CN115689485A - Engineering project progress management method, device and equipment and readable medium - Google Patents

Engineering project progress management method, device and equipment and readable medium Download PDF

Info

Publication number
CN115689485A
CN115689485A CN202211357735.0A CN202211357735A CN115689485A CN 115689485 A CN115689485 A CN 115689485A CN 202211357735 A CN202211357735 A CN 202211357735A CN 115689485 A CN115689485 A CN 115689485A
Authority
CN
China
Prior art keywords
project
progress
sub
level
plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211357735.0A
Other languages
Chinese (zh)
Inventor
苏畅
王�琦
杨美凤
云东
唐发启
赵森林
李密
李晓琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinosteel Equipment and Engineering Co Ltd
Original Assignee
Sinosteel Equipment and Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinosteel Equipment and Engineering Co Ltd filed Critical Sinosteel Equipment and Engineering Co Ltd
Priority to CN202211357735.0A priority Critical patent/CN115689485A/en
Publication of CN115689485A publication Critical patent/CN115689485A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a project progress management method, which comprises the following steps: the method comprises the steps of resolving the engineering project step by step to obtain sub projects of multiple levels, and assigning a project schedule plan to the sub projects of the multiple levels based on engineering project requirements, wherein the final-level sub project assigns the project schedule plan based on plan starting time and plan ending time; acquiring progress information of the final-stage sub-project regularly, and performing decomposition assignment and progress acquisition on the final-stage sub-project based on the progress information and a preset assignment rule; step-by-step ascending sub-project summary data of a last-level sub-project to a first-level sub-project based on assignments acquired by the project schedule plan and the project schedule; and carrying out statistical analysis on the data step by step, and generating a unit project progress report, a first-level sub-project report and a project total report based on a preset statistical rule. The invention also discloses a project progress management device, computer equipment and a readable storage medium.

Description

Engineering project progress management method, device, equipment and readable medium
Technical Field
The invention belongs to the technical field of digital management, and particularly relates to a method, a device, equipment and a readable medium for managing the progress of an engineering project.
Background
The ultimate purpose of project progress management is to promote the high-quality and efficient completion of a project, ensure the profit of a project contract unit, and play an important role in reducing the cost of the project contract unit, shortening the construction period and the like. The project progress management system of the enterprise is strengthened and perfected, and the establishment of a scientific project progress management mode has great significance for maintaining the development of the enterprise. The traditional management mode is combined with information technologies such as big data, internet, cloud computing and the like, innovation is carried out, informatization, digitization and intellectualization of project progress management are achieved to become the mainstream trend of development, and meanwhile, the digital transformation and intelligent manufacturing of enterprises can be accelerated.
The mainstream of the domestic engineering PROJECT schedule control mainly uses two kinds of software, namely P6 developed by American oracle corporation and PROJECT developed by Microsoft corporation. Most of domestic project progress management software is developed again based on the logics of the two types of software, the bottom layer architecture is similar to the technical thought, independent research and development and innovation are lacked, the development of the foreign project progress management logic referred by the management logic is lacked, the current situation of the domestic project progress management is lacked to be combined, and the domestic project progress management software is difficult to apply efficiently. The mainstream contract mode in the field of domestic engineering projects is an EPC general contract mode, but the traditional engineering project progress management mode of administrative management is adopted, the engineering project progress management of flow and professional collaborative operation is lacked, and the engineering project progress management adopts a text report management mode of using visual progress periodically. The management mode cannot intuitively and comprehensively understand the progress of the project, and the omnibearing progress analysis of the project is difficult to develop.
The prior art depends on a large amount of manual work to carry out offline operation, and is not favorable for fine management of projects. The problems that exist include: the project progress data is reported in a non-timely manner, the data is inaccurate, and the data structure and the form are inconsistent, so that the reported data is inconsistent with the actual project progress; heavy work is brought to statistical data and data analysis; the data structure and form of the progress report of each sub-project under the full-flow project are not uniform, the report, processing and analysis of data are completed on line, the data storage and check are complex, and the risk of loss exists; the data processing dimension, automation and digital processing degree are low, which is not beneficial to forming data assets of enterprises and is not beneficial to digital transformation of enterprises.
The information disclosed in this background section is only for enhancement of understanding of the general background of the invention and should not be taken as an acknowledgement or any form of suggestion that this information forms the prior art that is already known to a person skilled in the art.
Disclosure of Invention
The invention aims to provide a method, a device, equipment and a readable medium for managing the progress of an engineering project, which are used for realizing informatization, digitization and visualization of the progress management of the engineering project.
Based on the above purpose, an aspect of the embodiments of the present invention provides a method for managing a progress of an engineering project, including the following steps: the method comprises the steps of resolving the engineering project step by step to obtain sub projects of multiple levels, and assigning a project progress plan to the sub projects of the multiple levels based on engineering project requirements, wherein the final-level sub project assigns the project progress plan based on plan starting time and plan ending time; acquiring progress information of the final-stage sub-project regularly, and performing decomposition assignment and progress acquisition on the final-stage sub-project based on the progress information and a preset assignment rule; summarizing data from sub-projects of the last level up to a level of sub-projects step by step based on the project schedule and the valuations collected by the project schedule up to a level of sub-projects; and carrying out statistical analysis on the data step by step, and generating a unit project progress report, a first-level sub-project report and a project total report based on a preset statistical rule.
In some embodiments, progressively disassembling the engineering project to obtain a plurality of levels of sub-projects comprises: the engineering project is disassembled step by step to obtain a first-level sub project, a second-level sub project, a third-level sub project and a final-level sub project; the first-level sub project comprises a project stage, the second-level sub project comprises a plurality of sub unit projects, the third-level sub project comprises a plurality of branch projects, and the last-level sub project comprises a plurality of branch project operation items; assigning the project schedule to the plurality of levels of sub-projects based on the engineering project requirements comprises: the sum of the assignments of the project schedule for each level of sub-project is 100%.
In some embodiments, the assigning of the project schedule by the last-level sub-project based on the schedule start time and the schedule end time includes: respectively acquiring the planned starting time and the planned ending time of each project operation item, and calculating the construction period of the project operation item based on the planned starting time and the planned ending time; and adding the construction periods of the project operation items to obtain a total construction period, and assigning a project schedule plan based on the ratio of the construction periods of the project operation items to the total construction period.
In some embodiments, periodically collecting progress information for the last-level sub-item comprises: acquiring the completion condition of the drawing set number to determine the progress information of the final-stage sub-project in the design project stage; acquiring contract amount completion conditions to determine the progress information of the final-stage sub-project in the purchase project stage; and acquiring the completion condition of the item operation to determine the progress information of the final-stage sub-item of the construction project stage.
In some embodiments, collecting progress information of the last-level sub-item on a regular basis, and decomposing assignments and progress collection for the last-level sub-item based on the progress information and preset assignment rules comprises: acquiring progress information of the final-stage sub-project regularly through a webpage end and/or a mobile phone end, wherein the progress information comprises actual starting time, actual finishing time, estimated finishing time and an image progress photo of the engineering project; matching the progress information with the project progress plan, and assigning the progress acquisition to the final-stage sub-project based on a preset assignment rule; and generating an image progress photo library based on the image progress photos of the engineering project for the user to view.
In some embodiments, the method further comprises: and performing adjustment assignment on the project of the final-stage sub project on the progress plan based on the progress information of the final-stage sub project.
In some embodiments, statistically analyzing the data step by step and generating a unit project progress report, a level one sub-project report and a project total report includes: counting based on the system progress condition and the item operation condition to generate a progress S curve comparison graph and a unit project progress report; counting based on the progress condition of design/purchase/construction and the subentry operation condition to generate a design/purchase/construction weight configuration pie chart, a design/purchase/construction plan and actual progress curve comparison chart, a design/purchase/construction accumulated plan and actual completion operation columnar comparison chart and generate a design/purchase/construction progress report; and carrying out statistics on the basis of the progress condition, the sub-project operation condition, the purchasing bid condition, the construction sub-package condition and the main target progress to generate a comparison curve of the overall project progress and the actual progress, a project accumulated plan and actual completion operation histogram and a weight configuration diagram of each stage, and generating a project total report.
In another aspect of the embodiments of the present invention, there is provided an engineering project progress management apparatus, including: the system comprises a value assignment module, a data processing module and a data processing module, wherein the value assignment module is configured to disassemble an engineering project step by step to obtain sub projects of multiple levels, and perform the value assignment of a project schedule plan on the sub projects of the multiple levels based on the requirements of the engineering project, and the final-level sub project performs the value assignment of the project schedule plan based on the plan starting time and the plan ending time; the acquisition module is configured to periodically acquire the progress information of the final-stage sub-project, and perform decomposition assignment and progress acquisition on the final-stage sub-project based on the progress information and a preset assignment rule; a summary module configured to summarize data from sub-projects of the last level up to a level of sub-projects based on the project schedule and valuations gathered by the project schedule; and the analysis module is configured for carrying out statistical analysis on the data step by step and generating a unit project progress report, a first-level sub-project report and a project total report based on a preset statistical rule.
In another aspect of the embodiments of the present invention, there is provided a computer device, including: at least one processor; and a memory storing computer instructions executable on the processor, the instructions when executed by the processor implementing the steps of the method.
In another aspect of the embodiments of the present invention, a computer-readable storage medium is further provided, in which a computer program for implementing the above method steps is stored when the computer program is executed by a processor.
The invention has at least the following beneficial technical effects: the accurate project progress filling and uploading of the image progress photos are realized; the progress data statistical analysis is automatic and intelligent; the project progress report is automatically generated and visually displayed, so that related personnel can intuitively and quickly master the overall situation of the project.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other embodiments can be obtained by using the drawings without creative efforts.
FIG. 1 is a schematic diagram of an embodiment of a method for managing progress of an engineering project according to the present invention;
FIG. 2 is a form template of an embodiment of a project schedule management method provided by the present invention;
FIG. 3 is a schematic diagram of an embodiment of an engineering project progress management apparatus provided by the present invention;
FIG. 4 is a schematic diagram of an embodiment of a computer device provided by the present invention;
FIG. 5 is a schematic diagram of an embodiment of a computer-readable storage medium provided by the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the following detailed description of the embodiments of the present invention, but it should be understood that the scope of the present invention is not limited by the embodiments.
It should be noted that all expressions using "first" and "second" in the embodiments of the present invention are used for distinguishing two entities with the same name but different names or different parameters, and it should be noted that "first" and "second" are only used for convenience of expression and should not be construed as a limitation to the embodiments of the present invention, and no description is given in the following embodiments.
Throughout the specification and claims, unless explicitly stated otherwise, the word "comprise", or variations such as "comprises" or "comprising", will be understood to imply the inclusion of a stated element or component but not the exclusion of any other element or component.
In view of the above, a first aspect of the embodiments of the present invention provides an embodiment of a project progress management method. Fig. 1 is a schematic diagram illustrating an embodiment of a project progress management method according to the present invention. As shown in fig. 1, the method for managing the progress of the engineering project according to the embodiment of the present invention includes the following steps:
001. the method comprises the steps of progressively disassembling the engineering project to obtain sub-projects of multiple levels, and assigning a project schedule plan to the sub-projects of the multiple levels based on engineering project requirements, wherein the final-level sub-project assigns the project schedule plan based on plan start time and plan end time;
002. acquiring progress information of the final-stage sub-project regularly, and performing decomposition assignment and progress acquisition on the final-stage sub-project based on the progress information and a preset assignment rule;
003. step-by-step ascending sub-project summary data of a last-level sub-project to a first-level sub-project based on assignments acquired by the project schedule plan and the project schedule; and
004. and carrying out statistical analysis on the data step by step, and generating a unit project progress report, a first-level sub-project report and a project total report based on a preset statistical rule.
Fig. 2 is a table template of an embodiment of the project progress management method provided by the present invention. As shown in fig. 2, in this embodiment, an engineering project manager fills the table template with the four-level project tree structures of engineering projects according to engineering stages (including design, purchase, and construction), sub-unit projects, sub-project projects, and sub-project operations according to the table template, and then imports the schedule management system for assignment. Each responsible person for designing, purchasing and constructing fills the planning starting time and the planning ending time aiming at the project operation items divided according to a plurality of sub projects, and calculates the construction period of each operation. And automatically assigning according to the proportion of the project duration to the sum of days of the project duration of each project.
In this embodiment, the engineering project manager periodically collects the progress of the project sub-project operation project according to the progress of the project, i.e. fills in the "actual start time" and "actual completion time", uploads the image progress photos of the engineering project, and fills in the estimated completion time before the project is completed. And the progress management system platform can be filled and reported by the webpage end and the mobile phone end. And carrying out progressive detailed decomposition assignment on the final-level sub-project which can be subjected to further detailed assignment, and then carrying out progress acquisition.
In the embodiment, the system performs upward statistical assignment step by the sub-project operation, the sub-project, the sub-unit project and the design, purchase and construction according to a built-in rule, and summarizes data and performs statistical analysis. And carrying out statistical analysis step by step until the progress completion condition of the whole project is reached.
In the embodiment, the platform analyzes project progress data according to built-in rules, and automatically generates a progress report and a chart by automatically counting and analyzing data step by step through project operation, subsection engineering, sub-unit engineering, design, purchase and construction engineering; reports are mainly divided into three categories: a unit project progress report, a design procurement construction progress report and a project total report.
In some embodiments of the present invention, progressively disassembling the engineering project to obtain a plurality of levels of sub-projects comprises: the engineering project is disassembled step by step to obtain a first-level sub project, a second-level sub project, a third-level sub project and a final-level sub project; the first-level sub project comprises a project stage, the second-level sub project comprises a plurality of sub unit projects, the third-level sub project comprises a plurality of branch projects, and the last-level sub project comprises a plurality of branch project operation items; assigning a project schedule to a plurality of levels of sub-projects based on engineering project requirements includes: the total of the valuations of the project schedule for each level of sub-projects is 100%.
In this embodiment, the resolution is a step-by-step division of the project scope and deliverables into smaller, more manageable components, the degree of resolution depending on the degree of control required to achieve efficient management of the project. The first-level assignment is the percentage of the whole project of design, purchase and construction, the second-level assignment is the percentage of the project stage of the sub-unit project, the third-level assignment is the percentage of the sub-unit project to which the sub-unit project belongs, and the fourth-level assignment is the percentage of the sub-unit project to which the sub-unit project belongs. The four-level assignment process is as follows:
first-level assignment (design, purchase, construction assignment): according to the engineering contract mode, the assignment design, purchase and construction are i, j and k respectively, and i + j + k =100%. Wherein the value ranges of i, j and k are 0% -100%;
secondary assignment (sub-unit engineering assignment): each design, purchase and construction responsible person carries out assignment according to the sub-unit projects divided by the project, and the weights of the design, purchase and construction of the same sub-unit project can be different, but the sum of the assignment weights is required to be 100%. If an engineering project is divided into H, J, K, M and N,5 sub-unit projects, the design sub-unit project is assigned as follows: 35%, 20%, 10%, 15%; the procurement sub-unit project is assigned as: 40%, 20%, 10%; the construction sub-unit project is assigned as: 45%, 15%, 20% and 5%.
Three-level assignment (branch engineering assignment): design, purchase and construction individual responsible persons assign values to the project divided according to a plurality of sub-unit projects, the assigned weights of the same project can be different, but the sum of the assigned weights is required to be 100%. If a sub-unit project is divided into H1, H2, H3, H4, H5,5 sub-projects, the design sub-projects can be assigned as: 35%, 20%, 10%, 15%; the procurement subsection can be assigned as: 40%, 20%, 10%; the construction subsection can be assigned as: 45%, 15%, 20% and 5%.
Four-level assignment (automatic assignment of branch operation items): each responsible person for designing, purchasing and constructing fills the planning starting time and the planning ending time aiming at the project operation items divided according to a plurality of sub projects, and calculates the construction period of each operation. And automatically assigning according to the proportion of the project duration of the itemized operation to the sum of the days of the project duration of the itemized operation (without considering project duration coincidence state).
In some embodiments of the invention, the assigning of the project schedule by the last-level sub-project based on the schedule start time and the schedule end time comprises: respectively acquiring the planned starting time and the planned ending time of each project operation item, and calculating the construction period of the project operation item based on the planned starting time and the planned ending time; and adding the construction periods of each project operation item to obtain a total construction period, and assigning a project schedule plan based on the ratio of the construction periods of the project operation items to the total construction period.
In this embodiment, the project manager repeatedly estimates and sequences the duration of each task of the project, and determines the project milestones and critical paths for a plurality of times, so as to ensure that the project can be delivered according to the contract. In the design and purchase stage, a milestone node method is adopted by taking a design work package and a purchase package as units, each milestone point can be adjusted according to habits and project characteristics of an enterprise, and in the construction stage, key project completion is usually taken as a milestone node. Each responsible person for designing, purchasing and constructing fills the planning starting time and the planning ending time aiming at the project operation items divided according to a plurality of sub projects, and calculates the construction period of each operation. And automatically assigning according to the proportion of the project duration to the sum of days of the project duration of each project (without considering project duration coincidence state). For example, a part of the process is divided into three sub-operations h1, h2 and h 3. And the respective plan start, plan finish, construction period and assignment are shown in the following table:
subsection engineering Separate operation Plan start Plan completion Construction period (sky) Assignment of value
h1 6/month/11/2022 7/11/2022 30 37.50%
H1 h2 30 days 6 months in 2022 31/7/2022/month 31 38.75
h3
12 days 7 month in 2022 7/31/2022 19 23.75%
In total 80 100.00%
In the embodiment, the planned but not yet completed project needs to be filled with the estimated completion time, a project adopts a filling mechanism of the yet needed completion time/the estimated completion time, bidirectional mutual calculation is carried out on the yet needed construction period/the estimated completion time when the user selects and inputs the project, and meanwhile, the quick filtering and screening of the operation items can be carried out on the dimensions of the yet needed project, the non-start, the middle, completed project, milestones, key paths and the like. If the user has unfilled items in the data to be reported in the current reporting period, the embodiment automatically predicts and finishes the report after 14 days according to the operation items, the operation items in the next week are displayed in bright yellow, the operation items are conveyed to the user through visual comparison and are unfilled items in the last period, the user is reminded to collect as soon as possible, when the number of days which are automatically reported is less than 8 days, the actual/predicted collection completion bar returns to a white state, and if the user still does not report, the operation item is predicted and finished after 14 days is continuously judged according to the embodiment.
In some embodiments of the invention, periodically collecting progress information for the final sub-item comprises: acquiring the completion condition of the drawing set number to determine the progress information of the final-stage sub-project in the design project stage; acquiring contract amount completion conditions to determine progress information of a final-stage sub-project in a purchase project stage; and acquiring the completion condition of the item operation to determine the progress information of the final-stage sub-item of the construction project stage.
In this embodiment, the project manager periodically performs project sub-project schedule collection according to the project progress, that is, fills the actual start time and the actual completion time, uploads project image schedule photos, and fills the estimated completion time that is required to be completed but not completed. The progress management system platform can be filled and reported at a webpage end and a mobile phone end, wherein the completion of the designed work is determined according to the number of sets of drawings, the purchase is completed according to contract amount, and the construction is determined for the completion of each sub-operation.
In some embodiments of the invention, collecting progress information of the last-level sub-item on a regular basis, and performing the decomposition assignment and the progress collection on the last-level sub-item based on the progress information and the preset assignment rule comprises: acquiring progress information of the final-stage sub-project regularly through a webpage end and/or a mobile phone end, wherein the progress information comprises actual starting time, actual finishing time, estimated finishing time and an image progress photo of the engineering project; matching the progress information with the project progress plan, and assigning the progress acquisition to the final-stage sub-project based on a preset assignment rule; and generating an image progress photo library based on the image progress photos of the engineering project for the user to view.
In this embodiment, a progress acquisition template is generated at a web page end and a mobile phone end of an engineering progress management platform based on a latest version of a progress plan currently issued by a project, an engineering project manager can report actual progress data and a related progress report after completing an identity verification login platform, the engineering project manager regularly performs project sub-project operation project progress acquisition according to project progress conditions, namely, the 'actual start time' and the 'actual completion time' are reported, an image progress photo of the engineering project is uploaded, and estimated completion time needs to be filled when the project is completed but not completed. The progress management system platform can be filled and reported at the webpage end and the mobile phone end. And forming an image progress photo library by the system platform according to the project progress plan, the progress acquisition and the image progress photos uploaded by the user for the user to check.
In the embodiment, the collection remark filling for each job item is supported, the photo image progress and the text image progress aiming at the current progress percentage can be uploaded, and the photo image progress and the text image progress can be uniformly managed and consulted in the image progress overview photo library.
In some embodiments of the invention, the method further comprises: and carrying out adjustment and assignment on the project of the final-stage sub project in the progress plan based on the progress information of the final-stage sub project.
In this embodiment, the assignments are collectively four-level assignments, wherein the first three levels cannot be changed after the assignments are completed. The four levels can be adjusted according to the actual conditions of the engineering project, and can also be modified by exporting the tables and then importing the updated data. Considering that the planning item is often changed to a certain project level when the planning item is formulated and released to the actual approach operation. And the method supports the revision change of project work items of the issued schedule according to the period, reissues the project work items, synchronously updates the progress acquisition template, and acquires the progress according to the revised new schedule.
In this embodiment, once the plan is released, the plan is basically not changeable in the first three levels, but the plan completion time of the original plan can be adjusted in a certain sense by acquiring and confirming the actual completion time of the future time point for many times by the user during schedule acquisition based on a mechanism for adjusting and changing the content of the level of the project operation after the plan is released.
In some embodiments of the present invention, statistically analyzing the data step by step, and generating the unit project progress report, the first-level sub-project report, and the project total report includes: counting based on the branch progress condition and the item operation condition to generate a progress S-curve comparison graph and a unit project progress report; counting based on the progress condition of design/purchase/construction and the subentry operation condition to generate a design/purchase/construction weight configuration pie chart, a design/purchase/construction plan and actual progress curve comparison chart, a design/purchase/construction accumulated plan and actual completion operation columnar comparison chart and generate a design/purchase/construction progress report; and carrying out statistics on the basis of the progress condition, the sub-project operation condition, the purchasing bid condition, the construction sub-package condition and the main target progress to generate a comparison curve of the overall project progress and the actual progress, a project accumulated plan and actual completion operation histogram and a weight configuration diagram of each stage, and generating a project total report.
In the embodiment, the system performs upward statistical assignment, data summarization and statistical analysis step by step through project division, sub-unit project and design purchasing construction according to built-in rules. As shown in the following table, the itemized operations H1 and H2 in the current-stage progress acquisition report are completed in the period of the original plan, that is, the occupied weight is automatically collected to the completion condition of H1, and the itemized operation H3 is not completed in the period of the original plan, so that the number of the itemized processes collected is 0.00%. And by analogy, carrying out statistical analysis step by step until the progress of the whole project is completed.
Figure BDA0003920820650000101
Figure BDA0003920820650000111
The platform analyzes project progress data according to built-in rules, and automatically generates a progress report and a chart by performing automatic statistical analysis on data step by step through project division operation, project division, sub-unit project, design, purchase and construction project; reports are mainly classified into three categories: a unit project progress report, a design procurement construction progress report and a project total report.
The unit project progress report includes: and comparing the project progress condition, the branch operation condition and the project plan progress of each sub-unit with the actual project progress S curve. Wherein, the system progress condition comprises: accumulating the plan completion progress, accumulating the actual completion progress, accumulating the progress deviation, the plan completion progress of the current period, the actual completion progress of the current period and the progress deviation of the current period; the branch operation condition comprises the following steps: the project operation item, the plan completion operation item, the accumulated deviation, the plan completion operation of the current period, the actual completion operation of the current period and the deviation of the current period.
The design progress report includes: the method comprises the steps of comparing a design technology with an actual progress curve, and comparing a design accumulation plan with an actual completion operation histogram. Wherein, the progress condition comprises: accumulating plan completion progress, accumulating actual completion progress, accumulating progress deviation, planning completion progress of the current period, actual completion progress of the current period, deviation of the current period progress, planning total period of conversation completion date, counting deviation days, evaluating results and perhaps follow-up measures; the branch operation graph sending condition comprises the following steps: unit project, subsection project, total construction drawing, planned drawing, actual drawing, deviation and drawing which needs to be completed.
The procurement progress report includes: the method comprises the steps of obtaining a progress condition, a subentry operation condition, a mechanical equipment purchase package distribution condition, a current stage main progress, a recommended department concern item, a competent owner and an ineffectiveness factor influence, a value assignment method purchase weight preparation pie chart, a purchase plan and actual progress curve comparison, and a purchase accumulation plan and actual completion operation histogram comparison. Wherein, the progress condition comprises: accumulating plan completion progress, accumulating actual completion progress, accumulating progress deviation, planning completion progress of the current period, actual completion progress of the current period, deviation of the current period progress, planning total period of conversation completion date, counting deviation days, evaluating results and follow-up measures; the branch operation condition comprises: unit engineering, subsection engineering, project division operation, planned completion operation, actual completion operation, deviation and operation yet to be completed; the mechanical equipment purchasing package issuing condition comprises the following steps: purchase package, established purchase package, bid mid/in-process supplier, return funding supplier, completion rate.
The construction progress report includes: the method comprises the steps of progress condition, item operation condition, construction sub-packaging condition, determined sub-packaging unit operation item, operation item in bid inviting, unit operation item to be determined sub-packaging, main progress of the current stage, recommended department concern item, industry owner and insusceptibility factor influence, assignment method construction weight preparation pie chart, purchase plan and actual progress curve comparison, and purchase accumulation plan and actual completion operation histogram comparison. Wherein, the progress condition comprises: accumulating plan completion progress, accumulating actual completion progress, accumulating progress deviation, plan completion progress of the current period, actual completion progress of the current period, deviation of the current period, plan total construction period of conversation completion date, statistics deviation days, evaluation results and follow-up measures; the branch operation condition comprises: unit engineering, subsection engineering, project division operation, planned completion operation, actual completion operation, deviation and operation yet to be completed; construction subpackage condition: determining a subcontracting party, a subcontracting party in construction, a subcontracting quotient in bid invitation/flow and already settling the subcontracting.
The total report of the project includes: the method comprises the following steps of scheduling condition, sub-project operation condition, purchasing and bidding condition, construction sub-package condition, main schedule of the current period, and items required to be paid attention, supported and coordinated by a recommendation department, and weight configuration of each stage of the project, including the influence of owner and inequality factor, a comparison curve of the overall plan schedule and the actual schedule of the project, a project accumulation plan and an actual completion operation histogram and an assignment method. Wherein, the progress condition includes: accumulating plan completion progress, accumulating actual completion progress, accumulating progress deviation, plan completion progress of the current period, actual completion progress of the current period, deviation of the current period, plan total construction period of conversation completion date, statistics deviation days, evaluation results and follow-up measures; the branch operation condition comprises: unit engineering, subsection engineering, project division operation, planned completion operation, actual completion operation, deviation and operation yet to be completed; the purchase bidding conditions comprise: purchasing total amount of packages, signed contract, tender middling/flow subcontractor, non-tender contract; the construction subcontracting condition comprises: determining a subcontracting party, a construction subcontracting party, a bid inviting middling/flow subcontracting quotient and already settling subcontracting.
In some embodiments of the invention, further comprising: intelligent early warning in the report form, on-line progress warning, comparative analysis and reporting of the project by an administrator with reporting authority.
In this embodiment, according to a pre-designed project early warning threshold, functions of project progress on-line warning, digital front line, progress comparison analysis and the like, auxiliary guidance layer analysis decision making, and project control and correction scheme making as soon as possible are realized. According to the role division of the authority control module, a manager sets whether to report to the enterprise or not by a division manager and a project manager sets whether to report to the division or not, and the project reporting level is the project to which the report belongs by default.
In some embodiments of the invention, further comprising: and S, analyzing a progress curve.
In the embodiment, based on the actual progress acquisition data and the project basic progress data in each project periodic progress acquisition template, the dynamic relation between the actual progress and the planned progress value and the time interval is visually represented by adopting an S progress curve method, and the overall operation condition of the project can be known by judging the deviation and the historical track of the actual progress and the planned progress, so that the project is clear and stereoscopic. Besides the basic plan, actual and estimated progress 3 elements of the S curve, the method also supports the functions of automatically adding and comparing interval reference lines, displaying milestones, close-up interval progress curves and the like.
It should be particularly noted that, the steps in the embodiments of the engineering project schedule management method described above can be mutually intersected, replaced, added, or deleted, so that the engineering project schedule management method based on these reasonable permutation and combination transformations shall also belong to the scope of the present invention, and shall not limit the scope of the present invention to the embodiments.
In view of the above, according to a second aspect of the embodiments of the present invention, an engineering project progress management apparatus is provided. Fig. 3 is a schematic diagram of an embodiment of an engineering project progress management device provided by the invention. As shown in fig. 3, the project progress management apparatus according to the embodiment of the present invention includes the following modules: the assignment module 011 is configured to disassemble the engineering project step by step to obtain a plurality of levels of sub-projects, and to assign the project schedule plan to the plurality of levels of sub-projects based on the engineering project requirements, wherein the final level of sub-projects assigns the project schedule plan based on the plan start time and the plan end time; the acquisition module 012 is configured to periodically acquire the progress information of the final-stage sub-project, and perform decomposition assignment and progress acquisition on the final-stage sub-project based on the progress information and a preset assignment rule; a summarization module 013 configured to summarize data from sub-projects of a last level up to a next level in a hierarchy based on assignments collected by the project schedule plan and the project schedule up to the first level sub-project; and an analysis module 014 configured to perform statistical analysis on the data step by step, and generate a unit project progress report, a first-level sub-project report and a project total report based on preset statistical rules.
In view of the above object, a third aspect of the embodiments of the present invention provides a computer device. Fig. 4 is a schematic diagram of an embodiment of a computer device provided by the present invention. As shown in fig. 4, the computer apparatus of the embodiment of the present invention includes the following means: at least one processor 021; and a memory 022, the memory 022 storing computer instructions 023 executable on the processor, the instructions when executed by the processor implementing the steps of the above method.
The invention also provides a computer readable storage medium. FIG. 5 is a schematic diagram illustrating an embodiment of a computer-readable storage medium provided by the present invention. As shown in fig. 5, the computer readable storage medium 031 stores a computer program 032 which, when executed by a processor, performs the method as described above.
Finally, it should be noted that, as those skilled in the art can understand, all or part of the processes in the method according to the above embodiments may be implemented by instructing relevant hardware through a computer program, and the program of the method for managing progress of an engineering project may be stored in a computer-readable storage medium, and when executed, may include the processes according to the embodiments of the methods described above. The storage medium of the program may be a magnetic disk, an optical disk, a Read Only Memory (ROM), a Random Access Memory (RAM), or the like. The embodiments of the computer program may achieve the same or similar effects as any of the above-described method embodiments.
Furthermore, the methods disclosed according to embodiments of the present invention may also be implemented as a computer program executed by a processor, which may be stored in a computer-readable storage medium. Which when executed by a processor performs the above-described functions defined in the methods disclosed in embodiments of the invention.
Further, the above method steps and system elements may also be implemented using a controller and a computer readable storage medium for storing a computer program for causing the controller to implement the functions of the above steps or elements.
Those of skill would further appreciate that the various illustrative logical blocks, modules, circuits, and algorithm steps described in connection with the disclosure herein may be implemented as electronic hardware, computer software, or combinations of both. To clearly illustrate this interchangeability of hardware and software, various illustrative components, blocks, modules, circuits, and steps have been described above generally in terms of their functionality. Whether such functionality is implemented as software or hardware depends upon the particular application and design constraints imposed on the overall system. Skilled artisans may implement the described functionality in varying ways for each particular application, but such implementation decisions should not be interpreted as causing a departure from the scope of the present disclosure.
In one or more exemplary designs, the functions may be implemented in hardware, software, firmware, or any combination thereof. If implemented in software, the functions may be stored on or transmitted over as one or more instructions or code on a computer-readable medium. Computer-readable media includes both computer storage media and communication media including any medium that facilitates transfer of a computer program from one place to another. A storage media may be any available media that can be accessed by a general purpose or special purpose computer. By way of example, and not limitation, such computer-readable media can comprise RAM, ROM, EEPROM, CD-ROM or other optical disk storage, magnetic disk storage or other magnetic storage devices, or any other medium that can be used to carry or store desired program code in the form of instructions or data structures and that can be accessed by a general-purpose or special-purpose computer, or a general-purpose or special-purpose processor. Also, any connection is properly termed a computer-readable medium. For example, if the software is transmitted from a website, server, or other remote source using a coaxial cable, fiber optic cable, twisted pair, digital Subscriber Line (DSL), or wireless technologies such as infrared, radio, and microwave, then the coaxial cable, fiber optic cable, twisted pair, DSL, or wireless technologies such as infrared, radio, and microwave are included in the definition of medium. Disk and disc, as used herein, includes Compact Disc (CD), laser disc, optical disc, digital Versatile Disc (DVD), floppy disk, blu-ray disc where disks usually reproduce data magnetically, while discs reproduce data optically with lasers. Combinations of the above should also be included within the scope of computer-readable media.
The foregoing are exemplary embodiments of the present disclosure, but it should be noted that various changes and modifications could be made herein without departing from the scope of the present disclosure as defined by the appended claims. The functions, steps and/or actions of the method claims in accordance with the disclosed embodiments described herein need not be performed in any particular order. Furthermore, although elements of the embodiments of the invention may be described or claimed in the singular, the plural is contemplated unless limitation to the singular is explicitly stated.
It should be understood that, as used herein, the singular forms "a", "an" and "the" are intended to include the plural forms as well, unless the context clearly supports the exception. It should also be understood that "and/or" as used herein is meant to include any and all possible combinations of one or more of the associated listed items.
The numbers of the embodiments disclosed in the embodiments of the present invention are merely for description, and do not represent the merits of the embodiments.
It will be understood by those skilled in the art that all or part of the steps for implementing the above embodiments may be implemented by hardware, or may be implemented by a program instructing relevant hardware, and the program may be stored in a computer-readable storage medium, and the above-mentioned storage medium may be a read-only memory, a magnetic disk or an optical disk, etc.
Those of ordinary skill in the art will understand that: the discussion of any embodiment above is meant to be exemplary only, and is not intended to intimate that the scope of the disclosure, including the claims, of embodiments of the invention is limited to these examples; within the idea of an embodiment of the invention, also combinations between technical features in the above embodiments or in different embodiments are possible, and there are many other variations of the different aspects of the embodiments of the invention as described above, which are not provided in detail for the sake of brevity. Therefore, any omissions, modifications, substitutions, improvements, and the like that may be made without departing from the spirit and principles of the embodiments of the present invention are intended to be included within the scope of the embodiments of the present invention.

Claims (10)

1. A project progress management method is characterized by comprising the following steps:
the method comprises the steps of resolving the engineering project step by step to obtain sub projects of multiple levels, and assigning a project progress plan to the sub projects of the multiple levels based on engineering project requirements, wherein the final-level sub project assigns the project progress plan based on plan starting time and plan ending time;
acquiring progress information of the last-stage sub-project periodically, and performing decomposition assignment and progress acquisition on the last-stage sub-project based on the progress information and a preset assignment rule;
progressively adding sub-project summary data from the last level sub-project to an upper level of sub-projects up to a level of sub-projects based on the project schedule and the project schedule collected valuations; and
and carrying out statistical analysis on the data step by step, and generating a unit project progress report, a first-level sub-project report and a project total report based on a preset statistical rule.
2. The project progress management method of claim 1, wherein the parsing the project level by level to obtain a plurality of levels of sub-projects comprises:
the engineering project is disassembled step by step to obtain a first-level sub project, a second-level sub project, a third-level sub project and a final-level sub project;
the first-level sub project comprises a project stage, the second-level sub project comprises a plurality of sub unit projects, the third-level sub project comprises a plurality of branch projects, and the last-level sub project comprises a plurality of branch project operation items;
assigning the project schedule to the plurality of levels of sub-projects based on the engineering project requirements comprises:
the sum of the assignments of the project schedule for each level of sub-project is 100%.
3. The project schedule management method of claim 1, wherein assigning a project schedule by the final level sub-project based on the schedule start time and the schedule end time comprises:
respectively acquiring the planned starting time and the planned ending time of each project operation item, and calculating the construction period of the project operation item based on the planned starting time and the planned ending time;
and adding the construction periods of the project operation items to obtain a total construction period, and assigning a project schedule plan based on the ratio of the construction periods of the project operation items to the total construction period.
4. The project progress management method of claim 1, wherein periodically collecting progress information for the last-level sub-project comprises:
acquiring the completion condition of the drawing set number to determine the progress information of the final-stage sub-project in the design project stage;
acquiring contract amount completion conditions to determine the progress information of the final-stage sub-project in the purchase project stage;
and acquiring the completion condition of the item operation to determine the progress information of the final-stage sub-item of the construction project stage.
5. The project progress management method of claim 1, wherein collecting progress information of the last-level sub-project periodically, and performing decomposition assignment and progress collection on the last-level sub-project based on the progress information and preset assignment rules comprises:
acquiring progress information of the final-stage sub-project regularly through a webpage end and/or a mobile phone end, wherein the progress information comprises actual starting time, actual finishing time, estimated finishing time and an image progress photo of the engineering project;
matching the progress information with the project progress plan, and performing progress acquisition assignment on the final-stage sub-project based on a preset assignment rule;
and generating an image progress photo library based on the image progress photos of the engineering project for the user to view.
6. The project progress management method according to claim 1, further comprising:
and performing adjustment assignment on the project of the final-stage sub project on the progress plan based on the progress information of the final-stage sub project.
7. The project progress management method according to claim 1, wherein statistically analyzing the data level by level and generating a unit project progress report, a level one sub-project report and a project total report comprises:
counting based on the system progress condition and the item operation condition to generate a progress S curve comparison graph and a unit project progress report;
counting based on the progress condition of design/purchase/construction and the subentry operation condition to generate a design/purchase/construction weight configuration pie chart, a design/purchase/construction plan and actual progress curve comparison chart, a design/purchase/construction cumulative plan and actual completion operation columnar comparison chart and a design/purchase/construction progress report;
and carrying out statistics on the basis of the progress condition, the branch operation condition, the purchase bid condition, the construction sub-package condition and the main target progress to generate a comparison curve of the overall plan progress and the actual progress of the project, a histogram of the project accumulation plan and the actual completion operation and a weight configuration diagram of each stage, and generating a total project report.
8. An engineering project progress management apparatus, comprising:
the system comprises an assignment module, a scheduling module and a scheduling module, wherein the assignment module is configured to disassemble an engineering project step by step to obtain sub-projects of multiple levels, and assign a project schedule to the sub-projects of the multiple levels based on engineering project requirements, and the final-level sub-project assigns the project schedule based on a schedule starting time and a schedule ending time;
the acquisition module is configured to periodically acquire the progress information of the final-stage sub-project, and perform decomposition assignment and progress acquisition on the final-stage sub-project based on the progress information and a preset assignment rule;
a summarization module configured to summarize data from sub-projects of a last level up to a next level by levels based on the project schedule and the valuations collected by the project schedule; and
and the analysis module is configured for carrying out statistical analysis on the data step by step and generating a unit project progress report, a first-level sub-project report and a project total report based on a preset statistical rule.
9. A computer device, comprising:
at least one processor; and
a memory storing computer instructions executable on the processor, the computer instructions when executed by the processor implementing the steps of the method of any one of claims 1 to 7.
10. A computer-readable storage medium, in which a computer program is stored which, when being executed by a processor, carries out the steps of the method according to any one of claims 1 to 7.
CN202211357735.0A 2022-11-01 2022-11-01 Engineering project progress management method, device and equipment and readable medium Pending CN115689485A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211357735.0A CN115689485A (en) 2022-11-01 2022-11-01 Engineering project progress management method, device and equipment and readable medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211357735.0A CN115689485A (en) 2022-11-01 2022-11-01 Engineering project progress management method, device and equipment and readable medium

Publications (1)

Publication Number Publication Date
CN115689485A true CN115689485A (en) 2023-02-03

Family

ID=85048802

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211357735.0A Pending CN115689485A (en) 2022-11-01 2022-11-01 Engineering project progress management method, device and equipment and readable medium

Country Status (1)

Country Link
CN (1) CN115689485A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115878010A (en) * 2023-03-01 2023-03-31 南方科技大学 Operation interaction method and device, electronic equipment and computer-readable storage medium
CN116090847A (en) * 2023-03-06 2023-05-09 山东丰茂源认证服务有限公司 User identity data management system based on cloud platform and readable medium
CN116777387A (en) * 2023-06-29 2023-09-19 华腾建信科技有限公司 Engineering data processing method and system for visual progress display
CN117273391A (en) * 2023-11-07 2023-12-22 中航机载系统共性技术有限公司 Management method and device for complex airborne system development plan and electronic equipment
CN117408643A (en) * 2023-12-12 2024-01-16 长春建业集团股份有限公司 Progress monitoring management method and system applied to engineering number intelligent management platform
CN117455419A (en) * 2023-12-22 2024-01-26 江西五十铃汽车有限公司 Whole vehicle project management method and system
CN117952544A (en) * 2024-01-03 2024-04-30 上海普华科技发展股份有限公司 Progress management method and device based on multistage nested plan structure

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115878010A (en) * 2023-03-01 2023-03-31 南方科技大学 Operation interaction method and device, electronic equipment and computer-readable storage medium
CN116090847A (en) * 2023-03-06 2023-05-09 山东丰茂源认证服务有限公司 User identity data management system based on cloud platform and readable medium
CN116777387A (en) * 2023-06-29 2023-09-19 华腾建信科技有限公司 Engineering data processing method and system for visual progress display
CN117273391A (en) * 2023-11-07 2023-12-22 中航机载系统共性技术有限公司 Management method and device for complex airborne system development plan and electronic equipment
CN117408643A (en) * 2023-12-12 2024-01-16 长春建业集团股份有限公司 Progress monitoring management method and system applied to engineering number intelligent management platform
CN117408643B (en) * 2023-12-12 2024-03-22 长春建业集团股份有限公司 Progress monitoring management method and system applied to engineering number intelligent management platform
CN117455419A (en) * 2023-12-22 2024-01-26 江西五十铃汽车有限公司 Whole vehicle project management method and system
CN117952544A (en) * 2024-01-03 2024-04-30 上海普华科技发展股份有限公司 Progress management method and device based on multistage nested plan structure

Similar Documents

Publication Publication Date Title
CN115689485A (en) Engineering project progress management method, device and equipment and readable medium
US20110131220A1 (en) Systems and methods for generating an optimized output range for a data distribution in a hierarchical database
CN107358340A (en) A kind of project management system based on list of engineering
US20210304134A1 (en) Graphical user interface-based platform supporting bill of materials (bom) characterization
US11687989B2 (en) Graphical user interface-based platform supporting request for X (RFX) creation and response management
US20210304269A1 (en) Graphical user interface-based platform supporting price analysis visualization and control
US10642838B2 (en) Real-time or event-based analysis of process data
US20150120370A1 (en) Advanced planning in a rapidly changing high technology electronics and computer industry through massively parallel processing of data using a distributed computing environment
CN113674013B (en) Advertisement bidding adjustment method and system based on merchant custom rules
CN110728422A (en) Building information model, method, device and settlement system for construction project
Gomez Segura et al. Analysis of lean manufacturing strategy using system dynamics modelling of a business model
Akhoondi et al. A heuristic algorithm for master production scheduling problem with controllable processing times and scenario-based demands
CN110032154B (en) Production control method and system for small-batch products
CN110968751B (en) Dynamic display method and device for engineering project capital curve
CN114841788A (en) Engineering project construction management completion settlement overall process management system
US20210304273A1 (en) Graphical user interface-based platform supporting request for x (rfx) response compliance verification
US20210304272A1 (en) Graphical user interface-based platform supporting request for x (rfx) creation and management and response compliance checking
US20160217400A1 (en) Systems and methods of workforce planning
CN117540870A (en) Product shortage prediction method, system, equipment and readable medium
JP2003288476A (en) Line capacity integrated evaluation/management operation system for production line and line capacity integrated evaluation/management operation method for the production line
CN111738538A (en) Engineering project management system, management method, APP and storage medium
CN112801768A (en) Internet + government affair-based natural fund and performance data sharing system
CN117273511A (en) Data analysis method and device
NOVIKOV et al. Improving the enterprise resource planning system based on digital modules of the industry 4.0 concept
Badillo et al. Supply chain management from a systems science perspective

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination