CN115830818A - Early warning method, device, equipment and system for cast-in-situ bored pile construction - Google Patents

Early warning method, device, equipment and system for cast-in-situ bored pile construction Download PDF

Info

Publication number
CN115830818A
CN115830818A CN202211497821.1A CN202211497821A CN115830818A CN 115830818 A CN115830818 A CN 115830818A CN 202211497821 A CN202211497821 A CN 202211497821A CN 115830818 A CN115830818 A CN 115830818A
Authority
CN
China
Prior art keywords
construction
pouring
parameters
drilling
early warning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211497821.1A
Other languages
Chinese (zh)
Inventor
和晓楠
徐荣
李林川
张静涛
陈许明
李俊伟
赵健
卢永琪
韩焱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202211497821.1A priority Critical patent/CN115830818A/en
Publication of CN115830818A publication Critical patent/CN115830818A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The disclosure relates to a construction early warning method, device, equipment and system for a cast-in-situ bored pile. The method comprises the following steps: in the process of manufacturing the reinforcement cage, acquiring key parameters of the reinforcement cage, and performing early warning according to the key parameters of the reinforcement cage; after the reinforcement cage is manufactured, early warning is carried out according to drilling parameters of a single drill hole in the drilling construction process; after the drilling construction is finished, in the process of pouring concrete, pouring parameters are obtained, and early warning is carried out according to the pouring parameters. According to the method and the device, early warning is timely carried out according to the parameters of each of the three parts of the cast-in-situ bored pile construction. The passive quality inspection is changed into active quality inspection. The method is favorable for improving the engineering quality of the cast-in-situ bored pile construction engineering, avoiding rework caused by non-compliance parameters, improving the construction efficiency and improving the accuracy of construction quality control.

Description

Early warning method, device, equipment and system for cast-in-situ bored pile construction
Technical Field
The disclosure relates to the technical field of cast-in-place piles, in particular to a construction early warning method, device, equipment and system for a cast-in-place bored pile.
Background
Cast-in-situ bored piles are a very common construction project. In the related art, the construction quality inspection of the cast-in-situ bored pile is passive quality inspection. I.e. manually check the individual key parameters after the end of the project. Because the project is finished, if some serious problems are found, the project still needs to be reworked, the efficiency of the whole project is reduced, and the cost is wasted.
Disclosure of Invention
In order to overcome the problems in the related art, the present disclosure provides a pre-warning method, device, equipment and system for bored pile construction, so as to solve the above problems.
According to a first aspect of the embodiments of the present disclosure, there is provided a bored pile construction early warning method, including:
in the process of manufacturing the reinforcement cage, acquiring key parameters of the reinforcement cage, and performing early warning according to the key parameters of the reinforcement cage;
after the reinforcement cage is manufactured, early warning is carried out according to drilling parameters of a single drill hole in the drilling construction process;
after the drilling construction is finished, in the process of pouring concrete, pouring parameters are obtained, and early warning is carried out according to the pouring parameters.
In one embodiment, the method further comprises: after the reinforcement cage is manufactured, generating a reinforcement cage quality score according to the key parameters of the reinforcement cage;
after the single drilling is finished, generating a drilling quality score according to the drilling parameters of the single drilling;
after pouring is finished, determining a pouring construction quality score according to the pouring parameters;
and determining the quality score of the whole drilling hole pouring construction according to the steel reinforcement cage quality score, the drilling hole quality score and the pouring construction quality score.
In one embodiment, the concrete placement parameters include: slump, test piece strength, filling coefficient and filling time.
In one embodiment, before construction, early warning is performed according to the key parameters of the reinforcement cage, and the early warning comprises the following steps:
obtaining a design value and a construction value of key parameters of the reinforcement cage;
determining a construction error value of the key parameter according to the design value and the construction value of the key parameter;
determining the quality score of the reinforcement cage according to the construction error value;
the key parameters of the reinforcement cage include: the main rib spacing, the stirrup spacing, the cage diameter, the cage length and the cage top elevation;
and if the construction error value is greater than a preset early warning error threshold value, first warning information is sent out.
In one embodiment, the drilling parameters include: pile position coordinates, drilling depth, verticality, drilling diameter and sediment thickness;
in the drilling construction process, determining the construction quality score of the drill hole according to the drilling parameters of the single drill hole and giving an early warning, wherein the method comprises the following steps:
and controlling an alarm device to send out second alarm information in response to the fact that the difference value between the construction value and the design value of the drilling parameter is equal to or larger than a preset early-warning difference value threshold value.
In one embodiment, in the process of pouring concrete, obtaining pouring parameters, generating a pouring construction quality score according to the pouring parameters and performing early warning, the method comprises the following steps:
and controlling an alarm device to send out third alarm information in response to the fact that the difference value between the construction value and the design value of the pouring parameter is larger than the early-warning difference value threshold value.
In one embodiment, the pouring parameter is a pour time;
determining a design value for the perfusion time comprising:
acquiring the elevation of the designed top surface of the single pile;
determining theoretical concrete pouring amount according to the designed top surface elevation, the diameter of the drilled hole and the filling coefficient;
determining a design value of the pouring time according to the pouring amount of the tank car in unit time and the theoretical poured concrete amount;
and controlling an alarm device to send out third alarm information in response to the fact that the difference value between the construction value and the design value of the pouring time is larger than or equal to the pouring time difference value threshold.
According to a third aspect of the embodiments of the present disclosure, there is provided an electronic apparatus including: a processor; a memory for storing processor-executable instructions; wherein the processor is configured to execute the executable instructions to implement the steps of the above-described method.
According to a fourth aspect of embodiments of the present disclosure, there is provided a non-transitory computer readable storage medium having stored thereon computer program instructions which, when executed by a processor, implement the steps of the above-described method.
According to a fifth aspect of the embodiments of the present disclosure, a bored pile construction early warning system includes: the electronic device and the alarm device described above; the alarm device is connected with the electronic equipment; the electronic equipment and the alarm device are arranged in a cab of the drilling machine.
The technical scheme provided by the embodiment of the disclosure can have the following beneficial effects: according to the method and the device, early warning is timely carried out according to the parameters of each of the three parts of the cast-in-situ bored pile construction. The passive quality inspection is changed into active quality inspection. The method is favorable for improving the engineering quality of the cast-in-situ bored pile construction engineering, avoiding rework caused by non-compliance parameters, improving the construction efficiency and improving the accuracy of construction quality control.
It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the disclosure.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present disclosure and together with the description, serve to explain the principles of the disclosure.
FIG. 1 is a flow chart illustrating a method of pre-warning of bored pile construction according to an exemplary embodiment;
FIG. 2 is a block diagram illustrating a bored pile construction early warning apparatus in accordance with an exemplary embodiment;
FIG. 3 is a block diagram illustrating a bored pile construction early warning apparatus in accordance with an exemplary embodiment;
fig. 4 is a block diagram illustrating a bored pile construction early warning system in accordance with an exemplary embodiment.
Detailed Description
Reference will now be made in detail to the exemplary embodiments, examples of which are illustrated in the accompanying drawings. When the following description refers to the accompanying drawings, like numbers in different drawings represent the same or similar elements unless otherwise indicated. The implementations described in the exemplary embodiments below are not intended to represent all implementations consistent with the present disclosure. Rather, they are merely examples of apparatus and methods consistent with certain aspects of the present disclosure, as detailed in the appended claims.
It should be noted that all actions of acquiring signals, information or data in the present application are performed under the premise of complying with the corresponding data protection regulation policy of the country of the location and obtaining the authorization given by the owner of the corresponding device.
The application provides a construction early warning method for a cast-in-situ bored pile, which is shown in a flow chart of the construction early warning method for the cast-in-situ bored pile shown in the attached drawing 1; the method may comprise the steps of:
in the step S102, in the process of manufacturing the reinforcement cage, key parameters of the reinforcement cage are obtained, and early warning is carried out according to the key parameters of the reinforcement cage.
In this embodiment, the key parameters of the reinforcement cage may be the main reinforcement spacing, the stirrup spacing, the cage diameter, the cage length, and the cage top elevation.
And determining the difference value between the construction value and the design standard value of the key parameter of the reinforcement cage, and if the difference value reaches a preset reinforcement cage difference value early warning threshold value, alarming by adopting an alarming device, wherein the alarming information can be sent out, and can be voice or displayed on a display screen of the electronic equipment for characters.
The key parameter early warning threshold value of the reinforcement cage can be flexibly set, and can be set to be 80% or 90% of the difference threshold value of the key parameters of the reinforcement cage specified by the specification.
For example, the difference threshold value specified by the specification of the length of the reinforcement cage is 100 mm, the early warning threshold value of the length parameter can be set to 80 mm, and if the deviation of the actual length is equal to or greater than 80 mm, an alarm can be given.
After obtaining the key parameters of the reinforcement cage, the user can input the key parameters into the electronic equipment, and the electronic equipment can be movable electronic equipment. The electronic equipment is provided with a display screen which can display characters, and a sound production device which can give an alarm by voice. And after alarming, reminding a user of timely adjusting the reinforcement cage.
And step S104, after the reinforcement cage is manufactured, early warning is carried out according to drilling parameters of a single drill hole in the drilling construction process.
In this embodiment, in the drilling process, drilling parameters can be obtained, and if the deviation value of the drilling parameters reaches the early warning difference threshold value, an alarm can be given to the user, and the drilling machine can be stopped in time. Wherein, the drilling parameters can be the coordinates of the pile, the diameter of the hole, the verticality of the hole, the depth of the hole and the thickness of the sediment.
The drilling early warning difference threshold value can be flexibly set and can be set to be 80% or 90% of the difference threshold value specified by the specification.
The electronic equipment can be arranged in a cab of the drilling machine, the noise is high on the construction site, and if the electronic equipment is arranged in the cab, the electronic equipment gives an alarm voice, can remind a drilling driver in time and plays a role in giving an alarm in time. For example, if the depth of the borehole exceeds a predetermined depth value, the warning device may issue a voice prompt alerting the driver to stop digging the hole.
In step S106, after the drilling construction is finished, in the process of pouring concrete, pouring parameters are obtained, and early warning is carried out according to the pouring parameters.
In the present embodiment, the concrete pouring parameters include: slump, test piece strength, filling coefficient and filling time.
Taking slump as an example, in a construction site, a concrete sample is obtained, a measured value of the slump of the concrete is obtained and then input into the electronic equipment, and the electronic equipment compares the measured value with a preset theoretical design value of the slump. If the difference value between the slump and the theoretical design value is larger than a preset difference value early warning threshold value, the slump is unqualified, alarm information is sent out in time to give an alarm so as to remind field personnel, and the mix proportion of the concrete needs to be adjusted so as to meet the slump requirement.
The concrete pouring parameter difference early warning threshold value can be flexibly set. For example, the concrete pouring parameter difference early warning threshold may be set to 80% or 90% of the difference threshold of the concrete pouring parameter specified by the standard specification.
The difference threshold of the key parameters can be determined according to T _ CECS 592-2019-cast-in-situ bored pile construction technical standard.
The method of the invention respectively carries out parameter measurement and early warning work in the three aspects of manufacturing of the reinforcement cage, drilling construction and pouring construction, can obviously provide the engineering quality of the whole drilling and pouring construction, and is beneficial to avoiding the situations of engineering accidents, rework and the like caused by the failure of key parameters.
The quality of the engineering site is improved.
In order to realize more refined quality evaluation work, in one implementation mode, after the reinforcement cage is manufactured, a reinforcement cage quality score is generated according to the reinforcement cage key parameters.
In this embodiment, if the difference value of the key parameters of the steel reinforcement cage is less than or equal to the difference threshold value, quantitative scoring may be performed, and if the difference value is greater than the difference threshold value, the score is zero. For the condition that the difference value of the key parameters of the reinforcement cage is smaller than or equal to the difference value threshold value specified by the specification, the deduction value can be set to be positively correlated with the deviation value.
For example, a predetermined score may be set for each key, see table 1:
main rib spacing 25 minutes
Space between stirrups 25 minutes
Cage diameter 25 minutes
Cage length 25 minutes
TABLE 1
For example, if the difference between the measured cage length and the design value is greater than the error threshold specified by the specification, 25 points are completely deducted. If the difference of the cage length is within the error threshold value range specified by the specification, the deducted fraction is determined according to the proportion relation of the actual difference and the difference threshold value. The subtracted fraction = the actual deviation/difference threshold x the predetermined fraction for this parameter. For example, the specification for the length of the reinforcement cage specifies a difference threshold of 100 mm, while if the actual deviation is 10 mm, the score subtracted is 2.5 points, and the parameter score is 22.5 points. For another example, if the actual deviation is 20 mm, the score of the subtraction is 5 points, and the parameter score is 20 points.
In some embodiments, the parameter of the reinforcement cage further comprises a cage top elevation in order to control whether the lowering of the reinforcement cage is qualified. The elevation of the top of the cage is the depth of the steel reinforcement cage after the steel reinforcement cage is completely transferred. If the difference value between the construction value and the design value of the cage top elevation is larger than a preset early warning difference value threshold value, alarm information can be sent out in time. And if the difference value of the cage top elevation is within the error threshold value range specified by the specification, determining the deducted fraction according to the proportional relation between the actual difference value and the difference threshold value. Illustratively, the top elevation of the cage alone may be set to a predetermined score, for example, 40 points, and if the actual difference is greater than the difference threshold specified by the specification, the difference is rejected and 40 points are deducted. If the actual difference is less than the difference threshold specified by the specification, the installation ratio determines the score to be deducted, and thus the score is determined.
In some embodiments, after the single borehole is completed, a borehole quality score is generated from the drilling parameters of the single borehole.
Wherein, above-mentioned drilling parameter includes: pile position coordinates, drilling depth, perpendicularity, drilling diameter and sediment thickness.
Wherein the perpendicularity is determined according to the offset distance and the hole depth of the hole.
See table 2 for drilling parameter ratings.
Pile position coordinate 20 minutes
Depth of drilled hole 20 minutes
Verticality of a plane 20 minutes
Diameter of drilled hole 20 minutes
Thickness of sediment 20 minutes
TABLE 2
If the difference in the drilling parameters is within the difference threshold specified by the specifications, the subtracted score is determined as a function of the ratio of the actual difference to the difference threshold. The subtracted fraction = the actual bias/difference threshold gamma the predetermined fraction for the parameter. For example, the specification for hole depth specifies a difference threshold of 300 mm, while if the actual deviation is 30 mm, the number of subtracted points is 2, and the parameter is 18. As another example, if the actual deviation is 60 mm, the score of the subtraction is 4 points and the parameter score is 16 points. If the difference in the drilling parameters is above the difference threshold range specified by the specifications, the subtracted score is determined in proportion to the actual difference and the difference threshold. For example, if the actual deviation is 310 mm, 20 points are deducted, and the score is 0.
After determining the score for each borehole, the score for the entire borehole project may be determined from the score for each borehole.
For example, see table 3:
first bore hole 80 minutes
Second bore hole 90 minutes
Third bore hole 70 minutes
Fourth bore hole 60 minutes
Fifth bore hole 50 minutes
TABLE 3
The average scores of the five drill holes can be determined, and the quality performance of the engineering team in the drilling construction can be represented by the average scores.
In the drilling construction process, determining the construction quality score of the drill hole according to the drilling parameters of the single drill hole and giving an early warning, wherein the method comprises the following steps:
and controlling an alarm device to send out second alarm information in response to the fact that the difference value between the construction value and the design value of the drilling parameter is equal to or larger than a preset early warning difference value threshold value.
The drilling early warning difference threshold value can be flexibly set and can be set to be 80% of the difference threshold value specified by the specification. For example, the specification of the hole depth specifies that the difference threshold is 300 mm, and if the actual deviation is 241 mm, a second alarm message is sent.
And after the pouring is finished, determining a pouring construction quality score according to the pouring parameters.
In this example, see table 4 for illustration:
slump constant 25 minutes
Strength of test piece 25 minutes
Filling coefficient 25 minutes
Time of perfusion 25 minutes
TABLE 4
And if the difference value of the pouring parameters is within the range of the difference value threshold value specified by the specification, determining the deducted fraction according to the proportional relation between the actual difference value and the difference value threshold value. The subtracted fraction = the actual deviation/difference threshold gamma is a predetermined fraction of the parameter. For example, the value specified by the specification of the filling coefficient is 1, and is greater than or equal to 1, and the full score can be obtained. The warning value may be set to 0.8. If less than 0.8, alarm, if less than 0.8, deduct all scores, 0. If between 0.8 and 1, a deduction score value may be determined. The subtracted fractional value = (1-coefficient) predetermined fractional value. For example, if the coefficient is 0.9, the fractional value of the subtraction is 2.5 points.
And determining the quality score of the whole drilling hole pouring construction according to the steel reinforcement cage quality score, the drilling hole quality score and the pouring construction quality score.
In this embodiment, the quality score of the steel reinforcement cage, the quality score of the drilled hole and the quality score of the pouring construction may be summed to obtain the quality score of the whole drilling pouring construction. The construction team can be independently checked by independently applying the steel reinforcement cage quality score, the drilling quality score and the pouring construction quality score.
The method is beneficial to performance assessment of construction units by scoring, improves the accuracy of engineering quality assessment, can be used for independently assessing different construction tasks and assessing the total engineering. The construction quality of a construction unit is improved.
In an embodiment, in step S102, before the construction, the early warning is performed according to the key parameter of the steel reinforcement cage, and the method may further include the following steps:
obtaining a design value and a construction value of key parameters of the reinforcement cage; determining a construction error value of the key parameter according to the design value and the construction value of the key parameter; determining the quality score of the reinforcement cage according to the construction error value; and if the construction error value is greater than a preset early warning error threshold value, first warning information is sent out.
The key parameter early warning error threshold of the reinforcement cage can be flexibly set and can be set to be 80% of the difference threshold of the key parameters of the reinforcement cage specified by the specification. For example, the difference threshold value specified by the specification of the length of the reinforcement cage is 100 mm, the early warning threshold value of the length parameter can be set to 80 mm, and if the deviation of the actual length is equal to or greater than 80 mm, an alarm can be given to send out first alarm information.
According to the content regulation of T _ CECS 592-2019-cast-in-situ bored pile construction technical standard, the error threshold of the main rib spacing is 10 mm, the error threshold of the length is 100 mm, the error threshold of the stirrup spacing is 20 mm, and the error threshold of the diameter is 10 mm.
In one embodiment, in the process of pouring concrete, obtaining pouring parameters, generating a pouring construction quality score according to the pouring parameters, and performing early warning, the method may further include the following steps:
and controlling an alarm device to send out third alarm information in response to the fact that the difference value between the construction value and the design value of the pouring parameter is larger than the early-warning difference value threshold value.
The concrete pouring parameter difference early warning threshold value can be flexibly set. For example, the concrete pouring parameter difference early warning threshold may be set to 80% of the difference threshold of the concrete pouring parameter specified by the standard specification.
In this embodiment, with reference to table 4, if the error value of the perfusion time is greater than the predetermined early warning error threshold, a third warning message is sent out, and a score is generated.
To avoid the occurrence of overfill, in one embodiment, the pouring parameter is a pouring time;
determining the design value of the perfusion time may further comprise the steps of:
and acquiring the designed top surface elevation of the single pile.
And determining the theoretical poured concrete amount according to the designed top surface elevation, the diameter of the drilled hole and the filling coefficient.
Specifically, the top elevation is the height of the drilling cylinder according to the above design. The area of the cross section of the bore hole is determined from the diameter of the bore hole as described above. The volume of the cylindrical body of the borehole can be determined from the area of the cross-section and the elevation of the designed top surface as described above. The product of the volume of the cylinder of the borehole and the filling coefficient obtains the theoretical amount of poured concrete.
And determining the design value of the pouring time according to the pouring amount of the tank truck in unit time and the theoretical poured concrete amount.
And controlling an alarm device to send out third alarm information in response to the fact that the difference value between the construction value and the design value of the pouring time is larger than or equal to the pouring time difference value threshold.
Illustratively, the actual perfusion time is 10 minutes and 30 seconds, the theoretical design value is 10 minutes, and the difference is 30 seconds. The difference threshold is 1 minute. In this case, pass. If the actual pouring time is 12 minutes, the difference value is 2 minutes and is greater than the difference value threshold value by 1 minute, the method is unqualified and gives an alarm in time, so that the risks of huge economic loss, rework and dismantling caused by continuous pouring after the target elevation is reached are avoided.
In one embodiment, the method further comprises: while constructing, a Building Information Model (BIM) integration management model of the component; and outputting the three-dimensional drawing and the two-dimensional drawing by using the BIM integrated management model, and storing. For later verification and for business settlement against contracts. And when the construction is completed, the BIM integrated management model is completed.
Wherein, BIM integrated management model includes: and constructing a BIM model by using the single pile. The BIM model for single pile construction can be positioned according to the pile position coordinates and elevation information and integrated into the BIM integrated management model.
Wherein, the single pile construction BIM model specifically includes: generating a drilling construction BIM (building information modeling) model according to the relevant parameters of hole forming and hole cleaning; a steel reinforcement cage construction BIM model is generated according to the relevant parameters of the steel reinforcement cage; a concrete pouring construction BIM model is generated according to the concrete pouring related parameters; and combining the three construction models into a single-pile construction BIM model.
Wherein, the relevant parameters of pore-forming and pore-cleaning include: positioning, pile diameter, hole inclination, hole depth and sediment thickness. Relevant parameters of the reinforcement cage include: main muscle interval, stirrup interval, cage footpath, cage length, cage top elevation, the concrete placement relevant parameter includes: slump, test piece strength, filling coefficient and filling time. Each of the above related parameters is provided by a design unit, and is generally set according to the standard specification of the industry. For example, the standard specification is T _ CECS 592-2019-cast-in-situ bored pile construction technical standard.
The construction model is established in real time and is synchronous with the construction process, and the construction model also comprises time information used for recording the real-time construction time points of each component and step.
In some embodiments, prior to construction, a single pile design BIM model may be generated. The method specifically comprises the following steps: obtaining a drilling hole design BIM sub-model according to hole forming and cleaning design parameters; generating a design BIM sub-model of the reinforcement cage according to the design parameters of the reinforcement cage; generating a concrete pouring design BIM sub-model according to the concrete pouring design parameters; and integrating the three design sub-models to obtain the single-pile design BIM model.
In the construction process, the single-pile construction BIM model and the single-pile design BIM model can be compared to perform real-time quality recheck.
The method applies the BIM technology to the field of drilling and pouring, establishes a BIM design model according to the quality information management requirement of the cast-in-situ bored pile, establishes a BIM construction model according to the construction progress, synchronizes BIM modeling with actual construction, synchronizes information acquisition and information collection, determines parameters with problems in construction by comparing the BIM design model with the BIM construction model, and enables quality information management to run through each stage of design, construction and completion.
In a third aspect, the present application provides a bored pile construction early warning device, as shown in fig. 2, the device 200 includes:
the first processing module 21 is configured to, in a process of manufacturing a reinforcement cage, obtain key parameters of the reinforcement cage, and perform early warning according to the key parameters of the reinforcement cage.
And the second processing module 22 is used for performing early warning according to the drilling parameters of a single drill hole in the drilling construction process after the reinforcement cage is manufactured.
And the third processing module 23 is configured to obtain pouring parameters in a process of pouring concrete after the drilling construction is completed, and perform early warning according to the pouring parameters.
In an embodiment, the first processing module 21 is further configured to generate a steel reinforcement cage quality score according to the steel reinforcement cage key parameter after the steel reinforcement cage is manufactured.
The second processing module 22 is further configured to generate a drilling quality score according to the drilling parameters of the single drilling after the single drilling is completed.
The third processing module 23 is further configured to, after the pouring is completed, determine a pouring construction quality score according to the pouring parameters.
And the fourth processing module is used for determining the quality score of the whole drilling hole pouring construction according to the quality score of the reinforcement cage, the drilling hole quality score and the pouring construction quality score.
In one embodiment, the first processing module 21 is further configured to obtain design values and construction values of key parameters of the reinforcement cage;
determining a construction error value of the key parameter according to the design value and the construction value of the key parameter;
determining the quality score of the reinforcement cage according to the construction error value;
the key parameters of the reinforcement cage include: the main reinforcement spacing, the stirrup spacing, the cage diameter, the cage length and the cage top elevation;
and if the construction error value is larger than a preset error threshold value, sending first alarm information.
In one embodiment, the second processing module 22 is further configured to determine a construction quality score of a single borehole and perform early warning according to the drilling parameters of the borehole during the drilling construction, and includes:
controlling an alarm device to send out first alarm information in response to the fact that the construction value of the offset distance is larger than a design value; alternatively, the first and second electrodes may be,
and controlling an alarm device to send out first alarm information in response to the fact that the construction value of the hole spacing is larger than a design value.
In one embodiment, the third processing module 23 is further configured to control the alarm device to send out second alarm information in response to that a difference value between the construction value and the design value of the pouring parameter is greater than a difference threshold value.
In one embodiment, the third processing module 23 is further configured to obtain a designed top surface elevation of the mono-pile;
determining theoretical concrete pouring amount according to the designed top surface elevation, the diameter of the drilled hole and the filling coefficient;
determining a design value of the pouring time according to the pouring amount of the tank car in unit time and the theoretical poured concrete amount;
and controlling an alarm device to send out third alarm information in response to the fact that the difference value between the construction value and the design value of the pouring time is larger than or equal to the pouring time difference value threshold.
With regard to the apparatus in the above-described embodiment, the specific manner in which each module performs the operation has been described in detail in the embodiment related to the method, and will not be elaborated here.
According to a third aspect of the embodiments of the present disclosure, the present application further proposes an electronic device, referring to fig. 3, where the electronic device 300 includes: a processor 301; a memory 302 for storing processor-executable instructions; wherein the processor 301 is configured to execute the executable instructions to implement the method of any of the above.
According to a fourth aspect of embodiments of the present disclosure, there is provided a non-transitory computer readable storage medium having stored thereon computer program instructions which, when executed by a processor, implement the steps of the above-described method.
According to a fifth aspect of the disclosed embodiments, the present application provides a bored pile construction early warning system, referring to fig. 4, where the system 400 includes: the electronic device 300 and the alarm device 310 described above; the alarm device 310 is connected with the electronic device 300, and the electronic device 300 and the alarm device 310 are arranged in a cab of the drilling machine.
In this embodiment, the electronic device is further connected to a display screen, the display screen is provided with a human-computer interaction interface, a user can input the various parameters through the human-computer interaction interface, and the display screen can also display alarm information. Various sensors can be arranged on the construction site, and the sensors and the electronic equipment can be connected in a wireless communication mode. The sensor converts the detected data into an electric signal and sends the electric signal to the electronic equipment in a wireless mode. The alarm device can alarm by voice. Through setting up in the driver's cabin, can improve the effect of early warning for after the driver hears early warning information, the stop operation avoids causing bigger loss to drilling, perhaps the process of pouring.
In an embodiment of the invention, the processor may be an integrated circuit chip having signal processing capability. The Processor may be a general purpose Processor, a Digital Signal Processor (DSP), an Application Specific Integrated Circuit (ASIC), a Field Programmable Gate Array (FPGA) or other Programmable logic device, discrete Gate or transistor logic device, discrete hardware component.
The various methods, steps and logic blocks disclosed in the embodiments of the present invention may be implemented or performed. A general purpose processor may be a microprocessor or the processor may be any conventional processor or the like. The steps of the method disclosed in connection with the embodiments of the present invention may be directly implemented by a hardware decoding processor, or implemented by a combination of hardware and software modules in the decoding processor. The software module may be located in ram, flash memory, rom, prom, or eprom, registers, etc. storage media as is well known in the art. The processor reads the information in the storage medium and completes the steps of the method in combination with the hardware.
The storage medium may be a memory, for example, which may be volatile memory or nonvolatile memory, or may include both volatile and nonvolatile memory.
The nonvolatile Memory may be a Read-Only Memory (ROM), a Programmable ROM (PROM), an Erasable PROM (EPROM), an Electrically Erasable PROM (EEPROM), or a flash Memory.
The volatile Memory may be a Random Access Memory (RAM) which serves as an external cache. By way of example, and not limitation, many forms of RAM are available, such as Static Random Access Memory (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double Data Rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), SLDRAM (SLDRAM), and Direct Rambus RAM (DRRAM).
The storage media described in connection with the embodiments of the invention are intended to comprise, without being limited to, these and any other suitable types of memory.
Other embodiments of the disclosure will be apparent to those skilled in the art from consideration of the specification and practice of the disclosure. This application is intended to cover any variations, uses, or adaptations of the disclosure following, in general, the principles of the disclosure and including such departures from the present disclosure as come within known or customary practice within the art to which the disclosure pertains. It is intended that the specification and examples be considered as exemplary only, with a true scope and spirit of the disclosure being indicated by the following claims.
It will be understood that the present disclosure is not limited to the precise arrangements described above and shown in the drawings and that various modifications and changes may be made without departing from the scope thereof. The scope of the present disclosure is limited only by the appended claims.

Claims (10)

1. A construction early warning method for a cast-in-situ bored pile is characterized by comprising the following steps:
in the process of manufacturing the reinforcement cage, acquiring key parameters of the reinforcement cage, and performing early warning according to the key parameters of the reinforcement cage;
after the reinforcement cage is manufactured, early warning is carried out according to drilling parameters of a single drill hole in the drilling construction process;
after the drilling construction is finished, obtaining pouring parameters in the process of pouring concrete, and carrying out early warning according to the pouring parameters.
2. The pre-warning method for bored pile construction according to claim 1, further comprising:
after the reinforcement cage is manufactured, generating a reinforcement cage quality score according to the key parameters of the reinforcement cage;
after the single drilling is finished, generating a drilling quality score according to the drilling parameters of the single drilling;
after pouring is finished, determining a pouring construction quality score according to the pouring parameters;
and determining the quality score of the whole drilling hole pouring construction according to the steel reinforcement cage quality score, the drilling hole quality score and the pouring construction quality score.
3. The cast-in-situ bored pile construction early warning method according to claim 1, wherein the concrete pouring parameters include: slump, test piece strength, filling coefficient and filling time.
4. The pre-warning method for bored pile construction according to claim 1, wherein pre-warning is performed according to key parameters of the steel reinforcement cage before construction, and comprises:
obtaining a design value and a construction value of key parameters of the reinforcement cage;
determining a construction error value of the key parameter according to the design value and the construction value of the key parameter;
determining the quality score of the reinforcement cage according to the construction error value;
the key parameters of the reinforcement cage include: main reinforcement spacing, stirrup spacing, cage diameter and cage length;
and if the construction error value is greater than a preset early warning error threshold value, first warning information is sent out.
5. The pre-warning method for bored pile construction according to claim 1, wherein the drilling parameters include: pile position coordinates, drilling depth, verticality, drilling diameter and sediment thickness;
in the drilling construction process, determining the construction quality score of the drill hole according to the drilling parameters of the single drill hole and giving an early warning, wherein the method comprises the following steps:
and controlling an alarm device to send out second alarm information in response to the fact that the difference value between the construction value and the design value of the drilling parameter is equal to or larger than a preset early-warning difference value threshold value.
6. The pre-warning method for bored pile construction according to claim 3,
in the process of pouring concrete, obtaining pouring parameters, generating a pouring construction quality score according to the pouring parameters and early warning, wherein the method comprises the following steps:
and controlling an alarm device to send out third alarm information in response to the fact that the difference value between the construction value and the design value of the pouring parameter is larger than the early-warning difference value threshold value.
7. The pre-warning method for bored pile construction according to claim 6, wherein the casting parameter is casting time;
determining a design value for the perfusion time comprising:
acquiring the elevation of the designed top surface of the single pile;
determining theoretical concrete pouring amount according to the designed top surface elevation, the diameter of the drilled hole and the filling coefficient;
determining a design value of the pouring time according to the pouring amount of the tank car in unit time and the theoretical poured concrete amount;
and controlling an alarm device to send out third alarm information in response to the fact that the difference value between the construction value and the design value of the pouring time is larger than or equal to the pouring time difference value threshold.
8. The utility model provides a bored concrete pile construction early warning device which characterized in that includes:
the first early warning module is used for acquiring key parameters of the reinforcement cage in the process of manufacturing the reinforcement cage and carrying out early warning according to the key parameters of the reinforcement cage;
the second early warning module is used for early warning according to the drilling parameters of a single drill hole in the drilling construction process after the reinforcement cage is manufactured;
and the third early warning module is used for acquiring pouring parameters in the process of pouring concrete after the drilling construction is finished, and early warning is carried out according to the pouring parameters.
9. An electronic device, comprising: a processor; a memory for storing processor-executable instructions; wherein the processor is configured to execute the executable instructions to implement the method of any one of claims 1 to 7.
10. The utility model provides a bored concrete pile construction early warning system which characterized in that includes: the electronic device and the alarm apparatus of claim 9; the alarm device is connected with the electronic equipment; the electronic equipment and the alarm device are arranged in a cab of the drilling machine.
CN202211497821.1A 2022-11-28 2022-11-28 Early warning method, device, equipment and system for cast-in-situ bored pile construction Pending CN115830818A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211497821.1A CN115830818A (en) 2022-11-28 2022-11-28 Early warning method, device, equipment and system for cast-in-situ bored pile construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211497821.1A CN115830818A (en) 2022-11-28 2022-11-28 Early warning method, device, equipment and system for cast-in-situ bored pile construction

Publications (1)

Publication Number Publication Date
CN115830818A true CN115830818A (en) 2023-03-21

Family

ID=85531988

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211497821.1A Pending CN115830818A (en) 2022-11-28 2022-11-28 Early warning method, device, equipment and system for cast-in-situ bored pile construction

Country Status (1)

Country Link
CN (1) CN115830818A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117702727A (en) * 2024-02-06 2024-03-15 江苏筑港建设集团有限公司 Cast-in-place pile construction technology

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117702727A (en) * 2024-02-06 2024-03-15 江苏筑港建设集团有限公司 Cast-in-place pile construction technology

Similar Documents

Publication Publication Date Title
CN113378274B (en) Building construction monitoring method and system based on BIM
CN115830818A (en) Early warning method, device, equipment and system for cast-in-situ bored pile construction
CN112185072B (en) Deep foundation pit automatic monitoring method, device, equipment and medium based on Internet of things
CN111337944B (en) Tower footing acceptance check method and device based on foundation laser radar
JP2005213972A (en) Construction management system and its method
CN112948950B (en) BIM technology-based integrated information intelligent management system and management method
CN106500651A (en) A kind of method for safety monitoring of construction geometry deformation
CN112819781B (en) Concrete scouring quality assessment method, device and system
JP2018154975A (en) Quality control method of soil, and quality monitoring system of soil
JP2020007730A (en) Movable measuring device of water content, and rolling compaction method
CN113515654B (en) Pile foundation construction parameter visualization processing method and device based on building information modeling
CN113191747A (en) High-rise building engineering measurement supervision control method
CN102587386A (en) Reverse HPE (hydraulic perpendicular embedding) construction method for steel pipe columns in basement
CN117350974A (en) Engineering quality determining method, device, equipment and medium
DE102008035565B4 (en) System with a lightweight falling weight device and a measurement evaluation device and method
CN117332494A (en) Method, equipment and storage medium for real-time digital twinning of open caisson construction state
CN104005342A (en) Method and device for dynamic synchronous jacking compensation of bridge distortion
CN116972754A (en) Method and system for detecting welding seam of steel bar
CN115615407A (en) Solid structure substance quality detection method based on three-dimensional laser scanning
CN115116195A (en) Foundation pit monitoring method and device based on artificial intelligence
CN114880374A (en) Slope monitoring method, device, equipment and medium
CN114293664A (en) Quick installation process for ultrahigh-precision embedded part group
JP6906746B2 (en) Foundations, foundation construction methods, foundation inspection methods, building location information management methods, and various jigs used for these methods
JP2009235666A (en) Pile shape specifying device and pile shape specifying program
EP4332519A1 (en) Method for monitoring a climbing speed of a filling material, sensor device for monitoring the climbing speed, computer program product, computer readable medium and sensor control system comprising a sensor device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination