CN116104298A - Tripod jacking formwork platform for elevator shaft construction and construction method - Google Patents

Tripod jacking formwork platform for elevator shaft construction and construction method Download PDF

Info

Publication number
CN116104298A
CN116104298A CN202310062967.1A CN202310062967A CN116104298A CN 116104298 A CN116104298 A CN 116104298A CN 202310062967 A CN202310062967 A CN 202310062967A CN 116104298 A CN116104298 A CN 116104298A
Authority
CN
China
Prior art keywords
elevator shaft
supporting mechanism
tripod
construction
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310062967.1A
Other languages
Chinese (zh)
Inventor
冯勇慧
骆军
辛钰林
张运
李�根
赵涛
白杨
赵莉
董文燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Seventh Construction Group Co ltd
Original Assignee
Gansu Seventh Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Seventh Construction Group Co ltd filed Critical Gansu Seventh Construction Group Co ltd
Priority to CN202310062967.1A priority Critical patent/CN116104298A/en
Publication of CN116104298A publication Critical patent/CN116104298A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B50/00Energy efficient technologies in elevators, escalators and moving walkways, e.g. energy saving or recuperation technologies

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

The invention discloses a tripod jacking formwork platform for elevator shaft construction, which comprises: the lower tripod supporting mechanism is arranged on the wall of the elevator shaft; the lifting mechanism is arranged on the lower tripod supporting mechanism; the upper tripod supporting mechanism is arranged on the lifting mechanism; the template and hanging frame system is arranged on the upper tripod supporting mechanism and used for installing and fixing the template on the elevator shaft pouring operation position to perform main body pouring; the lower tripod supporting mechanism is arranged at the bottom layer of the elevator shaft, the lifting mechanism lifts the upper tripod supporting mechanism, the template and the hanging frame system enter an upper operation area, and the template and the hanging frame system are used for pouring the elevator shaft. The invention also discloses an elevator shaft construction method, which comprises the following steps: step one, constructing an N+1 layer elevator shaft; step two, lifting the supporting mechanism of the upper tripod; step three, lifting the lower tripod supporting mechanism; fourthly, constructing an N+2 layer elevator shaft; the above steps are cycled.

Description

一种用于电梯井施工的三角架顶升模架平台及施工方法A tripod jacking formwork platform and construction method for elevator shaft construction

技术领域technical field

本发明涉及建筑施工设备技术领域,特别涉及一种用于电梯井施工的三角架顶升模架平台及施工方法。The invention relates to the technical field of building construction equipment, in particular to a tripod jacking formwork platform and a construction method for elevator shaft construction.

背景技术Background technique

随着城市建设的不断发展,高层及超高层建筑越来越多,在高层或超高层建筑施工中,对于电梯井的施工无疑是一个难点,首先,由于电梯井上下贯通,中间没有水平层,无法直接在本层支设模板及其支承架,如果从最底层就开始搭设,不仅成本高,而且由于架体超高,安全性要求更高,技术难度大;第二,由于电梯井空间狭小,工人在狭小的环境中进行模板及其支架的搭设,操作过程较为困难,造成施工效率较低;第三,为了设置水平支点,一般会在墙上留洞,需要后期修补,不仅增加人工投入,还可能造成一定的质量隐患;第四,施工人员高处作业,缺少落脚点;第五,需要单独设置临边、洞口防护;第六。模板的安装过程需要塔吊配合,占用大型机械的有效工作时间。With the continuous development of urban construction, there are more and more high-rise and super high-rise buildings. In the construction of high-rise or super high-rise buildings, the construction of elevator shafts is undoubtedly a difficulty. It is impossible to directly support the formwork and its supporting frame on this floor. If it is erected from the bottom layer, not only the cost is high, but also due to the super high frame body, higher safety requirements and high technical difficulty; second, due to the small space of the elevator shaft , workers erect formwork and its brackets in a narrow environment, the operation process is more difficult, resulting in low construction efficiency; third, in order to set up horizontal fulcrums, holes are generally left on the wall, which requires later repairs, which not only increases labor input , may also cause certain quality hidden dangers; fourth, construction personnel work at heights and lack footholds; fifth, need to separately set up edge and hole protection; sixth. The installation process of the formwork requires the cooperation of the tower crane, which takes up the effective working time of large machinery.

基于以上原因,工程技术人员在施工过程中出现了用于电梯井施工的三角架施工平台,在一定程度上解决了电梯井施工的难题,但是,该三角架平台依然存在需要塔吊配合,起吊过程中需要三角架倾斜,出现重心偏移,需要人工调整,且调整过程存在较大的安全隐患等问题。Based on the above reasons, engineers and technicians appeared a tripod construction platform for elevator shaft construction during the construction process, which solved the difficult problem of elevator shaft construction to a certain extent. However, the tripod platform still needs the cooperation of tower cranes. In the process, the tripod needs to be tilted, the center of gravity is shifted, manual adjustment is required, and there are major safety hazards in the adjustment process.

发明内容Contents of the invention

针对上述问题,本发明提供了一种用于电梯井施工的三角架顶升模架平台及施工方法。In view of the above problems, the present invention provides a tripod jacking formwork platform and a construction method for elevator shaft construction.

为了实现上述目的,本发明的技术方案具体如下:In order to achieve the above object, the technical solution of the present invention is specifically as follows:

一种用于电梯井施工的三角架顶升模架平台,包括:A tripod jacking formwork platform for elevator shaft construction, comprising:

下三角架支撑机构,安装在电梯井井壁上;The lower tripod support mechanism is installed on the wall of the elevator shaft;

升降机构,设置在下三角架支撑机构上;The lifting mechanism is arranged on the lower tripod support mechanism;

上三角架支撑机构,设置在升降机构上;The upper tripod support mechanism is arranged on the lifting mechanism;

模板及挂架系统,设置在上三角架支撑机构上,用于将模板安装固定在电梯井浇筑作业位置上,进行主体浇筑;Formwork and hanger system, set on the upper tripod support mechanism, used to install and fix the formwork on the elevator shaft pouring operation position for main body pouring;

其中,下三角架支撑机构设置在电梯井底层,升降机构将上三角架支撑机构进行升举,使得模板及挂架系统进入上层作业区,利用模板及挂架系统进行电梯井浇筑。Among them, the lower tripod support mechanism is set at the bottom of the elevator shaft, and the lifting mechanism lifts the upper tripod support mechanism, so that the formwork and hanger system enters the upper working area, and the elevator shaft is poured using the formwork and hanger system.

所述下三角架支撑机构和上三角架支撑机构结构相同,所述下三角架支撑机构包括:The lower tripod support mechanism and the upper tripod support mechanism have the same structure, and the lower tripod support mechanism includes:

两个平行设置的型钢斜梁;Two profiled steel oblique beams arranged in parallel;

两个平行设置的立柱,其底部与两个型钢斜梁底部两两对应相互固定连接,其顶部与两个型钢斜梁顶部在同一水平面上,并且,立柱顶部与型钢斜梁顶部通过水平横梁相互连接,水平横梁上通过设置横向水平钢梁和纵向次梁形成水平安装面;Two columns arranged in parallel, the bottoms of which are fixedly connected with the bottoms of the two shaped steel slanted beams, and the tops of which are on the same level as the tops of the two shaped steel slanted beams, and the tops of the columns and the tops of the shaped steel slanted beams are interconnected by horizontal beams Connection, horizontal steel beams and longitudinal secondary beams are set on the horizontal beams to form a horizontal installation surface;

水平钢板,铺设在水平安装面上。The horizontal steel plate is laid on the horizontal installation surface.

所述型钢斜梁底部与电梯井井壁的接触处设置有自弹伸脚,便于下三角架支撑机构和上三角架支撑机构上升时,与电梯井井壁的顶紧与脱离。The contact between the bottom of the profiled steel inclined beam and the elevator shaft wall is provided with self-elastic stretching feet, which are convenient for the lower tripod support mechanism and the upper tripod support mechanism to be tightened and separated from the elevator shaft shaft wall when they rise.

所述升降机构为剪叉式升降机。The lifting mechanism is a scissor lift.

所述模板及挂架系统包括:The formwork and hanger system includes:

挂模支架,竖直设置在上三角架支撑机构上;The mold hanging bracket is vertically arranged on the upper tripod support mechanism;

电梯井筒子模,套装在挂模支架外部,且其顶部悬挂在挂模支架上。The shaft mold of the elevator shaft is set on the outside of the formwork support, and its top is suspended on the formwork support.

所述挂模支架包括:The hanging mold support includes:

格构柱;lattice column;

伸臂梁,设置在格构柱顶部,并通过钢丝绳与电梯井筒子模顶部连接。The outrigger beam is set on the top of the lattice column and connected to the top of the elevator shaft subform by a steel wire rope.

本发明还提供了一种电梯井施工方法,其包括以下步骤:The present invention also provides a kind of elevator shaft construction method, it comprises the following steps:

步骤一、N+1层电梯井施工Step 1, N+1 floor elevator shaft construction

初始状态,已完成N层及以下的电梯井施工,按要求安装平台,使下三角架支撑机构位于N-1层,上三角架支撑机构及升降机位于N层,模板及挂架系统位于N+1层,并将各部位按要求连接牢固;开始进行N+1层的电梯井施工,完成N+1层的钢筋绑扎,模板安装,混凝土浇筑,且混凝土达到规定的强度,拆除电梯井筒子模的横楞,电梯井筒子模收缩,使模板与电梯井混凝土壁分离;In the initial state, the elevator shaft construction on and below the N floor has been completed, and the platform is installed according to the requirements, so that the lower tripod support mechanism is located on the N-1 floor, the upper tripod support mechanism and the elevator are located on the N floor, and the formwork and hanger system is located on the N+ 1st floor, and connect all parts firmly as required; start the construction of the elevator shaft on the N+1 floor, complete the binding of steel bars on the N+1 floor, formwork installation, concrete pouring, and the concrete reaches the specified strength, and remove the elevator shaft shaft formwork The horizontal corrugation of the elevator shaft mold shrinks, so that the formwork is separated from the concrete wall of the elevator shaft;

