CN116163331A - Construction process of large-thickness variable-section raft foundation - Google Patents

Construction process of large-thickness variable-section raft foundation Download PDF

Info

Publication number
CN116163331A
CN116163331A CN202310295046.XA CN202310295046A CN116163331A CN 116163331 A CN116163331 A CN 116163331A CN 202310295046 A CN202310295046 A CN 202310295046A CN 116163331 A CN116163331 A CN 116163331A
Authority
CN
China
Prior art keywords
steel pipe
layer
raft foundation
support
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202310295046.XA
Other languages
Chinese (zh)
Other versions
CN116163331B (en
Inventor
赵乐
韦静林
柳印生
张阳
江强
方万刚
周少林
代林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202310295046.XA priority Critical patent/CN116163331B/en
Priority claimed from CN202310295046.XA external-priority patent/CN116163331B/en
Publication of CN116163331A publication Critical patent/CN116163331A/en
Application granted granted Critical
Publication of CN116163331B publication Critical patent/CN116163331B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ

Abstract

The invention discloses a construction process of a large-thickness variable-section raft foundation, which comprises the following steps: forming a bottom layer retaining wall, pouring into a top layer retaining wall, and forming a raft steel bar steel pipe support frame and a raft foundation to be poured and layered. The construction process of the large-thickness variable-section raft foundation can effectively solve the construction problem caused by large thickness and large substrate height difference, effectively cope with a soil layer structure, greatly firmly realize the foundation structure, greatly reduce the consumption of reinforcing steel bars, effectively reduce the cost, and be more convenient and efficient in construction.

Description

Construction process of large-thickness variable-section raft foundation
Technical Field
The invention relates to the technical field of construction of building raft foundation, in particular to a construction process of a large-thickness variable-section raft foundation.
Background
The raft foundation is a foundation structure adopted in the current building according to the conditions of foundation types, soil layer distribution and the like, wherein the large-thickness variable-section raft foundation is also called an ultra-thick variable-section raft foundation, because the height difference of the lowest position of the raft foundation is large, the raft foundation needs high structural requirements on the pit high side surface in the pit, and meanwhile, the raft foundation has to bear the foundation bearing capacity of the building, when the number of building layers is higher, the thickness is larger, and the influences of soil layer composition, rock mass characteristics and the like are caused, the conventional or old raft foundation cannot be constructed to meet the requirements, the construction is more difficult, the use amount of reinforcing steel bars is also increased sharply, and the cost is high.
Disclosure of Invention
The purpose of the invention is that: the construction process of the large-thickness variable-section raft foundation can cope with the loose soil layer structure and can provide a stable foundation for high-rise buildings.
The construction process of the large-thickness variable-section raft foundation comprises the following steps:
firstly, after excavating earthwork, constructing a bedding layer, vertically arranging a single-sided wood formwork support when constructing the bedding layer at the position with the base height difference being more than 0.5m and less than 2m, arranging a steel pipe diagonal bracing between the inner side of the single-sided wood formwork support and the bedding layer, and then carrying out concrete backfilling between the outer side of the single-sided wood formwork support and a side slope to form a bottom retaining wall;
setting up a single-sided wood template support vertically when a cushion layer at the position with the substrate height difference larger than 2m is constructed, setting up a steel pipe diagonal brace between the inner side of the single-sided wood template support and the cushion layer, setting up a top layer retaining wall steel bar on the cushion layer at the outer side of the single-sided wood template support, then carrying out concrete backfilling between the outer side of the single-sided wood template support and the earthwork to form a bottom layer retaining wall, setting up a double-sided wood template support on the top layer retaining wall steel bar extending out of the bottom layer retaining wall, setting up a steel pipe diagonal brace between one side of the double-sided wood template support and a side slope, setting up a steel pipe diagonal brace between one side of the double-sided wood template support and the cushion layer, and casting concrete into the double-sided wood template support to form the top layer retaining wall;
arranging concrete cushion blocks 31 on the inner bottom surface of the raft foundation in a matrix distribution manner, arranging longitudinal and transverse lower-layer steel bars on the concrete cushion blocks, binding, welding a bottom support on the lower-layer steel bars in a distribution manner, arranging steel pipe upright posts at the upper ends of the bottom supports, arranging one or more layers of spaced steel pipe cross beams in the middle of the steel pipe upright posts, binding middle-layer steel bars correspondingly, and arranging one layer of steel pipe cross beams at the top of the steel pipe upright posts, binding upper-layer steel bars correspondingly to form a raft steel bar steel pipe support frame;
and fourthly, performing concrete pouring on the pits in the inner pits of the raft foundation to form a first concrete pouring area, and performing concrete pouring on the pits on the upper part in the raft foundation to form a second concrete pouring area, thereby completing the layered forming of the raft foundation.
In the first and second steps, short steel bars for fixedly connecting the steel pipe diagonal braces are pre-buried on the cushion layer at intervals.
In the first and second steps, the steel pipe diagonal brace connected with the single-sided wood template support is two, and the steel pipe diagonal brace connected with the double-sided wood template support and the steel pipe top brace are five.
In the second step, the double-sided wood formwork support comprises a red formwork, a wood column vertical edge, a double-steel-pipe transverse edge and a high-strength opposite-pull screw rod.
In the third step, the bottom support is shaped like a Chinese character 'tu', the bottom support is connected with the lower layer steel bar in a spot welding mode, and the lower end of the steel tube upright post is sleeved with the upper end of the bottom support.
In the third step, the steel pipe column is fastened to the steel pipe beam through a fastener, and the steel pipe column, the steel pipe beam and the fastener are subjected to oil and rust removal treatment.
In the fourth step, a water stop steel plate is arranged on the inner side wall of the raft foundation.
Compared with the prior art, the construction process of the large-thickness variable-section raft foundation has the beneficial effects that: the construction problem caused by large thickness and large substrate height difference can be effectively solved, the soil layer structure is effectively treated, the foundation structure is very firm, the consumption of reinforcing steel bars is greatly reduced, the cost is effectively reduced, and the construction is more convenient and efficient.
Drawings
Fig. 1 is a schematic view of a construction structure of a retaining wall at a bottom layer according to an embodiment of the present invention;
FIG. 2 is a schematic view of construction structures of a bottom retaining wall and a top retaining wall according to an embodiment of the present invention;
fig. 3 is a schematic view of a construction structure of a top retaining wall according to an embodiment of the present invention;
fig. 4 is a schematic view of a construction structure of a raft reinforcement steel pipe support frame in an embodiment of the invention;
fig. 5 is a schematic view of a partial structure of a raft reinforcement steel tube support frame in an embodiment of the present invention;
FIG. 6 is an enlarged schematic view of a construction structure at a shoe in an embodiment of the invention;
fig. 7 is a schematic view of a construction structure of a raft foundation cast and layered forming in an embodiment of the invention.
Detailed Description
The following describes in further detail the embodiments of the present invention with reference to the drawings and examples. The following examples are illustrative of the invention and are not intended to limit the scope of the invention.
In the description of the present invention, it should be understood that the terms "mounted," "connected," and "connected" are to be construed broadly in this application, and may be either fixedly connected, detachably connected, or integrally connected, for example, unless otherwise explicitly stated and defined; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present invention will be understood in specific cases by those of ordinary skill in the art.
In the description of the present invention, it should be further understood that the terms "upper," "lower," "left," "right," "front," "rear," "top," "bottom," and the like indicate or are based on the orientation or positional relationship shown in the drawings, merely to facilitate description of the present invention and to simplify the description, and do not indicate or imply that the machine or element in question must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be construed as limiting the present invention. It should be understood that the terms "first," "second," and the like are used herein to describe various information, but such information should not be limited to these terms, which are used merely to distinguish one type of information from another. For example, a "first" message may also be referred to as a "second" message, and similarly, a "second" message may also be referred to as a "first" message, without departing from the scope of the invention.
Referring to fig. 1 to 7, the construction process of the large-thickness variable-section raft foundation according to the embodiment of the invention comprises the following steps:
firstly, after earthwork is excavated, a cushion layer 1 is constructed, when the cushion layer 1 with the base height difference being more than 0.5m and less than 2m is constructed, a single-sided wood template support 21 is vertically arranged at an excavation control line, a steel pipe diagonal bracing 22 is arranged between the inner side of the single-sided wood template support 21 and the cushion layer 1, and then concrete backfilling is carried out between the outer side of the single-sided wood template support 21 and a side slope to form a bottom retaining wall;
setting a single-sided wood formwork support 21 vertically at an excavation control line when the bedding layer 1 with the substrate height difference being larger than 2m is constructed, setting a steel pipe diagonal brace 22 between the inner side of the single-sided wood formwork support 21 and the bedding layer 1, setting a top layer retaining wall reinforcing steel bar 23 at the outer side of the single-sided wood formwork support 21, backfilling concrete between the outer side of the single-sided wood formwork support 21 and the earthwork to form a bottom layer retaining wall, setting a double-sided wood formwork support 24 on the top layer retaining wall reinforcing steel bar 23 extending out of the bottom layer retaining wall, setting a steel pipe diagonal brace 25 between one side of the double-sided wood formwork support 24 and a side slope, setting the steel pipe diagonal brace 22 between one side of the double-sided wood formwork support 24 and the bedding layer 1, pouring concrete into the double-sided wood formwork support 24 to form a top layer retaining wall, and backfilling between the top layer retaining wall and the side slope after the double-sided wood formwork support and the steel pipe support are removed;
arranging concrete cushion blocks 31 on the inner bottom surface of a raft foundation in a matrix distribution manner, arranging lower layer steel bars 32 in a longitudinal and transverse manner on the concrete cushion blocks 31, binding, welding a bottom support 33 corresponding to the concrete on the lower layer steel bars 32 in a distribution manner, arranging steel pipe upright posts 34 at the upper ends of the bottom supports 33, arranging one or more layers of spaced steel pipe cross beams 35 and corresponding binding middle layer steel bars 36 in the middle of the steel pipe upright posts 34, arranging one layer of steel pipe cross beams 35 and corresponding binding upper layer steel bars 37 at the top of the steel pipe upright posts 34, and forming a raft steel bar steel pipe support frame, thereby greatly saving the consumption of steel bars and simultaneously ensuring that the support frame has enough structural strength;
and fourthly, firstly, performing concrete pouring on the pits in the inner pits of the raft foundation to form a first concrete pouring area 41, and then performing concrete pouring on the pits on the upper part in the raft foundation to form a second concrete pouring area 42, so that the layered forming of the raft foundation pouring is completed, and the pouring construction is smoother.
Referring to fig. 1-3, in the first and second steps, short steel bars 26 for fixedly connecting the steel pipe diagonal braces 22 are pre-buried on the cushion layer 1 at intervals, so that construction is facilitated.
Referring to fig. 1 to 3, in the first and second steps, the steel pipe diagonal braces 22 connected to the single-sided wood form support 21 are two, and the steel pipe diagonal braces 22 and the steel pipe diagonal braces 25 connected to the double-sided wood form support 24 are five, respectively, so that the single-sided wood form support 21 and the double-sided wood form support 24 are firmly fixed.
Referring to fig. 3, in an exemplary second step, the double-sided wood formwork support 24 includes a red formwork, a wood beam vertical edge, a double-steel-pipe transverse edge and a high-strength opposite wire-drawing rod, preferably, the red formwork is 13mm to 18mm thick, the wood beam vertical edge is distributed at a horizontal distance of 300mm, the double-steel-pipe transverse edge is spaced at a horizontal distance of 500mm, and the high-strength opposite wire-drawing rod is ensured to construct and structurally strengthen the top-layer retaining wall.
Referring to fig. 6, in the third step, the shoe 33 is shaped like a letter "earth", the shoe 33 is spot-welded to the lower layer steel bar 32, and the lower end of the steel pipe column 34 is sleeved on the upper end of the shoe 33, so that the shoe 33 is firmly fixed and the steel pipe column 34 is firmly supported.
In the third step, the steel pipe column 34 is fastened to the steel pipe beam 35 through a fastener, and the steel pipe column 34, the steel pipe beam 35 and the fastener are subjected to oil and rust removal treatment, so that the structure is durable and the strength is firm.
In the fourth step, a water stop steel plate is arranged on the periphery of the inner side wall of the raft foundation, so that later-stage water seepage of the raft construction joint is effectively prevented.
Referring to fig. 1-5, an exemplary embodiment of the present invention provides a large-thickness variable-section raft foundation structure, including a retaining wall and a raft reinforcement steel tube support frame, where the retaining wall is disposed around the periphery of the raft foundation, the retaining wall includes a bottom retaining wall and a top retaining wall formed by layering from bottom to top, the raft reinforcement steel tube support frame includes a concrete pad 31, a lower layer reinforcement 32, a bottom support 33, a steel tube column 34, a steel tube beam 35, a middle layer reinforcement 36 and an upper layer reinforcement 37, the concrete pad 31 is distributed on an inner bottom of the raft foundation along a matrix, the lower layer reinforcement 32 is vertically and horizontally distributed and connected to the concrete pad 31, the bottom support 33 is distributed and connected to the lower layer reinforcement 32 along a matrix, each bottom support 33 is connected to one steel tube column 34, a middle layer or more of steel tube beam 35 and the middle layer reinforcement 36 are connected to the middle portion of the steel tube column 34, and the top of the steel tube column 34 is connected to one layer of steel tube beam 35 and the upper layer reinforcement 37, thereby well forming the raft foundation, the large-thickness and the large-thickness variable-section raft foundation structure is well reduced, and the cost of the raft foundation structure is well reduced.
Illustratively, the shoe 33 is made of a steel pipe with a diameter of 28mm or more, and the height of the shoe 33 is 260mm to 360mm.
Illustratively, the middle layer steel bar 36 and the upper layer steel bar 37 are respectively connected to the upper side of the steel pipe beam 35 through binding, so that the construction is easy, and the structure is firm.
Illustratively, the steel pipe column 34 is fastened to the steel pipe beam 35 by a fastener, which further reduces the construction time.
Referring to fig. 1 to 3, the bottom retaining wall is exemplarily made of concrete backfill between an earth slope and a single-sided timber formwork support 21, and the top retaining wall is made of cast concrete in a double-sided timber formwork support 24, thereby ensuring simple construction of the bottom retaining wall and having a firm structure, and effectively reducing the amount of concrete used for the top retaining wall.
The foregoing is merely a preferred embodiment of the present invention, and it should be noted that modifications and substitutions can be made by those skilled in the art without departing from the technical principles of the present invention, and these modifications and substitutions should also be considered as being within the scope of the present invention.

Claims (7)

1. The construction process of the large-thickness variable-section raft foundation is characterized by comprising the following steps of:
firstly, after excavating earthwork, constructing a bedding layer, vertically arranging a single-sided wood formwork support when constructing the bedding layer at the position with the base height difference being more than 0.5m and less than 2m, arranging a steel pipe diagonal bracing between the inner side of the single-sided wood formwork support and the bedding layer, and then carrying out concrete backfilling between the outer side of the single-sided wood formwork support and a side slope to form a bottom retaining wall;
setting up a single-sided wood template support vertically when a cushion layer at the position with the substrate height difference larger than 2m is constructed, setting up a steel pipe diagonal brace between the inner side of the single-sided wood template support and the cushion layer, setting up a top layer retaining wall steel bar on the cushion layer at the outer side of the single-sided wood template support, then carrying out concrete backfilling between the outer side of the single-sided wood template support and the earthwork to form a bottom layer retaining wall, setting up a double-sided wood template support on the top layer retaining wall steel bar extending out of the bottom layer retaining wall, setting up a steel pipe diagonal brace between one side of the double-sided wood template support and a side slope, setting up a steel pipe diagonal brace between one side of the double-sided wood template support and the cushion layer, and casting concrete into the double-sided wood template support to form the top layer retaining wall;
arranging concrete cushion blocks 31 on the inner bottom surface of the raft foundation in a matrix distribution manner, arranging longitudinal and transverse lower-layer steel bars on the concrete cushion blocks, binding, welding a bottom support on the lower-layer steel bars in a distribution manner, arranging steel pipe upright posts at the upper ends of the bottom supports, arranging one or more layers of spaced steel pipe cross beams in the middle of the steel pipe upright posts, binding middle-layer steel bars correspondingly, and arranging one layer of steel pipe cross beams at the top of the steel pipe upright posts, binding upper-layer steel bars correspondingly to form a raft steel bar steel pipe support frame;
and fourthly, performing concrete pouring on the pits in the inner pits of the raft foundation to form a first concrete pouring area, and performing concrete pouring on the pits on the upper part in the raft foundation to form a second concrete pouring area, thereby completing the layered forming of the raft foundation.
2. The large-thickness variable-section raft foundation construction process as claimed in claim 1, wherein: in the first step and the second step, short steel bars for fixedly connecting the steel pipe diagonal braces are pre-buried on the cushion layer at intervals.
3. The large-thickness variable-section raft foundation construction process as claimed in claim 1, wherein: in the first step and the second step, two steel pipe diagonal braces are connected with the single-sided wood template support, and five steel pipe diagonal braces are connected with the double-sided wood template support and the steel pipe top braces respectively.
4. The large-thickness variable-section raft foundation construction process as claimed in claim 1, wherein: in the second step, the double-sided wood template support comprises a red template, a wood column vertical edge, a double-steel-pipe transverse edge and a high-strength opposite-pull screw rod.
5. The large-thickness variable-section raft foundation construction process as claimed in claim 1, wherein: in the third step, the bottom support is shaped like a Chinese character 'Tu', the bottom support is connected with the lower layer steel bar in a spot welding mode, and the lower end of the steel pipe stand column is sleeved with the upper end of the bottom support.
6. The large-thickness variable-section raft foundation construction process as claimed in claim 1, wherein: in the third step, the steel pipe column is fastened with the steel pipe beam through a fastener, and oil and rust removal treatment is carried out on the steel pipe column, the steel pipe beam and the fastener.
7. The large-thickness variable-section raft foundation construction process as claimed in claim 1, wherein: in the fourth step, a water stop steel plate is arranged on the inner side wall of the raft foundation.
CN202310295046.XA 2023-03-23 Construction process of large-thickness variable-section raft foundation Active CN116163331B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310295046.XA CN116163331B (en) 2023-03-23 Construction process of large-thickness variable-section raft foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310295046.XA CN116163331B (en) 2023-03-23 Construction process of large-thickness variable-section raft foundation

Publications (2)

Publication Number Publication Date
CN116163331A true CN116163331A (en) 2023-05-26
CN116163331B CN116163331B (en) 2024-05-14

Family

ID=

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103572784A (en) * 2013-11-21 2014-02-12 中建二局第三建筑工程有限公司 Supporting system and construction method of post-cast strip template of super-thick raft
CN203795450U (en) * 2014-05-05 2014-08-27 上海绿地建设(集团)有限公司 Raft foundation steel bar binding supporting structure
WO2014139252A1 (en) * 2013-03-15 2014-09-18 中国十七冶集团有限公司 Method for constructing large raft foundation in high-temperature environment
WO2017152674A1 (en) * 2016-03-10 2017-09-14 何发林 Underground engineering waterproofing structure
CN215858626U (en) * 2021-08-12 2022-02-18 中国建筑第四工程局有限公司 Super thick raft foundation multilayer steel bar support frame

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014139252A1 (en) * 2013-03-15 2014-09-18 中国十七冶集团有限公司 Method for constructing large raft foundation in high-temperature environment
CN103572784A (en) * 2013-11-21 2014-02-12 中建二局第三建筑工程有限公司 Supporting system and construction method of post-cast strip template of super-thick raft
CN203795450U (en) * 2014-05-05 2014-08-27 上海绿地建设(集团)有限公司 Raft foundation steel bar binding supporting structure
WO2017152674A1 (en) * 2016-03-10 2017-09-14 何发林 Underground engineering waterproofing structure
CN215858626U (en) * 2021-08-12 2022-02-18 中国建筑第四工程局有限公司 Super thick raft foundation multilayer steel bar support frame

Similar Documents

Publication Publication Date Title
CN108005084A (en) The supporting of deep basal pit combined type and construction method
CN110777806B (en) Multi-connecting-rod plane frame permanent supporting structure and construction process thereof
CN116163331B (en) Construction process of large-thickness variable-section raft foundation
CN211340800U (en) Super dark foundation ditch earthwork excavation platform structure
CN219175307U (en) Large-thickness variable-section raft foundation structure
CN116163331A (en) Construction process of large-thickness variable-section raft foundation
CN207728018U (en) The building structure of skyscraper is built suitable for tier building set
CN110847188A (en) Ultra-deep foundation pit earth excavation platform structure and construction method thereof
CN206337566U (en) Foundation ditch vertical prestressing anchor pole supporting construction
CN216405155U (en) Box culvert construction is with template board of being convenient for pour
CN112095659B (en) Recyclable single-side formwork system and construction method
CN213773339U (en) Tubular pile with large bearing capacity
CN115506405A (en) Semi-inverse construction method for basement structure of ultra-large deep foundation pit
CN214219929U (en) Unilateral formwork reinforced structure of basement outer wall
CN213508572U (en) Piping lane supporting construction
CN107916798A (en) The building structure of skyscraper is built suitable for tier building set
CN210140833U (en) A single collateral branch mode structure of bailey piece for bridge and culvert engineering
CN114000514A (en) Construction method of deep foundation pit angle support pile column component
CN219364635U (en) Combined supporting structure for replacing support by utilizing basement structure and steel diagonal support
CN218436999U (en) Strong permeable stratum rotary excavating drilling bored concrete pile
CN115198787B (en) Steel tube column type tower crane foundation and construction method thereof, and cover-excavation reverse construction method
CN115324106B (en) Construction method for optimizing intermittent stopping point of synchronous reverse construction technology
CN213867917U (en) Connection structure of overhanging well and pool with overhanging well
CN215759042U (en) Batter pile bearing structure
CN219508592U (en) Lattice column reinforcing connection structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant