- CN115716033A CN115716033A CN202211257512.7A CN202211257512A CN115716033A CN 115716033 A CN115716033 A CN 115716033A CN 202211257512 A CN202211257512 A CN 202211257512A CN 115716033 A CN115716033 A CN 115716033A
- Authority
- CN
- China
- Prior art keywords
- base
- skylight glass
- slide rail
- fixedly connected
- top skylight
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
- Y02P70/10—Greenhouse gas [GHG] capture, material saving, heat recovery or other energy efficient measures, e.g. motor control, characterised by manufacturing processes, e.g. for rolling metal or metal working
Landscapes
- Spray Control Apparatus (AREA)
Abstract
The invention relates to a top skylight glass gluing device which comprises a base, wherein a placing area is arranged at the top of the base, an installation cavity is formed in an inner cavity of the base, a control panel is fixedly connected to the top of the front side of the base, a top frame is fixedly connected to one side, far away from the placing area, of the base, a positioning mechanism matched with the placing area is arranged on one side, close to the installation cavity, of the base, a displacement mechanism is arranged on one side, far away from the placing area, of the top frame, and a spraying mechanism matched with the placing area is arranged on the displacement mechanism. Through setting up positioning mechanism, adsorb the location processing in advance to top skylight glass, through setting up displacement mechanism, carry out the displacement to the shower nozzle according to top skylight glass rubber coating orbit and adjust, satisfy top skylight glass's accurate rubber coating demand, through setting up spraying mechanism, realize top skylight glass's automatic rubber coating work, improve top skylight glass's rubber coating efficiency and rubber coating quality.
Description
Technical Field
The invention relates to the technical field of automobile glass accessories, in particular to top skylight glass gluing equipment.
Background
Sunroof installs in the roof, can make the circulation of air in the car effectively, increases fresh air's entering, and sunroof also can open the field of vision and remove the shooting demand that the photography took a video recording simultaneously, sunroof can divide into roughly: the device is mainly installed on commercial SUVs, cars and other vehicle types.
All can install top skylight glass on the sunroof for the condition outside daylighting and the observation car, before top skylight glass installs, can carry out the rubber coating with rubber coating equipment to it and handle, the rubber coating equipment that adopts at present is mostly artifical rubber coating mode, can not adsorb earlier the location to top skylight glass, the automatic rubber coating flow process operation in orbit displacement and back leads to top skylight glass rubber coating inefficiency, and artifical rubber coating has great quality problem.
Disclosure of Invention
The invention aims to solve the defects that the prior art cannot perform flow operation of first adsorption positioning, then trajectory displacement and then automatic gluing on top skylight glass, and provides top skylight glass gluing equipment.
In order to achieve the purpose, the invention adopts the following technical scheme:
the utility model provides a top skylight glass rubber coating equipment, includes the base, the top of base is provided with places the district, the installation cavity has been seted up to the inner chamber of base, the positive top fixedly connected with of base controls the panel, one side fixedly connected with roof-rack in the district is kept away from to the base, one side that the base is close to the installation cavity is provided with and places the positioning mechanism that the district cooperation was used, one side that the district was kept away from to the roof-rack is provided with displacement mechanism, be provided with on the displacement mechanism and place the spraying mechanism that the district cooperation was used.
Preferably, positioning mechanism includes the booster suction pump, the booster suction pump is fixed in one side of installation cavity and the induction port intercommunication of booster suction pump has three way connection, three way connection's both ends all communicate has the other end intercommunication of corner tube and corner tube to have the house steward, the top of house steward communicates in proper order from a left side to the right side and has and place the sucking disc that the district cooperation was used.
Preferably, displacement mechanism includes the electronic slide rail of X axle, the electronic slide rail of X axle sets gradually from the front to the back and is close to sliding connection on one side of placing the district and the electronic slide rail of X axle at the roof-rack, the inner wall of the electronic slide rail slide of X axle is provided with sliding connection on the electronic slide rail of Z axle and the electronic slide rail of Z axle has the electronic slide rail slide of Z axle, the bottom fixedly connected with electric telescopic handle and the electric telescopic handle's of the electronic slide rail slide of Z axle piston rod fixedly connected with mounting panel.
Preferably, the spraying mechanism is including gluing the bucket, it places and inlays on the ladle body of gluing the bucket at the back of base and is equipped with level sensor to glue the bucket, the play of gluing the bucket is glued the mouth and is had the delivery port intercommunication of charge pump and charge pump through the rubber tube intercommunication and has the hose, the hose is close to the one end of charge pump and is provided with metering sensor and the other end intercommunication of hose have with mounting panel fixed coordination's shower nozzle.
Preferably, one side of the base, which is close to the placing area, is fixedly connected with a bearing pad, and the cross-sectional area of the bearing pad is larger than that of the placing area.
Preferably, the LED lamp that the inboard fixedly connected with of the equal fixedly connected with lamp plate in both sides of roof-rack and lamp plate and place the district cooperation and use.
Preferably, one side fixedly connected with of base near the installation cavity overhauls the apron and overhauls and has seted up the grid of taking a breath on the apron.
Compared with the prior art, the invention has the beneficial effects that:
this top skylight glass rubber coating equipment, through setting up positioning mechanism, provide the suction source by the booster suction pump, again by three way connection, the corner pipe, the cooperation of house steward and sucking disc, adsorb the location processing in advance to top skylight glass, through setting up displacement mechanism, by the electronic slide rail of X axle, the electronic slide rail of Z axle, the cooperation of the electronic slide rail slide of Z axle and electric telescopic handle, carry out displacement adjustment according to top skylight glass rubber coating orbit to the shower nozzle, satisfy top skylight glass's accurate rubber coating demand, through setting up spraying mechanism, by gluing the bucket, level sensor, the charge pump, the hose, the cooperation of measurement sensor and shower nozzle, realize top skylight glass's automatic rubber coating work, improve the rubber coating efficiency and the rubber coating quality of top skylight glass.
This top skylight glass rubber coating equipment through the bearing pad, and convenient to use person places the top skylight glass of treating the rubber coating, also cushions the bearing to the top skylight glass of placing simultaneously, through lamp plate and LED lamp, carries out the illumination to the top skylight glass of placing on the district and handles, and convenient to use person clearly observes top skylight glass's rubber coating process.
Drawings
FIG. 1 is a schematic structural diagram of a top skylight glass gluing device provided by the invention;
FIG. 2 is a structural rear view of a top skylight glass gluing device provided by the invention;
FIG. 3 is a front view of the base and top frame construction according to the present invention;
FIG. 4 is a bottom view of the positioning mechanism of the present invention;
fig. 5 is a structural bottom view of the displacement mechanism and the spraying mechanism provided by the invention.
In the figure: 1. a base; 2. a control panel; 3. a top frame; 4. a positioning mechanism; 41. a booster suction pump; 42. a three-way joint; 43. an angular tube; 44. a header pipe; 45. a suction cup; 5. a displacement mechanism; 51. an X-axis electric slide rail; 52. an X-axis electric slide rail slide carriage; 53. a Z-axis electric slide rail; 54. a Z-axis electric slide rail slide carriage; 55. an electric telescopic rod; 6. a spraying mechanism; 61. a glue barrel; 62. a level sensor; 63. a material pump; 64. a hose; 65. a metering sensor; 66. a spray head; 7. a support pad; 8. and a lamp panel.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Example one
Referring to fig. 1-5, a top skylight glass gluing device comprises a base 1, a placing area is arranged at the top of the base 1, an installation cavity is arranged in the inner cavity of the base 1, a control panel 2 is fixedly connected to the top of the front side of the base 1, a top frame 3 is fixedly connected to one side of the base 1 far away from the placing area, a positioning mechanism 4 matched with the placing area is arranged at one side of the base 1 close to the installation cavity, a pressure boosting suction pump 41 provides a suction source through the positioning mechanism 4, then the top skylight glass is subjected to pre-adsorption positioning treatment through the matching of a three-way joint 42, an angle pipe 43, a header pipe 44 and a suction disc 45, a displacement mechanism 5 is arranged at one side of the top frame 3 far away from the placing area, through setting up displacement mechanism 5, by X axle electric slide rail 51, X axle electric slide rail slide 52, Z axle electric slide rail 53, the cooperation of Z axle electric slide rail slide 54 and electric telescopic handle 55, carry out the displacement to shower nozzle 66 according to top skylight glass rubber coating orbit and adjust, satisfy top skylight glass's accurate rubber coating demand, be provided with on the displacement mechanism 5 and place the spraying mechanism 6 that the district cooperation was used, through setting up spraying mechanism 6, by gluing bucket 61, level sensor 62, material pump 63, hose 64, the cooperation of measurement sensor 65 and shower nozzle 66, realize top skylight glass's automatic rubber coating work, improve the rubber coating efficiency and the rubber coating quality of top skylight glass.
Example two
The improvement on the basis of the first embodiment: a top skylight glass gluing device comprises a base 1, a placing area is arranged at the top of the base 1, a bearing pad 7 is fixedly connected to one side of the base 1 close to the placing area, the cross-sectional area of the bearing pad 7 is larger than that of the placing area, a user can place top skylight glass to be glued conveniently, meanwhile, the placed top skylight glass is buffered and supported, an installation cavity is formed in the inner cavity of the base 1, an overhaul cover plate is fixedly connected to one side of the base 1 close to the installation cavity, a ventilation grating is arranged on the overhaul cover plate, the user can overhaul parts in the installation cavity conveniently, ventilation and heat dissipation treatment is carried out in the installation cavity, a control panel 2 is fixedly connected to the top of the front side of the base 1, an upper frame 3 is fixedly connected to one side of the base 1 far away from the placing area, lamp panels 8 are fixedly connected to two sides of the upper frame 3, and LED lamps matched with the placing area are fixedly connected to the inner sides of the lamp panels 8, the top skylight glass on the placing area is illuminated, a user can conveniently and clearly observe the gluing process of the top skylight glass, one side, close to an installation cavity, of a base 1 is provided with a positioning mechanism 4 matched with the placing area for use, the positioning mechanism 4 comprises a booster suction pump 41, the booster suction pump 41 is fixed on one side of the installation cavity, an air suction port of the booster suction pump 41 is communicated with a three-way joint 42, two ends of the three-way joint 42 are communicated with an angle pipe 43, the other end of the angle pipe 43 is communicated with a header pipe 44, the top end of the header pipe 44 is sequentially communicated with a sucker 45 matched with the placing area for use from left to right, through the arrangement of the positioning mechanism 4, the booster suction pump 41 provides a suction source, then through the matching of the three-way joint 42, the angle pipe 43, the header pipe 44 and the sucker 45, the top skylight glass is subjected to pre-adsorption positioning treatment, one side, far away from the placing area, of a top frame 3 is provided with a displacement mechanism 5, the displacement mechanism 5 comprises an X-axis electric slide rail 51, the X-axis electric slide rail 51 is sequentially arranged on one side of the top frame 3 close to the placing area from front to back, an X-axis electric slide rail slide seat 52 is connected on the X-axis electric slide rail 51 in a sliding manner, a Z-axis electric slide rail 53 is arranged on the inner wall of the X-axis electric slide rail slide seat 52, a Z-axis electric slide rail slide seat 54 is connected on the Z-axis electric slide rail 53 in a sliding manner, an electric telescopic rod 55 is fixedly connected at the bottom of the Z-axis electric slide rail slide seat 54, a piston rod of the electric telescopic rod 55 is fixedly connected with a mounting plate, and the displacement mechanism 5 is arranged to perform displacement adjustment on the spray head 66 according to the gluing track of the top skylight glass through the matching of the X-axis electric slide rail 51, the X-axis electric slide rail slide seat 52, the Z-axis electric slide rail slide seat 54 and the electric telescopic rod 55, satisfy top skylight glass's accurate rubber coating demand, be provided with on the displacement mechanism 5 and place the spraying mechanism 6 that the district cooperation was used, spraying mechanism 6 is including gluing bucket 61, it places at base 1's the back and inlays on the ladle body of gluing bucket 61 and be equipped with level sensor 62 to glue bucket 61, the play jiao kou of gluing bucket 61 has material pump 63 and the play jiao kou intercommunication of material pump 63 through the rubber tube intercommunication to have hose 64, the one end that hose 64 is close to material pump 63 is provided with metering sensor 65 and the other end intercommunication of hose 64 has with mounting panel fixed coordination's shower nozzle 66, through setting up spraying mechanism 6, by gluing bucket 61, level sensor 62, material pump 63, hose 64, metering sensor 65 and the cooperation of shower nozzle 66, realize top skylight glass's automatic rubber coating work, improve top skylight glass's rubber coating efficiency and rubber coating quality.
In the invention, a user firstly places top skylight glass to be glued at a preset position on a bearing pad 7 at the periphery of a placement area, then controls a booster suction pump 41 to be started by a control panel 2 and sequentially applies negative pressure suction force to two groups of suckers 45 through a three-way joint 42, two corner pipes 43 and two header pipes 44, so that the two groups of suckers 45 perform adsorption positioning on the top skylight glass, then controls two groups of X-axis electric slide rail slide carriages 52 to perform X-axis axial displacement synchronous regulation on two X-axis electric slide rails 51, performs Z-axis axial displacement regulation on a Z-axis electric slide rail 54, provides Y-axis axial height regulation for a sprayer 66 by an electric telescopic rod 55, installs a set track route, drives the sprayer 66 to move along a gluing track of the top skylight glass, simultaneously controls a material pump 63 to be started and supplies glue in a glue barrel 61 into a hose 64, performs real-time sensing on glue supply metering by a metering sensor 65, senses the glue level change in the glue barrel 61 in real time, and then the glue is coated on the gluing position of the top skylight glass in a gluing track moving state of the top skylight glass.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered as the technical solutions and the inventive concepts of the present invention within the technical scope of the present invention.
Claims (7)
1. The utility model provides a top skylight glass rubber coating equipment, includes base (1), its characterized in that: the top of base (1) is provided with places the district, the installation cavity has been seted up to the inner chamber of base (1), base (1) positive top fixedly connected with controls panel (2), one side fixedly connected with roof-rack (3) of placing the district are kept away from in base (1), one side that base (1) is close to the installation cavity is provided with and places positioning mechanism (4) that the district cooperation was used, one side of placing the district is kept away from in roof-rack (3) is provided with displacement mechanism (5), be provided with on displacement mechanism (5) and place spraying mechanism (6) that the district cooperation was used.
2. The gluing equipment for the top skylight glass according to claim 1, wherein the positioning mechanism (4) comprises a booster suction pump (41), the booster suction pump (41) is fixed on one side of the installation cavity, a three-way joint (42) is communicated with a suction port of the booster suction pump (41), two ends of the three-way joint (42) are communicated with an angle pipe (43), the other end of the angle pipe (43) is communicated with a header pipe (44), and the top end of the header pipe (44) is sequentially communicated with suckers (45) matched with the placement area from left to right.
3. The gluing equipment for the top skylight glass as claimed in claim 1, wherein the displacement mechanism (5) comprises an X-axis electric slide rail (51), the X-axis electric slide rail (51) is sequentially arranged from front to back on one side of the top frame (3) close to the placement area, an X-axis electric slide rail slide carriage (52) is connected onto the X-axis electric slide rail (51) in a sliding manner, a Z-axis electric slide rail slide carriage (54) is arranged on the inner wall of the X-axis electric slide rail slide carriage (52) and connected onto the Z-axis electric slide rail (53) in a sliding manner, and an electric telescopic rod (55) is fixedly connected to the bottom of the Z-axis electric slide rail slide carriage (54) and a piston rod of the electric telescopic rod (55) is fixedly connected to a mounting plate.
4. The glue spreading device for the top skylight glass according to claim 1, wherein the spraying mechanism (6) comprises a glue barrel (61), the glue barrel (61) is placed on the back of the base (1) and a material level sensor (62) is embedded on the barrel body of the glue barrel (61), a glue outlet of the glue barrel (61) is communicated with a material pump (63) through a glue pipe and a hose (64) is communicated with a glue outlet of the material pump (63), one end, close to the material pump (63), of the hose (64) is provided with a metering sensor (65), and the other end of the hose (64) is communicated with a spray head (66) fixedly matched with the mounting plate.
5. The gluing equipment for the top skylight glass according to claim 1, characterized in that a supporting pad (7) is fixedly connected to one side of the base (1) close to the placing area, and the cross-sectional area of the supporting pad (7) is larger than that of the placing area.
6. The gluing equipment for the top skylight glass as claimed in claim 1, wherein both sides of the top frame (3) are fixedly connected with lamp panels (8) and the inner sides of the lamp panels (8) are fixedly connected with LED lamps used in cooperation with the placing areas.
7. The glue coating equipment for the top skylight glass according to claim 1, wherein one side of the base (1) close to the installation cavity is fixedly connected with an access panel, and the access panel is provided with a ventilation grating.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211257512.7A CN115716033A (en) | 2022-10-14 | 2022-10-14 | Top skylight glass gluing equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211257512.7A CN115716033A (en) | 2022-10-14 | 2022-10-14 | Top skylight glass gluing equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115716033A true CN115716033A (en) | 2023-02-28 |
Family
ID=85254235
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211257512.7A Pending CN115716033A (en) | 2022-10-14 | 2022-10-14 | Top skylight glass gluing equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115716033A (en) |
-
2022
- 2022-10-14 CN CN202211257512.7A patent/CN115716033A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208213490U (en) | A kind of aluminium alloy extrusions outer surface paint spraying apparatus | |
CN207629355U (en) | Welding compound spraying coater and cell piece string welding machine | |
CN115716033A (en) | Top skylight glass gluing equipment | |
CN217277927U (en) | Photovoltaic module appearance imperfections testing platform | |
CN116764868B (en) | Coating spraying assembly based on track design and spraying process thereof | |
CN208679544U (en) | A kind of multistation integrated automation coating equipment | |
CN218077044U (en) | Wisdom is dust device for building site based on internet of things | |
CN214901474U (en) | Paster equipment is used in circuit board production equipment | |
CN214637817U (en) | Automatic rubber coating equipment of curved surface | |
CN115625052A (en) | A spraying plastics device for block terminal production | |
JPH0130543B2 (en) | ||
CN111841946B (en) | Spraying device of automobile spraying assembly line | |
CN212975710U (en) | Plastic extruder is used in auto-parts production | |
CN212975644U (en) | Surface spraying device for precision parts | |
CN112742633A (en) | Paint spraying apparatus is used in automobile parts production | |
CN218013603U (en) | Paint mist adsorption device | |
CN209337058U (en) | A kind of pre- laminating apparatus | |
CN113210200A (en) | Sealant applying device for sealant construction | |
CN206604687U (en) | Car repair speed spray instrument | |
CN208019966U (en) | A kind of material bottle paint removal device | |
CN218048625U (en) | Integrated spraying case of metal surface treatment | |
CN109457926A (en) | Indoor wall decorative panel assembled track mounting system | |
CN219129747U (en) | Glue spreader | |
CN221063186U (en) | Peripheral circle spraying equipment | |
CN220295027U (en) | Powder coating spray booth |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |