CN116024904A - A method of installation and construction of a long-span basket arch bridge - Google Patents
A method of installation and construction of a long-span basket arch bridge Download PDFInfo
- Publication number
- CN116024904A CN116024904A CN202211668138.XA CN202211668138A CN116024904A CN 116024904 A CN116024904 A CN 116024904A CN 202211668138 A CN202211668138 A CN 202211668138A CN 116024904 A CN116024904 A CN 116024904A
- Authority
- CN
- China
- Prior art keywords
- arch
- installation
- main
- bridge
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及提篮拱桥技术领域,具体地说,涉及一种大跨度提篮拱桥安装施工方法。其具有如下步骤:S1、构建桥墩支座;S2、安装主梁支架;S3、主梁吊装;S4、主拱支架定位安装;S5、主拱吊装;S6、拆除主拱支架;S7、桥面预制板的全面铺设;S8、安装吊杆,并进行吊杆初次张拉;S9、拆除主梁支架;S10、桥体补焊和补漆;S11、桥面预制板件的接缝浇筑;S12、吊杆末次张拉。通过本发明所提供的安装施工方法,能够较佳地基于支架吊装法实施,通过采用先梁后拱的施工方案,能够较佳地实现对大跨度提篮拱桥的安装施工。
The invention relates to the technical field of basket arch bridges, in particular to a method for installing and constructing large-span basket arch bridges. It has the following steps: S1, constructing the pier support; S2, installing the main beam support; S3, hoisting the main beam; S4, positioning and installing the main arch support; S5, hoisting the main arch; S6, removing the main arch support; S7, bridge deck Full laying of prefabricated slabs; S8, installation of suspenders, and initial tensioning of suspenders; S9, removal of main girder supports; S10, repair welding and painting of bridge body; S11, joint pouring of bridge deck prefabricated slabs; S12 , The last tensioning of the boom. The installation and construction method provided by the present invention can be preferably implemented based on the bracket hoisting method, and the installation and construction of the long-span basket arch bridge can be preferably realized by adopting the construction scheme of the beam first and the arch later.
Description
技术领域technical field
本发明涉及提篮拱桥技术领域,具体地说,涉及一种大跨度提篮拱桥安装施工方法。The invention relates to the technical field of basket arch bridges, in particular to a method for installing and constructing large-span basket arch bridges.
背景技术Background technique
在大跨度提篮拱桥的建设中,现有常见为支架法、转体施工法和斜拉扣挂法。工程建设单位一般会根据工程建设项目的具体需求和工程所处的地理环境采用相应的施工方法或是改进现有的施工方法。In the construction of long-span basket arch bridges, the existing common methods are support method, swivel construction method and cable-stayed buckle-hanging method. The engineering construction unit generally adopts the corresponding construction method or improves the existing construction method according to the specific needs of the engineering construction project and the geographical environment where the project is located.
目前针对大跨度的预制式提篮拱桥的施工,尚无较佳的解决方案。At present, there is no better solution for the construction of long-span prefabricated basket arch bridges.
发明内容Contents of the invention
本发明提供了一种大跨度提篮拱桥安装施工方法,其能够克服现有技术的某种或某些缺陷。The invention provides a method for installing and constructing a large-span basket arch bridge, which can overcome some or some defects of the prior art.
根据本发明的一种大跨度提篮拱桥安装施工方法,其具有如下步骤:According to a kind of large-span basket arch bridge installation and construction method of the present invention, it has the following steps:
S1、构建桥墩支座;S1, build the pier support;
S2、安装主梁支架;S2, install the main beam bracket;
S3、主梁吊装;S3. Hoisting of main girder;
S4、主拱支架定位安装;S4, positioning and installation of the main arch bracket;
S5、主拱吊装;S5. Hoisting of the main arch;
S6、拆除主拱支架;S6, remove the main arch support;
S7、桥面预制板的全面铺设;S7. Comprehensive laying of bridge deck prefabricated slabs;
S8、安装吊杆,并进行吊杆初次张拉;S8, install the suspender, and carry out the initial tensioning of the suspender;
S9、拆除主梁支架;S9, remove the main beam support;
S10、桥体补焊和补漆;S10, bridge repair welding and paint repair;
S11、桥面预制板件的接缝浇筑;S11. Joint pouring of bridge deck prefabricated panels;
S12、吊杆末次张拉。S12. The suspender is stretched for the last time.
作为优选,S1中,在桥墩支座构建完成后,对桥墩支座顶部标高及桥梁轴线进行复测。Preferably, in S1, after the construction of the pier support is completed, the elevation of the top of the pier support and the bridge axis are remeasured.
作为优选,S2中,主梁支架自桥体中部向两侧安装。As a preference, in S2, the main girder support is installed from the middle of the bridge body to both sides.
作为优选,S3中,自主梁中部节段向两侧阶段依次吊装,吊装过程中,完成主梁的横梁与纵梁间的装配,同时同步安装桥面预制板。As a preference, in S3, the middle section of the main girder is hoisted sequentially to both sides. During the hoisting process, the assembly between the beam and the longitudinal girder of the main girder is completed, and the bridge deck prefabricated slab is simultaneously installed.
作为优选,S4中,首先完成拱脚支架的定位安装,而后进行主拱支架的定位安装。Preferably, in S4, the positioning installation of the arch foot bracket is completed first, and then the positioning installation of the main arch bracket is performed.
作为优选,S5中,主拱从拱脚段向拱顶段对称吊装,相邻主拱段吊装定位后进行装配。Preferably, in S5, the main arch is hoisted symmetrically from the arch foot section to the vault section, and the adjacent main arch sections are hoisted and positioned for assembly.
本发明的有益效果在于:通过本发明所提供的安装施工方法,能够较佳地基于支架吊装法实施,通过采用先梁后拱的施工方案,能够较佳地实现对大跨度提篮拱桥的安装施工。The beneficial effect of the present invention is that: the installation and construction method provided by the present invention can be preferably implemented based on the bracket hoisting method, and the installation and construction of the long-span basket arch bridge can be preferably realized by adopting the construction scheme of the beam first and then the arch .
附图说明Description of drawings
图1为实施例1中的吊杆安装施工方法的流程图。Fig. 1 is the flow chart of the construction method of boom installation in embodiment 1.
图2为实施例1中吊索吊笼的结构示意图。FIG. 2 is a schematic structural view of the sling cage in Embodiment 1.
图3为实施例1中卷扬机布置图。FIG. 3 is a layout diagram of the winch in Embodiment 1. FIG.
图4为实施例1中汽车吊布置图。Fig. 4 is the arrangement diagram of the automobile crane in embodiment 1.
图5为实施例1中汽车吊布置图。Fig. 5 is the arrangement diagram of the automobile crane in embodiment 1.
图6为实施例1中吊索吊装示意图。Fig. 6 is a schematic diagram of hoisting with slings in Embodiment 1.
图7为实施例1中吊索吊装顺序示意图。Fig. 7 is a schematic diagram of the hoisting sequence of the slings in Embodiment 1.
图8为实施例1中张拉设备结构图。FIG. 8 is a structural diagram of the tensioning equipment in Embodiment 1.
具体实施方式Detailed ways
为进一步了解本发明的内容,结合实施例对本发明作详细描述。应当理解的是,实施例仅仅是对本发明进行解释而并非限定。In order to further understand the contents of the present invention, the present invention will be described in detail in conjunction with examples. It should be understood that the examples are only for explaining the present invention and not for limiting it.
实施例1Example 1
本实施例提供了一种大跨度提篮拱桥安装施工方法,其具有如下步骤:The present embodiment provides a method for installing and constructing a large-span basket arch bridge, which has the following steps:
S1、构建桥墩支座;S1, build the pier support;
S2、安装主梁支架;S2, install the main beam bracket;
S3、主梁吊装;S3. Hoisting of main girder;
S4、主拱支架定位安装;S4, positioning and installation of the main arch bracket;
S5、主拱吊装;S5. Hoisting of the main arch;
S6、拆除主拱支架;S6, remove the main arch support;
S7、桥面预制板的全面铺设;S7. Comprehensive laying of bridge deck prefabricated slabs;
S8、安装吊杆,并进行吊杆初次张拉;S8, install the suspender, and carry out the initial tensioning of the suspender;
S9、拆除主梁支架;S9, remove the main beam support;
S10、桥体补焊和补漆;S10, bridge repair welding and paint repair;
S11、桥面预制板件的接缝浇筑;S11. Joint pouring of bridge deck prefabricated panels;
S12、吊杆末次张拉。S12. The suspender is stretched for the last time.
本实施例的S1中,在桥墩支座构建完成后,对桥墩支座顶部标高及桥梁轴线进行复测。In S1 of this embodiment, after the construction of the pier support is completed, the elevation of the top of the pier support and the bridge axis are remeasured.
本实施例的S2中,主梁支架自桥体中部向两侧安装。In S2 of this embodiment, the main girder support is installed from the middle of the bridge body to both sides.
本实施例的S3中,自主梁中部节段向两侧阶段依次吊装,吊装过程中,完成主梁的横梁与纵梁间的装配,同时同步安装桥面预制板。In S3 of this embodiment, the middle section of the main girder is hoisted sequentially to both sides. During the hoisting process, the assembly between the beam and the longitudinal girder of the main girder is completed, and the bridge deck prefabricated slab is simultaneously installed.
本实施例的S4中,首先完成拱脚支架的定位安装,而后进行主拱支架的定位安装。In S4 of this embodiment, the positioning and installation of the arch foot support is completed first, and then the positioning and installation of the main arch support is performed.
本实施例的S5中,主拱从拱脚段向拱顶段对称吊装,相邻主拱段吊装定位后进行装配。In S5 of this embodiment, the main arch is hoisted symmetrically from the arch foot section to the vault top section, and the adjacent main arch sections are hoisted and positioned for assembly.
通过本实施例所提供的安装施工方法,能够较佳地基于支架吊装法实施,通过采用先梁后拱的施工方案,能够较佳地实现对大跨度提篮拱桥的安装施工。The installation and construction method provided by this embodiment can be preferably implemented based on the bracket hoisting method, and the installation and construction of the long-span basket arch bridge can be preferably realized by adopting the construction scheme of the beam first and the arch later.
本实施例中,能够首先安装架设桥面系,再安装主拱肋,待拱肋支架拆除后安装预制板,然后安装吊索,精确调整索力及线形后,拆除桥面系支架。In this embodiment, the bridge deck system can be installed first, and then the main arch rib can be installed. After the arch rib support is removed, the prefabricated plate can be installed, and then the sling can be installed. After the cable force and line shape are accurately adjusted, the bridge deck system support can be removed.
如图1所示,本实施例的S8具有以下步骤:As shown in Figure 1, S8 of the present embodiment has the following steps:
步骤S81、进行施工前的准备工作,其包括复核预埋管角度及耳板间距,根据拱桥的规格生产相匹配的吊杆;Step S81, preparatory work before construction, which includes reviewing the angle of the embedded pipe and the distance between the ear plates, and producing matching suspenders according to the specifications of the arch bridge;
步骤S82、进行吊杆的安装,其主要包括如下步骤:Step S82, installing the boom, which mainly includes the following steps:
步骤S821、将吊杆吊运到拱肋相应位置;Step S821, lifting the boom to the corresponding position of the arch rib;
步骤S822、通过卷扬机穿过拱肋处的预设孔将吊杆穿过塔端预埋管,并安装塔端螺母;Step S822, pass the hoist through the preset hole at the arch rib, pass the suspender through the pre-buried pipe at the tower end, and install the tower end nut;
步骤S823、在吊杆的下端安装销轴;Step S823, installing a pin shaft at the lower end of the boom;
步骤S83、安装拱端张拉设备并调试检查,随后按照要求分批对称张拉,待张拉到设计索力后,打紧紧定螺母;Step S83, install the tensioning equipment at the arch end, debug and check, then symmetrically tension in batches according to the requirements, and tighten the set nuts after the tension reaches the design cable force;
步骤S84、重复步骤S83,直至完成对于所有吊杆的张拉;Step S84, repeating step S83 until the tensioning of all suspenders is completed;
步骤S85、按设计要求对锚具进行防护处理。Step S85, performing protective treatment on the anchorage according to design requirements.
本实施例中,通过采用卷扬机对吊杆进行吊装,相比于通过吊车进行吊装的方式,不仅在安装设置时更为方便,可较为简便的将卷扬机固定于桥面处,相比于吊车的较大体积,占用桥面空间更小,并且在使用时更为方便,不会因为体积过大而导致对桥面处的施工造成干扰;从而方便了施工人员进行桥面的施工,同时,通过采用卷扬机的吊装方式,还较佳的降低了成本,节约了经济。In this embodiment, hoisting the boom by using a winch is not only more convenient in installation and setting than the way of hoisting by a crane, but also can be more convenient to fix the winch on the bridge deck. It is larger in size, takes up less space on the bridge deck, and is more convenient to use, and will not interfere with the construction of the bridge deck due to its large size; thus it is convenient for the construction personnel to carry out the construction of the bridge deck. At the same time, through The hoisting method of the winch is also used to reduce the cost and save the economy.
其具体操作步骤如下所示:The specific operation steps are as follows:
(1)确定主线工期:(1) Determine the duration of the main line:
施工准备-吊杆安装-张拉-调索--吊杆防护-施工收尾。Construction preparation-boom installation-tensioning-rope adjustment-boom protection-construction finishing.
(2)其他工序如:施工平台、吊杆倒运、吊杆安装、张拉、张拉设备倒运。(2) Other processes such as: construction platform, suspension of booms, installation of booms, tensioning, and transportation of tensioning equipment.
(3)加强横向联系,做好与各主桥施工单位的协调工作,合理使用施工用地、施工通道、施工平台及大型搬运设备。(3) Strengthen the horizontal connection, do a good job in coordination with the construction units of the main bridge, and rationally use the construction land, construction passages, construction platforms and large-scale handling equipment.
钢结构队伍复核预埋管角度及耳板间距,根据实际长度下料生产吊杆。The steel structure team checks the angle of the embedded pipe and the distance between the ear plates, and cuts the material according to the actual length to produce the suspender.
拱端施工平台Arch end construction platform
在拱顶设置吊笼吊点和安全绳,图2为吊索吊笼示意图,并将施工所需要的拱下施工建筑吊笼准备就位。主体是由2根70米长和6根70公分的5#角钢作为底部。Set the hoisting points and safety ropes of the hoisting cage on the vault. Figure 2 is a schematic diagram of the sling hoisting cage, and the construction hoisting cage under the arch required for construction is ready to be put in place. The main body is made of two 70-meter-long and six 70-centimeter 5# angle steels as the bottom.
在桥面上布置的主要设备包括:汽车吊(汽车吊的布置图如图4以及图5所示)、卷扬机、葫芦及导向系统,张拉千斤顶,油泵及组件。The main equipment arranged on the bridge deck includes: car cranes (the layout of the car cranes is shown in Figure 4 and Figure 5), winches, hoists and guiding systems, tension jacks, oil pumps and components.
为确保吊杆拱上、梁端挂设等工序的操作方便、控制准确,作为重要施工设备的卷扬机应选用状况良好的卷扬机,各卷扬机均配置滑车。根据本项目索体重量,吊杆安装布置卷扬机需在安全保证系数内。In order to ensure the convenient operation and accurate control of the procedures such as boom arching and beam end hanging, hoists as important construction equipment should be selected in good condition, and each hoist should be equipped with a block. According to the weight of the cable body in this project, the installation and arrangement of the hoist must be within the safety guarantee factor.
吊索起重设备包括卷扬机、钢丝绳、梁端导向点、拱端导向点等等,在两侧桥台上各布置两台3T卷扬机,钢丝绳从桥面拱肋预留人洞口进入拱内,在各个横隔板焊接角度导向,在拱内设置临时吊点,从索导管下穿钢丝绳,布置好钢丝绳牵引系统,结合图3所示:The sling hoisting equipment includes hoists, wire ropes, beam end guide points, arch end guide points, etc. Two 3T hoists are arranged on the abutments on both sides. The welding angle of each diaphragm is oriented, and temporary lifting points are set in the arch, and the wire rope is passed through the cable guide, and the wire rope traction system is arranged, as shown in Figure 3:
Z1、吊点布置在拱端锚箱内,利用锚箱在拱端锚垫板正上方设置卷扬机钢丝绳吊装反力点,钢丝绳采用Φ15.6mm的钢丝绳,起重最大可以承受4吨的荷载;Z1. The hoisting point is arranged in the anchor box at the arch end. Use the anchor box to set the hoisting reaction point of the hoist wire rope directly above the anchor pad at the arch end. The wire rope adopts a Φ15.6mm wire rope, and the maximum lifting load can bear 4 tons;
Z2、3T卷扬机安装在两岸桥台位置,并做好临时固定,以免在起重作业过程中发生意外;Z2 and 3T winches are installed at the abutments on both sides of the bank, and are temporarily fixed to avoid accidents during the lifting operation;
Z3、卷扬机,将钢丝绳放出后,绕过拱上临时吊点点,将钢丝绳穿过正下方的索导管放至拱端索导管出口,在旁边增设2台2吨手拉葫芦;Z3, hoist, after releasing the steel wire rope, bypass the temporary lifting point on the arch, put the steel wire rope through the cable guide directly below to the exit of the cable guide at the arch end, and add two 2-ton chain hoists beside it;
Z4、起重设备安装完毕。Z4. The lifting equipment has been installed.
通过上述步骤,较佳的增强了卷扬机对于吊杆的吊装性能,从而较佳的提升了卷扬机在吊装吊杆时的稳定性。Through the above steps, the hoisting performance of the hoist for the boom is better enhanced, thereby better improving the stability of the hoist when hoisting the boom.
根据设计图纸对于吊杆索力的要求,千斤顶选用YCW200千斤顶,满足索力最大170吨的要求,根据对称原则进行张拉控制,双吊杆结构,4个点对称同步进行张拉,采用8台千斤顶+8台油泵+8套张拉工装配套组合,油泵使用ZB4-500型即可,油泵在张拉过程中布置在桥面,油管通过临时人孔进入拱肋内与千斤顶连接,拱肋内与桥面操作人员通过对讲机进行张拉沟通联系,千斤顶和张拉工装等在拱肋内移动时,主要是通过人工与手拉葫芦配合,拱肋内移动千斤顶和工装空间小,安全隐患大,需要格外注意。According to the requirements of the design drawings for the cable force of the boom, the jack is YCW200 jack, which meets the requirement of a maximum cable force of 170 tons. The tension is controlled according to the principle of symmetry. The structure of the double boom is symmetrical and synchronous at 4 points, and 8 sets are used. Jack + 8 sets of oil pumps + 8 sets of tensioning tools. The oil pump can use ZB4-500 type. The oil pump is arranged on the bridge deck during the tensioning process. The oil pipe enters the arch rib through the temporary manhole and connects with the jack. Communicate with bridge deck operators through walkie-talkies. When jacks and tensioning tools are moved in the arch rib, they are mainly coordinated with hand chain hoists. The space for moving jacks and tooling in the arch rib is small, and there are great potential safety hazards. Requires extra attention.
张拉工装和设备中最重的就是千斤顶,从拱脚往拱顶移动时,需要使用手拉葫芦进行辅助牵引,在拱肋隔板的人孔位置用手拉葫芦吊重辅助人工过孔;设备和工装在拱肋吊重时可以提前放入拱肋内,减少一次搬运。The heaviest piece of tensioning tooling and equipment is the jack. When moving from the arch foot to the vault, it is necessary to use a chain hoist for auxiliary traction. At the manhole position of the arch rib partition, use a chain hoist to lift the weight to assist manual passage; Equipment and tooling can be put into the arch rib in advance when the arch rib is hoisting, reducing one-time handling.
吊杆主要施工方法The main construction method of the boom
索导管的处理Cable Catheter Handling
吊杆锚头外径与索套管的内径相差较小,吊杆安装时极易产生位置偏差,从而造成锚头外螺牙和吊杆PE保护套的损伤,因此吊杆安装前应对拱肋端索套管进行全面的检查,对索套管内的焊渣、毛刺等进行打平磨光。The difference between the outer diameter of the anchor head of the boom and the inner diameter of the cable casing is small, and the position deviation is very likely to occur during the installation of the boom, which will cause damage to the outer thread of the anchor head and the PE protective sleeve of the boom. Conduct a comprehensive inspection of the cable casing at the end, and smooth and polish the welding slag and burrs in the cable casing.
梁端耳板处理Beam end lug treatment
检查梁端耳板位置、角度及孔径。Check the position, angle and hole diameter of the lug plate at the beam end.
吊索上端锚头吊装(吊索吊装示意图如图6所示)Hoisting of the anchor head at the upper end of the sling (the schematic diagram of the sling hoisting is shown in Figure 6)
G1、缓缓放下卷扬机牵引吊装系统的连接装置,与吊索上端锚头连接牢固,解除吊索上的抱箍;G1. Slowly lower the connecting device of the hoisting hoisting system of the hoist, connect firmly with the anchor head at the upper end of the sling, and release the hoop on the sling;
G2、开启卷扬机,缓缓地将上锚头牵引至拱下锚箱预埋管位置,施工平台上的工作人员调整好吊索上端锚头方向并对中,以便顺利穿过预埋管到达拱肋横隔板;G2. Turn on the hoist and slowly pull the upper anchor head to the position of the embedded pipe in the anchor box under the arch. The staff on the construction platform adjust the direction of the anchor head at the upper end of the sling and center it so that it can pass through the embedded pipe to reach the arch Rib diaphragm;
G3、继续提升,将上锚头提升至设计位置并旋紧上端螺母,并将吊索上锚头临时锚固。G3. Continue to lift, lift the upper anchor head to the design position and tighten the upper nut, and temporarily anchor the upper anchor head of the sling.
G4、吊杆安装顺序,吊杆安装应从拱座往跨中侧安装(吊索吊装顺序示意图如图7所示)。G4. The installation sequence of the suspenders. The suspenders should be installed from the abutment to the mid-span side (the schematic diagram of the sling hoisting sequence is shown in Figure 7).
通过本实施例中的施工工艺,能够较佳的实现对于吊索上端锚头吊装。Through the construction process in this embodiment, the hoisting of the anchor head at the upper end of the sling can be better realized.
吊索下端锚头安装Anchor head installation at the lower end of the sling
(1)根据吊杆位置布置卷扬机及滑车。(1) Arrange the hoist and block according to the position of the boom.
(2)在吊杆末端安装辅助夹具,利用卷扬机将吊杆叉耳拉近耳板位置。梁面工作人员通过手拉葫芦配合调整叉耳位置和角度,待位置合适时插入销轴。(2) Install an auxiliary fixture at the end of the boom, and use a hoist to pull the fork ear of the boom closer to the ear plate. The staff on the beam surface adjust the position and angle of the fork ear through the hand chain hoist, and insert the pin shaft when the position is appropriate.
吊杆张拉布置Boom tension arrangement
根据设计图纸对于吊杆索力的要求,千斤顶选用YCW100千斤顶,满足索力最大170吨的要求,根据对称原则进行张拉控制,双吊杆结构,4个点对称同步进行张拉,采用16台千斤顶+8台油泵+8套张拉工装配套组合,油泵使用ZB4-500型即可,油泵在张拉过程中布置在桥面,在桥面进行张拉工装的安装及转运,张拉工装和设备中最重的就是千斤顶,使用吊车或者人工安装。According to the requirements of the design drawings for the cable force of the boom, the jack is YCW100 jack, which meets the requirement of a maximum cable force of 170 tons. The tension control is carried out according to the principle of symmetry. The structure of the double boom is symmetrical and synchronous at 4 points, and 16 sets are used. Jack + 8 sets of oil pumps + 8 sets of tensioning tooling. The oil pump can use ZB4-500 type. The oil pump is arranged on the bridge deck during the tensioning process, and the tensioning tooling is installed and transferred on the bridge deck. The tensioning tooling and The heaviest piece of equipment is the jack, which can be installed by a crane or manually.
张拉系统tensioning system
为了保证吊杆应力满足设计要求,施工中每根吊杆拉力误差不超过±2﹪,成桥后每根吊杆不超过±1﹪,张拉时严格按工艺控制进行,而且施工前必须提供以下项目:In order to ensure that the stress of the suspender meets the design requirements, the tension error of each suspender during construction shall not exceed ±2%, and after the completion of the bridge, the error of each suspender shall not exceed ±1%. The following items:
1、吊杆安装控制张拉力,该值由监控单位以监控指令形式提供给安装施工单位;1. The boom installation controls the tension, which is provided by the monitoring unit to the installation and construction unit in the form of monitoring instructions;
2、吊杆安装控制张拉力作用下,吊杆锚固点计算相对位移量(或变形量),是该吊杆所在竖直平面内下端锚点竖向位移和上锚点竖直位移,由监控单位临时给出;2. Under the tension force of the boom installation control, the relative displacement (or deformation) of the anchor point of the boom is calculated, which is the vertical displacement of the lower anchor point and the vertical displacement of the upper anchor point in the vertical plane where the boom is located. temporarily given by the unit;
3、主梁相应截面的相关物理参数,该参数一般根据设计而定;3. The relevant physical parameters of the corresponding section of the main beam, which are generally determined according to the design;
4、吊杆索体几何和物理参数,由吊杆产品供方提供。4. The geometric and physical parameters of the boom cable body shall be provided by the supplier of the boom product.
张拉工艺Tension process
吊杆张拉工艺说明:根据吊杆的结构,吊杆的调节装置设置在下端叉耳和下锚头之间,因此需要采用扁担的张拉方式,使用两台千斤顶与拉杆同步张拉,拉杆与千斤顶设置与吊杆的轴向中心线平行,千斤顶在加载过程中,通过上下扁担梁(结构图8所示)把吊杆的调节连接装置“压松”,然后通过对吊杆调节装置连接套筒的旋紧和旋送对吊杆索力实现张拉和放张,(边拉边旋转调节套筒以调节吊杆长度)从而能够较为方便的实现对于吊杆的张拉。Explanation of the boom tensioning process: According to the structure of the boom, the adjustment device of the boom is set between the lower fork lug and the lower anchor head, so it is necessary to adopt the tensioning method of the pole, and use two jacks to pull the pull rod synchronously, and the pull rod The jack is set parallel to the axial center line of the boom. During the loading process, the jack "presses loose" the adjustment connection device of the boom through the upper and lower shoulder beams (shown in structural diagram 8), and then connects the boom adjustment device. The tightening and screwing of the sleeve realize the tensioning and releasing of the tension of the boom cable, (rotate and adjust the sleeve while pulling to adjust the length of the boom), so that the tensioning of the boom can be realized more conveniently.
上述装置由如下部件组成:The above device consists of the following components:
下扁担梁:与吊杆下叉耳临时连接固定。上扁担梁:与吊杆下锚头临时连接固定。临时拉杆:全螺纹,两端分别穿过下扁担梁和上扁担梁,用螺母临时固定。千斤顶:加载荷载,通过拉杆将吊杆往下拉至设计位置,或者放松至设计位置。Lower pole beam: temporarily connected and fixed with the lower fork lug of the boom. Upper pole beam: temporarily connected and fixed with the lower anchor head of the suspender. Temporary pull rod: full thread, both ends pass through the lower shoulder beam and the upper shoulder beam respectively, and are temporarily fixed with nuts. Jack: Load the load, pull the boom down to the design position through the pull rod, or relax it to the design position.
张拉程序tensioning procedure
张拉过程中根据监控单位给的张拉顺序对称同步张拉,同步张拉的不同步拉力差值不超出设计规定值。各个千斤顶同步之差不大于油表读数的最小分格,索力中值误差小于±2%。During the tensioning process, symmetrical and synchronous tensioning is performed according to the tensioning sequence given by the monitoring unit, and the difference between synchronous tensioning and asynchronous tensions does not exceed the design value. The synchronous difference of each jack is not greater than the minimum division of the oil gauge reading, and the error of the median value of the cable force is less than ±2%.
1、吊杆分两次张拉,首先是挂索时的索体预紧及正式开始张拉,最后是在二期恒荷载加载完成后根据已成线性、实测索力,对全桥吊杆拉索进行补张或放张。本实施例中,通过对吊杆进行两次张拉,能够较佳的提升吊杆的张紧程度,从而较佳的保证了吊杆对于桥面的提升能力,进一步的提升了拱桥的稳定性。1. The suspenders are stretched twice, the first is the pre-tensioning of the cable body when the cables are hung and the formal start of tensioning, and the last is the linear and measured cable force after the completion of the second phase of constant load loading. Dragline fills up sheet or releases sheet. In this embodiment, by stretching the suspender twice, the tension degree of the suspender can be better improved, thereby better ensuring the lifting ability of the suspender to the bridge deck, and further improving the stability of the arch bridge .
2、收到设计张拉指令后,依据千斤顶标定书上的回归方程,把指令上的拉力值转换为每一组张拉设备上的油压读数值,并把张拉操作指令以书面形式交给每一组张拉设备的负责人,并交代有关注意事项;2. After receiving the design tensioning instruction, according to the regression equation on the jack calibration book, convert the tension value on the instruction into the oil pressure reading value on each group of tensioning equipment, and submit the tensioning operation instruction in written form To the person in charge of each group of tensioning equipment, and explain the relevant precautions;
3、张拉顺序应从中间往两侧进行张拉。3. The tension sequence should be stretched from the middle to both sides.
本实施例中,通过将张拉顺序设置为从中间往两侧进行张拉,能够使得每根吊杆均能够较佳的对桥面进行张拉,从而较佳的提升了吊杆对于桥面的提升效果,同时将张拉顺序设置为从中间往两侧进行张拉,也使得施工人员可从拱桥中心处至两端同时施工,避免了在施工时出现干扰,提升了对于拱桥的施工效率。In this embodiment, by setting the stretching sequence as stretching from the middle to both sides, each suspender can better stretch the bridge deck, thereby better improving the suspender's effect on the bridge deck. At the same time, the tensioning sequence is set to stretch from the middle to both sides, which also enables the construction personnel to construct from the center to both ends of the arch bridge at the same time, avoiding interference during construction, and improving the construction efficiency of the arch bridge .
张拉过程tensioning process
①接通油泵和千斤顶的油管,检查精密压力表是否与千斤顶相符,在未张拉之前,可以在空载的情况下活动两个行程,确保千斤顶在张拉时无任何问题;① Connect the oil pipe of the oil pump and the jack, and check whether the precision pressure gauge is consistent with the jack. Before tensioning, two strokes can be moved under no-load conditions to ensure that the jack has no problems when tensioning;
②张拉千斤顶和油压表必须在张拉前进行标定;②The tensioning jack and oil pressure gauge must be calibrated before tensioning;
③启动油泵,按张拉指令对称的吊杆同步分级均衡缓慢加载,分级张拉程序为:0→0.3σ→0.6σ→0.8σ→1.0σ;张拉过程中,吊杆索缓慢上升,与此同时跟进拧紧吊杆索螺母;③Start the oil pump, load the symmetrical suspender synchronously and in stages according to the tensioning command, and load slowly. At the same time follow up to tighten the suspender cable nut;
④当达到设计、监测监控要求后,应稳住油压,然后旋紧螺母,使螺母与锚垫板充分结合。最后,卸除油压,回油、关机、断电,完成张拉工作;④ When the design and monitoring requirements are met, the oil pressure should be stabilized, and then the nut should be tightened to fully combine the nut with the anchor backing plate. Finally, remove the oil pressure, return the oil, shut down, and cut off the power to complete the tensioning work;
⑤在张拉过程中配合检测单位做好每根索的索力测量工作。⑤Cooperate with the inspection unit to measure the cable force of each cable during the tensioning process.
4、一个索号的吊杆张拉完成后,认真检查记录,确认无误后方可拆卸张拉设备,进行下一索号的安装、张拉。4. After the suspender tensioning of a cable number is completed, carefully check the records, and the tensioning equipment can be disassembled only after confirmation is correct, and the installation and tensioning of the next cable number can be carried out.
吊杆调索施工Boom Adjustment Construction
在吊杆安装完后可能需要分阶段分部位进行调索。调索部位和控制索力由监控单位提供,对超张索进行放张,索力不足的进行补张。After the boom is installed, it may be necessary to adjust the rope in stages and parts. The cable adjustment position and the control cable force are provided by the monitoring unit, and the overstretched cable is released, and the insufficient cable force is supplemented.
防腐作业Anti-corrosion work
张拉结束后,对锚杯内部表面涂抹缓释膏250-300um;锚杯、锚圈、锚垫板端部外露钢件表面先涂缓释膏250-300um,再缠包缓释带,重叠率50%,最后涂外防护剂2道。After the tensioning is finished, apply 250-300um of slow-release ointment to the inner surface of the anchor cup; first apply 250-300um of slow-release ointment to the surface of the exposed steel parts at the end of the anchor cup, anchor ring, and anchor backing plate, and then wrap the slow-release tape, overlapping The rate is 50%, and finally apply 2 coats of external protective agent.
通过本实施例中的防腐作业,能够有效地对锚具进行防腐处理,从而可较佳的提升锚具的使用寿命。Through the anticorrosion work in this embodiment, the anchorage can be effectively treated with anticorrosion, so that the service life of the anchorage can be better improved.
减振器安装Shock absorber installation
内置式减震器一般包括减震体、金属圈、锲块、拉杆、螺母、弹簧垫圈等部件。减震器安装时,先将减振器平推入预埋管,在固定楔块上安装活动楔块,通过对减振器楔块顶压使减振橡胶沿径向膨胀,从而将吊杆楔紧,同时减震器也达到固定效果。Built-in shock absorbers generally include shock absorbers, metal rings, wedges, pull rods, nuts, spring washers and other components. When installing the shock absorber, first push the shock absorber flat into the embedded pipe, install the movable wedge on the fixed wedge, and press the shock absorber wedge to expand the vibration-absorbing rubber in the radial direction, so that the boom The wedge is tight, and the shock absorber also achieves a fixed effect at the same time.
采用自制吊笼作为减振器的安装平台,吊笼使用5#角钢焊接。从需安装的索号的上方焊接一个临时吊点,再使用Ф16钢丝绳和葫芦垂吊吊笼,手拉葫芦用来调节吊笼高度,以方便施工操作。临时焊接吊点放下一根Ф16钢丝绳栓住吊笼,以防意外。The self-made hanging cage is used as the installation platform of the shock absorber, and the hanging cage is welded with 5# angle steel. Weld a temporary lifting point above the cable number to be installed, and then use Ф16 steel wire rope and hoist to hang the cage. The chain hoist is used to adjust the height of the cage to facilitate construction operations. A Ф16 steel wire rope is put down at the temporary welding lifting point to tie the cage to prevent accidents.
吊笼平台考虑使用汽车吊进行安装和悬挂。The cage platform considers using a car crane for installation and suspension.
容易理解的是,本领域技术人员在本申请提供的一个或几个实施例的基础上,可以对本申请的实施例进行结合、拆分、重组等得到其他实施例,这些实施例均没有超出本申请的保护范围。It is easy to understand that, on the basis of one or several embodiments provided by this application, those skilled in the art can combine, split, recombine, etc., the embodiments of this application to obtain other embodiments, and these embodiments do not exceed the scope of this application. The scope of protection applied for.
以上示意性的对本发明及其实施方式进行了描述,该描述没有限制性,实施例所示的也只是本发明的实施方式的部分,实际的结构并不局限于此。所以,如果本领域的普通技术人员受其启示,在不脱离本发明创造宗旨的情况下,不经创造性的设计出与该技术方案相似的结构方式及实施例,均应属于本发明的保护范围。The above schematically describes the present invention and its implementation, but the description is not restrictive, and the examples show only part of the implementation of the present invention, and the actual structure is not limited thereto. Therefore, if a person of ordinary skill in the art is inspired by it, without departing from the inventive concept of the present invention, without creatively designing a structural mode and embodiment similar to the technical solution, it shall all belong to the protection scope of the present invention .
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211668138.XA CN116024904A (en) | 2022-12-23 | 2022-12-23 | A method of installation and construction of a long-span basket arch bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211668138.XA CN116024904A (en) | 2022-12-23 | 2022-12-23 | A method of installation and construction of a long-span basket arch bridge |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116024904A true CN116024904A (en) | 2023-04-28 |
Family
ID=86090633
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211668138.XA Pending CN116024904A (en) | 2022-12-23 | 2022-12-23 | A method of installation and construction of a long-span basket arch bridge |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116024904A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116219878A (en) * | 2022-12-23 | 2023-06-06 | 中铁十局集团第三建设有限公司 | A construction method for installing suspenders of a large-span basket-carrying arch bridge |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102154988A (en) * | 2011-04-22 | 2011-08-17 | 中交隧道工程局有限公司 | Arch-after-girder construction method of large-span steel box tacked arch bridge |
| CN103290784A (en) * | 2013-07-02 | 2013-09-11 | 永升建设集团有限公司 | Arched beam combination bridge lifting construction method |
| CN203755130U (en) * | 2014-03-10 | 2014-08-06 | 中交第三公路工程局有限公司 | Front beam and rear arch stacking device for steel arch bridge |
| CN217974045U (en) * | 2022-02-16 | 2022-12-06 | 中铁十局集团第三建设有限公司 | A kind of tooling used for tensioning the suspension rod of basket-type steel box girder |
| CN116219878A (en) * | 2022-12-23 | 2023-06-06 | 中铁十局集团第三建设有限公司 | A construction method for installing suspenders of a large-span basket-carrying arch bridge |
-
2022
- 2022-12-23 CN CN202211668138.XA patent/CN116024904A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102154988A (en) * | 2011-04-22 | 2011-08-17 | 中交隧道工程局有限公司 | Arch-after-girder construction method of large-span steel box tacked arch bridge |
| CN103290784A (en) * | 2013-07-02 | 2013-09-11 | 永升建设集团有限公司 | Arched beam combination bridge lifting construction method |
| CN203755130U (en) * | 2014-03-10 | 2014-08-06 | 中交第三公路工程局有限公司 | Front beam and rear arch stacking device for steel arch bridge |
| CN217974045U (en) * | 2022-02-16 | 2022-12-06 | 中铁十局集团第三建设有限公司 | A kind of tooling used for tensioning the suspension rod of basket-type steel box girder |
| CN116219878A (en) * | 2022-12-23 | 2023-06-06 | 中铁十局集团第三建设有限公司 | A construction method for installing suspenders of a large-span basket-carrying arch bridge |
Non-Patent Citations (2)
| Title |
|---|
| 刘东跃: "《施工临时支撑结构专项技术方案》", 30 September 2013, 辽宁科学技术出版社, pages: 391 - 392 * |
| 焦胜军: "《高速铁路桥梁施工与维护(下册)》", 31 May 2011, 西南交通大学出版社, pages: 188 * |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116219878A (en) * | 2022-12-23 | 2023-06-06 | 中铁十局集团第三建设有限公司 | A construction method for installing suspenders of a large-span basket-carrying arch bridge |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6725559B2 (en) | Hanging material replacement device and hanging material replacement method using the same | |
| CN103741601B (en) | Tower, beam and cable synchronous bridge forming technology | |
| CN115506487A (en) | The method of overall lifting and installation after overlapping and assembling double-layer steel trusses on the ground | |
| CN111042540A (en) | Construction method of aerial docking of super-span prestressed pipe truss ground hanging cables | |
| CN103410094B (en) | Installation construction method for bridge rigid hinge | |
| CN108678388B (en) | Short mast multi-point integral lifting construction method for large-capacity circular storage tank | |
| CN107815969A (en) | A kind of filled-type epoxy coating strand drag-line construction technology | |
| CN106193618A (en) | A kind of Long span aerial steel structure truss construction | |
| WO2022217911A1 (en) | Method for replacing sling by means of tensioning at single suspension point for suspension bridge | |
| CN107013038A (en) | A kind of steel structure slipping of building roof lighting Zhongting changes column construction method | |
| CN111519545A (en) | Pier and capping beam integrated construction platform and construction method thereof | |
| CN203654702U (en) | Operating platform for construction of reinforced concrete chimney | |
| CN106744351A (en) | The method of hoisting the main girder of the cable-stayed bridge by using the cable crane | |
| CN108913164A (en) | The symmetrical lifting coke oven furnace stay of truck crane, protection board structure and protection board pressure method | |
| CN102275829B (en) | Frame high-altitude piece mounting method of dry quenching lifter device | |
| CN114908968B (en) | Construction method of large-span fish-bellied pipe truss in gymnasium | |
| CN117328367A (en) | Overall hoisting construction method of super-large and over-heavy steel box girder by floating crane for cross-sea bridge | |
| CN202591864U (en) | Lifting type welding service trolley | |
| CN205973618U (en) | Shell ring hoisting device in chimney | |
| CN115404783A (en) | Sliding construction method for super-wide separated steel box girder of super-large cable-stayed bridge | |
| CN116024904A (en) | A method of installation and construction of a long-span basket arch bridge | |
| CN110077963B (en) | Installation method of large tank | |
| CN101195988A (en) | Stay cable soft and hard combined three-stage traction process and connecting device | |
| CN116219878A (en) | A construction method for installing suspenders of a large-span basket-carrying arch bridge | |
| CN102267046B (en) | Device for separated assembling of dry-quenching hoister frame |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |
