node of the execution result, and make correction notification to the management module and the execution main body on the task execution chain. A task execution chain is error free, a record may be saved.
It should be apparent to those skilled in the art that implementing all or part of the above-described embodiments may be accomplished by computer programs to instruct related hardware, and the programs may be stored in a computer readable storage medium, which when executed may include the processes of the embodiments of the controls described above. It will be appreciated by those skilled in the art that implementing all or part of the above-described embodiments may be accomplished by computer programs to instruct related hardware, and the programs may be stored in a computer readable storage medium, which when executed may include the processes of the embodiments of the controls described above. The storage medium may be a magnetic disk, an optical disc, a Read-only memory (ROM), a random access memory (RandomAccessMemory, RAM), a flash memory (flash memory), a hard disk (HDD), or a Solid State Drive (SSD); the storage medium may also comprise a combination of memories of the kind described above.
Example 2
Based on the implementation principle of embodiment 1, in another aspect of the present application, a concrete digital management system is provided, for implementing the concrete digital management method, including:
the function management unit is configured with a plurality of concrete digital management modules with different service attributes;
the business concrete task management unit is used for creating and issuing business concrete management tasks to the function management unit by the background manager and auditing the execution results reported by the response;
the scheduling unit is used for scheduling the corresponding concrete digital management module in the function management unit according to the business concrete management flow of the current business concrete management task, and executing the business concrete management task in a circulating way;
and the application terminal is used for receiving and responding to the task execution list and reporting the execution result.
The functions and interactions of the respective application bodies described above are specifically referred to the description of embodiment 1.
The modules or steps of the invention described above may be implemented in a general-purpose computing device, they may be centralized in a single computing device, or distributed across a network of computing devices, or they may alternatively be implemented in program code executable by a computing device, such that they may be stored in a memory device and executed by a computing device, or they may be separately fabricated into individual integrated circuit modules, or multiple modules or steps within them may be fabricated into a single integrated circuit module. Thus, the present invention is not limited to any specific combination of hardware and software.
Example 3
Still further, another aspect of the present application further provides an electronic device of a concrete digital management system, including:
a processor;
a memory for storing processor-executable instructions;
wherein the processor is configured to implement the concrete digital management system when executing the executable instructions.
Embodiments of the present disclosure provide for an electronic device that includes a processor and a memory for storing processor-executable instructions. Wherein the processor is configured to implement any of the foregoing concrete digital management systems when executing the executable instructions.
Here, it should be noted that the number of processors may be one or more. Meanwhile, in the electronic device of the embodiment of the disclosure, an input device and an output device may be further included. The processor, the memory, the input device, and the output device may be connected by a bus, or may be connected by other means, which is not specifically limited herein.
The memory is a computer-readable storage medium that can be used to store software programs, computer-executable programs, and various modules, such as: the concrete digital management system of the embodiment of the disclosure corresponds to a program or a module. The processor executes various functional applications and data processing of the electronic device by running software programs or modules stored in the memory.
The input device may be used to receive an input number or signal. Wherein the signal may be a key signal generated in connection with user settings of the device/terminal/server and function control. The output means may comprise a display device such as a display screen.
The foregoing description of the embodiments of the present disclosure has been presented for purposes of illustration and description, and is not intended to be exhaustive or limited to the embodiments disclosed. Many modifications and variations will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the various embodiments described. The terminology used herein was chosen in order to best explain the principles of the embodiments, the practical application, or the technical improvement of the technology in the marketplace, or to enable others of ordinary skill in the art to understand the embodiments disclosed herein.

Claims (10)

1. The concrete digital management method is characterized by comprising the following steps of:
presetting a business concrete supply chain, and configuring corresponding node numbers for each business concrete management node of the business concrete supply chain;
based on an ERP management platform, constructing a corresponding concrete digital management system, and configuring the business concrete supply chain on the concrete digital management system;
establishing corresponding business concrete management tasks on the concrete digital management system according to the node numbers of all business concrete management nodes;
and issuing the business concrete management task to the corresponding business concrete management node, and waiting for the response of the corresponding business concrete management node.
2. The concrete digital management method according to claim 1, wherein constructing a corresponding concrete digital management system based on an ERP management platform and configuring the commercial concrete supply chain on the concrete digital management system comprises:
constructing corresponding concrete digital management rules according to the commercial concrete supply chain and configuring the concrete digital management rules on an ERP management platform;
according to the concrete digital management rule, constructing concrete digital management modules with different service attributes in each business concrete management link on an ERP management platform;
and adding each business concrete management node in the business concrete supply chain into the corresponding concrete digital management module according to the business attribute.
3. The concrete digital management method according to claim 2, wherein a corresponding concrete digital management system is constructed based on an ERP management platform, and the commercial concrete supply chain is configured on the concrete digital management system, further comprising:
constructing a background manager for carrying out background management on the business concrete supply chain on an ERP management platform;
the background manager is associated with each concrete digital management module, and the node numbers of the business concrete management nodes in the business concrete supply chain are sent to the background manager;
and storing the node numbers in the background manager to generate the concrete digital management system.
4. A concrete digitization management method according to claim 3, wherein establishing a corresponding business concrete management task on the concrete digitization management system according to the node number of each business concrete management node comprises:
initiating a business concrete task creation request to the background manager;
the background manager receives the business concrete task creation request and acquires node numbers of business concrete management nodes which need to execute business concrete management tasks in the business concrete task creation request;
and creating a corresponding business concrete management flow according to the business concrete task creation request, adding the node number of each business concrete management node into each business concrete management link in the business concrete management flow, and generating a current business concrete management task.
5. The method for digitally managing concrete according to claim 4, wherein corresponding business concrete management tasks are established on the concrete digital management system according to node numbers of the business concrete management nodes, further comprising:
acquiring a business concrete management flow of the current business concrete management task;
and the background manager issues and circulates the business concrete management tasks among the corresponding concrete digital management modules according to the business concrete management flow of the current business concrete management tasks.
6. The method of claim 5, wherein issuing the business concrete management task to a corresponding business concrete management node awaiting a response from the corresponding business concrete management node, comprises:
the current concrete digital management module receives the business concrete management task issued by the background manager;
analyzing the business concrete management task to obtain a task execution node and a task execution list in the business concrete management task;
in the current concrete digital management module, identifying node numbers of all the business concrete management nodes, and finding out node numbers matched with the task execution nodes;
and issuing the task execution list to the business concrete management node serving as a target node corresponding to the node number.
7. The method of digitized concrete management of claim 6 wherein issuing the business concrete management task to a corresponding business concrete management node awaiting a response from the corresponding business concrete management node further comprises:
the business concrete management node serving as a target node receives the task execution list issued by the concrete digital management module at present and starts to respond to the business concrete task of the current link;
after the business concrete task of the current link is executed, reporting an execution result to the current concrete digital management module by the business concrete management node serving as a target node;
and the current concrete digital management module receives and records the execution result, and reports the execution result and the node number of the corresponding business concrete management node to the background manager.
8. The method of digitized concrete management of claim 7 further comprising, after said business concrete management node responds:
the background manager receives all execution results reported by the concrete digital management modules;
checking all execution results reported by each concrete digital management module through the background manager, and judging whether the execution results with errors exist in all the execution results or not:
if so, finding out the execution result with errors and the node number of the corresponding business concrete management node, and notifying;
if not, recording and storing the execution result.
9. A concrete digitalized management system for implementing the digitalized management method of any one of claims 1-8, characterized by comprising:
the function management unit is configured with a plurality of concrete digital management modules with different service attributes;
the business concrete task management unit is used for creating and issuing business concrete management tasks to the function management unit by the background manager and auditing the execution results reported by the response;
the scheduling unit is used for scheduling the corresponding concrete digital management module in the function management unit according to the business concrete management flow of the current business concrete management task, and executing the business concrete management task in a circulating way;
and the application terminal is used for receiving and responding to the task execution list and reporting the execution result.
10. An electronic device, comprising:
a processor;
a memory for storing processor-executable instructions;
wherein the processor is configured to implement the concrete digitization management method of any one of claims 1-8 when executing the executable instructions.
CN202310454846.1A 2023-04-23 2023-04-23 Digital concrete management system Pending CN116485585A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310454846.1A CN116485585A (en) 2023-04-23 2023-04-23 Digital concrete management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310454846.1A CN116485585A (en) 2023-04-23 2023-04-23 Digital concrete management system

Publications (1)

Publication Number Publication Date
CN116485585A true CN116485585A (en) 2023-07-25

Family

ID=87215206

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310454846.1A Pending CN116485585A (en) 2023-04-23 2023-04-23 Digital concrete management system

Country Status (1)

Country Link
CN (1) CN116485585A (en)

Citations (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000049490A (en) * 2000-03-30 2000-08-05 이영종 Method for offer information about housing in the electronic-commerce
DE102006019627A1 (en) * 2006-04-25 2007-10-31 Sieber Forming Solutions Gmbh Customized production system of products from metal e.g. shaping tools, has concrete offer provided for transmission to external computer on basis of final definition or image representation of product
US20110029339A1 (en) * 2009-07-31 2011-02-03 Ciright Systems, Inc Enterprise and Sales Management Platform
CN102571815A (en) * 2012-02-13 2012-07-11 浪潮集团山东通用软件有限公司 Method of integrated ERP (Enterprise Resource Planning) user authentication for e-procurement private cloud
KR20120080795A (en) * 2011-01-10 2012-07-18 한국도로공사 Integrated information system for improving field construction process of concrete
CN105205592A (en) * 2015-09-06 2015-12-30 北京瑞宏科技有限公司 Electronic invoice posting and reimbursing realization system based on cloud platform and method thereof
CN105260842A (en) * 2015-10-12 2016-01-20 用友网络科技股份有限公司 Communication method and communication system between heterogeneous ERP systems
CN105654251A (en) * 2016-02-19 2016-06-08 浪潮通用软件有限公司 Business flow realization method in field of ERP
CN106408367A (en) * 2016-08-25 2017-02-15 北京三快在线科技有限公司 Order information obtaining method and device
CN108459567A (en) * 2018-02-11 2018-08-28 成都兴联宜科技有限公司 A kind of ERP system of concrete mixing plant
CN108748694A (en) * 2018-06-22 2018-11-06 成都精准混凝土有限公司 A kind of concrete mixing plant system and its operation method
CN108958188A (en) * 2018-07-03 2018-12-07 中联重科股份有限公司 A kind of transmission of concrete information and management equipment, system, method
CN109325824A (en) * 2018-08-28 2019-02-12 广州市惠邦信息科技有限公司 Quotient's concrete intelligence production method and system
CN109784436A (en) * 2018-12-20 2019-05-21 上海建工集团股份有限公司 A kind of intelligent concrete management-control method and system
CN110216789A (en) * 2019-07-15 2019-09-10 广州瀚阳工程咨询有限公司 A kind of intelligent control system of bridge subsection precasting yard
CN209401047U (en) * 2018-12-20 2019-09-17 上海建工集团股份有限公司 A kind of intelligent concrete managing and control system
CN110284503A (en) * 2019-06-13 2019-09-27 水电水利规划设计总院 A kind of construction control method of the pre- anti-cold seam of casting of concrete in mass
CN210627271U (en) * 2019-11-16 2020-05-26 浙江省水利水电工程质量与安全监督管理中心 Concrete test block tracing device
CN112099803A (en) * 2020-07-30 2020-12-18 山东浪潮通软信息科技有限公司 Incremental deployment method and system of ERP system
CN112184185A (en) * 2020-10-27 2021-01-05 陈双红 ERP system of commercial concrete mixing plant
CN112801628A (en) * 2021-02-05 2021-05-14 西安高科新达混凝土有限责任公司 Concrete production management system
CN113114451A (en) * 2021-03-04 2021-07-13 西安交通大学 Data statistical analysis method and system for enterprise cloud ERP system based on homomorphic encryption
CN113139733A (en) * 2021-04-30 2021-07-20 广州粤建三和软件股份有限公司 Concrete quality tracing system
WO2021143651A1 (en) * 2020-01-17 2021-07-22 深圳前海点金保理有限公司 Blockchain technology-based supply chain finance platform system
CN114897450A (en) * 2022-07-13 2022-08-12 浙江筑梦侠科技有限公司 Cloud digital supply chain service management platform

Patent Citations (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000049490A (en) * 2000-03-30 2000-08-05 이영종 Method for offer information about housing in the electronic-commerce
DE102006019627A1 (en) * 2006-04-25 2007-10-31 Sieber Forming Solutions Gmbh Customized production system of products from metal e.g. shaping tools, has concrete offer provided for transmission to external computer on basis of final definition or image representation of product
US20110029339A1 (en) * 2009-07-31 2011-02-03 Ciright Systems, Inc Enterprise and Sales Management Platform
KR20120080795A (en) * 2011-01-10 2012-07-18 한국도로공사 Integrated information system for improving field construction process of concrete
CN102571815A (en) * 2012-02-13 2012-07-11 浪潮集团山东通用软件有限公司 Method of integrated ERP (Enterprise Resource Planning) user authentication for e-procurement private cloud
CN105205592A (en) * 2015-09-06 2015-12-30 北京瑞宏科技有限公司 Electronic invoice posting and reimbursing realization system based on cloud platform and method thereof
CN105260842A (en) * 2015-10-12 2016-01-20 用友网络科技股份有限公司 Communication method and communication system between heterogeneous ERP systems
CN105654251A (en) * 2016-02-19 2016-06-08 浪潮通用软件有限公司 Business flow realization method in field of ERP
CN106408367A (en) * 2016-08-25 2017-02-15 北京三快在线科技有限公司 Order information obtaining method and device
CN108459567A (en) * 2018-02-11 2018-08-28 成都兴联宜科技有限公司 A kind of ERP system of concrete mixing plant
CN108748694A (en) * 2018-06-22 2018-11-06 成都精准混凝土有限公司 A kind of concrete mixing plant system and its operation method
CN108958188A (en) * 2018-07-03 2018-12-07 中联重科股份有限公司 A kind of transmission of concrete information and management equipment, system, method
CN109325824A (en) * 2018-08-28 2019-02-12 广州市惠邦信息科技有限公司 Quotient's concrete intelligence production method and system
CN109784436A (en) * 2018-12-20 2019-05-21 上海建工集团股份有限公司 A kind of intelligent concrete management-control method and system
CN209401047U (en) * 2018-12-20 2019-09-17 上海建工集团股份有限公司 A kind of intelligent concrete managing and control system
CN110284503A (en) * 2019-06-13 2019-09-27 水电水利规划设计总院 A kind of construction control method of the pre- anti-cold seam of casting of concrete in mass
CN110216789A (en) * 2019-07-15 2019-09-10 广州瀚阳工程咨询有限公司 A kind of intelligent control system of bridge subsection precasting yard
CN210627271U (en) * 2019-11-16 2020-05-26 浙江省水利水电工程质量与安全监督管理中心 Concrete test block tracing device
WO2021143651A1 (en) * 2020-01-17 2021-07-22 深圳前海点金保理有限公司 Blockchain technology-based supply chain finance platform system
CN112099803A (en) * 2020-07-30 2020-12-18 山东浪潮通软信息科技有限公司 Incremental deployment method and system of ERP system
CN112184185A (en) * 2020-10-27 2021-01-05 陈双红 ERP system of commercial concrete mixing plant
CN112801628A (en) * 2021-02-05 2021-05-14 西安高科新达混凝土有限责任公司 Concrete production management system
CN113114451A (en) * 2021-03-04 2021-07-13 西安交通大学 Data statistical analysis method and system for enterprise cloud ERP system based on homomorphic encryption
CN113139733A (en) * 2021-04-30 2021-07-20 广州粤建三和软件股份有限公司 Concrete quality tracing system
CN114897450A (en) * 2022-07-13 2022-08-12 浙江筑梦侠科技有限公司 Cloud digital supply chain service management platform

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李海红;姚明海;朱肖肖;蒋勇;: "基于三层架构的预拌混凝土现代集成控制系统的研究", 混凝土, no. 07, 15 July 2007 (2007-07-15), pages 110 - 112 *

Similar Documents

Publication Publication Date Title
CN109118347B (en) Automatic cooperation method and system
CN108984418A (en) Software testing management method, device, electronic equipment and storage medium
CN109636320A (en) Workflow examination and approval method and terminal device
US7827273B2 (en) Machine cluster topology representation for automated testing
US20030101085A1 (en) Method and system for vendor communication
CN106600226B (en) Method and device for optimizing process management system
US9542161B2 (en) Method and system for generating a source code for a computer program for execution and simulation of a process
CN115857884A (en) Business flow chart generation method and device
CN110490559A (en) A kind of mobile law enforcement inspection method, device, system and server
CN111459631A (en) Automatic batch processing method and system for server
CN116185383A (en) Draggable self-configuration workflow generation method and system
CN114721824A (en) Resource allocation method, medium and electronic device
CN113658351A (en) Product production method and device, electronic equipment and storage medium
TWI804694B (en) Method, mobile terminal, and storage medium for checking fixed asset
CN112232758A (en) Engineering change timeliness management method and system based on product life cycle management
Ebrahimifard et al. Mapping BPMN 2.0 choreography to WS-CDL: a systematic method
CN116485585A (en) Digital concrete management system
CN108921499A (en) A kind of exhibition room finishing workflow method and its system
KR100976420B1 (en) Software configuration management system and method therefore
CN115617480A (en) Task scheduling method, device and system and storage medium
CN111145004B (en) Intelligent financial auditing platform based on editable workflow
JP6559214B2 (en) Schedule management system and schedule management program
CN109697599B (en) System and method for driving flow
KR20210026946A (en) Method for processing of cargo receipt based on blockchain and transport management server
CN113886043B (en) Simulation task scheduling system for comprehensively deploying public cloud and private cloud

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination