CN116397644A - Double-hook marine crane piling ship and construction method - Google Patents

Double-hook marine crane piling ship and construction method Download PDF

Info

Publication number
CN116397644A
CN116397644A CN202310506752.4A CN202310506752A CN116397644A CN 116397644 A CN116397644 A CN 116397644A CN 202310506752 A CN202310506752 A CN 202310506752A CN 116397644 A CN116397644 A CN 116397644A
Authority
CN
China
Prior art keywords
pile
double
hook
precast
ship
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310506752.4A
Other languages
Chinese (zh)
Inventor
宋政昌
张振
崔进
寇盼
吴世琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Xian Port Navigation Shipbuilding Technology Co Ltd
Original Assignee
PowerChina Xian Port Navigation Shipbuilding Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Xian Port Navigation Shipbuilding Technology Co Ltd filed Critical PowerChina Xian Port Navigation Shipbuilding Technology Co Ltd
Priority to CN202310506752.4A priority Critical patent/CN116397644A/en
Publication of CN116397644A publication Critical patent/CN116397644A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B75/00Building or assembling floating offshore structures, e.g. semi-submersible platforms, SPAR platforms or wind turbine platforms
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/18Control systems or devices
    • B66C13/46Position indicators for suspended loads or for crane elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/36Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
    • B66C23/52Floating cranes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/64Jibs
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/06Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers for observation while placing
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • E02D7/14Components for drivers inasmuch as not specially for a specific driver construction
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • E02D7/14Components for drivers inasmuch as not specially for a specific driver construction
    • E02D7/16Scaffolds or supports for drivers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/727Offshore wind turbines

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Ocean & Marine Engineering (AREA)
  • Automation & Control Theory (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The application provides a double hook marine engineering hanging pile driving ship and construction method, pile driving ship includes: the device comprises a ship body, a double-hook crane, a pile gripper and an overhanging bracket; the double-hook crane is arranged on a deck of the ship body; the plurality of the outriggers are fixedly connected to the same ship side of the ship body; the two pile embracing devices are respectively connected with the external support; the pile gripper can be sleeved with a precast pile; the double-hook marine engineering pile driving ship places the precast pile on the pile gripper through the double-hook crane; moving the pile gripper and the overhanging support to position the precast pile; sinking a plurality of precast piles to the sea bottom through the pile embracing device and locking; detecting the sinking position of the precast pile; if the sinking position of the precast pile deviates from the preset precast pile position, driving the ship body to the preset precast pile position, so as to solve the problem of low construction efficiency of the piling ship.

Description

Double-hook marine crane piling ship and construction method
Technical Field
The application relates to the technical field of piling mechanical equipment, in particular to a double-hook marine crane piling ship and a construction method.
Background
Solar energy resources are rich and clean renewable energy sources, and development and utilization of the solar energy resources are effective means for adjusting energy structures and implementing sustainable development of energy sources. The water photovoltaic power generation project can replace part of coal-fired units, reduces the emission of atmospheric pollutants, does not destroy the original ecological and human living environment, effectively reduces the environmental pressure caused by energy consumption, is beneficial to the adjustment and economic construction of local property structures, and has good social benefit and comprehensive economic benefit.
In some embodiments, the above water photovoltaic project first requires construction of a civil pile foundation using a piling ship. The piling operation of the piling ship needs to be supported by a large crane, and as each crane can only fix one lifting hook and can not simultaneously hoist at multiple points, the operation efficiency of the piling ship is low, and the construction of the whole water photovoltaic project is affected.
Disclosure of Invention
The application provides a double-hook marine engineering lifting pile driving ship and a construction method, which are used for solving the problem of low construction efficiency of the pile driving ship.
The first aspect of the present application provides a double hook marine lifting piling vessel, comprising: the device comprises a ship body, a double-hook crane, a pile gripper and an overhanging bracket;
the double-hook crane is arranged on a deck of the ship body; the plurality of the outriggers are fixedly connected to the same ship side of the ship body; the two pile embracing devices are respectively connected with the external support; the pile gripper can be sleeved with a precast pile; the double-hook marine crane piling ship is constructed according to the following steps:
placing the precast pile on the pile gripper through the double-hook crane;
moving the pile gripper and the overhanging support to position the precast pile;
sinking a plurality of precast piles to the sea bottom through the pile embracing device and locking;
detecting the sinking position of the precast pile;
and if the sinking position of the precast pile deviates from the preset precast pile position, driving the ship body to the preset precast pile position.
The pile driving ship is matched with the double-hook crane by arranging a plurality of the overhanging brackets and the pile clasping device, so that a plurality of precast piles can be fed together, and the problem of low construction efficiency of the pile driving ship is solved.
Optionally, the system further comprises anchoring equipment, mooring equipment, trolley positioning equipment, positioning piles and a positioning controller;
the anchoring device, the mooring device and the trolley positioning device are arranged on a deck of the ship body; the trolley positioning equipment is sleeved with the positioning pile; the positioning controller is in communication connection with the mooring device, the mooring device and the trolley positioning device.
The positioning controller is used for controlling the anchoring equipment and the mooring equipment to initially position the piling ship, and then controlling the trolley positioning equipment to use the positioning pile to further position the piling ship, so that the positioning accuracy is improved, the probability of repeated positioning due to the positioning deviation of the piling ship is reduced, and the construction efficiency of the piling ship is further improved.
Optionally, the device also comprises a tubular pile stacking area; the tubular pile stacking area is arranged in the middle of the deck of the ship body; a bracket is arranged on the tubular pile stacking area, and the cross section of the bracket is U-shaped; the spud and the precast pile may be placed on the bracket.
The pile driving ship is provided with the pile piling area, can store the piles such as the positioning piles, the precast piles and the like, saves construction time, and is convenient for taking and placing the double-hook crane. The cross sections of the positioning piles and the precast piles are round, so that the precast piles are easy to roll; the bracket can limit the rolling range of the positioning pile and the precast pile, and reduces the probability of wasting construction time caused by rolling damage of the positioning pile and the precast pile to other equipment and rolling out of the picking and placing range of the double-hook crane due to shaking of the piling ship.
Optionally, a piling component storage area is also included; the piling component storage area is arranged on a deck of the ship body; the pile component storage zone is located on a side remote from the outrigger.
The piling ship is provided with the piling component storage area, can store components such as a piling head, a piling hammer and the like, saves construction time, is convenient for the double-hook crane to pick and place, and is convenient for the transport ship to supplement the piling components.
Optionally, the double-hook crane comprises a base, a tower body, a cab, a boom, a main hook and an auxiliary hook;
the base and the cab are fixedly connected with the tower body; the suspension arm is hinged with the tower body; the main hook and the auxiliary hook are in sliding connection with the suspension arm.
Because the double-hook crane is arranged by double hooks comprising a main hook and an auxiliary hook, the double-hook crane not only can carry out multi-point hoisting at the same time, but also can realize the translation and turnover functions of the precast pile, and improves the construction efficiency of a piling ship.
Optionally, the pile driving device also comprises a laser positioning device and a pile driving hammer; the laser positioning device is arranged on the pile gripper; the pile hammer and the double-hook crane can be clamped.
The laser positioning device can accurately position the pile center of the precast pile, monitor whether the precast pile is inclined or not in real time when the pile hammer is used for piling, and reduce the probability of low efficiency caused by excessive inclination of piling.
A second aspect of the present application provides a construction method for a double-hook marine crane pile driving ship, to which the double-hook marine crane pile driving ship provided in the first aspect is applied, the construction method comprising:
placing the precast pile on a pile gripper through a double-hook crane;
moving the pile gripper and the overhanging support to position the precast pile;
sinking a plurality of precast piles to the sea bottom through the pile embracing device and locking;
detecting the sinking position of the precast pile;
and if the sinking position of the precast pile deviates from the preset precast pile position, driving the ship body to the preset precast pile position.
According to the method, the double-hook crane, the overhanging bracket and the pile gripper are controlled simultaneously, so that a plurality of precast piles are accurately positioned at the preset precast pile position, and meanwhile, the pile is fed to solve the problem of low construction efficiency of a piling ship.
Optionally, the construction method further includes:
driving the ship body to reach a construction water area;
the anchoring equipment and the mooring equipment are controlled by the positioning controller to initially position the ship body;
placing the positioning pile on a trolley positioning device;
and controlling the trolley positioning equipment through the positioning controller to enable the positioning pile to be placed at a preset positioning pile position.
According to the method, the anchoring equipment and the mooring equipment are controlled by the positioning controller to perform preliminary positioning on the piling ship, the trolley positioning equipment is controlled to further position the piling ship by using the positioning piles, positioning accuracy is improved, the occurrence probability of repeated positioning due to positioning deviation of the piling ship is reduced, and construction efficiency of the piling ship is further improved.
Optionally, driving the hull to perform lateral or longitudinal displacement according to a preset construction route; the preset construction route is an S-shaped route.
The ship body can carry out transverse or longitudinal displacement according to the S-shaped route, can move to a preset position more quickly, and improves the construction efficiency of the piling ship.
Optionally, the construction method further includes:
placing a pile driving hammer on the precast pile through a double-hook crane;
moving the pile gripper and the overhanging support to position the precast pile;
monitoring the pile center position of the precast pile in real time through a laser positioning device;
if the pile center position of the precast pile deviates from the preset pile center position, moving the pile gripper and the outrigger to the preset pile center position;
and driving the precast pile to a preset depth through the pile driving hammer.
According to the method, the precast pile is positioned through the pile gripper and the overhanging support, and then whether the precast pile is inclined or not is monitored in real time when the pile hammer is used for piling through the laser positioning device, so that the probability of low efficiency caused by excessive inclination of piling is reduced.
According to the technical scheme, the application provides a double-hook marine engineering lifting pile driving ship and a construction method, wherein the pile driving ship comprises: the device comprises a ship body, a double-hook crane, a pile gripper and an overhanging bracket; the double-hook crane is arranged on a deck of the ship body; the plurality of the outriggers are fixedly connected to the same ship side of the ship body; the two pile embracing devices are respectively connected with the external support; the pile gripper can be sleeved with a precast pile; the double-hook marine engineering pile driving ship places the precast pile on the pile gripper through the double-hook crane; moving the pile gripper and the overhanging support to position the precast pile; sinking a plurality of precast piles to the sea bottom through the pile embracing device and locking; detecting the sinking position of the precast pile; if the sinking position of the precast pile deviates from the preset precast pile position, driving the ship body to the preset precast pile position, so as to solve the problem of low construction efficiency of the piling ship.
Drawings
In order to more clearly illustrate the technical solutions of the present application, the drawings that are needed in the embodiments will be briefly described below, and it will be obvious to those skilled in the art that other drawings can be obtained from these drawings without inventive effort.
Fig. 1 is a schematic front view of a double-hook marine lifting pile driving ship according to an embodiment of the present application;
FIG. 2 is a schematic top view of a double hook marine lifting pile driving vessel according to an embodiment of the present application;
FIG. 3 is a schematic diagram of a double hook crane structure of a double hook marine crane piling vessel according to an embodiment of the present application;
FIG. 4 is a schematic view of a ship moving and positioning prior to construction of a double hook marine crane pile driving ship according to an embodiment of the present application;
FIG. 5 is a schematic view of a hoisting process of a precast pile in the construction of a double-hook marine crane pile driving ship according to an embodiment of the present application;
FIG. 6 is a schematic diagram of a precast pile feeding process in the construction of a double-hook marine crane pile driving ship according to an embodiment of the present application;
FIG. 7 is a schematic view of a connection structure of an outrigger and a pile gripper of a double-hook marine lifting pile driving vessel according to an embodiment of the present application;
FIG. 8 is a schematic view of a longitudinal construction process of a double-hook marine crane piling ship according to an embodiment of the present application;
FIG. 9 is a schematic diagram of a transverse construction process of a double-hook marine crane piling ship according to an embodiment of the present application;
FIG. 10 is a schematic diagram of pile feeding flow in the construction method of the double-hook marine crane pile driving ship according to the embodiment of the application;
FIG. 11 is a schematic diagram of a positioning flow in the construction method of the double-hook marine crane piling ship according to the embodiment of the application;
fig. 12 is a schematic view of a pile driving flow in the construction method of the double-hook maritime crane pile driving ship according to the embodiment of the application.
Illustration of:
wherein 1-the hull; 2-mooring equipment; 3-mooring equipment; 4-a trolley positioning device; 5-double hook crane; 51-a base; 52-tower body; 53-cab; 54-a boom; 55-main hook; 56-secondary hooks; 6-pile gripper; 7-a tubular pile stacking area; 8-a piling component storage area; 9-positioning piles; 10-positioning controller; 11-brackets; 12-precast piles; 13-outriggers; 14-presetting the position of the precast pile.
Detailed Description
In order to facilitate the technical solution of the application, some concepts related to the present application will be described below first.
Towing wheel: is used for towing ships without self-propulsion, wood rows or assisting large ships to enter and leave ports, lean against wharfs or as ships for salvaging marine vessels in distress. The tugboat has no cargo hold for loading cargoes, has a small hull, is provided with a high-power propulsion host and towing equipment, and has the characteristics of small equipment volume and large towing force.
And (3) floating crane: a floating platform carrying a crane which can be moved to a desired location in a port, either to berth or to anchor for turning cargo.
Reference will now be made in detail to the embodiments, examples of which are illustrated in the accompanying drawings. When the following description refers to the accompanying drawings, the same numbers in different drawings refer to the same or similar elements, unless otherwise indicated. The embodiments described in the examples below do not represent all embodiments consistent with the present application. Merely as examples of systems and methods consistent with some aspects of the present application as detailed in the claims.
The construction of civil pile foundation is needed to be carried out by using piling ships in the water photovoltaic project. The piling operation of the piling ship needs to be supported by a large crane, and as each crane can only fix one lifting hook and can not simultaneously hoist at multiple points, the operation efficiency of the piling ship is low, and the construction of the whole water photovoltaic project is affected.
In order to solve the problem of low construction efficiency of a piling ship, referring to fig. 1 to 12, some embodiments of the present application provide a double-hook marine crane piling ship, which includes: the ship body 1, the double-hook crane 5, the pile gripper 6 and the overhanging bracket 13; the double-hook crane 5 is arranged on the deck of the ship body 1; a plurality of outriggers 13 are fixedly connected to the same side of the hull 1; the two pile holders 6 are respectively connected with the overhanging bracket 13; the pile gripper 6 can be sleeved with the precast pile 12.
It should be understood that the number of the double-hook cranes 5 can be multiple, as shown in fig. 1 and 2, the number of the double-hook cranes 5 can be two, and the two double-hook cranes 5 are respectively arranged on the front side and the rear side of the ship body 1, so that the efficiency of the piling ship can be improved, and the upper bearing limit of the piling ship cannot be exceeded due to the excessive weight of the double-hook cranes 5. The number of the overhanging support 13 is four, so that the pile feeding of eight precast piles 12 can be completed at one time, and the efficiency of the piling ship is improved. In addition, the outrigger 13 is a hydraulic outrigger, can be opened before pile feeding, and can be retracted to the side of the ship after pile driving is finished, so that excessive space is not occupied.
As shown in fig. 6 and 10, the double-hook marine crane piling ship is constructed according to the following steps:
s200: placing the precast pile 12 on the pile gripper 6 through the double-hook crane 5;
s210: moving the pile gripper 6 and the overhanging support 13 to position the precast pile 12;
s220: sinking a plurality of precast piles 12 to the sea bottom through a pile gripper 6 and locking;
s230: detecting the sinking position of the precast pile 12;
s240: comparing whether the sinking position of the precast pile 12 deviates from the preset precast pile position:
s241: if the sinking position of the precast pile 12 deviates from the preset precast pile position, the ship body 1 is driven to the preset precast pile position.
It should be understood that the preset precast pile position is determined according to a construction drawing designed by a designer. In some embodiments, the device also comprises a draft measuring device and a transverse inclinometer, which are used for monitoring whether the ship body 1 is kept horizontal or not, so that the probability of affecting piling accuracy due to the floating state of the ship body 1 is reduced.
The pile driving ship is matched with the double-hook crane 5 by arranging a plurality of overhanging brackets 13 and pile claspers 6, so that a plurality of precast piles 12 can be fed together, and the problem of low construction efficiency of the pile driving ship is solved.
In some embodiments, further comprises mooring equipment 2, mooring equipment 3, trolley positioning equipment 4, positioning piles 9, positioning controllers 10;
the mooring equipment 2, the mooring equipment 3 and the trolley positioning equipment 4 are arranged on the deck of the ship body 1; the trolley positioning equipment 4 is sleeved with the positioning pile 9; the positioning controller 10 is in communication with the mooring apparatus 2, the mooring apparatus 3 and the trolley positioning apparatus 4.
It will be appreciated that the mooring apparatus 2 comprises anchors, chains and motors; the motor is connected to the positioning controller 10. The anchor is placed into the sea bottom by the motor controlled by the positioning controller 10, and the combined holding power of the anchor and the anchor chain is larger than the sum of external force, so that the ship body 1 is safely moored without moving due to the action of the external force. As shown in fig. 1 and 2, the mooring device 2 can be four in number, so that the ship body 1 can be moored more stably.
The mooring 3 comprises a cable shaft arrangement and a cable; the positioning controller 10 controls the cable shaft means to retract the cable for safe mooring of the hull 1 by connecting one end of the cable to a terminal structure such as a quay, a berth, a jetty, a pontoon, a floating structure, an offshore structure or another vessel.
The trolley positioning equipment 4 comprises a winch, an oil cylinder, a positioning device and a track; one end of a steel wire rope of the winch is bound on the positioning pile 9, and the other end of the steel wire rope is connected with the oil cylinder; the positioning device is sleeved with the positioning pile 9; the track is horizontally arranged on the ship body 1, and the positioning device is in sliding connection with the track. The trolley device not only can enable the positioning pile 9 to move along the vertical and horizontal directions, but also can drive the ship body 1 to move and position, thereby playing a role in accurate positioning.
After reaching the construction water area, determining the position according to the longitude and latitude of the GPS positioning system and the construction design drawing, and controlling a motor of the anchoring equipment 2 to put an anchor connected with an anchor chain into the sea bottom through the positioning controller 10; the cable shaft device of the mooring equipment 3 is controlled to tighten the cable connected with the terminal mechanism, the piling ship is initially positioned, and then the control trolley positioning equipment 4 further positions the piling ship by using the positioning piles 9, so that the piling ship is accurately positioned. The positioning accuracy is improved, the probability of repeated positioning due to positioning deviation of the piling ship is reduced, and the construction efficiency of the piling ship is further improved.
In some embodiments, the positioning controller 10 is a PLC controller, and has the characteristics of convenient use, wide application range, high reliability, strong anti-interference capability, simple programming, and the like.
As shown in fig. 2, in some embodiments, a tube stake stacking zone 7 is also included; the tubular pile stacking area 7 is arranged in the middle of the deck of the ship body 1; a bracket 11 is arranged on the tubular pile stacking area 7, and the cross section of the bracket 11 is U-shaped; the spud 9 and the precast pile 12 may be placed on the bracket 11.
It should be understood that 64 precast piles 12 can be placed in the pile piling area 7, so that the pile repairing can be performed after the pile driving ship finishes driving eight groups, and the construction time is saved. The U-shaped cross sections at the two sides of the bracket 11 are opposite to the side of the ship body 1, so that the transportation ship is convenient to repair piles close to the side of the ship; and simultaneously, the double-hook crane 5 is convenient to take and put.
The piling ship is provided with a pipe pile piling area 7, and can store the components such as the positioning pile 9, the precast pile 12 and the like, thereby saving the construction time and facilitating the taking and placing of the double-hook crane 5. The cross sections of the positioning piles 9 and the precast piles 12 are round, so that the precast piles are easy to roll; the bracket 11 can limit the rolling range of the positioning pile 9 and the precast pile 12, and reduces the probability of the situation that the positioning pile 9 and the precast pile 12 roll to damage other equipment and roll out of the picking and placing range of the double-hook crane 5 due to shaking of a piling ship.
As shown in fig. 2, in some embodiments, a piling component storage area 8 is also included; the piling component storage area 8 is arranged on the deck of the ship body 1; the pile member storage zone 8 is located on the side remote from the outriggers 13.
The piling ship is provided with a piling component storage area 8 for storing components such as a piling head, a piling hammer and the like, so that the construction time is saved, the double-hook crane 5 is convenient to take and place, and the transportation ship is convenient to supplement.
As shown in fig. 3, in some embodiments, the double hook crane 5 includes a base 51, a tower 52, a cab 53, a boom 54, a primary hook 55, and a secondary hook 56;
the base 51 and the cab 53 are fixedly connected with the tower 52; boom 54 is hinged to body 52; the main hook 55 and the sub-hook 56 are slidably connected to the boom 54.
As shown in fig. 5, it should be understood that since the weight of the single precast pile 12 is 10-15 tons and the lifting capacity of the main hook 55 of the double hook crane 5 is 30 tons and the lifting capacity of the sub hook 56 is 30 tons, the turning of the single precast pile 12 can be achieved by the main hook 55 and the sub hook 56, for example: adjust from the horizontal state to the vertical state. The main hook 55 is a gable hook, the main hook 55 of the gable hook can hoist the precast pile 12 on one side, and the other side is connected with a pile hammer; when the pile driving device is lifted, the precast pile 12 and the pile driving hammer are lifted at the same time, so that the construction efficiency of the pile driving ship is improved.
Through the double-hook arrangement of the main hook 55 and the auxiliary hook 56, not only can multi-point hoisting be carried out simultaneously, but also the translation and turnover functions of the precast pile 12 can be realized, and the construction efficiency of a piling ship is improved.
In some embodiments, the laser positioning device is further included; the laser positioning device is arranged on the pile gripper 6; the pile hammer and the double-hook crane 5 can be clamped.
For example, when the double hook crane 5 lifts up the precast pile, two hooks of the main hook 55 can be simultaneously used for clamping with the pile hammer; when piling is completed, the two hooks of the main hook 55 can be opened and detached from the piling hammer.
The laser positioning device can accurately position the pile center of the precast pile 12, and monitors whether the precast pile 12 is inclined or not in real time when a pile driving hammer is used for driving. The probability of inefficiency caused by excessive inclination of piling is reduced.
Another part of embodiments of the present application provides a construction method of a double-hook marine crane pile driving ship, which is applied to any one of the double-hook marine crane pile driving ships described in the above embodiments, as shown in fig. 10, and the construction method includes:
s200: placing the precast pile 12 on the pile gripper 6 through the double-hook crane 5;
s210: moving the pile gripper 6 and the overhanging support 13 to position the precast pile 12;
s220: sinking a plurality of precast piles 12 to the sea bottom through a pile gripper 6 and locking;
s230: detecting the sinking position of the precast pile 12;
s240: comparing whether the sinking position of the precast pile 12 deviates from the preset precast pile position:
s241: if the sinking position of the precast pile 12 deviates from the preset precast pile position, the ship body 1 is driven to the preset precast pile position.
It should be understood that if the position of the sinking of the precast pile 12 does not deviate from the preset precast pile position, the sinking of the precast pile 12 is continued. In addition, because the pile clasping devices 6 are in one-to-one correspondence with the precast pile positions, the pile clasping devices 6 can be positioned by accurately positioning the precast piles 12.
In some embodiments, one end of the precast pile 12 is self-contained with a pile driving head, without additional installation; in other embodiments, where there is no pile driving head at one end of the precast pile 12, it is desirable to install the pile driving head at one end of the precast pile 12 before the double hook crane 5 places the precast pile 12 on the pile gripper 6.
As shown in fig. 7, in some embodiments, the outrigger 13 is a hydraulic outrigger including a hydraulic device and a bracket; one end of the bracket is fixedly connected with the ship body 1; during piling operation, the support can be opened through the hydraulic device, and the precast pile 12 is placed above the pile gripper 6 through the double-hook crane 5, so that the precast pile 12 penetrates through the pile gripper 6 until the pile head part of the precast pile 12 contacts the sea floor to lock, and pile feeding is completed.
According to the method, the double-hook crane 5, the outriggers 13 and the pile gripper 6 are controlled simultaneously, so that the precast piles 12 are accurately positioned at the preset precast pile positions, and meanwhile, the pile is fed to solve the problem of low construction efficiency of a piling ship.
As shown in fig. 4 and 11, in some embodiments, the construction method further includes:
s100: driving the ship body 1 to reach a construction water area;
s110: the positioning controller 10 controls the anchoring equipment 2 and the mooring equipment 3 to initially position the ship body 1;
s120: placing the positioning pile 9 on the trolley positioning device 4;
s130: the trolley positioning device 4 is controlled by the positioning controller 10 to place the spud 9 at a preset spud position.
It should be appreciated that the predetermined spud positions are determined from the construction drawings of the designer. The hull 1 is driven into the construction area, and in some embodiments, is positioned into the construction area by GPS mounted on the hull 1, and the hull 1 is towed into the construction area by a tow boat. In the towing process, the positioning pile 9 is not connected with the trolley positioning equipment 4, and after the positioning pile 9 reaches a construction water area, the positioning pile 9 is connected with the trolley positioning equipment 4 through a floating crane.
As shown in fig. 2, two trolley positioning devices 4 can be selected and respectively placed at the positions of the ship body 1 close to the bow and the stern; the positioning of the ship body 1 is more accurate.
When the ship is moved, the control trolley positioning equipment 4 lifts the positioning pile 9 and uses a positioning device to fix the positioning pile; the anchoring equipment 2 and the mooring equipment 3 are controlled to loosen the connection with the ship body 1, the ship body 1 is pulled to move to the next pile position through the oil cylinder, and then the positioning pile 9 is lowered to the seabed by the control trolley equipment; the mooring device 2 and the mooring device 3 are controlled again to tighten the connection with the hull 1.
According to the method, the anchoring equipment 2, the mooring equipment 3 and the trolley positioning equipment 4 are controlled by the positioning controller 10, so that the positioning accuracy can be improved, the probability of repeated positioning due to positioning deviation of the piling ship is reduced, and the construction efficiency of the piling ship is further improved.
In some embodiments, the hull 1 is driven to displace transversely or longitudinally according to a preset construction route; the preset construction route is an S-shaped route.
As shown in fig. 8 to 9, in order to facilitate site construction and to realize simultaneous operation of multiple vessels, the hull 1 may adopt two modes of lateral displacement and longitudinal displacement, respectively. The ship body 1 can transversely or longitudinally displace according to the S-shaped route, can move more quickly and improves the construction efficiency of the piling ship.
In some embodiments, as shown in fig. 12, the construction method further comprises:
s300: placing a pile hammer on the precast pile 12 through the double-hook crane 5;
s310: moving the pile gripper 6 and the overhanging support 13 to position the precast pile 12;
s320: monitoring the pile center position of the precast pile 12 in real time by a laser positioning device;
s330: comparing whether the pile center position of the precast pile 12 deviates from the preset pile center position:
s331: if the pile center position of the precast pile 12 deviates from the preset pile center position, moving the pile gripper 6 and the overhanging support 13 to the preset pile center position;
s340: the precast pile 12 is driven to a preset depth by a pile driving hammer.
It will be appreciated that in some embodiments, draft measuring devices and inclinometers may also be optional to monitor whether the hull 1 is held horizontally, reducing the chance of affecting pile accuracy due to buoyancy of the hull 1. When piling is completed, the outriggers 13 are retracted by hydraulic means. The position of the preset pile core and the preset depth are determined according to a construction drawing designed by a designer.
The method is characterized in that the precast pile 12 is positioned through the pile gripper 6 and the overhanging bracket 13, and then whether the precast pile 12 is inclined or not is monitored in real time when a pile hammer is driven through a laser positioning device. The probability of inefficiency caused by excessive inclination of piling is reduced.
According to the technical scheme, the embodiment of the application provides a double-hook marine engineering lifting pile driving ship and a construction method, wherein the pile driving ship comprises: the ship body 1, the double-hook crane 5, the pile gripper 6 and the overhanging bracket 13; the double-hook crane 5 is arranged on the deck of the ship body 1; a plurality of outriggers 13 are fixedly connected to the same side of the hull 1; the two pile holders 6 are respectively connected with the overhanging bracket 13; the pile gripper 6 can be sleeved with a precast pile 12; the double-hook sea crane piling ship places the precast pile 12 on the pile gripper 6 through the double-hook crane 5; moving the pile gripper 6 and the overhanging support 13 to position the precast pile 12; sinking a plurality of precast piles 12 to the sea bottom through a pile gripper 6 and locking; detecting the sinking position of the precast pile 12; if the sinking position of the precast pile 12 deviates from the preset precast pile 12 position, the ship body 1 is driven to the preset precast pile 12 position, so that the problem of low construction efficiency of the piling ship is solved.
The foregoing detailed description of the embodiments is merely illustrative of the general principles of the present application and should not be taken in any way as limiting the scope of the invention. Any other embodiments developed in accordance with the present application without inventive effort are within the scope of the present application for those skilled in the art.

Claims (10)

1. A double-hooked marine lifting pile driving vessel, comprising: the ship comprises a ship body (1), a double-hook crane (5), a pile gripper (6) and an overhanging bracket (13);
the double-hook crane (5) is arranged on the deck of the ship body (1); a plurality of the outriggers (13) are fixedly connected to the same side of the hull (1); the two pile embracing devices (6) are respectively connected with the overhanging support (13); the pile gripper (6) can be sleeved with a precast pile (12); the double-hook marine crane piling ship is used for piling construction according to the following steps:
placing the precast pile (12) on the pile gripper (6) through a double-hook crane (5);
moving the pile gripper (6) and the overhanging support (13) to position the precast pile (12);
sinking a plurality of precast piles (12) to the sea floor through the pile embracing device (6) and locking;
detecting the sinking position of the precast pile (12);
and if the sinking position of the precast pile (12) deviates from the preset precast pile position, driving the ship body (1) to the preset precast pile position.
2. Double-hooked maritime work hanging piling ship according to claim 1, characterized in that it further comprises anchoring equipment (2), mooring equipment (3), trolley positioning equipment (4), positioning piles (9) and positioning controllers (10);
the mooring device (2), the mooring device (3) and the trolley positioning device (4) are arranged on the deck of the hull (1); the trolley positioning equipment (4) is sleeved with the positioning pile (9); the positioning controller (10) is in communication connection with the mooring device (2), the mooring device (3) and the trolley positioning device (4).
3. A double-hooked marine lifting piling vessel according to claim 2, characterised by further comprising a pile stacking zone (7); the tubular pile stacking area (7) is arranged in the middle of a deck of the ship body (1); a bracket (11) is arranged on the tubular pile stacking area (7), and the cross section of the bracket (11) is U-shaped; the spud (9) and the precast pile (12) may be placed on the bracket (11).
4. Double-hooked maritime work hanging piling ship according to claim 1, characterized in that it further comprises a piling component storage area (8); the piling component storage area (8) is arranged on the deck of the ship body (1); the pile component storage area (8) is located on the side remote from the outrigger (13).
5. Double-hook marine crane piling vessel according to claim 1, characterized in that the double-hook crane (5) comprises a foundation (51), a tower (52), a cab (53), a boom (54), a primary hook (55) and a secondary hook (56);
the base (51) and the cab (53) are fixedly connected with the tower body (52); the suspension arm (54) is hinged with the tower body (52); the main hook (55) and the auxiliary hook (56) are in sliding connection with the boom (54).
6. The double-hooked marine lifting piling vessel of claim 1, further comprising a laser positioning device and a piling hammer; the laser positioning device is arranged on the pile gripper (6); the pile hammer and the double-hook crane (5) can be clamped.
7. A construction method for a double-hook marine crane pile driving ship, which is applied to the double-hook marine crane pile driving ship according to any one of claims 1 to 6, and comprises the following steps:
the precast pile (12) is placed on the pile gripper (6) through the double-hook crane (5);
moving the pile gripper (6) and the overhanging support (13) to position the precast pile (12);
sinking a plurality of precast piles (12) to the sea floor through the pile embracing device (6) and locking;
detecting the sinking position of the precast pile (12);
and if the sinking position of the precast pile (12) deviates from the preset precast pile position, driving the ship body (1) to the preset precast pile position.
8. The method of double-hooked marine lifting piling vessel construction according to claim 7, further comprising:
driving the ship body (1) to reach a construction water area;
the anchoring equipment (2) and the mooring equipment (3) are controlled by the positioning controller (10) to initially position the ship body (1);
placing the positioning pile (9) on the trolley positioning equipment (4);
and the trolley positioning equipment (4) is controlled by the positioning controller (10) to enable the positioning pile (9) to be placed at a preset positioning pile position.
9. The method for constructing a double-hooked marine lifting pile driving vessel according to claim 8, wherein,
driving the ship body (1) to transversely or longitudinally displace according to a preset construction route; the preset construction route is an S-shaped route.
10. The method of double-hooked marine lifting piling vessel construction according to claim 7, further comprising:
placing a piling hammer on the precast pile (12) through the double-hook crane (5);
moving the pile gripper (6) and the overhanging support (13) to position the precast pile (12);
monitoring the pile core position of the precast pile (12) in real time through a laser positioning device;
if the pile center position of the precast pile (12) deviates from the preset pile center position, moving the pile gripper (6) and the overhanging support (13) to the preset pile center position;
and driving the precast pile (12) to a preset depth through the pile driving hammer.
CN202310506752.4A 2023-05-04 2023-05-04 Double-hook marine crane piling ship and construction method Pending CN116397644A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310506752.4A CN116397644A (en) 2023-05-04 2023-05-04 Double-hook marine crane piling ship and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310506752.4A CN116397644A (en) 2023-05-04 2023-05-04 Double-hook marine crane piling ship and construction method

Publications (1)

Publication Number Publication Date
CN116397644A true CN116397644A (en) 2023-07-07

Family

ID=87010586

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310506752.4A Pending CN116397644A (en) 2023-05-04 2023-05-04 Double-hook marine crane piling ship and construction method

Country Status (1)

Country Link
CN (1) CN116397644A (en)

Similar Documents

Publication Publication Date Title
CN109952246B (en) System and method for reconfiguring mobile docking equipment for transporting, removing, assembling, housing and transferring assets
EP2724021B1 (en) A self-propelled offshore wind farm installation vessel, and method of installation used in the construction of an offshore wind turbine farm
CN111762287B (en) Method for securing and transferring loads between a vessel and an offshore installation and apparatus therefor
CN101774422B (en) Novel offshore installation construction resource-combined type pontoon barge
CN101417693B (en) Oceanography engineering module integral hoisting method
CN201268389Y (en) Multifunctional construction platform
US11161571B2 (en) Method of securing and transferring a load between a vessel and an offshore installation and an apparatus therefor
US20120201608A1 (en) Foundation for offshore wind turbine and method and means for its transportation and installation in deepwaters
WO2010109243A2 (en) Apparatus and method for handling a submersible item
CN116397644A (en) Double-hook marine crane piling ship and construction method
CN115258092A (en) Floating type water photovoltaic integral installation method
CN104627326A (en) Special lifting and vibration-driving ship for integrated driving of cell type steel sheet pile large cylinders and vice cells
CN104097748A (en) Parking craning method for vibration sinking construction of steel cylinders
JP7197118B2 (en) Work barge equipped with a crane and its crane operation method
CN113605309A (en) Multi-module floating breakwater offshore laying ship and laying method
WO2017141177A1 (en) Barge system
Dymarski et al. Technology concept of TLP platform towing and installation in waters with depth of 60 m
US20120082530A1 (en) System and method for submerging a hydraulic turbine engine
TWI834746B (en) Work platform vessel equipped with crane and method of using the crane
NL2031544B1 (en) Jack-up vessel and method for the installation of elongate construction elements offshore
CN215629937U (en) Overwater piling operation platform
WO2024018024A1 (en) Monopiles transport and installation vessel
CN115285317A (en) Offshore wind turbine-foundation integrated installation vessel and installation method
CN116648421A (en) Offshore wind turbine assembly vessel
CN114148463A (en) Construction process of semi-submersible marine installation operation platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication