CN115928731A - Construction method for vertically positioning sludge geological pile foundation - Google Patents

Construction method for vertically positioning sludge geological pile foundation Download PDF

Info

Publication number
CN115928731A
CN115928731A CN202211680797.5A CN202211680797A CN115928731A CN 115928731 A CN115928731 A CN 115928731A CN 202211680797 A CN202211680797 A CN 202211680797A CN 115928731 A CN115928731 A CN 115928731A
Authority
CN
China
Prior art keywords
pile foundation
pile
positioning device
edge
laser
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211680797.5A
Other languages
Chinese (zh)
Inventor
马健勇
王琮
于海涛
相福至
樊建军
郭洪新
时林朋
杨韬
刘洋
王俊鸿
詹桦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Bureau Development and Construction Co Ltd
Original Assignee
China Construction Eighth Bureau Development and Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Bureau Development and Construction Co Ltd filed Critical China Construction Eighth Bureau Development and Construction Co Ltd
Priority to CN202211680797.5A priority Critical patent/CN115928731A/en
Publication of CN115928731A publication Critical patent/CN115928731A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention provides a construction method for vertically positioning a silt geological pile foundation, belonging to the technical field of vertical positioning of pile foundations, and the construction method for vertically positioning the silt geological pile foundation comprises the following steps: preparing a positioning device; marking a lower outer side line pile position edge control point and a lower central pile position control point; mounting a first edge verticality positioning device and a laser receiving plate; marking an upper outer side line pile position control point and an upper central pile position control point; installing a second edge verticality positioning device and a second central verticality positioning device; preparing a display device; placing the guide frame to a pile foundation inserting and beating position, and placing section steel under the guide frame for supporting; roughly leveling the guide frame; accurately leveling the guide frame; placing a pile foundation value to a pile foundation inserting and driving position; adjusting the position of the pile foundation; starting to insert and beat the pile foundation for one time; judging whether the pile foundation is inclined or not; measuring the depth of the pile foundation inserted into the ground; the problem of can't the real-time observation pile foundation whether produce the slope and can't carry out accurate regulation is solved.

Description

Construction method for vertically positioning sludge geological pile foundation
Technical Field
The invention belongs to the technical field of vertical positioning of pile foundations, and particularly relates to a construction method for vertical positioning of a silt geological pile foundation.
Background
Deep foundations consisting of piles and pile caps (called caps for short) connecting pile tops or single-pile foundations consisting of columns and pile foundations, called pile foundations for short). If the pile body is completely buried in the soil and the bottom surface of the bearing platform is contacted with the soil body, the pile body is called a low bearing platform pile foundation; when the upper part of the pile body is exposed out of the ground and the bottom of the pile cap is positioned above the ground, the pile body is called a high pile cap pile foundation. Building pile foundations are typically low cap pile foundations. In high-rise buildings, pile foundations are widely applied. The perpendicularity of the pile foundation is very important in the building, and the precision of the perpendicularity of the pile foundation not only influences the quality of the pile foundation, but also influences the stress condition of the pile foundation; a certain safety distance is reserved outside the structure during construction, so that influence of pile foundation invasion on the internal structure is avoided; the reservation is great then can cause the structure concrete to exceed the side, reserves less then has the pile foundation to invade inner structure problem. Therefore, the control of the perpendicularity of the enclosure pile foundation is of great importance to the economic cost and the structural safety, and the foundation is difficult to correct in the later period and high in factory return cost if inclined in the process of entering the foundation, so that the construction period is prolonged, inconvenience is caused, the effective detection on the perpendicularity of the pile foundation is required in time in the construction process, and the dynamic deviation correction is carried out when problems are found.
At present, in the existing construction method for vertically positioning the pile foundation, the inclination and the inclination angle of the pile foundation need to be measured before the pile is formed, an inclinometer pipe needs to be embedded in the pile, and the problems that whether the pile foundation is inclined or not can not be observed in real time and accurate adjustment cannot be carried out exist.
Disclosure of Invention
In view of the above, the invention provides a construction method for vertically positioning a sludge geological pile foundation, and aims to solve the problems that whether the pile foundation is inclined or not cannot be observed in real time and accurate adjustment cannot be performed in the conventional construction method for vertically positioning the pile foundation.
The invention is realized in the following way:
the invention provides a construction method for vertically positioning a silt geological pile foundation, which specifically comprises the following steps:
s1: preparing a first edge verticality positioning device, a second edge verticality positioning device, a first central verticality positioning device, a second central verticality positioning device and a laser positioning plate;
s2: according to the coordinate reference points and the supporting engineering construction drawing, injecting pile position edge control points and lower center pile position control points of the lower outer side line of the pile foundation according to icons;
s3: fixedly installing a first edge verticality positioning device on a pile position edge control point of a lower outer side line of the pile foundation at the top of the pile foundation, fixedly installing a first central pile foundation verticality positioning device on a lower central pile position control point, and fixedly installing a laser positioning plate on the top of the pile foundation;
s4: marking out the pile position control point of the upper outer edge line of the pile hammer and the pile position control point of the upper center of the pile hammer of the pile driver according to the lower pile position control point of the outer edge line of the pile foundation and the lower center pile position control point of the pile foundation in the step S3;
s5: fixedly installing a second edge verticality positioning device on the pile hammer outer edge pile position control point, and fixedly installing a second central verticality positioning device on the pile hammer central pile position control point;
s6: preparing a display device and a control chip, and electrically connecting the control chip with a first edge verticality positioning device, a second edge verticality positioning device, a first central verticality positioning device, a second central verticality positioning device, a laser positioning plate and the display device;
s7: placing the guide frame to a pile foundation inserting and striking position, and placing section steel under the guide frame for supporting;
s8: roughly leveling the guide frame;
s9: accurately leveling the guide frame;
s10: the pile foundation value is placed to the pile foundation inserting and striking position by controlling a pile foundation control line, the pile foundation is inserted into an upper through hole of a first pile foundation of the guide frame and stops being inserted after penetrating through a lower through hole of the first pile foundation by a first threshold distance;
s11: manually rotating the pile foundation and pushing the pile foundation to adjust the position of the pile foundation so that the first edge verticality positioning device and the second edge verticality positioning device are on the same axis, and the first central verticality positioning device and the second central verticality positioning device are on the same axis;
s12: the pile foundation is inserted and punched at one time, and the pile foundation is sunk by utilizing the self weight of the pile foundation and the pile hammer;
s13: judging whether the pile foundation is skewed, and repeating the step S12 if the pile foundation is not skewed; if the pile foundation is inclined, repeating the step S11;
s14: measuring the depth of the pile foundation inserted into the ground, and if the depth of the pile foundation inserted into the ground is greater than a second threshold value, ending piling; if the depth of the pile foundation inserted into the ground is smaller than the second threshold value, repeating the step S12 and the step S13 until the depth of the pile foundation inserted into the ground is larger than the second threshold value, and finishing piling;
wherein, the display device is a display.
The construction method for vertically positioning the silt geological pile foundation provided by the invention has the following technical effects: by arranging the first edge verticality positioning device, the second edge verticality positioning device, the first central verticality positioning device, the second central verticality positioning device and the laser receiving plate, and manually rotating the pile foundation and pushing the pile foundation to adjust the position of the pile foundation, the first edge verticality positioning device and the second edge verticality positioning device are on the same axis, and the first central verticality positioning device and the second central verticality positioning device are on the same axis, when the second edge verticality positioning device and the second central verticality positioning device send laser signals to the first edge verticality positioning device, the first central verticality positioning device and the laser receiving plate, whether the pile foundation keeps a vertical state or not is judged by judging whether the first edge verticality positioning device and the first central verticality positioning device receive the laser signals; if the pile foundation does not keep vertical, the distance between the second central verticality positioning device and the first central verticality positioning device received on the laser receiving plate can be observed according to the display device, and the deflection degree of the pile foundation is determined and adjusted.
On the basis of the technical scheme, the construction method for vertically positioning the silt geological pile foundation can be further improved as follows:
in step S1, the first edge verticality positioning device includes a first laser receiver, a second laser receiver, a third laser receiver, and a fourth laser receiver; the second edge perpendicularity positioning device comprises a first laser transmitter, a second laser transmitter, a third laser transmitter and a fourth laser transmitter; wherein the content of the first and second substances,
the first laser receiver and the first laser transmitter are on the same axis; the second laser receiver and the second laser transmitter are on the same axis;
the third laser receiver and the third laser transmitter are on the same axis; the fourth laser receiver and the fourth laser transmitter are on the same axis.
Further, in step S1, the first central verticality positioning device is a fifth laser receiver, the second central verticality positioning device is a fifth laser transmitter, wherein,
the fifth laser receiver and the fifth laser transmitter are on the same axis, and the fifth laser receiver is electrically connected with the control chip;
and the fifth laser transmitter is electrically connected with the control chip.
In step S2, the number of the lower outer edge line pile position edge control points is 4, the 4 lower outer edge line pile position edge control points divide the outer edge line of the top of the pile foundation into four equal parts, and the lower center pile position control point is arranged at the center of the circle of the top of the pile foundation.
Further, in step S4, the number of the lower outer edge pile position edge control points is 4, the 4 upper outer edge pile position edge control points divide the outer edge line of the bottom of the pile hammer into four equal parts, the upper central pile position control point is arranged at the center of the top of the pile foundation, the upper outer edge pile position edge control point and the lower outer edge pile position edge control point are located on the same axis, and the lower central pile position control point and the upper central pile position control point are located on the same axis.
Wherein, in step S9, the step of accurately leveling the guide frame specifically comprises the following steps:
the method comprises the following steps: leveling for the first time by jacks at four corners of the guide frame;
step two: the plumb bob and the leveling rod are used for vertical and horizontal control, and secondary leveling is carried out;
step three: fixing a steel plate under the guide frame, and welding and fixing the guide frame, the steel plate pad and the profile steel supporting pad by spot welding;
step four: and (5) removing the jack.
In step S10, the first threshold is 0.3m to 0.4m.
Wherein, in step S11, the position of artifical rotatory pile foundation, promotion pile foundation adjustment pile foundation specifically includes following step:
s111: installing an indicator light on the side wall of the pile foundation;
s112: the constructor pulls the pile foundation control line to carry out rotary pulling treatment on the pile foundation;
s113: judging whether the pile foundation is aligned with the pile hammer, and stopping adjustment when the indicator light on the side wall of the pile foundation is fully on and indicates that the pile foundation is aligned with the pile hammer; when the indicator light on the side wall of the pile foundation is partially not bright, the pile foundation is not aligned with the pile hammer, and the step S112 is repeated;
the indicating lamp comprises a first indicating lamp, a second indicating lamp, a third indicating lamp and a fourth indicating lamp, the first indicating lamp is electrically connected with the first laser receiver, the second indicating lamp is electrically connected with the second laser receiver, the third indicating lamp is electrically connected with the third laser receiver, and the fourth indicating lamp is electrically connected with the fourth laser receiver.
Further, in step S13, determining whether the pile foundation is inclined, specifically including the following steps:
s131: the second edge verticality positioning device and the second center verticality positioning device emit laser signals;
s132: judging whether the first edge verticality positioning device, the first center verticality positioning device and the laser positioning plate receive laser signals or not, if so, fully lighting an indicator lamp on the side wall of the pile foundation to indicate that the pile foundation is not inclined, and finishing the judgment; if the laser signal is not received, the indicator lights on the side wall of the pile foundation are all on or part of the indicator lights are not on, and step S133 is executed;
s133: and observing the direction and the distance between the laser emitted by the second central verticality positioning device and the first central verticality positioning device received on the laser positioning plate according to a display device, and adjusting the position of the pile foundation to enable the pile foundation to be vertical again.
In step S14, the second threshold is 6m to 10m.
Compared with the prior art, the construction method for vertically positioning the silt geological pile foundation has the beneficial effects that: by arranging the first edge verticality positioning device, the second edge verticality positioning device, the first central verticality positioning device, the second central verticality positioning device and the laser receiving plate, and manually rotating the pile foundation and pushing the pile foundation to adjust the position of the pile foundation, the first edge verticality positioning device and the second edge verticality positioning device are on the same axis, and the first central verticality positioning device and the second central verticality positioning device are on the same axis, when the second edge verticality positioning device and the second central verticality positioning device send laser signals to the first edge verticality positioning device, the first central verticality positioning device and the laser receiving plate, whether the pile foundation keeps a vertical state or not is judged by judging whether the first edge verticality positioning device and the first central verticality positioning device receive the laser signals; if the pile foundation is not kept vertical, the distance from the second central verticality positioning device to the first central verticality positioning device received on the laser receiving plate can be observed according to the display device, and the deflection degree of the pile foundation is determined and adjusted.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required to be used in the description of the embodiments of the present invention will be briefly introduced below, and it is obvious that the drawings in the description below are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to the drawings without inventive labor.
FIG. 1 is a flow chart of a construction method for vertical positioning of a silt geological pile foundation;
FIG. 2 is an electrical schematic diagram of vertical positioning of a silt geological pile foundation;
FIG. 3 is a schematic structural diagram of a pile foundation and a pile hammer of the construction method for vertically positioning a silt geological pile foundation;
FIG. 4 is an enlarged schematic view of A of FIG. 3;
FIG. 5 is a flow chart of step S11 of the construction method for vertically positioning the silt geological pile foundation;
FIG. 6 is a flow chart of step S13 of the construction method for vertical positioning of the silt geological pile foundation;
in the drawings, the reference numbers indicate the following list of parts:
1. a pile foundation; 11. a first edge perpendicularity positioning device; 12. a first central perpendicularity positioning device; 13. laser positioning plate; 2. a pile hammer; 21. a second edge perpendicularity positioning device; 22. and a second central verticality positioning device.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention more apparent, the technical solutions of the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings of the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be obtained by a person skilled in the art without inventive efforts based on the embodiments of the present invention, are within the scope of protection of the present invention.
Thus, the following detailed description of the embodiments of the present invention, presented in the figures, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. All other embodiments, which can be obtained by a person skilled in the art without any inventive step based on the embodiments of the present invention, are within the scope of the present invention.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, it need not be further defined or explained in subsequent figures.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", and the like, indicate orientations and positional relationships based on those shown in the drawings, and are used only for convenience of description and simplicity of description, and do not indicate or imply that the equipment or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be considered as limiting the present invention.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless specifically defined otherwise.
As shown in fig. 1 to 4, the present invention provides a first embodiment of a construction method for vertically positioning a silt geological pile foundation, and in this embodiment, the method specifically includes the following steps:
s1: preparing a first edge verticality positioning device, a second edge verticality positioning device, a first central verticality positioning device, a second central verticality positioning device and a laser positioning plate;
s2: according to the coordinate reference points and the supporting engineering construction drawing, injecting pile position edge control points and lower center pile position control points of the lower outer side line of the pile foundation according to icons;
s3: fixedly installing a first edge verticality positioning device on a pile position edge control point of a pile foundation lower outer side line at the top of the pile foundation, fixedly installing a first central pile foundation verticality positioning device on a lower central pile position control point, and fixedly installing a laser positioning plate on the top of the pile foundation;
s4: according to the lower pile position control point of the outer side line of the pile foundation and the lower central pile position control point of the pile foundation in the step S3, the pile position control point of the outer side line of the pile hammer and the upper central pile position control point of the pile hammer of the pile driver are marked;
s5: fixedly installing a second edge verticality positioning device on the pile hammer outer edge pile position control point, and fixedly installing a second central verticality positioning device on the pile hammer central pile position control point;
s6: preparing a display device and a control chip, and electrically connecting the control chip with a first edge verticality positioning device, a second edge verticality positioning device, a first central verticality positioning device, a second central verticality positioning device, a laser positioning plate and the display device;
s7: placing the guide frame to a pile foundation inserting and striking position, and placing section steel under the guide frame for supporting;
s8: roughly leveling the guide frame;
s9: accurately leveling the guide frame;
s10: the pile foundation value is placed to the pile foundation inserting and striking position by controlling a pile foundation control line, the pile foundation is inserted into an upper through hole of a first pile foundation of the guide frame and penetrates through a lower through hole of the first pile foundation by a first threshold distance, and then the insertion is stopped;
s11: manually rotating the pile foundation and pushing the pile foundation to adjust the position of the pile foundation so that the first edge verticality positioning device and the second edge verticality positioning device are on the same axis, and the first central verticality positioning device and the second central verticality positioning device are on the same axis;
s12: starting to insert and beat the pile foundation at one time, and sinking the pile foundation by utilizing the self weight of the pile foundation and the pile hammer;
s13: judging whether the pile foundation is skewed, and repeating the step S12 if the pile foundation is not skewed; if the pile foundation is inclined, repeating the step S11;
s14: measuring the depth of the pile foundation inserted into the ground, and if the depth of the pile foundation inserted into the ground is greater than a second threshold value, ending piling; if the depth of the pile foundation inserted into the ground is smaller than the second threshold value, repeating the step S12 and the step S13 until the depth of the pile foundation inserted into the ground is larger than the second threshold value, and finishing piling;
wherein, the display device is a display.
The laser positioning plate is JY-MRT which is produced by Guangzhou Xin photoelectric technology limited company; the control chip adopts a model ES8P5066 produced by Shanghai east soft Carrier microelectronics Limited; the display adopts an industrial display produced by Nanjing InformationTechnique, inc.
In the above technical solution, in step S1, the first edge perpendicularity positioning device includes a first laser receiver, a second laser receiver, a third laser receiver, and a fourth laser receiver; the second edge perpendicularity positioning device comprises a first laser transmitter, a second laser transmitter, a third laser transmitter and a fourth laser transmitter; wherein, the first and the second end of the pipe are connected with each other,
the first laser receiver and the first laser transmitter are on the same axis; the second laser receiver and the second laser transmitter are on the same axis;
the third laser receiver and the third laser transmitter are on the same axis; the fourth laser receiver and the fourth laser transmitter are on the same axis.
The first laser receiver, the second laser receiver, the third laser receiver and the fourth laser receiver are all manufactured by the model LVTSL-316D-I3 sold by Shenzhen Shangliu photoelectricity Limited company; the first laser transmitter, the second laser transmitter, the third laser transmitter and the fourth laser transmitter are of a model LV02-DT49-5A42-CC sold by Shenzhen Shenzhu photoelectricity Limited company.
Further, in the above technical solution, in step S1, the first central verticality positioning device is a fifth laser receiver, and the second central verticality positioning device is a fifth laser transmitter, wherein,
the fifth laser receiver and the fifth laser transmitter are on the same axis, and the fifth laser receiver is electrically connected with the control chip;
and the fifth laser transmitter is electrically connected with the control chip.
In the above technical solution, in step S2, the number of the lower outer edge pile position edge control points is 4, the 4 lower outer edge pile position edge control points divide the outer edge line of the top of the pile foundation into four equal parts, and the lower central pile position control point is arranged at the center of the circle of the top of the pile foundation.
Further, in the above technical solution, in step S4, the number of the lower outer side line pile position edge control points is 4, the 4 upper outer side line pile position edge control points divide the outer edge line of the bottom of the pile hammer into four equal parts, the upper central pile position control point is disposed at the center of the circle of the top of the pile foundation, the upper outer side line pile position edge control point and the lower outer side line pile position edge control point are located on the same axis, and the lower central pile position control point and the upper central pile position control point are located on the same axis.
Wherein, in the above technical scheme, in step S9, the accurate leveling of the guide frame specifically includes the following steps:
the method comprises the following steps: leveling for the first time by jacks at four corners of the guide frame;
step two: the plumb bob and the level ruler are used for vertical and horizontal control, and secondary leveling is carried out;
step three: fixing a steel plate under the guide frame, and welding and fixing the guide frame, the steel plate pad and the profile steel support pad by spot welding;
step four: and (5) removing the jack.
In the above technical solution, in step S10, the first threshold is 0.3m to 0.4m.
Wherein, as shown in fig. 5, in the above technical solution, in step S11, the position of the pile foundation is adjusted by manually rotating the pile foundation and pushing the pile foundation, which specifically includes the following steps:
s111: installing an indicator light on the side wall of the pile foundation;
s112: the constructor pulls the pile foundation control line to carry out rotary pulling treatment on the pile foundation;
s113: judging whether the pile foundation is aligned with the pile hammer, and stopping adjustment when the indicator light on the side wall of the pile foundation is fully on and indicates that the pile foundation is aligned with the pile hammer; when the indicator light on the side wall of the pile foundation is partially not bright, the pile foundation is not aligned with the pile hammer, and the step S112 is repeated;
the indicating lamp comprises a first indicating lamp, a second indicating lamp, a third indicating lamp and a fourth indicating lamp, the first indicating lamp is electrically connected with the first laser receiver, the second indicating lamp is electrically connected with the second laser receiver, the third indicating lamp is electrically connected with the third laser receiver, and the fourth indicating lamp is electrically connected with the fourth laser receiver.
Further, as shown in fig. 6, in the above technical solution, in the step S13, determining whether the pile foundation is inclined specifically includes the following steps:
s131: the second edge verticality positioning device and the second center verticality positioning device emit laser signals;
s132: judging whether the first edge verticality positioning device, the first center verticality positioning device and the laser positioning plate receive laser signals or not, if so, fully lighting an indicator lamp on the side wall of the pile foundation to indicate that the pile foundation is not inclined, and finishing the judgment; if the laser signal is not received, the indicator lights on the side wall of the pile foundation are all on or part of the indicator lights are not on, and step S133 is executed;
s133: and (4) observing the direction and distance from the laser emitted by the second central verticality positioning device to the first central verticality positioning device on the laser positioning plate according to the display device, and adjusting the position of the pile foundation to enable the pile foundation to be vertical again.
In the above technical solution, in step S14, the second threshold is 6m to 10m.
Specifically, the principle of the invention is as follows: by arranging the first edge verticality positioning device, the second edge verticality positioning device, the first central verticality positioning device, the second central verticality positioning device and the laser receiving plate, and manually rotating the pile foundation and pushing the pile foundation to adjust the position of the pile foundation, the first edge verticality positioning device and the second edge verticality positioning device are on the same axis, and the first central verticality positioning device and the second central verticality positioning device are on the same axis, when the second edge verticality positioning device and the second central verticality positioning device send laser signals to the first edge verticality positioning device, the first central verticality positioning device and the laser receiving plate, whether the pile foundation keeps a vertical state or not is judged by judging whether the first edge verticality positioning device and the first central verticality positioning device receive the laser signals; if the pile foundation does not keep vertical, the distance between the second central verticality positioning device and the first central verticality positioning device received on the laser receiving plate can be observed according to the display device, and the deflection degree of the pile foundation is determined and adjusted.
The above description is only for the specific embodiments of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art can easily conceive of the changes or substitutions within the technical scope of the present invention, and all the changes or substitutions should be covered within the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (10)

1. A construction method for vertically positioning a silt geological pile foundation is characterized by comprising the following steps:
s1: preparing a first edge verticality positioning device, a second edge verticality positioning device, a first central verticality positioning device, a second central verticality positioning device and a laser positioning plate;
s2: according to the coordinate reference points and the supporting engineering construction drawing, injecting pile position edge control points and lower center pile position control points of the lower outer side line of the pile foundation according to icons;
s3: fixedly installing a first edge verticality positioning device on a pile position edge control point of a lower outer side line of the pile foundation at the top of the pile foundation, fixedly installing a first central pile foundation verticality positioning device on a lower central pile position control point, and fixedly installing a laser positioning plate on the top of the pile foundation;
s4: according to the lower pile position control point of the outer side line of the pile foundation and the lower central pile position control point of the pile foundation in the step S3, the pile position control point of the outer side line of the pile hammer and the upper central pile position control point of the pile hammer of the pile driver are marked;
s5: fixedly installing a second edge verticality positioning device on an outer side line edge pile position control point on the pile hammer, and fixedly installing a second central verticality positioning device on a central pile position control point on the pile hammer;
s6: preparing a display device and a control chip, and electrically connecting the control chip with a first edge verticality positioning device, a second edge verticality positioning device, a first central verticality positioning device, a second central verticality positioning device, a laser positioning plate and the display device;
s7: placing the guide frame to a pile foundation inserting and beating position, and placing section steel under the guide frame for supporting;
s8: roughly leveling the guide frame;
s9: accurately leveling the guide frame;
s10: the pile foundation value is placed to the pile foundation inserting and striking position by controlling a pile foundation control line, the pile foundation is inserted into an upper through hole of a first pile foundation of the guide frame and stops being inserted after penetrating through a lower through hole of the first pile foundation by a first threshold distance;
s11: manually rotating the pile foundation and pushing the pile foundation to adjust the position of the pile foundation so that the first edge verticality positioning device and the second edge verticality positioning device are on the same axis, and the first central verticality positioning device and the second central verticality positioning device are on the same axis;
s12: starting to insert and beat the pile foundation at one time, and sinking the pile foundation by utilizing the self weight of the pile foundation and the pile hammer;
s13: judging whether the pile foundation is skewed, and repeating the step S12 if the pile foundation is not skewed; if the pile foundation is inclined, repeating the step S11;
s14: measuring the depth of the pile foundation inserted into the ground, and if the depth of the pile foundation inserted into the ground is greater than a second threshold value, ending piling; if the depth of the pile foundation inserted into the ground is smaller than the second threshold value, repeating the step S12 and the step S13 until the depth of the pile foundation inserted into the ground is larger than the second threshold value, and finishing piling;
wherein, the display device is a display.
2. The construction method for vertically positioning the sludge geological pile foundation according to the claim 1, characterized in that in the step S1, the first edge verticality positioning device comprises a first laser receiver, a second laser receiver, a third laser receiver and a fourth laser receiver; the second edge perpendicularity positioning device comprises a first laser transmitter, a second laser transmitter, a third laser transmitter and a fourth laser transmitter; wherein the content of the first and second substances,
the first laser receiver and the first laser transmitter are on the same axis; the second laser receiver and the second laser transmitter are on the same axis;
the third laser receiver and the third laser transmitter are on the same axis; the fourth laser receiver and the fourth laser transmitter are on the same axis.
3. The construction method for vertically positioning a sludge geological pile foundation according to the claim 2, characterized in that in the step S1, the first central verticality positioning device is a fifth laser receiver, the second central verticality positioning device is a fifth laser transmitter, wherein,
the fifth laser receiver and the fifth laser transmitter are on the same axis, and the fifth laser receiver is electrically connected with the control chip;
and the fifth laser transmitter is electrically connected with the control chip.
4. The construction method for vertically positioning a sludge geological pile foundation according to claim 1, characterized in that in step S2, the number of the lower outer edge line pile position edge control points is 4, the 4 lower outer edge line pile position edge control points divide the outer edge line of the top of the pile foundation into four equal parts, and the lower central pile position control point is arranged at the center of the circle of the top of the pile foundation.
5. The construction method for vertically positioning a silt geological pile foundation according to claim 4, wherein in step S4, the number of the lower outer side line pile position edge control points is 4, the 4 upper outer side line pile position edge control points are used for dividing the outer edge line of the bottom of the pile hammer into four equal parts, the upper central pile position control point is arranged at the center of the top of the pile foundation, the upper outer side line pile position edge control point and the lower outer side line pile position edge control point are on the same axis, and the lower central pile position control point and the upper central pile position control point are on the same axis.
6. The construction method for vertically positioning the silt geological pile foundation according to claim 1, wherein in the step S9, the step of accurately leveling the guide frame specifically comprises the following steps:
the method comprises the following steps: leveling for the first time by jacks at four corners of the guide frame;
step two: the plumb bob and the leveling rod are used for vertical and horizontal control, and secondary leveling is carried out;
step three: fixing a steel plate under the guide frame, and welding and fixing the guide frame, the steel plate pad and the profile steel supporting pad by spot welding;
step four: and (5) removing the jack.
7. The construction method for vertically positioning the sludge geological pile foundation according to the claim 1, wherein the first threshold value is 0.3 m-0.4 m in the step S10.
8. The construction method for vertically positioning the silt geological pile foundation according to claim 1, wherein in the step S11, the pile foundation is manually rotated and pushed to adjust the position of the pile foundation, and the method specifically comprises the following steps:
s111: installing an indicator light on the side wall of the pile foundation;
s112: the constructor pulls the pile foundation control line to carry out rotary pulling treatment on the pile foundation;
s113: judging whether the pile foundation is aligned with the pile hammer, and stopping adjustment when the indicator light on the side wall of the pile foundation is fully on and indicates that the pile foundation is aligned with the pile hammer; when the indicator light on the side wall of the pile foundation is partially not bright, the pile foundation is not aligned with the pile hammer, and the step S112 is repeated;
the indicating lamp comprises a first indicating lamp, a second indicating lamp, a third indicating lamp and a fourth indicating lamp, the first indicating lamp is electrically connected with the first laser receiver, the second indicating lamp is electrically connected with the second laser receiver, the third indicating lamp is electrically connected with the third laser receiver, and the fourth indicating lamp is electrically connected with the fourth laser receiver.
9. The construction method for vertically positioning the sludge geological pile foundation according to claim 8, wherein in the step S13, whether the pile foundation is inclined or not is judged, and the method specifically comprises the following steps:
s131: the second edge verticality positioning device and the second center verticality positioning device emit laser signals;
s132: judging whether the first edge verticality positioning device, the first center verticality positioning device and the laser positioning plate receive laser signals or not, if so, fully lighting an indicator lamp on the side wall of the pile foundation to indicate that the pile foundation is not inclined, and finishing the judgment; if the laser signal is not received, the indicator lights on the side wall of the pile foundation are all on or part of the indicator lights are not on, and step S133 is executed;
s133: and observing the direction and distance from the laser emitted by the second central verticality positioning device to the first central verticality positioning device on the laser positioning plate according to a display device, and adjusting the position of the pile foundation to enable the pile foundation to be vertical again.
10. The construction method for vertically positioning the sludge geological pile foundation according to the claim 1, wherein the second threshold value is 6m to 10m in the step S14.
CN202211680797.5A 2022-12-27 2022-12-27 Construction method for vertically positioning sludge geological pile foundation Pending CN115928731A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211680797.5A CN115928731A (en) 2022-12-27 2022-12-27 Construction method for vertically positioning sludge geological pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211680797.5A CN115928731A (en) 2022-12-27 2022-12-27 Construction method for vertically positioning sludge geological pile foundation

Publications (1)

Publication Number Publication Date
CN115928731A true CN115928731A (en) 2023-04-07

Family

ID=86550465

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211680797.5A Pending CN115928731A (en) 2022-12-27 2022-12-27 Construction method for vertically positioning sludge geological pile foundation

Country Status (1)

Country Link
CN (1) CN115928731A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117231201A (en) * 2023-10-12 2023-12-15 广东省建设工程质量安全检测总站有限公司 Error elimination method and related device for pile foundation drill hole inclination measurement

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117231201A (en) * 2023-10-12 2023-12-15 广东省建设工程质量安全检测总站有限公司 Error elimination method and related device for pile foundation drill hole inclination measurement
CN117231201B (en) * 2023-10-12 2024-03-29 广东省建设工程质量安全检测总站有限公司 Error elimination method and related device for pile foundation drill hole inclination measurement

Similar Documents

Publication Publication Date Title
CN108280969B (en) High-slope surface deformation monitoring and early warning system and early warning method thereof
CN104563171B (en) A kind of pile penetration checkout gear of steel pipe pile hammer piling and detection method
CN115928731A (en) Construction method for vertically positioning sludge geological pile foundation
JP5486863B2 (en) Vertical accuracy control method for structural pillars
CN112554222B (en) Pile foundation reinforcement cage elevation and centering positioning device and method
CN110984967A (en) Drilling depth and verticality measuring device and using method
CN113431039A (en) Construction method of bridge implanted pile
CN112049648B (en) Pipe jacking construction monitoring control method
CN210797670U (en) Deep basal pit supporting construction top horizontal displacement monitoring devices
CN112187843A (en) BIM-based system and method for automatically monitoring capital construction risks of deep foundation pit
CN215052830U (en) Earthwork measuring instrument
CN109736296B (en) Method for setting factory building reference
CN107489140B (en) A kind of method of accurate control CFG stake top elevation
CN111963053B (en) Positioning system-based hole forming control method and system for cast-in-place pile machine
CN109868851B (en) Measuring method for controlling verticality of wind power foundation steel pipe pile
CN115450437A (en) Steel pipe column rear-inserting construction method based on reverse construction
CN210151532U (en) Side pile positioning device for roadbed and pavement engineering construction
CN209230632U (en) A kind of measurement and positioning and the fixed control stake of elevation
CN110206075A (en) A kind of deep foundation pit supporting structure top horizontal displacement monitor and application method
CN110685303B (en) Method for measuring base section in sinking process of open caisson
CN219547784U (en) Perpendicularity control device of foundation pit supporting occlusion pile
CN110629756A (en) Anchor cable removing method
CN111395339A (en) Mounting structure and mounting method for accurately embedding cast-in-situ bored pile casing
CN216689506U (en) Foundation pit construction ground layer subsides detector
CN214939994U (en) Earthwork flat foundation monitoring system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination