CN113957805B - Installation device and method for bridge under-hanging water supply and drainage pipeline - Google Patents

Installation device and method for bridge under-hanging water supply and drainage pipeline Download PDF

Info

Publication number
CN113957805B
CN113957805B CN202111410913.7A CN202111410913A CN113957805B CN 113957805 B CN113957805 B CN 113957805B CN 202111410913 A CN202111410913 A CN 202111410913A CN 113957805 B CN113957805 B CN 113957805B
Authority
CN
China
Prior art keywords
bridge
pipe
steel pipe
cantilever
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111410913.7A
Other languages
Chinese (zh)
Other versions
CN113957805A (en
Inventor
张放明
郑全兴
任九天
刘锐
张建
华杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Changjiang Water Co ltd
Original Assignee
Jiangsu Changjiang Water Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Changjiang Water Co ltd filed Critical Jiangsu Changjiang Water Co ltd
Priority to CN202111410913.7A priority Critical patent/CN113957805B/en
Publication of CN113957805A publication Critical patent/CN113957805A/en
Application granted granted Critical
Publication of CN113957805B publication Critical patent/CN113957805B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00—Structural or constructional details of bridges
    • E01D19/08—Damp-proof or other insulating layers; Drainage arrangements or devices ; Bridge deck surfacings
    • E01D19/086—Drainage arrangements or devices
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10—Cantilevered erection
    • E01D21/105—Balanced cantilevered erection
    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00—Energy generation through renewable energy sources
    • Y02E10/20—Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了给排水领域内的一种桥梁下挂给排水管道的安装装置及方法,包括悬挂在大桥侧面的悬臂工作台,所述悬臂工作台安装在配重推车上,所述配重推车设置在大桥的桥面上,所述大桥的外边里侧设置有支架,所述支架安装在桥梁板上并处于桥面下方,所述支架配套设置有延伸管;采用悬臂工作平台+配重推车,解决自来水管道吊装就位、对口焊接的难题,本发明可以用于桥梁给排水管道的下挂安装。

Figure 202111410913

The invention discloses a device and method for installing a water supply and drainage pipeline under a bridge in the field of water supply and drainage, comprising a cantilever workbench suspended on the side of the bridge, the cantilever workbench is installed on a counterweight trolley, and the counterweight The trolley is set on the deck of the bridge, and the outside and inside of the bridge are provided with brackets, and the brackets are installed on the bridge deck and under the bridge deck, and the brackets are equipped with extension pipes; the cantilever working platform + matching The heavy trolley solves the problems of hoisting and fitting of tap water pipes and butt joint welding, and the invention can be used for hanging installation of water supply and drainage pipes of bridges.

Figure 202111410913

Description

一种桥梁下挂给排水管道的安装装置及方法Installation device and method for water supply and drainage pipes hanging under bridges

技术领域technical field

本发明涉及一种给排水领域内的桥梁通水管的安装装置和方法。The invention relates to a bridge water pipe installation device and method in the field of water supply and drainage.

背景技术Background technique

供水管网是城市建设重要的生命线之一,也是关乎民生的基础设施,供水管道一旦损坏,会严重影响人们的生活和生产,所以施工要认真贯彻执行现行国家标准,严格控制施工质量。现有技术中,给排水管道要么从水下安装布置,要么下挂在大桥的桥身下方。选择从水面下布管施工成本高,并且维护不便;而选择下挂在桥身下方,则需要用到浮桥,搭设浮桥成本高,并且桥身钢筋混凝土内实外光,表面平整,桥身任何地方不能钻孔,影响结构安全,施工脚手架等辅助工具不能固定在桥梁上,桥身没有受力点;并且为了将减少雨淋,给排水管道需要落在桥板下方的支架上,起重机械吊装无法将钢管着落在支架上。The water supply pipe network is one of the important lifelines of urban construction, and it is also an infrastructure related to people's livelihood. Once the water supply pipe is damaged, it will seriously affect people's life and production. Therefore, the construction must conscientiously implement the current national standards and strictly control the construction quality. In the prior art, the water supply and drainage pipelines are either installed and arranged underwater, or hung below the bridge body of the bridge. The construction cost of laying pipes from the water surface is high, and it is inconvenient to maintain; while the choice of hanging under the bridge body requires the use of pontoon bridges. Drilling is not allowed in the place, which will affect the safety of the structure. Auxiliary tools such as construction scaffolding cannot be fixed on the bridge, and the bridge body has no stress points; Hoisting cannot land the steel pipe on the support.

发明内容Contents of the invention

本发明的目的是提供一种桥梁下挂给排水管道的安装装置及方法,采用悬臂工作平台+配重推车,解决自来水管道吊装就位、对口焊接的难题。The purpose of the present invention is to provide an installation device and method for water supply and drainage pipes hanging under bridges, which uses a cantilever working platform + counterweight trolley to solve the problems of hoisting and welding of tap water pipes.

为实现上述目的,本发明提供了一种桥梁下挂给排水管道的安装装置,包括悬挂在大桥侧面的悬臂工作台,所述悬臂工作台安装在配重推车上,所述配重推车设置在大桥的桥面上,所述大桥的外边里侧设置有支架,所述支架安装在桥梁板上并处于桥面下方,所述支架配套设置有延伸管。In order to achieve the above object, the present invention provides an installation device for hanging water supply and drainage pipes under the bridge, which includes a cantilever workbench suspended on the side of the bridge, the cantilever workbench is installed on a counterweight trolley, and the counterweight trolley It is arranged on the bridge deck of the bridge, and the outside and inside of the bridge are provided with brackets, the brackets are installed on the bridge deck and are located below the bridge deck, and the brackets are equipped with extension pipes.

与现有技术相比,本发明的有益效果在于,在吊装的钢管两端各设置一套悬臂工作台+配重推车,悬臂工作台可以悬挂在桥梁的侧面下方,使得施工人员能够通过悬臂工作台处于桥梁的下方,延伸管可以插接在支架上,使得支架的长度得到延长伸出桥梁的侧面,进而方便起重机械将钢管吊装在延伸管上,进而施工人员通过手拉葫芦来将放置在延伸管上的钢管送入支架上,实现钢管的吊装就位,而配重推车在一节钢管安装就位之后,可以在拆除延伸管后带动悬臂工作台移朝着下一个安装段位移动;采用悬臂工作平台+配重推车,解决自来水管道吊装就位、对口焊接的难题,本发明可以用于桥梁给排水管道的下挂安装。Compared with the prior art, the beneficial effect of the present invention is that a set of cantilever workbench + counterweight trolley is installed at both ends of the hoisted steel pipe, and the cantilever workbench can be suspended under the side of the bridge, so that construction personnel can pass the cantilever The workbench is under the bridge, and the extension pipe can be plugged into the bracket, so that the length of the bracket can be extended to extend out of the side of the bridge, so that it is convenient for the hoisting machinery to hoist the steel pipe on the extension pipe, and then the construction personnel can use the chain hoist to lift the The steel pipe placed on the extension pipe is sent to the bracket to realize the hoisting of the steel pipe in place, and the counterweight trolley can drive the cantilever workbench to move to the next installation section after the extension pipe is removed after a section of steel pipe is installed in place Mobile: the cantilever working platform + counterweight trolley is used to solve the problems of hoisting and welding of tap water pipes, and the invention can be used for the hanging installation of bridge water supply and drainage pipes.

作为本发明的进一步改进,所述悬臂工作台包括矩形平台,所述矩形平台的外侧边设置有附加槽钢的固定板,所述矩形平台的其余三面设置有下护栏,所述固定板的顶部设置带有龙骨的顶板,所述顶板与连接板相连,所述连接板经螺栓与配重推车相连,所述固定板的一侧设置有上护栏,所述顶板和上护栏之间留有间距,所述固定板的内侧面安装有爬梯,所述爬梯设置在连接板和上护栏之间,这样矩形平台的四面被固定板以及下护栏所包围,使得施工人员能够安全得站在其中进行施工操作,而固定板、顶板以及连接板使得矩形平台能够与配重推车连接,使得配重推车能够带动悬臂工作台沿着桥面移动,上护栏只设置一面,这样钢管两端的才能被推入悬臂工作台与桥梁下方里侧面,便于施工人员将钢管通过手拉葫芦推入支架上,进而实现桥梁下方的安装施工。As a further improvement of the present invention, the cantilever workbench includes a rectangular platform, the outer side of the rectangular platform is provided with a fixed plate with additional channel steel, the remaining three sides of the rectangular platform are provided with lower guardrails, the fixed plate A top plate with a keel is arranged on the top, the top plate is connected with the connecting plate, the connecting plate is connected with the counterweight trolley through bolts, an upper guardrail is arranged on one side of the fixed plate, and there is a gap between the top plate and the upper guardrail. There is a gap, the inner side of the fixed plate is installed with a ladder, and the ladder is arranged between the connecting plate and the upper guardrail, so that the four sides of the rectangular platform are surrounded by the fixed plate and the lower guardrail, so that the construction personnel can stand safely in it For construction operations, the fixed plate, top plate and connecting plate enable the rectangular platform to be connected to the counterweight trolley, so that the counterweight trolley can drive the cantilever worktable to move along the bridge deck. Pushed into the cantilever workbench and the inner side of the bridge, it is convenient for construction personnel to push the steel pipe into the bracket through the chain hoist, and then realize the installation and construction under the bridge.

作为本发明的进一步改进,所述配重推车包括底座,所述底座上设置有质量不低于1吨的配重块,所述底座的底部上设置有定向轮,所述顶板靠近连接板的部分设置有制动杆,这样配重推车能够通过定向轮沿着一条直线放线移动,带动悬臂工作台沿着桥梁移动就位,而配重块能够确保在施工人员进入悬臂工作台后进行操作时依然保持平衡,确保安全,制动杆在在施工时将其余桥面压紧,使得配重推车不会出现移动,进一步确保施工安全。As a further improvement of the present invention, the counterweight trolley includes a base on which a counterweight with a mass of not less than 1 ton is arranged, directional wheels are arranged on the bottom of the base, and the top plate is close to the connecting plate The part of the cantilever is equipped with a brake lever, so that the counterweight trolley can move along a straight line through the directional wheels, driving the cantilever worktable to move along the bridge in place, and the counterweight can ensure that after the construction personnel enter the cantilever workbench The balance is still maintained during operation to ensure safety, and the brake lever will press the rest of the bridge deck during construction, so that the counterweight trolley will not move, further ensuring construction safety.

为实现上述目的,本发明提供了一种桥梁下挂给排水管道的安装方法,包括以下步骤:步骤1,支架制作安装;步骤2,管道吊装、就位;步骤3,管道对口、焊接;步骤4,管道伸缩节的安装。In order to achieve the above object, the present invention provides a method for installing water supply and drainage pipes under bridges, comprising the following steps: Step 1, manufacturing and installing the bracket; Step 2, hoisting and placing the pipes in place; Step 3, matching and welding the pipes; 4. Installation of pipe expansion joints.

作为本发明的进一步改进,所述步骤1的具体内容如下:As a further improvement of the present invention, the specific content of said step 1 is as follows:

先将槽钢按图纸尺寸下料,进行预制,支架整体呈L形,支架的横担距桥板下方的垂直距离1.1m,横担的尾端在大桥的桥板外边沿里侧,距桥板外边沿水平距离为0.3m,将延伸管插接在支架的横担端头,将支架焊接在预埋与桥身内的钢板,所有支架及钢构件在安装前进行防腐处理并且支架焊接后,焊接处要进行二次防腐处理。Firstly, the channel steel is blanked according to the size of the drawing, and prefabricated. The bracket is L-shaped as a whole. The vertical distance between the cross arm of the bracket and the bottom of the bridge deck is 1.1m. The horizontal distance of the outer edge of the plate is 0.3m. Insert the extension pipe to the end of the cross arm of the bracket, and weld the bracket to the steel plate embedded in the bridge body. Secondary anti-corrosion treatment should be carried out at the welding place.

作为本发明的进一步改进,所述步骤2的具体内容如下:As a further improvement of the present invention, the specific content of said step 2 is as follows:

步骤2.1,悬臂工作平台和配重推车各两套并且准备就位,施工人员通过爬梯进入悬臂工作台的矩形平台上,汽车起重机在桥面停稳支腿后,缓缓地将钢管吊起,在钢管两端捆绑1根牵引绳索,起吊时用以调整管道的姿势;Step 2.1, two sets of cantilever working platform and counterweight trolley are ready to be put in place. The construction personnel enter the rectangular platform of the cantilever working platform through the ladder. After the truck crane stops on the bridge deck, the steel pipe is slowly lifted , bind a traction rope at both ends of the steel pipe to adjust the posture of the pipe when lifting;

步骤2.2,桥面施工人员通过牵引绳索将管道调整平行于桥身,缓慢地向外移至桥外边沿,使得钢管距桥栏杆水平距离1m;Step 2.2, bridge deck construction personnel adjust the pipe parallel to the bridge body by pulling the rope, and slowly move it outward to the outer edge of the bridge, so that the horizontal distance between the steel pipe and the bridge railing is 1m;

步骤2.3,待钢管整体稳定后,通知桥下方的处于矩形平台上的施工人员做好准备工作并将牵引绳索传递给矩形平台上的施工人员,拉动牵引绳索调整钢管的状态,钢管缓慢地着落在支架的延伸管上,然后将钢管的两端分别拉进悬臂工作台的爬梯与桥身之间的空间;Step 2.3, after the overall stability of the steel pipe, notify the construction personnel on the rectangular platform under the bridge to prepare for the work and pass the traction rope to the construction personnel on the rectangular platform, pull the traction rope to adjust the state of the steel pipe, and the steel pipe slowly lands on the On the extension pipe of the bracket, and then pull the two ends of the steel pipe into the space between the ladder of the cantilever workbench and the bridge body;

步骤2.4,在预埋的钢板上端焊接扣环上下挂手拉葫芦,在手拉葫芦尼龙吊带系好钢管后,利用手拉葫芦分别调节钢管前后两端的径向距离,调整完毕解开钢丝绳及牵引绳索,通知桥面人员收回。Step 2.4: Weld the buckle on the upper end of the pre-embedded steel plate to hang the chain hoist up and down. After the steel pipe is fastened with the nylon sling of the chain hoist, use the chain hoist to adjust the radial distance between the front and rear ends of the steel pipe respectively. After the adjustment, untie the wire rope and pull it Rope, notify the bridge deck personnel to take it back.

作为本发明的进一步改进,所述步骤3的具体内容如下:As a further improvement of the present invention, the specific content of said step 3 is as follows:

步骤3.1,在拟安装管道前端和后端的支架上分别安装一个龙门架,在龙门架的中点挂上手拉葫芦,将葫芦系在钢管上;Step 3.1, install a gantry on the brackets at the front end and rear end of the pipeline to be installed, hang a chain hoist at the midpoint of the gantry, and tie the hoist to the steel pipe;

步骤3.2,利用杠杆原理,用手拉葫芦拉起钢管前端和后端,然后把带有管箍的管托放置在支架上方,放置位置要彩色拉线,确保钢管中心线满足设计要求,每次安放8个管托,钢管定位焊接后,将管托焊接牢固,并进行防腐处理;Step 3.2, using the principle of leverage, pull up the front and rear ends of the steel pipe with a hand chain hoist, and then place the pipe support with pipe hoops on the top of the bracket. 8 pipe holders, after the steel pipe is positioned and welded, the pipe holders are welded firmly and anti-corrosion treatment is carried out;

步骤3.3,钢管就位后,在钢管前端另外配套一台手拉葫芦,用于在调节钢管的轴向位移,使得钢管能与前面安装的钢管进行对口焊接。In step 3.3, after the steel pipe is in place, a hand chain hoist is provided at the front end of the steel pipe to adjust the axial displacement of the steel pipe, so that the steel pipe can be welded to the steel pipe installed in front.

步骤3.4,管道吊装、焊接工作完成后,将悬臂工作平台上的施工设备、工具材料全部转移至桥面,悬臂工作台上的所有施工人员撤离到桥面上,移动配重推车将悬臂工作平台移至下一工作区段重复上述步骤。Step 3.4: After the pipeline hoisting and welding work is completed, all the construction equipment and tools and materials on the cantilever work platform are transferred to the bridge deck, all construction personnel on the cantilever work platform are evacuated to the bridge deck, and the counterweight trolley is moved to work the cantilever. The platform moves to the next working section and repeats the above steps.

作为本发明的进一步改进,所述步骤3.3的具体内容如下:As a further improvement of the present invention, the specific content of said step 3.3 is as follows:

钢管的表面缠绕粗麻布带,用以保护管道表面涂层,再将尼龙纤维吊带多圈、紧密缠绕在麻布带中间,将手拉葫芦的吊钩与吊带环扣牢后,调节葫芦链索与吊带长度,从而调节管道端面对接的轴向间距,当对口精度达到规定要求后,立即用电焊在环向焊缝上多点定位焊接,以固定管道端面,焊点不少于3个,点焊长度为80 mm~100mm,点焊间距不大于400 mm,焊缝高度为2 mm~4mm。The surface of the steel pipe is wrapped with a burlap belt to protect the surface coating of the pipe, and then the nylon fiber sling is tightly wound in the middle of the burlap belt for multiple turns. The length of the sling, so as to adjust the axial distance between the end faces of the pipes. When the matching accuracy reaches the specified requirements, immediately use multi-point positioning welding on the circumferential weld to fix the end faces of the pipes. There are no less than 3 welding points, spot welding The length is 80 mm to 100 mm, the spot welding distance is not more than 400 mm, and the weld height is 2 mm to 4 mm.

作为本发明的进一步改进,所述步骤4的具体内容如下:As a further improvement of the present invention, the specific content of said step 4 is as follows:

伸缩节在安装前进行检验;伸缩节与钢管采用法兰连接,法兰应与管道保持同心,且两法兰间保持平行,与法兰接口的两侧相邻的第一至第二个焊接接口,待法兰螺栓紧固后方可焊接;钢管组成的给排水管道上分别在两端以及中部各安装一只伸缩节。The expansion joint shall be inspected before installation; the expansion joint and the steel pipe shall be connected by flanges, the flange shall be kept concentric with the pipe, and the two flanges shall be kept parallel, and the first to the second welding joint adjacent to the two sides of the flange interface shall be The interface can be welded after the flange bolts are tightened; on the water supply and drainage pipeline composed of steel pipes, an expansion joint is installed at both ends and in the middle.

附图说明Description of drawings

图1为本发明吊装结构示意图一。Fig. 1 is a first schematic diagram of the hoisting structure of the present invention.

图2为本发明吊装结构示意图二。Fig. 2 is the second schematic diagram of the hoisting structure of the present invention.

图3为本发明安装结构示意图。Fig. 3 is a schematic diagram of the installation structure of the present invention.

图4为本发明配重推车和悬臂工作台结构示意图一。Fig. 4 is a structural schematic diagram of a counterweight trolley and a cantilever workbench according to the present invention.

图5为本发明配重推车和悬臂工作台结构示意图二。Fig. 5 is a structural schematic diagram II of the counterweight trolley and the cantilever workbench of the present invention.

图6为本发明支架结构示意图。Fig. 6 is a schematic diagram of the stent structure of the present invention.

其中,1大桥,2悬臂工作台,3配重推车,4汽车起重机,5钢管,6制动杆,7延伸管,8支架,9矩形平台,10下护栏,11底座,12定向轮,13配重块,14顶板,15固定板,16连接板,17爬梯,18上护栏,19管箍,20管托,21横担。Among them, 1 bridge, 2 cantilever workbench, 3 counterweight trolley, 4 truck crane, 5 steel pipe, 6 brake lever, 7 extension pipe, 8 bracket, 9 rectangular platform, 10 lower guardrail, 11 base, 12 directional wheel, 13 counterweight, 14 top plate, 15 fixed plate, 16 connecting plate, 17 climbing ladder, 18 upper guardrail, 19 pipe collar, 20 pipe holder, 21 cross arm.

具体实施方式Detailed ways

下面结合附图对本发明进一步说明:Below in conjunction with accompanying drawing, the present invention is further described:

如图1-6所示的一种桥梁下挂给排水管道的安装装置,包括悬挂在大桥1侧面的悬臂工作台2,所述悬臂工作台2安装在配重推车3上,所述配重推车3设置在大桥1的桥面上,所述大桥1的外边里侧设置有支架8,支架8安装在桥梁板上并处于桥面下方,所述支架8配套设置有延伸管7。As shown in Figure 1-6, an installation device for hanging water supply and drainage pipes under a bridge includes a cantilever workbench 2 suspended on the side of the bridge 1, the cantilever workbench 2 is installed on a counterweight trolley 3, and the cantilever workbench 2 is mounted on a counterweight trolley 3. The heavy trolley 3 is arranged on the deck of the bridge 1, and the outside and inside of the bridge 1 are provided with a bracket 8, the bracket 8 is installed on the bridge deck and is below the bridge deck, and the bracket 8 is equipped with an extension pipe 7.

所述悬臂工作台2包括矩形平台9,所述矩形平台9的外侧边设置有附加槽钢的固定板15,所述矩形平台9的其余三面设置有下护栏10,所述固定板15的顶部设置带有龙骨的顶板14,顶板14与连接板16相连,所述连接板16经螺栓与配重推车3相连,所述固定板15的一侧设置有上护栏18,所述连接板16和上护栏18之间留有间距,所述固定板15的内侧面安装有爬梯17,所述爬梯17设置在连接板16和上护栏18之间。Described cantilever workbench 2 comprises rectangular platform 9, and the outside edge of described rectangular platform 9 is provided with the fixed plate 15 of additional channel steel, and the remaining three sides of described rectangular platform 9 are provided with lower guardrail 10, and the fixed plate 15 A top plate 14 with a keel is arranged on the top, and the top plate 14 is connected with a connecting plate 16, and the connecting plate 16 is connected with the counterweight trolley 3 through bolts, and an upper guardrail 18 is provided on one side of the fixed plate 15, and the connecting plate 16 and the upper guardrail 18 with spacing, the inner surface of the fixed plate 15 is equipped with a ladder 17, the ladder 17 is arranged between the connecting plate 16 and the upper guardrail 18.

所述配重推车3包括底座11,所述底座11上设置有质量不低于1吨的配重块13,所述底座11的底部上设置有定向轮12,所述顶板14靠近连接板16的部分设置有制动杆6。The counterweight trolley 3 includes a base 11, on which a counterweight 13 with a mass of not less than 1 ton is arranged, on the bottom of the base 11, directional wheels 12 are arranged, and the top plate 14 is close to the connecting plate The part of 16 is provided with brake lever 6.

如图1-6所示的一种大桥1给排水管道的安装方法,包括以下步骤:A method for installing the water supply and drainage pipeline of the bridge 1 as shown in Figure 1-6 comprises the following steps:

步骤1,支架8制作安装:Step 1, make and install bracket 8:

先将槽钢按图纸尺寸下料,进行预制,支架8整体呈L形,支架8的横担21距桥板下方的垂直距离1.1m,横担21的尾端在大桥1的桥板外边沿里侧,距桥板外边沿水平距离为0.3m,将延伸管7插接在支架8的横担21端头,将支架8焊接在预埋与桥身内的钢板,所有支架8及钢构件在安装前进行防腐处理并且支架8焊接后,焊接处要进行二次防腐处理。First, the channel steel is blanked according to the size of the drawing, and prefabricated. The bracket 8 is L-shaped as a whole. The vertical distance between the cross arm 21 of the bracket 8 and the bottom of the bridge deck is 1.1m, and the tail end of the cross arm 21 is on the outer edge of the bridge deck of the bridge 1. On the inner side, the horizontal distance from the outer edge of the bridge deck is 0.3m. The extension pipe 7 is inserted into the end of the cross arm 21 of the bracket 8, and the bracket 8 is welded to the steel plate embedded in the bridge body. All the brackets 8 and steel components are in the Carry out anti-corrosion treatment before installation and after the bracket 8 is welded, the welding place will carry out secondary anti-corrosion treatment.

步骤2,管道吊装、就位:Step 2, pipe hoisting and positioning:

步骤2.1,悬臂工作平台和配重推车3各两套并且准备就位,施工人员通过爬梯17进入悬臂工作台2的矩形平台9上,汽车起重机4在桥面停稳支腿后,缓缓地将钢管5吊起,在钢管5两端捆绑1根牵引绳索,起吊时用以调整管道的姿势;In step 2.1, two sets of cantilever work platforms and counterweight trolleys 3 are ready to be put in place. The construction personnel enter the rectangular platform 9 of the cantilever workbench 2 through the ladder 17. After the truck crane 4 stops the legs on the bridge deck, slowly The steel pipe 5 is hoisted safely, and a traction rope is tied at both ends of the steel pipe 5 to adjust the posture of the pipe during hoisting;

步骤2.2,桥面施工人员通过牵引绳索将管道调整平行于桥身,缓慢地向外移至桥外边沿,使得钢管5距桥栏杆水平距离1m;Step 2.2, bridge deck construction personnel adjust the pipeline parallel to the bridge body by pulling the rope, and slowly move outward to the outer edge of the bridge, so that the horizontal distance between the steel pipe 5 and the bridge railing is 1m;

步骤2.3,待钢管5整体稳定后,通知桥下方的处于矩形平台9上的施工人员做好准备工作并将牵引绳索传递给矩形平台9上的施工人员,拉动牵引绳索调整钢管5的状态,钢管5缓慢地着落在支架8的延伸管7上,然后将钢管5的两端分别拉进悬臂工作台2的爬梯17与桥身之间的空间;Step 2.3, after the overall stability of the steel pipe 5, notify the construction personnel on the rectangular platform 9 under the bridge to prepare for the work and pass the traction rope to the construction personnel on the rectangular platform 9, and pull the traction rope to adjust the state of the steel pipe 5. 5 slowly land on the extension pipe 7 of the support 8, and then pull the two ends of the steel pipe 5 into the space between the ladder 17 of the cantilever workbench 2 and the bridge body;

步骤2.4,在预埋的钢板上端焊接扣环上下挂手拉葫芦,在手拉葫芦尼龙吊带系好钢管5后,利用手拉葫芦分别调节钢管5前后两端的径向距离,调整完毕解开钢丝绳及牵引绳索,通知桥面人员收回。Step 2.4: Weld the buckle on the upper end of the pre-embedded steel plate to hang the chain hoist up and down. After the steel pipe 5 is fastened with the nylon sling of the chain hoist, use the chain hoist to adjust the radial distance between the front and rear ends of the steel pipe 5 respectively, and untie the steel wire rope after adjustment. And pull the rope, notify the bridge deck personnel to take it back.

步骤3,管道对口、焊接:Step 3, pipe alignment and welding:

步骤3.1,在拟安装管道前端和后端的支架8上分别安装一个龙门架,在龙门架的中点挂上手拉葫芦,将葫芦系在钢管5上;Step 3.1, install a gantry on the brackets 8 at the front end and rear end of the pipeline to be installed, hang a chain hoist at the midpoint of the gantry, and tie the hoist to the steel pipe 5;

步骤3.2,利用杠杆原理,用手拉葫芦拉起钢管5前端和后端,然后把带有管箍19的管托20放置在支架8上方,放置位置要彩色拉线,确保钢管5中心线满足设计要求,每次安放8个管托20,钢管5定位焊接后,将管托20焊接牢固,并进行防腐处理;Step 3.2, using the principle of leverage, pull up the front and rear ends of the steel pipe 5 with a hand chain hoist, and then place the pipe support 20 with the pipe collar 19 above the bracket 8, and place the colored pull wire to ensure that the center line of the steel pipe 5 meets the design It is required that 8 pipe holders 20 are placed each time, and after the steel pipe 5 is positioned and welded, the pipe holders 20 are firmly welded and anti-corrosion treatment is carried out;

步骤3.3,钢管5就位后,在钢管5前端另外配套一台手拉葫芦,用于在调节钢管5的轴向位移,使得钢管5能与前面安装的钢管5进行对口焊接,钢管5的表面缠绕粗麻布带,用以保护管道表面涂层,再将尼龙纤维吊带多圈、紧密缠绕在麻布带中间,将手拉葫芦的吊钩与吊带环扣牢后,调节葫芦链索与吊带长度,从而调节管道端面对接的轴向间距,当对口精度达到规定要求后,立即用电焊在环向焊缝上多点定位焊接,以固定管道端面,焊点不少于3个,点焊长度为80 mm~100mm,点焊间距不大于400 mm,焊缝高度为2 mm~4mm。Step 3.3, after the steel pipe 5 is in place, an additional hand chain hoist is provided at the front end of the steel pipe 5 to adjust the axial displacement of the steel pipe 5, so that the steel pipe 5 can be welded with the steel pipe 5 installed earlier, and the surface of the steel pipe 5 Wrap the burlap belt to protect the surface coating of the pipeline, and then wrap the nylon fiber sling multiple times tightly in the middle of the sackcloth belt. After fastening the hook and sling ring of the chain hoist firmly, adjust the length of the chain hoist and sling. In order to adjust the axial spacing of the pipe end faces, when the matching accuracy meets the specified requirements, immediately use multi-point positioning welding on the circumferential weld to fix the end face of the pipe. There are no less than 3 welding points, and the spot welding length is 80 mm ~ 100mm, the spot welding spacing is not greater than 400 mm, and the weld height is 2 mm ~ 4mm.

步骤3.4,管道吊装、焊接工作完成后,将悬臂工作平台上的施工设备、工具材料全部转移至桥面,悬臂工作台2上的所有施工人员撤离到桥面上,移动配重推车3将悬臂工作平台移至下一工作区段重复上述步骤。Step 3.4, after the pipeline hoisting and welding work is completed, all the construction equipment and tools and materials on the cantilever work platform are transferred to the bridge deck, all construction personnel on the cantilever work platform 2 are evacuated to the bridge deck, and the counterweight trolley 3 is moved to the bridge deck. The cantilever working platform moves to the next working section and repeats the above steps.

步骤4,管道伸缩节的安装:Step 4, installation of pipe expansion joints:

伸缩节在安装前进行检验;伸缩节与钢管5采用法兰连接,法兰应与管道保持同心,且两法兰间保持平行,与法兰接口的两侧相邻的第一至第二个焊接接口,待法兰螺栓紧固后方可焊接;钢管5组成的给排水管道上分别在两端以及中部各安装一只伸缩节。The expansion joint shall be inspected before installation; the expansion joint and the steel pipe 5 shall be connected by flanges, the flange shall be kept concentric with the pipe, and the two flanges shall be kept parallel, and the first to the second adjacent to the two sides of the flange interface shall be The welding interface can be welded after the flange bolts are tightened; the water supply and drainage pipeline composed of steel pipes 5 is respectively installed with an expansion joint at both ends and in the middle.

本发明中,配重推车3的底座11平台尺寸为2m×2.6m,配重推车3主体结构采用10﹟槽钢和50×5的角钢焊制,底座11四角各设一只直径为10cm的定向轮12便于推车移动,底座11平台上装载总质量不小于1000kg的混凝土预制块作为配重以增强推车的稳定性,配重推车3设有制动杆6,制动时限制推车的移动,保证施工人员在施工作业时平台不能移动,确保施工安全。桥面下方的悬臂工作平台呈矩形,长度3.2m,宽度2.6m,采用规格为10﹟槽钢和50×5的角钢焊制而成,悬臂工作平台和配重推车3用10﹟槽钢连接,并焊接型钢爬梯17,型钢爬梯17与栏杆外侧净距不小于1.2m,为了保护桥面栏杆,防止刮擦。悬臂工作平台便于钢管5焊接施工,距桥板下方的距离约1.8m,在桥面下方焊接钢管5的两端各设置一组悬臂工作平台,通过人力移动配重推车3带动桥下的工作平台沿桥身平行移动,便于管道吊装、就位。施工人员系安全带,安全带系在配重推车3顶部的型钢靠背上且固定可靠,确保作业人员在空中施工安全。In the present invention, the size of the base 11 platform of the counterweight trolley 3 is 2m × 2.6m, the main structure of the counterweight trolley 3 adopts 10﹟ channel steel and 50 × 5 angle steel welding, and the four corners of the base 11 are each provided with a diameter of The directional wheel 12 of 10cm is convenient for cart to move, and the concrete prefabricated block of loading total mass not less than 1000kg is used as counterweight on the platform of base 11 to strengthen the stability of cart, counterweight cart 3 is provided with brake lever 6, when braking Limit the movement of the trolley, ensure that the construction personnel cannot move the platform during construction work, and ensure construction safety. The cantilever working platform under the bridge deck is rectangular, with a length of 3.2m and a width of 2.6m. It is welded by 10﹟ channel steel and 50×5 angle steel. The cantilever working platform and counterweight trolley 3 use 10﹟ channel steel Connect and weld the shaped steel ladder 17, the net distance between the shaped steel ladder 17 and the outside of the railing should not be less than 1.2m, in order to protect the railings on the bridge deck and prevent scratches. The cantilever working platform is convenient for the welding construction of the steel pipe 5, and the distance from the bottom of the bridge deck is about 1.8m. A set of cantilever working platforms are installed at both ends of the welded steel pipe 5 under the bridge deck, and the counterweight trolley 3 is moved by manpower to drive the work under the bridge. The platform moves parallelly along the bridge body, which is convenient for pipeline hoisting and positioning. The construction personnel wear safety belts, and the safety belts are fastened on the shaped steel backrest at the top of the counterweight trolley 3 and are fixed reliably, so as to ensure the safety of the operating personnel during construction in the air.

支架8安装时,先将槽钢按图纸尺寸下料,进行预制,支架8整体呈L形,由22﹟B槽钢组成,支架8的两根槽钢与预埋在桥梁的下侧桥身上的800mm×300mm钢板底座11焊接组对相连,根据所放线的标高安装支架8。When the bracket 8 is installed, the channel steel is cut according to the size of the drawing and prefabricated. The bracket 8 is L-shaped as a whole and is composed of 22﹟B channel steel. The two channel steels of the bracket 8 are embedded in the lower bridge body of the bridge. The 800mm * 300mm steel plate base 11 is welded and connected to each other, and the bracket 8 is installed according to the elevation of the line.

下料的横担21长度约为2.1m,距桥板下方的垂直距离1.1m,横担21尾端在桥板外边沿里侧,距桥板外边沿水平距离为0.3m,防止支架8因淋雨腐蚀而影响其使用寿命;所有支架8及钢构件在安装前进行防腐处理,支架8焊接后,焊接处要进行二次防腐处理。The length of the cross arm 21 for blanking is about 2.1m, and the vertical distance from the bottom of the bridge plate is 1.1m. Rain corrosion affects its service life; all brackets 8 and steel components are subjected to anti-corrosion treatment before installation, and after the bracket 8 is welded, secondary anti-corrosion treatment is carried out at the welding place.

考虑吊装的安全,拟吊装的管道不能过长,运上桥面的DN800钢管5,每根钢管5长度12m,2根组对在桥面上进行对口焊接,焊接成型后,吊装管道长度为24m,吊装总质量不超过6t。Considering the safety of hoisting, the pipeline to be hoisted should not be too long. 5 DN800 steel pipes transported to the bridge deck, each steel pipe 5 is 12m in length, and 2 pairs are welded on the bridge deck. , the total mass of hoisting shall not exceed 6t.

吊装前,在约20 m的两端各设置1套悬臂工作平台+配重推车3,其间距在15 m~20m。吊装机械选用一台25t汽车起重机4,在桥面停稳支腿后,缓缓地将钢管5吊起,在钢管5两端捆绑1根直径为2cm的尼龙纤维牵引绳索,长度约为10m,起吊时用以调整管道的姿势。桥面施工人员通过牵引绳索将管道调整平行于桥身,缓慢地外移至桥外边沿,距桥栏杆水平距离约1m,稳定一会儿,通知桥下方的施工人员(施工人员通过顶板14行走至爬梯17上,再进入矩形平台9上,矩形平台9处于桥下方)做好准备工作后,将牵引绳索传递给桥下方的施工人员,调整钢管5的状态,钢管5缓慢地着落在支架8的延伸管7(采用矩形管)上,然后将钢管5的两端分别拉进型钢爬梯17与桥身之间的空间。Before hoisting, a set of cantilever working platforms + counterweight trolleys 3 are installed at both ends of about 20 m, and the distance between them is 15 m ~ 20 m. A 25t truck crane 4 is selected as the hoisting machine. After the outriggers are stopped on the bridge deck, the steel pipe 5 is slowly lifted, and a nylon fiber traction rope with a diameter of 2cm is tied to both ends of the steel pipe 5, and the length is about 10m. It is used to adjust the posture of the pipeline when lifting. The construction personnel on the bridge deck adjust the pipeline parallel to the bridge body by pulling the rope, and slowly move it to the outer edge of the bridge, about 1m horizontal distance from the bridge railing, stabilize for a while, and notify the construction personnel below the bridge (the construction personnel walk through the roof 14 to the ladder 17, and then enter the rectangular platform 9, the rectangular platform 9 is below the bridge) After the preparations are done, the traction rope is passed to the construction personnel below the bridge, and the state of the steel pipe 5 is adjusted, and the steel pipe 5 slowly falls on the extension of the support 8 Pipe 7 (adopting rectangular pipe), then the two ends of steel pipe 5 are pulled into the space between shaped steel ladder 17 and the bridge body respectively.

其中悬臂支架8横担21在桥板外边沿里侧,自来水钢管5无法着落在横担21上,在拟安装管道的支架8上套上矩形管,延长横担21长度,每根矩形管长度1.6m,在矩形管一端打2个孔,第一个孔距管端5 cm,孔距20cm,孔径12mm,在支架8下方用螺栓把矩形管紧固在悬臂支架8上,延长长度约1m,重叠0.6m,共安装8根矩形管,吊装时钢管5就下落在矩形管上,在预埋800mm×300mm钢板上端焊接扣环,用于下挂手拉葫芦,分别调节钢管5前后两端的径向距离,在手拉葫芦尼龙吊带系好钢管5后,解开管道上的尼龙吊带、钢丝绳及牵引绳索,通知桥面人员收回。Wherein the cantilever support 8 cross arms 21 are on the inner side of the outer edge of the bridge deck, the tap water steel pipe 5 cannot land on the cross arms 21, put a rectangular tube on the support 8 of the pipeline to be installed, extend the length of the cross arms 21, and the length of each rectangular tube 1.6m, drill 2 holes at one end of the rectangular tube, the first hole is 5 cm away from the tube end, the hole distance is 20 cm, and the hole diameter is 12 mm. Fasten the rectangular tube to the cantilever bracket 8 with bolts under the bracket 8, and the extension length is about 1m , with an overlap of 0.6m, a total of 8 rectangular pipes are installed. When hoisting, the steel pipe 5 falls on the rectangular pipe, and a buckle is welded on the upper end of the pre-embedded 800mm×300mm steel plate, which is used to hang the chain hoist. Adjust the front and rear ends of the steel pipe 5 respectively. Radial distance, after the steel pipe 5 is fastened by the nylon sling of the hand chain hoist, untie the nylon sling, steel wire rope and traction rope on the pipeline, and notify the bridge deck personnel to take it back.

每个支架8都安装管箍19,管箍19平分为两个半圆,下方的管箍19焊接在管托20上,管托20凹槽距支架8最小距离8cm,上方没有受力点,而且管道净距只有20 cm左右,因此需要在拟安装的钢管5前端的支架8上安装一个简易的龙门架,在龙门架的中点挂上手拉葫芦,因行程不够,去掉吊钩,将葫芦系在钢管5上,利用杠杆原理,用手拉葫芦拉起钢管5前端,然后把带有管箍19的管托20放置在支架8上方,放置位置要彩色拉线,确保钢管5中心线满足设计要求,用同样的方法,在拟安装的钢管5末端用简易龙门架抬高钢管5末端,安放管托20,每次安放8个管托20左右,管道定位焊接后,将管托20焊接牢固,并进行防腐处理。钢管5就位后,需要与前面安装的管道进行对口焊接,还必须在管道前端配套使用另1台手拉葫芦微调管道的轴向位移,在调节管道轴向位移时,新吊装管道表面缠绕粗麻布带,用以保护管道表面涂层,再将尼龙纤维吊带多圈、紧密缠绕在麻布带中间,将葫芦吊钩与吊带环扣牢后,调节葫芦链索与吊带长度,从而调节管道端面对接的轴向间距,当对口精度达到规定要求后,立即用电焊在环向焊缝上多点定位焊接,以固定管道端面,焊点不少于3个,点焊长度为80 mm~100mm,点焊间距不大于400 mm,焊缝高度为2 mm~4mm。Each bracket 8 is equipped with a pipe collar 19, and the pipe collar 19 is equally divided into two semicircles, and the pipe collar 19 below is welded on the pipe support 20, and the groove of the pipe support 20 has a minimum distance of 8cm from the support 8, and there is no stress point on the top, and The net distance of the pipeline is only about 20 cm, so it is necessary to install a simple gantry frame on the bracket 8 at the front end of the steel pipe 5 to be installed, and hang a chain hoist on the midpoint of the gantry frame. On the steel pipe 5, use the lever principle to pull up the front end of the steel pipe 5 with a hand chain hoist, and then place the pipe support 20 with the pipe collar 19 on the top of the bracket 8, and place the colored pull wire at the position to ensure that the center line of the steel pipe 5 meets the design requirements , using the same method, use a simple gantry to raise the end of the steel pipe 5 at the end of the steel pipe 5 to be installed, place the pipe holder 20, and place about 8 pipe holders 20 each time. After the pipe is positioned and welded, weld the pipe holder 20 firmly. And carry out anti-corrosion treatment. After the steel pipe 5 is in place, it needs to be welded with the previously installed pipe, and another hand chain hoist must be used at the front end of the pipe to fine-tune the axial displacement of the pipe. The linen belt is used to protect the surface coating of the pipeline, and then the nylon fiber sling is tightly wound in the middle of the linen belt for multiple turns. After the gourd hook and the sling ring are fastened, adjust the length of the gourd chain cable and the sling to adjust the connection between the end of the pipeline When the accuracy of the counterpart meets the specified requirements, immediately use multi-point positioning welding on the circumferential weld to fix the end face of the pipe. The welding spacing is not greater than 400 mm, and the welding seam height is 2 mm to 4 mm.

管道环向焊缝根据焊接工艺指导书施工焊接,注意与支架8之间的距离,净距离不小于100mm,每完成一道焊缝,用焊缝量规、钢尺测量焊缝的高度、宽度、咬边、错边的尺寸,逐口检查焊缝的外观质量,钢管5焊接完成后,焊缝质量经过X射线100%探伤检测,焊缝内部没有裂纹、气孔、夹渣等缺陷,焊缝的焊接质量满足国家现行相关规范的要求。检测项目达标后,拆除矩形钢管5和手拉葫芦悬吊系统,对因吊装而损坏的钢管5表面进行补漆,对管道环向焊缝、管箍19的焊缝及附近区域进行表面清理,将上半圆管箍19用螺栓与下半圆的管箍19连接,管箍19与管道的接触面应平整、干净,防止管道滚动,但在轴向上无卡涩现象,保证管道伸缩自由。Pipeline circumferential welds are constructed and welded according to the welding process instruction book, pay attention to the distance from the bracket 8, the net distance is not less than 100mm, and measure the height, width, and bite of the welds with weld gauges and steel rulers after each weld is completed. The size of the side and wrong side, check the appearance quality of the weld seam one by one. After the steel pipe 5 is welded, the quality of the weld seam has passed the X-ray 100% flaw detection test. There are no cracks, pores, slag inclusions and other defects inside the weld seam. The quality meets the requirements of the current relevant national norms. After the test items meet the standards, dismantle the rectangular steel pipe 5 and the chain hoist suspension system, repair the paint on the surface of the steel pipe 5 damaged by hoisting, and clean the surface of the circumferential weld seam of the pipe, the weld seam of the pipe collar 19 and the surrounding area. Connect the upper semicircular pipe collar 19 with the lower semicircular pipe collar 19 with bolts. The contact surface between the pipe collar 19 and the pipe should be flat and clean to prevent the pipe from rolling, but there is no jamming phenomenon in the axial direction to ensure the free expansion and contraction of the pipe.

本区段内的管道吊装、焊接工作完成后,将悬臂工作平台上的施工设备、工具材料全部转移至桥面,桥面下方所有工作人员撤离到桥面上,移动配重推车3将悬臂工作平台移至下一工作区段重复上述施工方法。After the pipeline hoisting and welding work in this section is completed, all the construction equipment and tools and materials on the cantilever working platform will be transferred to the bridge deck, and all the workers below the bridge deck will be evacuated to the bridge deck, and the counterweight trolley 3 will move the cantilever The working platform moves to the next working section and repeats the above-mentioned construction method.

钢管5裸露在空中,受温度、风荷载、不同基础刚度引起的差异沉降等因素的影响,容易出现变形,在管道轴向、径向出现不同的应力,导致管道被破坏,采用伸缩节补偿管道的变形量,保证供水管道的安全。伸缩节是管道中的薄弱环节,又下挂在桥面下方,一旦损坏无法修理,输送的自来水压力较大,对其密封性能要求也高,这对产品的质量和安装的质量提出更高的要求。伸缩节在安装前进行检验,先进行预拉伸或压缩,检查其伸缩性能,密封橡胶圈应平直、无扭曲、正确就位,在有效伸缩范围内,自由伸缩且保持密封性能。伸缩节与钢管5采用法兰连接,法兰应与管道保持同心,且两法兰间保持平行,与法兰接口的两侧相邻的第一至第二个焊接接口,待法兰螺栓紧固后方可焊接。伸缩节也要与管道保持同轴,不得利用伸缩节的轴向、径向、扭转变形来调节管位安装误差。由于桥梁引道和桥身主体地基刚度不同,铺设在引道段的管道与下挂在桥梁下方的管道可能因为差异沉降而变形,在引道段浇筑混凝土止推墩时,对地基进行夯实处理,防止管道通水后因地基下沉而使钢管5产生径向应力,损坏伸缩节。桥梁上的管道全长安装了3只限位伸缩节,每只伸缩节的调节范围不大于150mm,安装伸缩节,既要保证管道安全运行,又要便于其维护,综合考虑,在河两岸各安装1只伸缩节,其距钢管5始端下挂点都约为200m,在枯水季节,两岸的伸缩节还处在陆域上方,可搭设脚手架,便于伸缩节的维修。还有1只伸缩节安装在桥梁中心点附近,距其他2只伸缩节均约为400m。The steel pipe 5 is exposed in the air, affected by factors such as temperature, wind load, and differential settlement caused by different foundation stiffnesses, it is prone to deformation, and different stresses appear in the axial and radial directions of the pipe, resulting in damage to the pipe. The expansion joint is used to compensate the pipe The amount of deformation ensures the safety of the water supply pipeline. The expansion joint is the weak link in the pipeline, and it hangs below the bridge deck. Once damaged, it cannot be repaired. The pressure of the tap water to be transported is high, and the requirements for its sealing performance are also high, which puts higher demands on the quality of the product and the quality of the installation. Require. The expansion joint shall be inspected before installation, pre-stretched or compressed first, and its expansion and contraction performance shall be checked. The sealing rubber ring shall be straight, without distortion, and in place correctly. The expansion joint and the steel pipe 5 are connected by flanges. The flanges should be kept concentric with the pipes, and the two flanges should be kept parallel. It can be welded after solidification. The expansion joint should also be coaxial with the pipe, and the axial, radial and torsional deformation of the expansion joint should not be used to adjust the installation error of the pipe position. Due to the difference in stiffness between the bridge approach and the foundation of the main body of the bridge, the pipes laid in the approach section and the pipes hanging below the bridge may be deformed due to differential settlement. When pouring concrete thrust piers in the approach section, the foundation should be compacted , to prevent the radial stress of the steel pipe 5 due to the subsidence of the foundation after the pipeline is passed through the water, and damage the expansion joint. Three limit expansion joints are installed on the entire length of the pipeline on the bridge, and the adjustment range of each expansion joint is not greater than 150mm. The installation of expansion joints not only ensures the safe operation of the pipeline, but also facilitates its maintenance. Install one expansion joint, which is about 200m away from the hanging point at the beginning of the steel pipe 5. In the dry season, the expansion joints on both sides are still above the land, and scaffolding can be erected to facilitate the maintenance of the expansion joint. There is also one expansion joint installed near the center point of the bridge, about 400m away from the other two expansion joints.

本发明可以用于桥下水面无法架设浮桥或者架设成本过高的情况,在桥身平整光滑,无理想的支撑点,施工人员不借助外部条件无法进入桥下作业的条件下,采用悬臂工作平台2+配重推车3的装置来辅助施工解决了支架安装、管道吊装就位、管道对口焊接等问题,用单面焊接双面成型焊接方法前,进行了焊接试验,并编制焊接工艺指导书,根据焊接工艺指导书施焊,克服了单面焊接双面成型出现的缺陷,保证了焊缝的质量。合理设置伸缩节成功解决了管道伸缩变形的问题,能够经历了严寒极端天气的考验,管道运行平稳,保证了人们正常的生活和生产用水。The present invention can be used in the situation where the floating bridge cannot be erected on the water surface under the bridge or the erection cost is too high. Under the condition that the bridge body is flat and smooth, there is no ideal support point, and construction personnel cannot enter the bridge to work without external conditions, the cantilever working platform is adopted. The device of 2+counterweight trolley 3 is used to assist the construction to solve the problems of bracket installation, pipe hoisting in place, pipe butt joint welding, etc. Before using the single-side welding and double-side forming welding method, the welding test was carried out, and the welding process instruction was compiled , Welding according to the welding process instruction book, which overcomes the defects of single-sided welding and double-sided forming, and ensures the quality of the weld. Reasonable setting of expansion joints has successfully solved the problem of expansion and deformation of the pipeline. It has experienced the test of severe cold and extreme weather, and the pipeline runs smoothly, ensuring people's normal living and production water.

本发明不局限于上述实施例,在本公开的技术方案的基础上,本领域的技术人员根据所公开的技术内容,不需要创造性的劳动就可以对其中的一些技术特征作出一些替换和变形,这些替换和变形均在本发明的保护范围内。The present invention is not limited to the above-mentioned embodiments. On the basis of the disclosed technical solutions, those skilled in the art can make some replacements and deformations to some of the technical features according to the disclosed technical content without creative work. These substitutions and modifications are all within the protection scope of the present invention.

Claims (4)

1.一种桥梁下挂给排水管道的安装方法,利用一种桥梁下挂给排水管道的安装装置,包括悬挂在大桥侧面的悬臂工作台,所述悬臂工作台安装在配重推车上,所述配重推车设置在大桥的桥面上,所述大桥的外边里侧设置有支架,所述支架安装在桥梁板上并处于桥面下方,所述支架配套设置有延伸管;所述悬臂工作台包括矩形平台,所述矩形平台的外侧边设置有附加槽钢的固定板,所述矩形平台的其余三面设置有下护栏,所述固定板的顶部设置带有龙骨的顶板,所述顶板与连接板相连,所述连接板经螺栓与配重推车相连,所述固定板的一侧设置有上护栏,所述顶板和上护栏之间留有间距,所述固定板的内侧面安装有爬梯,所述爬梯设置在连接板和上护栏之间;所述配重推车包括底座,所述底座上设置有质量不低于1吨的配重块,所述底座的底部上设置有定向轮,所述顶板靠近连接板的部分设置有制动杆,其特征在于:包括以下步骤:1. An installation method for hanging water supply and drainage pipelines under a bridge, utilizing a kind of installation device for hanging water supply and drainage pipelines under a bridge, comprising a cantilever workbench suspended on the bridge side, said cantilever workbench being installed on a counterweight trolley, The counterweight trolley is arranged on the deck of the bridge, and a bracket is arranged on the outside and inside of the bridge, and the bracket is installed on the bridge deck and is located below the bridge deck, and the bracket is equipped with an extension pipe; The cantilever workbench includes a rectangular platform, the outer side of the rectangular platform is provided with a fixed plate with additional channel steel, the remaining three sides of the rectangular platform are provided with lower guardrails, and the top of the fixed plate is provided with a top plate with a keel. The top plate is connected with the connecting plate, and the connecting plate is connected with the counterweight trolley through bolts. One side of the fixed plate is provided with an upper guardrail, and there is a distance between the top plate and the upper guardrail. A ladder is installed on the side, and the ladder is arranged between the connecting plate and the upper guardrail; the counterweight trolley includes a base, and a counterweight with a mass of not less than 1 ton is arranged on the base, and the bottom of the base Orientation wheels are provided, and a brake lever is provided on the part of the top plate close to the connecting plate, which is characterized in that it includes the following steps: 步骤1,支架制作安装;Step 1, making and installing the bracket; 先将槽钢按图纸尺寸下料,进行预制,支架整体呈L形,支架的横担距桥板下方的垂直距离1.1m,横担的尾端在大桥的桥板外边沿里侧,距桥板外边沿水平距离为0.3m,将延伸管插接在支架的横担端头,将支架焊接在预埋于桥身内的钢板,所有支架及钢构件在安装前进行防腐处理并且支架焊接后,焊接处要进行二次防腐处理;Firstly, the channel steel is blanked according to the size of the drawing, and prefabricated. The bracket is L-shaped as a whole. The vertical distance between the cross arm of the bracket and the bottom of the bridge deck is 1.1m. The horizontal distance of the outer edge of the plate is 0.3m. Insert the extension pipe to the end of the cross arm of the bracket, and weld the bracket to the steel plate embedded in the bridge body. Secondary anti-corrosion treatment shall be carried out at the welding place; 步骤2,管道吊装、就位;Step 2, pipe hoisting and positioning; 步骤2.1,悬臂工作平台和配重推车各两套并且准备就位,施工人员通过爬梯进入悬臂工作台的矩形平台上,汽车起重机在桥面停稳支腿后,缓缓地将钢管吊起,在钢管两端捆绑1根牵引绳索,起吊时用以调整管道的姿势;Step 2.1, two sets of cantilever working platform and counterweight trolley are ready to be put in place. The construction personnel enter the rectangular platform of the cantilever working platform through the ladder. After the truck crane stops on the bridge deck, the steel pipe is slowly lifted , bind a traction rope at both ends of the steel pipe to adjust the posture of the pipe when lifting; 步骤2.2,桥面施工人员通过牵引绳索将管道调整平行于桥身,缓慢地向外移至桥外边沿,使得钢管距桥栏杆水平距离1m;Step 2.2, bridge deck construction personnel adjust the pipe parallel to the bridge body by pulling the rope, and slowly move it outward to the outer edge of the bridge, so that the horizontal distance between the steel pipe and the bridge railing is 1m; 步骤2.3,待钢管整体稳定后,通知桥下方的处于矩形平台上的施工人员做好准备工作并将牵引绳索传递给矩形平台上的施工人员,拉动牵引绳索调整钢管的状态,钢管缓慢地着落在支架的延伸管上,然后将钢管的两端分别拉进悬臂工作台的爬梯与桥身之间的空间;Step 2.3, after the overall stability of the steel pipe, notify the construction personnel on the rectangular platform under the bridge to prepare for the work and pass the traction rope to the construction personnel on the rectangular platform, pull the traction rope to adjust the state of the steel pipe, and the steel pipe slowly lands on the On the extension pipe of the bracket, and then pull the two ends of the steel pipe into the space between the ladder of the cantilever workbench and the bridge body; 步骤2.4,在预埋的钢板上端焊接扣环上下挂手拉葫芦,在手拉葫芦尼龙吊带系好钢管后,利用手拉葫芦分别调节钢管前后两端的径向距离,调整完毕解开钢丝绳及牵引绳索,通知桥面人员收回;Step 2.4: Weld the buckle on the upper end of the pre-embedded steel plate to hang the chain hoist up and down. After the steel pipe is fastened with the nylon sling of the chain hoist, use the chain hoist to adjust the radial distance between the front and rear ends of the steel pipe respectively. After the adjustment, untie the wire rope and pull it Ropes, notify bridge deck personnel to take them back; 步骤3,管道对口、焊接;Step 3, pipe alignment and welding; 步骤4,管道伸缩节的安装。Step 4, installation of pipe expansion joints. 2.根据权利要求1所述的一种桥梁下挂给排水管道的安装方法,其特征在于,所述步骤3的具体内容如下:2. The installation method of a water supply and drainage pipeline hanging under a bridge according to claim 1, wherein the specific content of the step 3 is as follows: 步骤3.1,在拟安装管道前端和后端的支架上分别安装一个龙门架,在龙门架的中点挂上手拉葫芦,将葫芦系在钢管上;Step 3.1, install a gantry on the brackets at the front end and rear end of the pipeline to be installed, hang a chain hoist at the midpoint of the gantry, and tie the hoist to the steel pipe; 步骤3.2,利用杠杆原理,用手拉葫芦拉起钢管前端和后端,然后把带有管箍的管托放置在支架上方,放置位置要彩色拉线,确保钢管中心线满足设计要求,每次安放8个管托,钢管定位焊接后,将管托焊接牢固,并进行防腐处理;Step 3.2, using the principle of leverage, pull up the front and rear ends of the steel pipe with a hand chain hoist, and then place the pipe support with pipe hoops on the top of the bracket. 8 pipe holders, after the steel pipe is positioned and welded, the pipe holders are welded firmly and anti-corrosion treatment is carried out; 步骤3.3,钢管就位后,在钢管前端另外配套一台手拉葫芦,用于在调节钢管的轴向位移,使得钢管能与前面安装的钢管进行对口焊接;Step 3.3, after the steel pipe is in place, a hand chain hoist is provided at the front end of the steel pipe to adjust the axial displacement of the steel pipe, so that the steel pipe can be welded with the steel pipe installed in front; 步骤3.4,管道吊装、焊接工作完成后,将悬臂工作平台上的施工设备、工具材料全部转移至桥面,悬臂工作台上的所有施工人员撤离到桥面上,移动配重推车将悬臂工作平台移至下一工作区段重复上述步骤。Step 3.4: After the pipeline hoisting and welding work is completed, all the construction equipment and tools and materials on the cantilever work platform are transferred to the bridge deck, all construction personnel on the cantilever work platform are evacuated to the bridge deck, and the counterweight trolley is moved to work the cantilever. The platform moves to the next working section and repeats the above steps. 3.根据权利要求2所述的一种桥梁下挂给排水管道的安装方法,其特征在于,所述步骤3.3的具体内容如下:3. The installation method of a water supply and drainage pipeline hanging under a bridge according to claim 2, wherein the specific content of the step 3.3 is as follows: 钢管的表面缠绕粗麻布带,用以保护管道表面涂层,再将尼龙纤维吊带多圈、紧密缠绕在麻布带中间,将手拉葫芦的吊钩与吊带环扣牢后,调节葫芦链索与吊带长度,从而调节管道端面对接的轴向间距,当对口精度达到规定要求后,立即用电焊在环向焊缝上多点定位焊接,以固定管道端面,焊点不少于3个,点焊长度为80 mm~100mm,点焊间距不大于400mm,焊缝高度为2 mm~4mm。The surface of the steel pipe is wrapped with a burlap belt to protect the surface coating of the pipe, and then the nylon fiber sling is tightly wound in the middle of the burlap belt for multiple turns. The length of the sling, so as to adjust the axial distance between the end faces of the pipes. When the matching accuracy reaches the specified requirements, immediately use multi-point positioning welding on the circumferential weld to fix the end faces of the pipes. There are no less than 3 welding points, spot welding The length is 80 mm to 100 mm, the spot welding distance is not more than 400 mm, and the weld height is 2 mm to 4 mm. 4.根据权利要求3所述的一种桥梁下挂给排水管道的安装方法,其特征在于,所述步骤4的具体内容如下:4. The installation method of a water supply and drainage pipeline hanging under a bridge according to claim 3, wherein the specific content of the step 4 is as follows: 伸缩节在安装前进行检验;伸缩节与钢管采用法兰连接,法兰应与管道保持同心,且两法兰间保持平行,与法兰接口的两侧相邻的第一至第二个焊接接口,待法兰螺栓紧固后方可焊接;钢管组成的给排水管道上分别在两端以及中部各安装一只伸缩节。The expansion joint shall be inspected before installation; the expansion joint and the steel pipe shall be connected by flanges, the flange shall be kept concentric with the pipe, and the two flanges shall be kept parallel, and the first to the second welding joint adjacent to the two sides of the flange interface shall be The interface can be welded after the flange bolts are tightened; on the water supply and drainage pipeline composed of steel pipes, an expansion joint is installed at both ends and in the middle.
CN202111410913.7A 2021-11-25 2021-11-25 Installation device and method for bridge under-hanging water supply and drainage pipeline Active CN113957805B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111410913.7A CN113957805B (en) 2021-11-25 2021-11-25 Installation device and method for bridge under-hanging water supply and drainage pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111410913.7A CN113957805B (en) 2021-11-25 2021-11-25 Installation device and method for bridge under-hanging water supply and drainage pipeline

Publications (2)

Publication Number Publication Date
CN113957805A CN113957805A (en) 2022-01-21
CN113957805B true CN113957805B (en) 2023-06-16

Family

ID=79472056

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111410913.7A Active CN113957805B (en) 2021-11-25 2021-11-25 Installation device and method for bridge under-hanging water supply and drainage pipeline

Country Status (1)

Country Link
CN (1) CN113957805B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117303199B (en) * 2023-10-27 2026-08-11 国网新源集团有限公司 A bridge crane track handling tool

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112482237A (en) * 2020-09-30 2021-03-12 广西正景机械制造有限公司 Bridge rain pipe construction vehicle
CN113215978A (en) * 2021-05-13 2021-08-06 中国化学工程第四建设有限公司 Construction method for laying pipeline along with bridge

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN206591432U (en) * 2017-01-18 2017-10-27 湖南瑞涪科技实业有限公司 Pipe installing job platform
CN209523118U (en) * 2019-01-16 2019-10-22 中交四公局第六工程有限公司 A mobile safety gondola for the installation of drainage pipes under bridges
KR102155675B1 (en) * 2019-06-24 2020-09-14 한국토지주택공사 Bridge work carriage and pipeline construction method
CN212582430U (en) * 2020-05-18 2021-02-23 中建三局第三建设工程有限责任公司 Installation equipment for water drain pipe of overwater super-large bridge

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112482237A (en) * 2020-09-30 2021-03-12 广西正景机械制造有限公司 Bridge rain pipe construction vehicle
CN113215978A (en) * 2021-05-13 2021-08-06 中国化学工程第四建设有限公司 Construction method for laying pipeline along with bridge

Also Published As

Publication number Publication date
CN113957805A (en) 2022-01-21

Similar Documents

Publication Publication Date Title
CN109137867B (en) One kind, which is made and lies on one's side for large jacket side, builds transportation technology
CN107013038B (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN103123016B (en) Construction method for laying gas pipelines along bridge
CN110127530A (en) For hanging apparatus and its application method in restricted clearance workshop
CN108678388B (en) Short mast multi-point integral lifting construction method for large-capacity circular storage tank
CN104670418B (en) Assembly process of helideck of offshore platform
CN110616638A (en) Bracket-free hoisting method for steel box girder in shallow beach area of suspension bridge
CN116281640A (en) A Retrofitting Method for Extending the Main Girder on the Riverside of a Riverside Container Crane
CN116043713A (en) A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air
CN102226497B (en) Manufacturing method of large rubber rolling curtain sealed dry-type gas holder
CN103486330B (en) Either inside high-altitude pipeline mounting construction method
CN205716004U (en) A kind of high pressure vertical shaft penstock erecting device
CN102423833A (en) Method for welding and integrally hoisting volute choke plug of large-sized hydropower station
CN116024904A (en) A method of installation and construction of a long-span basket arch bridge
CN103171976A (en) Hoisting method for shipyard gantry crane
CN110255359A (en) A spreader for hoisting segmental steel girders
CN212599995U (en) Welding installation equipment for hot-melt welded pipe
CN111379900B (en) Method for installing indoor horizontal large flue of large sintering plant
CN113957805A (en) Installation device and method for hanging water supply and drainage pipeline under bridge
CN110094577B (en) Device and method for installing oversized-diameter inclined dam rear open pipe under strong wind condition
CN118729052A (en) A pipeline construction method for a pipeline gallery
CN215803106U (en) Safe construction platform system for mounting steel inner barrel of multi-pipe chimney
CN210890358U (en) Exposed tube installation device behind super major diameter tilting dam under strong wind condition
CN205578897U (en) Deep water J type is system of laying fast
CN210127045U (en) Movable hanging bracket for offshore platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A mounting device and method for water supply and drainage pipes suspended under a bridge

Granted publication date: 20230616

Pledgee: Jiangsu Yangzhou Rural Commercial Bank Co.,Ltd.

Pledgor: Jiangsu Changjiang Water Co.,Ltd.

Registration number: Y2025980057819

PE01 Entry into force of the registration of the contract for pledge of patent right