步骤二、顶升上三角架支撑机构Step 2. Lift the upper tripod support mechanism

启动电机,电机旋转,通过减速机带动螺杆正向低速旋转,进一步带动剪叉式支撑架伸展,顶推上三角架支撑机构上升,当上三角架底部上升至井道区域时,在井道壁的挤压下,自弹伸脚缩进,不阻碍上三角架支撑机构顺利上升,当自弹伸脚通过井道区域,到达N+1层电梯门区域时,挤压力消失,自弹伸脚弹出,此时,上三角架支撑机构已经到达N+1层,电机反向旋转,剪叉式支撑架收缩,上三角架支撑机构下降,使自弹伸脚落实到N+1层,完成上三角架支撑机构的顶升作业;Start the motor, the motor rotates, the reducer drives the screw to rotate forward at low speed, and further drives the scissor support frame to extend, pushing the upper tripod support mechanism up. Press down, and the self-elastic stretching feet will retract without hindering the smooth rise of the upper tripod support mechanism. When the self-elastic stretching legs pass through the hoistway area and reach the elevator door area on the N+1 floor, the squeezing force disappears, and the self-elastic stretching legs pop out. At this time, the upper tripod support mechanism has reached the N+1 floor, the motor rotates in the opposite direction, the scissor support frame shrinks, and the upper tripod support mechanism descends, so that the self-elastic stretching feet are placed on the N+1 floor, and the upper tripod is completed. Jacking operation of supporting mechanism;

步骤三、提升下三角架支撑机构Step 3: Lift the lower tripod support mechanism

上三角架支撑机构落实后,继续反向旋转螺杆,剪叉式支撑架进一步收缩,此时,由于上三角架支撑机构已经固定,因此,可将下三角架支撑机构提起,当下三角架支撑机构底部提升至井道区域时,在井道壁的挤压下,自弹伸脚缩进,不阻碍下三角架支撑机构顺利提升,当自弹伸脚通过井道区域,到达N层电梯门区域时,挤压力消失,自弹伸脚弹出,此时,下三角架支撑机构已经到达N层,电机正向旋转,剪叉式支撑架伸展,下三角架支撑机构下降,使自弹伸脚落实到N层,完成下三角架支撑机构的提升作业;After the upper tripod support mechanism is implemented, continue to reversely rotate the screw rod, and the scissor support frame will shrink further. At this time, since the upper tripod support mechanism has been fixed, the lower tripod support mechanism can be lifted, and the lower tripod support mechanism When the bottom is lifted to the hoistway area, under the extrusion of the hoistway wall, the self-elastic stretching legs are retracted, which does not hinder the smooth lifting of the lower tripod support mechanism. The pressure disappears, and the self-elastic stretching foot pops up. At this time, the lower tripod support mechanism has reached the N floor, the motor rotates forward, the scissor support frame is extended, and the lower tripod support mechanism is lowered, so that the self-elastic stretching foot is implemented to N Layer, to complete the lifting operation of the lower tripod support mechanism;

步骤四、N+2层电梯井施工Step 4, N+2 floor elevator shaft construction

此时,三角架顶升模架平台已完成新一层电梯井施工的顶升作业,下三角架支撑机构位于N层,上三角架支撑机构及剪叉式升降机4位于N+1层,模板及挂架系统位于N+2层,即可开始进行N+2层的电梯井施工;At this time, the tripod jacking formwork platform has completed the jacking operation of the elevator shaft construction on the new floor, the lower tripod support mechanism is located on the N floor, the upper tripod support mechanism and the scissor lift 4 are located on the N+1 floor, and the formwork And the hanger system is located on the N+2 floor, and the elevator shaft construction on the N+2 floor can be started;

循环以上步骤,完成整栋楼的施工。Repeat the above steps to complete the construction of the whole building.

与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:

1、本发明在新高层建筑电梯井施工时,不需要再依靠塔吊的配合,就能独立完成电梯井混凝土施工的全部施工任务,释放了塔吊的有效工作时间,提高了施工效率。1. When the present invention is used in the construction of elevator shafts in new high-rise buildings, it does not need to rely on the cooperation of tower cranes, and can independently complete all the construction tasks of the concrete construction of elevator shafts, releasing the effective working time of tower cranes and improving construction efficiency.

2、本发明结构简单,操作简便,机械化程度高,为电梯井混凝土工程提供了可靠的施工平台,采用螺杆控制剪叉式支撑架,由于螺杆的自锁性能,顶升及提升过程安全可靠。2. The invention has the advantages of simple structure, easy operation and high degree of mechanization, and provides a reliable construction platform for the concrete engineering of the elevator shaft. The scissor support frame is controlled by the screw rod. Due to the self-locking performance of the screw rod, the jacking and lifting process is safe and reliable.

3、由于有了该平台,模板支设施工时无需将模板完全拆除,也无需单另设置放置模板的临时平台,仅需将模板与混凝土壁微微脱离,即可整体升移至上一层进行施工,节约了模板施工的工作强度和作业时间。3. Thanks to this platform, it is not necessary to completely dismantle the formwork during construction of the formwork support, and it is not necessary to separately set up a temporary platform for placing the formwork. It only needs to slightly separate the formwork from the concrete wall, and the whole can be lifted to the upper floor for construction. The work intensity and operation time of formwork construction are saved.

附图说明Description of drawings

图1是本发明的结构示意图。Fig. 1 is a structural schematic diagram of the present invention.

图2是本发明的爆炸图。Figure 2 is an exploded view of the present invention.

图3是上三角架支撑机构的结构示意图。Fig. 3 is a structural schematic diagram of the upper tripod support mechanism.

图4是升降机的连接示意图。Figure 4 is a schematic diagram of the connection of the elevator.

图5是模板及挂架系统的爆炸图。Figure 5 is an exploded view of the formwork and hanger system.

图6是本发明施工方法作业时的初始状态示意图。Fig. 6 is a schematic diagram of the initial state when the construction method of the present invention is in operation.

图7是本发明施工方法作业时的本层混凝土浇筑完成示意图。Fig. 7 is a schematic diagram of the completion of concrete pouring in this layer when the construction method of the present invention is in operation.

图8是本发明施工方法作业时的顶升上三角架支撑机构示意图。Fig. 8 is a schematic diagram of the jacking upper tripod support mechanism during operation of the construction method of the present invention.

图9是本发明施工方法作业时的上三角架支撑机构及模架顶升到位示意图。Fig. 9 is a schematic diagram of the upper tripod support mechanism and the formwork being lifted into place during the operation of the construction method of the present invention.

图10是本发明施工方法作业时的提升下三角架支撑机构示意图。Fig. 10 is a schematic diagram of the tripod support mechanism under the lifting during operation of the construction method of the present invention.

图11是本发明施工方法作业时的顶升作业完成示意图。Fig. 11 is a schematic diagram of the completion of the jacking operation during the operation of the construction method of the present invention.

图12是本发明施工方法流程图。Fig. 12 is a flow chart of the construction method of the present invention.

其中, 1、上三角架支撑机构;2、下三角架支撑机构;3、自弹伸脚;4、升降机:401、电动机;402、减速机;403、螺杆;404;剪叉式支撑架;5、模板及挂架系统:501、电梯井筒子模;502挂模支架:521格构柱;522、伸臂梁。Among them, 1. Upper tripod support mechanism; 2. Lower tripod support mechanism; 3. Self-elastic stretching feet; 4. Lift: 401, motor; 402, reducer; 403, screw; 404; scissors support frame; 5. Formwork and hanger system: 501, elevator shaft sub-form; 502 hanging formwork support: 521 lattice column; 522, outrigger beam.

具体实施方式Detailed ways

为使本发明的目的、技术方案和优点更加清楚明了,下面结合具体实施方式并参照附图,对本发明进一步详细说明。应该理解,这些描述只是示例性的,而并非要限制本发明的范围。此外,在以下说明中,省略了对公知结构和技术的描述,以避免不必要地混淆本发明的概念。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in combination with specific embodiments and with reference to the accompanying drawings. It should be understood that these descriptions are exemplary only, and are not intended to limit the scope of the present invention. Also, in the following description, descriptions of well-known structures and techniques are omitted to avoid unnecessarily obscuring the concept of the present invention.

如图1和图2所示,一种用于电梯井施工的三角架顶升模架平台,包括:下三角架支撑机构2,安装在电梯井井壁上;升降机构4,设置在下三角架支撑机构2上;上三角架支撑机构1,设置在升降机构4上;模板及挂架系统5,设置在上三角架支撑机构1上,用于将模板安装固定在电梯井浇筑作业位置上,进行主体浇筑;其中,下三角架支撑机构2设置在电梯井底层,升降机构4将上三角架支撑机构1进行升举,使得模板及挂架系统5进入上层作业区,利用模板及挂架系统5进行电梯井浇筑。As shown in Figures 1 and 2, a tripod jacking formwork platform for elevator shaft construction includes: a lower tripod support mechanism 2, which is installed on the elevator shaft wall; a lifting mechanism 4, which is arranged on the lower tripod On the support mechanism 2; the upper tripod support mechanism 1 is arranged on the lifting mechanism 4; the formwork and hanger system 5 is arranged on the upper tripod support mechanism 1, which is used to install and fix the formwork on the elevator shaft pouring operation position, The main body is poured; among them, the lower tripod support mechanism 2 is set at the bottom of the elevator shaft, and the lifting mechanism 4 lifts the upper tripod support mechanism 1, so that the formwork and hanger system 5 enters the upper working area, and the formwork and hanger system is used to 5 Carry out elevator shaft pouring.

如图2和图3所示,下三角架支撑机构2和上三角架支撑机构1结构相同,所述下三角架支撑机构2包括:两个平行设置的型钢斜梁;两个平行设置的立柱,其底部与两个型钢斜梁底部两两对应相互固定连接,其顶部与两个型钢斜梁顶部在同一水平面上,并且,立柱顶部与型钢斜梁顶部通过水平横梁相互连接,水平横梁上通过设置横向水平钢梁和纵向次梁形成水平安装面;水平钢板,铺设在水平安装面上。As shown in Figure 2 and Figure 3, the lower tripod support mechanism 2 has the same structure as the upper tripod support mechanism 1, and the lower tripod support mechanism 2 includes: two parallel profiled steel oblique beams; two parallel vertical columns , the bottom of which is fixedly connected to the bottom of the two shaped steel inclined beams in pairs, and its top is on the same level as the top of the two shaped steel inclined beams, and the top of the column and the top of the shaped steel inclined beams are connected to each other through a horizontal beam, and the horizontal beam passes through Set horizontal horizontal steel beams and longitudinal secondary beams to form a horizontal installation surface; horizontal steel plates are laid on the horizontal installation surface.

如图2所示,型钢斜梁底部与电梯井井壁的接触处设置有自弹伸脚3,便于下三角架支撑机构2和上三角架支撑机构1上升时,与电梯井井壁的顶紧与脱离。As shown in Figure 2, self-elastic stretching feet 3 are provided at the contact between the bottom of the shaped steel inclined beam and the elevator shaft wall, so that when the lower tripod support mechanism 2 and the upper tripod support mechanism 1 rise, they will contact with the top of the elevator shaft wall. Tight and loose.

如图2和图4所示,升降机构4为剪叉式升降机。As shown in Figures 2 and 4, the lifting mechanism 4 is a scissor lift.

如图2和图5所示,模板及挂架系统5包括:挂模支架502,竖直设置在上三角架支撑机构1上;电梯井筒子模501,套装在挂模支架502外部,且其顶部悬挂在挂模支架502上。As shown in Fig. 2 and Fig. 5, the formwork and hanger system 5 includes: hanging formwork bracket 502, which is vertically arranged on the upper tripod support mechanism 1; The top is suspended on the hanging formwork support 502.

如图5所示,挂模支架502包括:格构柱521;伸臂梁522,设置在格构柱521顶部,并通过钢丝绳与电梯井筒子模501顶部连接。As shown in FIG. 5 , the formwork support 502 includes: a lattice column 521 ; an outrigger beam 522 is arranged on the top of the lattice column 521 and connected to the top of the elevator shaft subform 501 through a wire rope.

如图6至图11以及图12所示,本发明还提供了一种电梯井施工方法,其包括以下步骤:As shown in Fig. 6 to Fig. 11 and Fig. 12, the present invention also provides an elevator shaft construction method, which includes the following steps:

步骤一、N+1层电梯井施工Step 1, N+1 floor elevator shaft construction

初始状态,已完成N层及以下的电梯井施工,按要求安装平台,使下三角架支撑机构2位于N-1层,上三角架支撑机构1及升降机4位于N层,模板及挂架系统5位于N+1层,并将各部位按要求连接牢固;开始进行N+1层的电梯井施工,完成N+1层的钢筋绑扎,模板安装,混凝土浇筑,且混凝土达到规定的强度,拆除电梯井筒子模501的横楞,电梯井筒子模501收缩,使模板与电梯井混凝土壁分离;In the initial state, the elevator shaft construction on and below the N floor has been completed, and the platform is installed according to the requirements, so that the lower tripod support mechanism 2 is located on the N-1 floor, the upper tripod support mechanism 1 and the elevator 4 are located on the N floor, and the formwork and hanger system 5 Located on the N+1 floor, and connect all parts firmly according to the requirements; start the elevator shaft construction on the N+1 floor, complete the steel bar binding on the N+1 floor, formwork installation, concrete pouring, and the concrete reaches the specified strength, demolish The horizontal corrugation of the elevator shaft sub-form 501, the elevator shaft sub-form 501 shrinks, so that the formwork is separated from the concrete wall of the elevator shaft;

步骤二、顶升上三角架支撑机构Step 2. Lift the upper tripod support mechanism

启动电机401,电机旋转,通过减速机402带动螺杆403正向低速旋转,进一步带动剪叉式支撑架404伸展,顶推上三角架支撑机构1上升,当上三角架底部上升至井道区域时,在井道壁的挤压下,自弹伸脚3缩进,不阻碍上三角架支撑机构1顺利上升,当自弹伸脚3通过井道区域,到达N+1层电梯门区域时,挤压力消失,自弹伸脚3弹出,此时,上三角架支撑机构1已经到达N+1层,电机反向旋转,剪叉式支撑架404收缩,上三角架支撑机构1下降,使自弹伸脚3落实到N+1层,完成上三角架支撑机构1的顶升作业;Start the motor 401, the motor rotates, the reducer 402 drives the screw 403 to rotate forward at a low speed, further drives the scissor support frame 404 to extend, and pushes the upper tripod support mechanism 1 to rise. When the bottom of the upper tripod rises to the hoistway area, Under the extrusion of the hoistway wall, the self-elastic extension foot 3 retracts without hindering the smooth rise of the upper tripod support mechanism 1. When the self-elastic extension foot 3 passes through the hoistway area and reaches the elevator door area on the N+1 floor, the extrusion force disappears, and the self-elastic stretching foot 3 pops up. At this time, the upper tripod support mechanism 1 has reached the N+1 floor, the motor rotates in reverse, the scissor type support frame 404 shrinks, and the upper tripod support mechanism 1 descends, so that the self-elastic stretch The foot 3 is implemented to the N+1 floor, and the jacking operation of the upper tripod support mechanism 1 is completed;

步骤三、提升下三角架支撑机构Step 3: Lift the lower tripod support mechanism

上三角架支撑机构1落实后,继续反向旋转螺杆403,剪叉式支撑架404进一步收缩,此时,由于上三角架支撑机构1已经固定,因此,可将下三角架支撑机构2提起,当下三角架支撑机构2底部提升至井道区域时,在井道壁的挤压下,自弹伸脚3缩进,不阻碍下三角架支撑机构2顺利提升,当自弹伸脚3通过井道区域,到达N层电梯门区域时,挤压力消失,自弹伸脚3弹出,此时,下三角架支撑机构2已经到达N层,电机401正向旋转,剪叉式支撑架404伸展,下三角架支撑机构2下降,使自弹伸脚3落实到N层,完成下三角架支撑机构2的提升作业;After the upper tripod support mechanism 1 is implemented, continue to reversely rotate the screw rod 403, and the scissors type support frame 404 will shrink further. At this time, since the upper tripod support mechanism 1 has been fixed, the lower tripod support mechanism 2 can be lifted. When the bottom of the lower tripod support mechanism 2 is lifted to the hoistway area, under the extrusion of the hoistway wall, the self-elastic extension foot 3 retracts, which does not hinder the smooth lifting of the lower tripod support mechanism 2. When the self-elastic extension foot 3 passes through the hoistway area, When reaching the elevator door area on the N floor, the extrusion force disappears, and the self-elastic stretching foot 3 pops up. At this time, the lower tripod support mechanism 2 has reached the N floor, the motor 401 rotates forward, the scissor support frame 404 stretches, and the lower triangle The frame support mechanism 2 descends, so that the self-elastic stretching feet 3 are implemented to the N floor, and the lifting operation of the lower tripod support mechanism 2 is completed;

步骤四、N+2层电梯井施工Step 4, N+2 floor elevator shaft construction

此时,三角架顶升模架平台已完成新一层电梯井施工的顶升作业,下三角架支撑机构2位于N层,上三角架支撑机构1及剪叉式升降机4位于N+1层,模板及挂架系统5位于N+2层,即可开始进行N+2层的电梯井施工;At this time, the tripod jacking formwork platform has completed the jacking operation of the elevator shaft construction on the new floor, the lower tripod support mechanism 2 is located on the N floor, the upper tripod support mechanism 1 and the scissor lift 4 are located on the N+1 floor , the formwork and hanger system 5 is located on the N+2 floor, and the elevator shaft construction on the N+2 floor can be started;

循环以上步骤,完成整栋楼的施工。Repeat the above steps to complete the construction of the whole building.

应当理解的是,本发明的上述具体实施方式仅仅用于示例性说明或解释本发明的原理,而不构成对本发明的限制。因此,在不偏离本发明的精神和范围的情况下所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。此外,本发明所附权利要求旨在涵盖落入所附权利要求范围和边界、或者这种范围和边界的等同形式内的全部变化和修改例。It should be understood that the above specific embodiments of the present invention are only used to illustrate or explain the principle of the present invention, and not to limit the present invention. Therefore, any modification, equivalent replacement, improvement, etc. made without departing from the spirit and scope of the present invention shall fall within the protection scope of the present invention. Furthermore, it is intended that the appended claims of the present invention embrace all changes and modifications that come within the scope and metesques of the appended claims, or equivalents of such scope and metes and bounds.

Claims (7)

1. A tripod jacking formwork platform for hoistway construction, comprising:
the lower tripod supporting mechanism (2) is arranged on the wall of the elevator shaft;
the lifting mechanism (4) is arranged on the lower tripod supporting mechanism (2);
the upper tripod supporting mechanism (1) is arranged on the lifting mechanism (4);
the template and hanging frame system (5) is arranged on the upper tripod supporting mechanism (1) and is used for installing and fixing the template at the elevator shaft pouring operation position to perform main body pouring;
the lower tripod supporting mechanism (2) is arranged at the bottom layer of the elevator shaft, the lifting mechanism (4) lifts the upper tripod supporting mechanism (1) so that the template and the hanging frame system (5) enter an upper operation area, and the template and the hanging frame system (5) are used for pouring the elevator shaft.
2. A tripod jacking formwork platform for use in hoistway construction as defined in claim 1, wherein: the lower tripod supporting mechanism (2) and the upper tripod supporting mechanism (1) are identical in structure, and the lower tripod supporting mechanism (2) comprises:
two profile steel inclined beams arranged in parallel;
the bottoms of the two parallel upright posts are fixedly connected with the bottoms of the two section steel inclined beams in a pairwise corresponding manner, the tops of the two upright posts and the tops of the two section steel inclined beams are on the same horizontal plane, the tops of the upright posts and the tops of the section steel inclined beams are connected with each other through horizontal cross beams, and the horizontal cross beams form a horizontal mounting surface through arranging horizontal steel beams and longitudinal secondary beams;
the horizontal steel plate is paved on the horizontal installation surface.
3. The tripod jacking formwork platform for the construction of the elevator shaft according to claim 2, wherein the contact part of the bottom of the profile steel inclined beam and the elevator shaft wall is provided with a self-bouncing extension foot (3) so as to be convenient for jacking and separating with the elevator shaft wall when the lower tripod supporting mechanism (2) and the upper tripod supporting mechanism (1) are lifted.
4. Tripod jacking formwork platform for use in elevator hoistway construction according to claim 1, characterized in that the lifting mechanism (4) is a scissor lift.
5. Tripod jacking formwork platform for use in elevator hoistway construction according to claim 1, characterized in that said formwork and pylon system (5) comprises:
the die hanging bracket (502) is vertically arranged on the upper tripod supporting mechanism (1);
the elevator shaft sub-die (501) is sleeved outside the die hanging bracket (502), and the top of the elevator shaft sub-die is hung on the die hanging bracket (502).
6. A tripod jacking formwork platform for elevator shaft construction as defined in claim 5, wherein said formwork hanging bracket (502) comprises:
-lattice columns (521);
and the cantilever beam (522) is arranged at the top of the lattice column (521) and is connected with the top of the elevator shaft sub-mold (501) through a steel wire rope.
7. The elevator shaft construction method is characterized by comprising the following steps of:
step one, construction of an N+1 layer elevator shaft
In an initial state, the construction of the elevator shaft of N layers and below is completed, a platform is installed according to the requirement, a lower tripod supporting mechanism (2) is positioned on the N-1 layer, an upper tripod supporting mechanism (1) and a lifter 4 are positioned on the N layer, a template and a hanging frame system (5) are positioned on the N+1 layer, and all parts are firmly connected according to the requirement; starting to perform construction of the elevator shaft of the layer N+1, finishing binding steel bars of the layer N+1, installing a template, pouring concrete, dismantling transverse edges of the elevator shaft sub-mould (501) and contracting the elevator shaft sub-mould (501) to separate the template from the elevator shaft concrete wall, wherein the concrete reaches the specified strength;
step two, lifting up tripod supporting mechanism
Starting a motor (401), driving a screw (403) to rotate at a low speed in a forward direction through a speed reducer (402), further driving a scissor type support frame (404) to extend, pushing an upper tripod support mechanism (1) to rise, retracting a self-ejecting foot (3) under extrusion of a well wall when the bottom of the upper tripod rises to the well area, preventing the upper tripod support mechanism (1) from rising smoothly, and enabling the extrusion force to disappear when the self-ejecting foot (3) passes through the well area and reaches an N+1 layer elevator door area, and ejecting the self-ejecting foot (3), wherein at the moment, the upper tripod support mechanism (1) reaches an N+1 layer, the motor rotates reversely, the scissor type support frame (404) is contracted, and the upper tripod support mechanism (1) descends, so that the self-ejecting foot (3) is enabled to be in an N+1 layer, and the jacking operation of the upper tripod support mechanism (1) is completed;
step three, lifting lower tripod supporting mechanism
After the upper tripod supporting mechanism (1) is implemented, the screw (403) is continuously rotated in the opposite direction, the scissor type supporting frame (404) is further contracted, at this time, because the upper tripod supporting mechanism (1) is fixed, the lower tripod supporting mechanism (2) can be lifted, when the bottom of the lower tripod supporting mechanism (2) is lifted to a well region, under the extrusion of the well wall, the self-bouncing foot (3) is retracted, the lower tripod supporting mechanism (2) is not blocked from being smoothly lifted, when the self-bouncing foot (3) passes through the well region and reaches an N-layer elevator door region, the extrusion force disappears, the self-bouncing foot (3) pops out, at the moment, the lower tripod supporting mechanism (2) reaches an N layer, the motor (401) rotates positively, the scissor type supporting frame (404) stretches, the lower tripod supporting mechanism (2) descends, the self-bouncing foot (3) is enabled to be implemented to the N layer, and the lifting operation of the lower tripod supporting mechanism (2) is completed;
step four, construction of N+2 layer elevator shaft
At this time, the tripod jacking mould frame platform has completed the jacking operation of the new layer of elevator shaft construction, the lower tripod supporting mechanism (2) is positioned on the N layer, the upper tripod supporting mechanism (1) and the scissor fork type lifter (4) are positioned on the N+1 layer, the mould plate and the hanging frame system (5) are positioned on the N+2 layer, and the elevator shaft construction of the N+2 layer can be started;
and (5) circulating the steps to finish the construction of the whole building.
CN202310062967.1A 2023-01-17 2023-01-17 Tripod jacking formwork platform for elevator shaft construction and construction method Pending CN116104298A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310062967.1A CN116104298A (en) 2023-01-17 2023-01-17 Tripod jacking formwork platform for elevator shaft construction and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310062967.1A CN116104298A (en) 2023-01-17 2023-01-17 Tripod jacking formwork platform for elevator shaft construction and construction method

Publications (1)

Publication Number Publication Date
CN116104298A true CN116104298A (en) 2023-05-12

Family

ID=86255703

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310062967.1A Pending CN116104298A (en) 2023-01-17 2023-01-17 Tripod jacking formwork platform for elevator shaft construction and construction method

Country Status (1)

Country Link
CN (1) CN116104298A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2025083616A1 (en) * 2023-10-20 2025-04-24 Gregory John Neighbours Self climbing jump form for high rise structures

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102661039A (en) * 2012-05-11 2012-09-12 上海建工集团股份有限公司 Drum frame supporting power built-in integrated jacking steel platform formwork system and construction method
CN205296803U (en) * 2015-12-28 2016-06-08 中建八局第二建设有限公司 Elevator automatic lifting operation panel
CN108979112A (en) * 2018-08-23 2018-12-11 中国建筑第二工程局有限公司 Elevator shaft multifunctional operating platform system and construction method thereof
CN111155754A (en) * 2020-01-08 2020-05-15 甘肃建投建设有限公司 Automatic elevator shaft jacking platform and using method thereof
CN214462415U (en) * 2021-01-04 2021-10-22 云南建投建筑机械有限公司 Elevator shaft construction protection and template automatic lifting device
US20220024727A1 (en) * 2018-12-18 2022-01-27 Inventio Ag Method for operating a construction site device and construction site device
CN218912242U (en) * 2023-01-17 2023-04-25 甘肃第七建设集团股份有限公司 Tripod extension jacking formwork platform for elevator shaft construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102661039A (en) * 2012-05-11 2012-09-12 上海建工集团股份有限公司 Drum frame supporting power built-in integrated jacking steel platform formwork system and construction method
CN205296803U (en) * 2015-12-28 2016-06-08 中建八局第二建设有限公司 Elevator automatic lifting operation panel
CN108979112A (en) * 2018-08-23 2018-12-11 中国建筑第二工程局有限公司 Elevator shaft multifunctional operating platform system and construction method thereof
US20220024727A1 (en) * 2018-12-18 2022-01-27 Inventio Ag Method for operating a construction site device and construction site device
CN111155754A (en) * 2020-01-08 2020-05-15 甘肃建投建设有限公司 Automatic elevator shaft jacking platform and using method thereof
CN214462415U (en) * 2021-01-04 2021-10-22 云南建投建筑机械有限公司 Elevator shaft construction protection and template automatic lifting device
CN218912242U (en) * 2023-01-17 2023-04-25 甘肃第七建设集团股份有限公司 Tripod extension jacking formwork platform for elevator shaft construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2025083616A1 (en) * 2023-10-20 2025-04-24 Gregory John Neighbours Self climbing jump form for high rise structures

Similar Documents

Publication Publication Date Title
CN105297635B (en) Assembled lifting type construction platform for pier column construction and construction method thereof
KR100968068B1 (en) How to form multiple horizontal structural members
CN103806644A (en) Hydraulic telescopic device for elevator shaft mold and operating method thereof
CN109457930B (en) Integral lifting steel platform for irregular wall construction and construction method thereof
US10829927B2 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
CN205296803U (en) Elevator automatic lifting operation panel
JP6503716B2 (en) Demolition system and demolition method
US11946217B1 (en) Top plate jacking device and jacking construction method configured for V-shaped columns
CN116104298A (en) Tripod jacking formwork platform for elevator shaft construction and construction method
CN210636796U (en) High-rise elevator shaft jacking formwork system
CN218912242U (en) Tripod extension jacking formwork platform for elevator shaft construction
KR101364198B1 (en) Variable scaffold for vuilding outer wall construction
KR100647977B1 (en) Lifting method of formwork scaffolding with detachable cylinder and moving pump
CN213836318U (en) Bridge floor wet joint hangs mould structure
KR20120122800A (en) Apparatus for forming underground dome structure by oil pressure type lift and constructing method using the same
CN113175222A (en) Installation method of embedded prefabricated external wall panel component
KR20120122790A (en) Apparatus for forming underground dome structure by oil pressure type lift and constructing method using the same
CN116838083A (en) An integral climbing steel platform formwork and its climbing method
CN114809580A (en) Self-lifting method of elevator shaft construction operation platform
CN214656379U (en) Integral steelframe platform rollover construction system of high mound hydraulic jacking
CN202689494U (en) Elevator shaft template support
JP6508959B2 (en) Demolition system and demolition method
CN109372242B (en) Elevator shaft construction safety lifting platform device and using method
CN211421802U (en) High-rise building construction machinery
CN114250975A (en) A wellbore hydraulic integrated distribution platform for building construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination