CN115627781B - A slope reinforcement structure and construction method for rapid treatment of existing slope collapse - Google Patents
A slope reinforcement structure and construction method for rapid treatment of existing slope collapse Download PDFInfo
- Publication number
- CN115627781B CN115627781B CN202211277421.XA CN202211277421A CN115627781B CN 115627781 B CN115627781 B CN 115627781B CN 202211277421 A CN202211277421 A CN 202211277421A CN 115627781 B CN115627781 B CN 115627781B
- Authority
- CN
- China
- Prior art keywords
- nail
- slope
- pile
- main
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000002787 reinforcement Effects 0.000 title claims abstract description 56
- 238000010276 construction Methods 0.000 title claims abstract description 44
- 239000002689 soil Substances 0.000 claims abstract description 34
- 239000004576 sand Substances 0.000 claims abstract description 16
- 239000004567 concrete Substances 0.000 claims abstract description 13
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 5
- 238000000034 method Methods 0.000 claims description 11
- 239000007787 solid Substances 0.000 claims description 11
- 229910000831 Steel Inorganic materials 0.000 claims description 8
- 239000010959 steel Substances 0.000 claims description 8
- 238000009412 basement excavation Methods 0.000 claims description 7
- 230000008569 process Effects 0.000 claims description 7
- 238000006073 displacement reaction Methods 0.000 claims description 6
- 238000005192 partition Methods 0.000 claims description 5
- 238000013461 design Methods 0.000 claims description 3
- 238000011156 evaluation Methods 0.000 claims description 3
- 238000011835 investigation Methods 0.000 claims description 3
- 238000012544 monitoring process Methods 0.000 claims description 3
- 239000002131 composite material Substances 0.000 claims description 2
- 230000006641 stabilisation Effects 0.000 claims description 2
- 238000011105 stabilization Methods 0.000 claims description 2
- 240000000233 Melia azedarach Species 0.000 abstract 1
- 230000000694 effects Effects 0.000 description 12
- 230000002195 synergetic effect Effects 0.000 description 6
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 230000008878 coupling Effects 0.000 description 2
- 238000010168 coupling process Methods 0.000 description 2
- 238000005859 coupling reaction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- OKTJSMMVPCPJKN-UHFFFAOYSA-N Carbon Chemical compound [C] OKTJSMMVPCPJKN-UHFFFAOYSA-N 0.000 description 1
- 230000001133 acceleration Effects 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 229910052799 carbon Inorganic materials 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000003090 exacerbative effect Effects 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 230000008595 infiltration Effects 0.000 description 1
- 238000001764 infiltration Methods 0.000 description 1
- 238000009440 infrastructure construction Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000007726 management method Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 230000000087 stabilizing effect Effects 0.000 description 1
- 238000012876 topography Methods 0.000 description 1
- 238000013316 zoning Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
- E02D13/04—Guide devices; Guide frames
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/08—Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/10—Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D33/00—Testing foundations or foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/30—Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/52—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/23—Dune restoration or creation; Cliff stabilisation
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
Description
技术领域Technical Field
本发明涉及既有边坡滑塌加固结构,特别是一种用于既有边坡滑塌快速处治的边坡加固结构及施工方法。The invention relates to an existing side slope landslide reinforcement structure, in particular to a side slope reinforcement structure and a construction method for rapid treatment of existing side slope landslide.
背景技术Background technique
边坡滑塌发生不仅会造成人民生命财产损失,而且严重妨碍交通安全运行,并破坏自然环境。Slope landslides not only cause loss of life and property, but also seriously hinder safe traffic operations and damage the natural environment.
边坡滑塌与自然因素有关,也与人类行为相关,比如自然因素中降雨入渗会导致边坡排水不通畅,人为行为中建构物施工易扰动边坡原始平衡。这些自然因素与人类行为引起边坡滑塌的机制是,一方面增大边坡的下滑能力,另一方面削弱边坡的抗滑能力。由此,为了提高边坡的稳定性,相对应地要降低边坡下滑力并提高边坡抗滑力。Slope collapse is related to natural factors and human behavior. For example, rainfall infiltration in natural factors can lead to poor slope drainage, and construction of structures in human behavior can easily disturb the original balance of the slope. The mechanism of slope collapse caused by these natural factors and human behavior is that on the one hand, the slope's sliding ability is increased, and on the other hand, the slope's anti-sliding ability is weakened. Therefore, in order to improve the stability of the slope, the slope's sliding force should be reduced and its anti-sliding force should be increased accordingly.
当前可采用的提高边坡稳定性的措施有削坡、抗滑桩加固和预应力锚索框架梁系统加固。对于削坡来说,其通过降低坡高与减缓坡度来达到降低边坡下滑力的目的,并以此来维持边坡稳定状态。然而,削坡措施需要通过人工或机械来对原始边坡进行大开大挖,其改变了原始边坡地形,破坏了当地生态环境。此外,削坡时施工扰动下的不当施工行为可能引发开挖边坡的局部滑塌,从而造成施工安全事故发生。对于抗滑桩加固和预应力锚索框架梁系统加固来说,其通过施加人工构筑物来阻挡边坡下滑,并以此提高边坡的抗滑能力。然而,无论是抗滑桩还是预应力锚索框架梁系统,其均要现挖现做,需配置大量人工或机械来完成施作,且对边坡形成有效防护所需的施工时间较长。由此,抗滑桩或预应力锚索框架梁系统加固措施不太适合于已发生滑塌或潜在滑塌边坡快速处治,与此同时,大量人力和物力需求造成抗滑桩以及预应力锚索框架梁系统加固的施工成本较高,也给施工安全性带来了不稳定因素。The current measures to improve slope stability include slope cutting, anti-slide pile reinforcement and prestressed anchor cable frame beam system reinforcement. For slope cutting, the purpose of reducing the downward force of the slope is achieved by reducing the slope height and slowing down the slope, thereby maintaining the stability of the slope. However, slope cutting measures require large-scale excavation of the original slope by manpower or machinery, which changes the original slope topography and damages the local ecological environment. In addition, improper construction behavior under construction disturbance during slope cutting may cause local collapse of the excavated slope, thereby causing construction safety accidents. For anti-slide pile reinforcement and prestressed anchor cable frame beam system reinforcement, artificial structures are applied to prevent the slope from sliding down, thereby improving the anti-slide ability of the slope. However, whether it is anti-slide piles or prestressed anchor cable frame beam systems, they must be excavated and constructed on the spot, and a large number of manpower or machinery are required to complete the construction, and the construction time required to effectively protect the slope is relatively long. Therefore, the anti-slide pile or prestressed anchor frame beam system reinforcement measures are not suitable for the rapid treatment of slopes that have already collapsed or are potentially prone to collapse. At the same time, the large amount of manpower and material resources required result in high construction costs for anti-slide piles and prestressed anchor frame beam system reinforcement, which also brings unstable factors to construction safety.
伴随着国内基础设施建设步伐的加快,人类行为对原始边坡的扰动更多,所引发的边坡滑塌问题也变得较为严重。此外,随着全球环境气候的变化,极端恶劣天气频发,进一步加剧了山区边坡的滑塌。也就是说,当前所面临的边坡处治形势非常严峻,特别是对突发的已滑塌或潜在滑塌边坡的快速处治成为一种迫切需求。With the acceleration of domestic infrastructure construction, human behavior has disturbed the original slopes more, and the slope collapse problem has become more serious. In addition, with the changes in the global environment and climate, extreme weather has occurred frequently, further exacerbating the collapse of mountain slopes. In other words, the current situation of slope treatment is very severe, especially the rapid treatment of sudden collapsed or potential collapsed slopes has become an urgent need.
发明内容Summary of the invention
本发明所要解决的技术问题是,针对现有已滑塌或潜在滑塌边坡处治方法的不足,本发明提供一种易于实施、快速便捷的用于既有边坡滑塌快速处治的边坡加固结构及施工方法。The technical problem to be solved by the present invention is that, in view of the shortcomings of existing methods for treating collapsed or potentially collapsed slopes, the present invention provides an easy-to-implement, fast and convenient slope reinforcement structure and construction method for quickly treating existing slope collapse.
为解决上述技术问题,本发明采用了如下技术方案:In order to solve the above technical problems, the present invention adopts the following technical solutions:
一种用于既有边坡滑塌快速处治的边坡加固结构,包括边坡,并在边坡潜在滑动体下部且靠近坡脚处的位置连续布置至少一排桩钉组合结构;A slope reinforcement structure for rapid treatment of existing slope collapse, comprising a slope, and at least one row of pile nail combination structures continuously arranged at a position below a potential sliding body of the slope and close to the slope foot;
所述桩钉组合结构包括呈Y型嵌固在边坡稳定土层内的主钉、辅钉、左翼钉和右翼钉,所述主钉位于所述辅钉、所述左翼钉和所述右翼钉之间,且所述主钉与所述辅钉、所述左翼钉和所述右翼钉之间分别通过钢筋混凝土连梁连接,所述主钉与所述左翼钉之间的连梁同所述主钉与所述右翼钉之间的连梁形成V型夹角,并面向所述边坡潜在滑动体设置,所述主钉和所述辅钉之间的连梁平行于所述边坡潜在滑动体主滑动方向设置,使各桩钉组合结构的主钉和辅钉整体形成双排桩结构;The pile-nail combination structure comprises a main nail, an auxiliary nail, a left wing nail and a right wing nail which are embedded in a Y-shaped soil layer of the slope stabilization layer. The main nail is located between the auxiliary nail, the left wing nail and the right wing nail, and the main nail is connected to the auxiliary nail, the left wing nail and the right wing nail respectively through reinforced concrete connecting beams. The connecting beam between the main nail and the left wing nail forms a V-shaped angle with the connecting beam between the main nail and the right wing nail, and is arranged facing the potential sliding body of the slope. The connecting beam between the main nail and the auxiliary nail is arranged parallel to the main sliding direction of the potential sliding body of the slope, so that the main nails and the auxiliary nails of each pile-nail combination structure form a double-row pile structure as a whole;
所述桩钉包括预制管桩和嵌套在预制管桩内的骨架,且所述预制管桩和骨架在边坡现场用混凝土浇筑成一体;The pile nails include prefabricated pipe piles and a frame embedded in the prefabricated pipe piles, and the prefabricated pipe piles and the frame are cast into one piece with concrete on the slope site;
所述稳定土层上依次铺设砂垫层和原状土层。A sand cushion layer and an original soil layer are laid in sequence on the stabilized soil layer.
优选地,所述左翼钉和所述右翼钉对称布置,且所述V型夹角在60°~120°之间。Preferably, the left wing nail and the right wing nail are arranged symmetrically, and the V-shaped angle is between 60° and 120°.
优选地,所述桩钉嵌固在所述稳定土层中的长度不小于桩长的1/2。Preferably, the length of the pile nail embedded in the stabilized soil layer is not less than 1/2 of the pile length.
优选地,所述预制管桩为方形或圆形的空心钢管桩,且所述预制管桩的桩端为实心锥体。Preferably, the prefabricated pipe pile is a square or round hollow steel pipe pile, and the pile end of the prefabricated pipe pile is a solid cone.
优选地,所述预制管桩的内壁上沿管桩高度方向依次设置多块横隔板。Preferably, a plurality of transverse partitions are sequentially arranged on the inner wall of the prefabricated pipe pile along the height direction of the pipe pile.
优选地,所述预制管桩的桩顶配有桩帽。Preferably, the top of the prefabricated pipe pile is provided with a pile cap.
优选地,所述骨架包括多根与桩身同长的实心杆件,所述实心杆件的顶部连接U型部件,所述U型部件包括中部空心的方形部件和两块相对设置在方形部件顶面的挡板,所述骨架嵌套在所述预制管桩内时,所述方形部件置于所述预制管桩的顶部,两块所述挡板在所述边坡潜在滑动体主滑动方向上依次设置。Preferably, the skeleton comprises a plurality of solid rods having the same length as the pile body, the top of the solid rods being connected to a U-shaped component, the U-shaped component comprising a square component having a hollow middle portion and two baffles arranged oppositely on the top surface of the square component, and when the skeleton is nested in the prefabricated pipe pile, the square component is placed on the top of the prefabricated pipe pile, and the two baffles are arranged sequentially in the main sliding direction of the potential sliding body of the slope.
优选地,所述方形部件的空心截面与所述预制管桩的空心截面一致,且所述方形部件的最小厚度与所述预制管桩的桩壁厚度一致。Preferably, the hollow cross-section of the square component is consistent with the hollow cross-section of the prefabricated pipe pile, and the minimum thickness of the square component is consistent with the thickness of the pile wall of the prefabricated pipe pile.
优选地,所述方形部件的高度与所述砂垫层的高度相同,所述挡板的高度与所述连梁的高度一致。Preferably, the height of the square component is the same as the height of the sand cushion layer, and the height of the baffle is consistent with the height of the connecting beam.
基于同一发明构思,本发明还提供了一种用于既有边坡滑塌快速处治的边坡加固施工方法,其包括下列步骤:Based on the same inventive concept, the present invention also provides a slope reinforcement construction method for rapid treatment of existing slope landslides, which comprises the following steps:
(1)根据《岩土工程勘察规范》要求,探明边坡地质、水文地质以及地层分布情况,并分析边坡潜在滑动体可能范围和大小以及主滑动方向;(1) According to the requirements of the Geotechnical Engineering Investigation Code, the geology, hydrogeology and stratum distribution of the slope shall be investigated, and the possible range and size of the potential sliding body of the slope and the main sliding direction shall be analyzed;
(2)按照《建筑边坡工程技术规范》对边坡抗滑桩设计规定,结合桩钉预制管桩尺寸以及施工要求,拟定桩钉间距,然后,基于规范推荐的边坡稳定性评价方法以及边坡稳定所需满足的安全系数大小,确定桩钉在坡脚处的具体位置,并计算桩钉嵌入边坡潜在滑动体以下稳定土层中的长度;(2) According to the design requirements of slope anti-slide piles in the Technical Code for Slope Engineering, the pile spacing is determined in combination with the size of the prefabricated pipe piles and the construction requirements. Then, based on the slope stability evaluation method recommended by the code and the safety factor required for slope stability, the specific position of the piles at the slope foot is determined, and the length of the piles embedded in the stable soil layer below the potential sliding body of the slope is calculated;
(3)从边坡潜在滑动体两侧周边稳定土体开始逐渐向潜在滑动体中部来开展权利要求1 -9中任一项所述桩钉组合结构施作,采取一个一个桩钉组合结构逐步施工方式,并按照局部开挖→管桩定位→锤击打入管桩→放入管桩内嵌套骨架→施作砂垫层和边坡排水管→浇筑混凝土管桩和连梁→回填原状土的顺序布置各桩钉,在此过程中,将连梁间断处留置在桩钉的方形部件内,并预留搭接钢筋,然后继续下个桩钉施工,直到联排的桩钉组合结构施作完成;(3) The pile-nail combination structure described in any one of claims 1 to 9 is constructed starting from the stable soil around the potential sliding body on both sides of the slope and gradually moving toward the middle of the potential sliding body. The pile-nail combination structure is constructed one by one in a step-by-step manner, and the piles are arranged in the order of local excavation → positioning of pipe piles → hammering into pipe piles → placing nested skeletons in pipe piles → constructing sand cushion layers and slope drainage pipes → pouring concrete pipe piles and connecting beams → backfilling original soil. During this process, the discontinuity of the connecting beam is left in the square part of the pile, and overlapping steel bars are reserved. Then, the next pile is constructed until the construction of the row of pile-nail combination structures is completed;
(4)在边坡以及桩钉上设置位移监测点,持续观察加固后边坡位移变化,并判别其稳定状况以及评价桩钉组合结构加固的有效性与可靠性。(4) Displacement monitoring points are set up on the slope and piles to continuously observe the displacement changes of the slope after reinforcement, determine its stability, and evaluate the effectiveness and reliability of the pile-nail composite structure reinforcement.
本发明的结构特点在于:The structural features of the present invention are:
(1)本发明桩钉式加固结构采用“Y”型布置,并由主钉、辅钉、左翼钉和右翼钉组成,各桩钉之间利用钢筋混凝土连梁连接,使之形成整体,主钉与左翼钉和右翼钉之间形成“V”型,如此可通过发挥其协同与顶推作用在较大范围内对边坡潜在滑动体形成加固,并实现潜在滑动体分区治理,同时主钉和辅钉形成双排桩,极大程度增大了桩钉的抗滑作用以及稳定性;(1) The pile-type reinforcement structure of the present invention adopts a "Y"-shaped arrangement and is composed of a main nail, an auxiliary nail, a left wing nail and a right wing nail. The piles are connected by a reinforced concrete connecting beam to form a whole. The main nail and the left wing nail and the right wing nail form a "V" shape. In this way, the potential sliding body of the slope can be reinforced in a larger range by exerting their synergistic and jacking effects, and the potential sliding body can be controlled in different areas. At the same time, the main nails and the auxiliary nails form double rows of piles, which greatly increases the anti-slip effect and stability of the piles;
(2)本发明“Y”型桩钉式加固结构布置在边坡潜在滑动体下部且靠近坡脚处的位置,可发挥“Y”型桩钉式结构的最佳加固作用;(2) The Y-shaped pile-type reinforcement structure of the present invention is arranged at the lower part of the potential sliding body of the slope and close to the slope foot, which can play the best reinforcement role of the Y-shaped pile-type structure;
(3)本发明“Y”型桩钉式加固结构中主钉和辅钉连线平行于潜在滑动体主滑动方向,左、右翼钉对称布置,两者与主钉形成的“V”型夹角在60°~120°之间,可发挥“Y”型桩钉式加固结构对潜在滑动体的最大阻挡作用;(3) In the Y-shaped pile-nail reinforcement structure of the present invention, the connecting line of the main nail and the auxiliary nail is parallel to the main sliding direction of the potential sliding body, and the left and right wing nails are symmetrically arranged, and the "V" angle formed by the two and the main nail is between 60° and 120°, which can maximize the blocking effect of the "Y"-shaped pile-nail reinforcement structure on the potential sliding body;
(4)本发明桩钉嵌固在潜在滑动体下部的稳定土层中,嵌固长度不小于桩长的1/2,充分发挥了桩钉对潜在滑动体的阻滑作用;(4) The pile nails of the present invention are embedded in the stable soil layer below the potential sliding body, and the embedding length is not less than 1/2 of the pile length, so that the pile nails can fully exert their anti-sliding effect on the potential sliding body;
(5)本发明桩钉在自身阻滑作用以及“Y”型布局协同效应下,桩钉尺寸无需过大,且可被设计成小型或微型桩,以便于现场机械化施工;(5) Due to the anti-slip effect of the pile nails themselves and the synergistic effect of the "Y"-shaped layout, the pile nail size does not need to be too large, and can be designed as a small or micro pile to facilitate on-site mechanized construction;
(6)本发明桩钉包括预制管桩和嵌套在预制管桩内的骨架,如此可减少现场施工对人工的需求,并为快速化和安全化施工提供了便利和保障;(6) The pile nail of the present invention comprises a prefabricated pipe pile and a frame embedded in the prefabricated pipe pile, which can reduce the demand for manpower in on-site construction and provide convenience and guarantee for rapid and safe construction;
(7)本发明桩钉中预制管桩为方形或圆形空心钢管桩,桩端为实心椎体,便于桩钉锤击打入时桩端带动桩身嵌入土层,并深入到稳定地层当中;(7) The prefabricated pipe pile in the pile nail of the present invention is a square or round hollow steel pipe pile, and the pile end is a solid cone, so that when the pile nail is hammered in, the pile end drives the pile body to embed into the soil layer and penetrate into the stable stratum;
(8)本发明桩钉中预制管桩桩壁厚度满足桩身锤击打入施工所需的强度要求,管桩内部设置横隔板,避免了管桩打入时桩身出现弯曲而发生破坏;(8) The wall thickness of the prefabricated pipe pile in the pile nail of the present invention meets the strength requirement for the pile body to be hammered into the construction, and a transverse partition is arranged inside the pipe pile to prevent the pile body from bending and being damaged when the pipe pile is driven into the pile.
(9)本发明桩钉中预制管桩通过锤击打入土体,锤击施工时,预制管桩的桩顶配有桩帽,桩帽能避免锤击直接作用于桩钉而引起其强度损伤,并将重锤作用均匀地分散到桩身与桩端以防止管桩打歪;(9) The prefabricated pipe piles in the pile nails of the present invention are driven into the soil by hammering. During the hammering construction, the pile tops of the prefabricated pipe piles are equipped with pile caps, which can prevent the hammer from directly acting on the pile nails and causing damage to their strength, and evenly distribute the heavy hammer effect to the pile body and the pile end to prevent the pipe piles from being driven crooked.
(10)本发明桩钉中预制管桩内嵌套骨架,骨架中的实心杆件与后续浇筑的混凝土形成共同作用,使得预制管桩与连梁构成整体,进而发挥出“Y”型桩钉加固结构的协同效应;(10) In the pile nail of the present invention, a framework is embedded in the prefabricated pipe pile, and the solid rods in the framework work together with the subsequently poured concrete, so that the prefabricated pipe pile and the connecting beam form a whole, thereby exerting the synergistic effect of the "Y"-shaped pile nail reinforcement structure;
(11)本发明预制管桩内嵌套骨架中,方形部件的中部空心与预制管桩内部空心形状上一致,厚度(方形管桩)或最薄厚度(圆形管桩)与管桩厚度一致,高度与后期施作的排水砂垫层高度相同,方便混凝土浇筑后预制管桩与桩顶的连梁形成一体,且桩钉间排水砂垫层的施工不会与管桩与桩顶连梁混凝土浇筑形成冲突;(11) In the nested skeleton of the prefabricated pipe pile of the present invention, the middle hollow of the square component is consistent with the hollow shape inside the prefabricated pipe pile, the thickness (square pipe pile) or the thinnest thickness (round pipe pile) is consistent with the thickness of the pipe pile, and the height is the same as the height of the drainage sand cushion layer applied later, which facilitates the integration of the prefabricated pipe pile and the connecting beam at the top of the pile after concrete pouring, and the construction of the drainage sand cushion layer between the pile nails will not conflict with the concrete pouring of the pipe pile and the connecting beam at the top of the pile;
(12)本发明的骨架中配置的前后挡板的高度与连梁高度一致,一方面,挡板将预制管桩与连梁在其节点处连成整体,另一方面,挡板也可当作连梁浇筑时的模板使用;(12) The height of the front and rear baffles configured in the frame of the present invention is consistent with the height of the connecting beam. On the one hand, the baffles connect the prefabricated pipe piles and the connecting beam at their nodes into a whole. On the other hand, the baffles can also be used as a template when pouring the connecting beam.
(13)本发明桩钉施工工序的特点是:在桩钉布置处局部开挖至管桩桩顶设计位置→管桩定位并在桩顶处套上桩帽→锤击打入管桩至设计深度→取下桩帽并放入管桩内嵌套骨架→在桩钉之间施作排水砂垫层→搭建连梁施工模板并绑扎连梁钢筋→浇筑混凝土使管桩与连梁形成一体→拆除连梁施工模板并回填原状土至初始标高。依据此施工工序完成施作,可快速实现桩钉对边坡潜在滑体的抗滑作用,并在“Y”型桩钉式加固结构协同效应下达到整体加固边坡的目的。(13) The characteristics of the pile nail construction process of the present invention are: local excavation at the pile nail arrangement location to the designed position of the top of the pipe pile → positioning the pipe pile and putting the pile cap on the top of the pile → hammering the pipe pile to the designed depth → removing the pile cap and inserting the nesting frame into the pipe pile → applying a drainage sand cushion layer between the pile nails → building a connecting beam construction template and tying the connecting beam steel bars → pouring concrete to make the pipe pile and the connecting beam form a whole → removing the connecting beam construction template and backfilling the original soil to the initial elevation. According to this construction process, the pile nail can quickly realize the anti-sliding effect of the potential sliding body of the slope, and achieve the purpose of overall reinforcement of the slope under the synergistic effect of the "Y" type pile nail reinforcement structure.
与现有技术相比,本发明的有益效果是:Compared with the prior art, the present invention has the following beneficial effects:
本发明针对已滑塌或潜在滑塌边坡的快速处治,研发了如上所述的“Y”型桩钉式加固结构,系统提出了桩钉式加固结构“Y”型布局和桩钉施工工序,形成了一套“Y”型桩钉式加固结构“即作即用”和“安全高效”的施工方法,实现了单独小型或微型预制桩钉形成“Y”型整体而发挥其协同效应来对边坡形成最大阻滑作用的目的。Aiming at the rapid treatment of collapsed or potentially collapsed slopes, the present invention has developed the "Y"-shaped pile-nail reinforcement structure as described above, and systematically proposed a "Y"-shaped layout and pile construction process of the pile-nail reinforcement structure, forming a set of "ready-to-use" and "safe and efficient" construction methods for the "Y"-shaped pile-nail reinforcement structure, thereby achieving the purpose of forming a "Y"-shaped whole with individual small or micro prefabricated piles to exert their synergistic effect to form the maximum anti-slip effect on the slope.
本发明方法采用小型或微型预制构件施工,避免了边坡大开大挖,降低了施工成本,减小了对原始边坡造成较大扰动,达到环境友好目的,并在发挥“Y”型桩钉式结构协同效应下可快速、安全、有效地实现边坡加固以及分区治理,非常有利于不稳定边坡的紧急处治。The method of the present invention adopts small or micro prefabricated components for construction, avoids large-scale excavation of the slope, reduces construction costs, reduces major disturbances to the original slope, achieves environmental friendliness, and can quickly, safely and effectively realize slope reinforcement and zoning management by giving full play to the synergistic effect of the "Y"-shaped pile-nail structure, which is very beneficial to the emergency treatment of unstable slopes.
本发明结构及方法易于实施、快速便捷、安全可靠、成本低、效率高、低碳环保、效果良好、适用范围广。The structure and method of the present invention are easy to implement, fast and convenient, safe and reliable, low in cost, high in efficiency, low in carbon and environmentally friendly, with good effects and a wide range of applications.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
图1为本发明边坡加固结构的立体结构图。FIG. 1 is a three-dimensional structural diagram of the slope reinforcement structure of the present invention.
图2为本发明边坡加固结构的平面图。FIG. 2 is a plan view of the slope reinforcement structure of the present invention.
图3为本发明Y型桩钉结构的立体图。FIG. 3 is a perspective view of a Y-shaped pile structure of the present invention.
图4为图1的A-A断面图。FIG. 4 is a cross-sectional view taken along line AA of FIG. 1 .
图5为方形桩钉的部件分解图。FIG. 5 is an exploded view of the square peg.
图6为方形桩钉的C-C剖视图。FIG. 6 is a CC cross-sectional view of a square pile.
图7为圆形桩钉的部件分解图。FIG. 7 is an exploded view of a circular peg.
图8为圆形桩钉的D-D剖视图。FIG. 8 is a DD cross-sectional view of a circular pile.
图9为本发明桩钉的E-E断面图。FIG. 9 is a cross-sectional view taken along line EE of the pile nail of the present invention.
图10为本发明实施例的桩钉施工工序图,其中a为桩钉布置处局部开挖;b为管桩定位及锤击打入;c为管桩内放入骨架;d为施作排水砂垫层(含排水管);e为浇筑混凝土; f为回填原状土。Fig. 10 is a process diagram of pile construction according to an embodiment of the present invention, wherein a is local excavation at the pile arrangement location; b is positioning and hammering of the pipe pile; c is placing a skeleton into the pipe pile; d is applying a drainage sand cushion layer (including a drainage pipe); e is pouring concrete; and f is backfilling the original soil.
图例说明:illustration:
1、斜坡面;1. Slope surface;
2、坡底面;2. Slope bottom;
3、坡顶面;3. Slope top surface;
4、潜在滑动体;4. Potential sliding body;
5、潜在滑动体主滑动方向;5. Main sliding direction of potential sliding body;
6、桩钉组合结构;6. Pile-nail combination structure;
7、主钉;7. Main nail;
8、辅钉;8. Auxiliary nails;
9、左翼钉;9. Left wing nail;
10、右翼钉;10. Right wing nail;
11、连梁;11. Connecting beam;
12、砂垫层;12. Sand cushion layer;
13、原状土层;13. Original soil layer;
14、管桩;14. Pipe piles;
15、桩帽;15. Pile cap;
16、骨架;16. Skeleton;
17、管桩桩身;17. Pipe pile body;
18、管桩桩端;18. Pipe pile end;
19、管桩桩壁;19. Pipe pile wall;
20、横隔板。20. Horizontal partition.
具体实施方式Detailed ways
以下结合具体优选的实施例对本发明作进一步描述,但并不因此而限制本发明的保护范围。The present invention is further described below in conjunction with specific preferred embodiments, but the protection scope of the present invention is not limited thereby.
为了便于描述,各部件的相对位置关系,如:上、下、左、右等的描述均是根据说明书附图的布图方向来进行描述的,并不对本专利的结构起限定作用。For the convenience of description, the relative position relationship of each component, such as up, down, left, right, etc., is described according to the layout direction of the drawings in the specification, and does not limit the structure of this patent.
如图1-图3所示,本发明用于既有边坡滑塌快速处治的边坡加固结构一实施例包括:As shown in FIG. 1 to FIG. 3 , an embodiment of a slope reinforcement structure for rapid treatment of existing slope collapse of the present invention comprises:
在边坡潜在滑动体4下部且靠近坡脚处的位置连续布置至少一排桩钉组合结构6;At least one row of pile assembly structures 6 is continuously arranged at a position below the potential sliding body 4 of the slope and close to the slope foot;
所述桩钉组合结构6包括呈Y型嵌固在边坡稳定土层内的主钉7、辅钉8、左翼钉9和右翼钉10,所述主钉7位于所述辅钉8、左翼钉9和所述右翼钉10之间,且所述主钉7与所述辅钉8、所述左翼钉9和所述右翼钉10之间分别通过钢筋混凝土连梁11连接。所述左翼钉9 和所述右翼钉10在所述主钉7两侧对称布置,且连接所述主钉7和所述左翼钉9的连梁11 与连接所述主钉7和所述右翼钉10的连梁11之间形成60°~120°的V型夹角,所述V型夹角面向所述边坡潜在滑动体4设置。所述主钉7和所述辅钉8之间的连梁11平行于所述边坡潜在滑动体主滑动方向5设置,使各桩钉组合结构6的主钉7和辅钉8整体形成双排桩结构;The pile-nail combination structure 6 includes a main nail 7, an auxiliary nail 8, a left wing nail 9 and a right wing nail 10 embedded in the slope stabilizing soil layer in a Y shape. The main nail 7 is located between the auxiliary nail 8, the left wing nail 9 and the right wing nail 10, and the main nail 7 is connected to the auxiliary nail 8, the left wing nail 9 and the right wing nail 10 through a reinforced concrete connecting beam 11. The left wing nail 9 and the right wing nail 10 are symmetrically arranged on both sides of the main nail 7, and a V-shaped angle of 60° to 120° is formed between the connecting beam 11 connecting the main nail 7 and the left wing nail 9 and the connecting beam 11 connecting the main nail 7 and the right wing nail 10, and the V-shaped angle is arranged facing the potential sliding body 4 of the slope. The connecting beam 11 between the main nail 7 and the auxiliary nail 8 is arranged parallel to the main sliding direction 5 of the potential sliding body of the slope, so that the main nails 7 and the auxiliary nails 8 of each pile-nail combination structure 6 form a double-row pile structure as a whole;
所述稳定土层上依次铺设排水用砂垫层12和原状土层13。A drainage sand cushion layer 12 and an original soil layer 13 are laid in sequence on the stabilized soil layer.
为充分发挥桩钉对边坡潜在滑动体4的阻滑作用,所述桩钉嵌固在所述稳定土层中的长度不小于桩长的1/2。In order to give full play to the anti-slip effect of the pile nails on the potential sliding body 4 of the slope, the length of the pile nails embedded in the stable soil layer is not less than 1/2 of the pile length.
如图4-图9所示,所述桩钉包括预制管桩14和嵌套在预制管桩14内的骨架16,且所述预制管桩14和骨架16在边坡现场用混凝土浇筑成一体。As shown in FIG. 4 to FIG. 9 , the pile nail includes a prefabricated pipe pile 14 and a skeleton 16 embedded in the prefabricated pipe pile 14 , and the prefabricated pipe pile 14 and the skeleton 16 are cast into one piece with concrete on the slope site.
所述预制管桩14为方形或圆形的空心钢管桩,且所述预制管桩14的管桩桩端18为实心锥体。所述预制管桩14的内壁上沿管桩高度方向依次设置多块横隔板20。所述预制管桩14 的桩顶配有桩帽15。The prefabricated pipe pile 14 is a square or round hollow steel pipe pile, and the pile end 18 of the prefabricated pipe pile 14 is a solid cone. A plurality of transverse partitions 20 are sequentially arranged on the inner wall of the prefabricated pipe pile 14 along the height direction of the pipe pile. The pile top of the prefabricated pipe pile 14 is provided with a pile cap 15.
所述骨架16包括多根与桩身(此处桩身为管桩桩身17与方形部件的高度和)同长的实心杆件,所述实心杆件的顶部连接U型部件,所述U型部件包括中部空心的方形部件和两块相对设置在方形部件顶面的挡板。所述骨架16嵌套在所述预制管桩14内时,所述方形部件置于所述预制管桩14的顶部,两块所述挡板在所述边坡潜在滑动体主滑动方向5上依次设置。The skeleton 16 includes a plurality of solid rods of the same length as the pile body (here, the pile body is the height of the pile body 17 and the square component), and the top of the solid rod is connected to a U-shaped component, and the U-shaped component includes a square component with a hollow center and two baffles arranged on the top surface of the square component. When the skeleton 16 is nested in the prefabricated pipe pile 14, the square component is placed on the top of the prefabricated pipe pile 14, and the two baffles are arranged in sequence in the main sliding direction 5 of the potential sliding body of the slope.
为保持桩钉全长度强度一致,所述方形部件的空心截面与所述预制管桩14的空心截面一致,且所述方形部件的最小厚度与所述预制管桩14的管桩桩壁19的厚度一致。In order to maintain the uniform strength of the pile nail over its entire length, the hollow section of the square component is consistent with the hollow section of the prefabricated pipe pile 14 , and the minimum thickness of the square component is consistent with the thickness of the pipe pile wall 19 of the prefabricated pipe pile 14 .
为方便砂垫层12及排水管的设置,所述方形部件的高度与所述砂垫层12的高度相同。To facilitate the installation of the sand cushion layer 12 and the drainage pipe, the height of the square component is the same as the height of the sand cushion layer 12 .
所述挡板的高度与所述连梁的高度一致。如此,可通过挡板将预制管桩14与连梁11在其节点处连成整体,还可将挡板当作连梁11浇筑时的模板使用。The height of the baffle is consistent with the height of the connecting beam. In this way, the prefabricated pipe pile 14 and the connecting beam 11 can be connected as a whole at their nodes through the baffle, and the baffle can also be used as a template when the connecting beam 11 is poured.
为验证本发明用于既有边坡滑塌快速处治的边坡加固结构的加固效果,本申请发明人做了下述试验:In order to verify the reinforcement effect of the slope reinforcement structure of the present invention for rapid treatment of existing slope collapse, the inventors of the present application conducted the following experiments:
选择一坡高约40米与坡角约35°的残积土边坡,且在人为扰动破坏以及长时间降雨作用下此边坡已出现了浅层滑塌。为了防止边坡失稳范围进一步扩大,并保障边坡滑动破坏范围内人民生命财产安全以及交通正常运行,拟对边坡进行加固处治。边坡加固处治措施应该确保有效,且能保证加固处治措施的施工扰动在合理范围内而不会引起边坡再次发生失稳。为此,本发明用于既有边坡滑塌快速处治的边坡加固结构被采用。桩钉采用小型预制管桩锤击打入施工,无需对边坡进行大开大挖。同时,桩钉组合结构6从边坡潜在滑动体4两侧稳定土体向中部不稳定土体逼近施工,两侧已完工的桩钉可对边坡潜在滑体形成约束,为中部不稳定土体处施工提供安全保障。此外,预制件施工可快速对边坡形成有效阻滑作用,且利用桩钉组合结构6的协同与成排效应来构建有利的加固体系,使得加固处治措施的施工扰动控制在合理范围内。A residual soil slope with a height of about 40 meters and a slope angle of about 35° is selected, and shallow landslides have occurred in this slope due to human disturbance and long-term rainfall. In order to prevent the further expansion of the instability range of the slope and to ensure the safety of people's lives and property and the normal operation of traffic within the range of slope sliding damage, it is planned to reinforce the slope. The slope reinforcement treatment measures should ensure effectiveness and ensure that the construction disturbance of the reinforcement treatment measures is within a reasonable range and will not cause the slope to become unstable again. For this reason, the slope reinforcement structure of the present invention for rapid treatment of existing slope landslides is adopted. The piles are hammered into the construction using small prefabricated pipe piles, and there is no need to dig the slope. At the same time, the pile-nail combination structure 6 approaches the unstable soil body in the middle from the stable soil body on both sides of the potential sliding body 4 of the slope. The completed piles on both sides can constrain the potential sliding body of the slope, providing safety for the construction of the unstable soil body in the middle. In addition, the construction of prefabricated parts can quickly form an effective anti-slip effect on the slope, and utilize the synergy and row effect of the pile-nail combination structure 6 to construct a favorable reinforcement system, so that the construction disturbance of the reinforcement treatment measures is controlled within a reasonable range.
具体操作如下:The specific operations are as follows:
(1)根据《岩土工程勘察规范》(GB 50021-2001)要求,探明边坡地质、水文地质以及地层分布情况,并分析边坡潜在滑体可能范围和大小以及主滑动方向;(1) According to the requirements of the Code for Geotechnical Engineering Investigation (GB 50021-2001), the geology, hydrogeology and stratum distribution of the slope shall be investigated, and the possible range and size of the potential sliding body of the slope and the main sliding direction shall be analyzed;
(2)按照《建筑边坡工程技术规范》(GB 50330-2013)对边坡抗滑桩设计规定,结合桩钉预制管桩尺寸以及施工要求,拟定桩钉间距,然后,基于规范推荐的边坡稳定性评价方法以及边坡稳定所需满足的安全系数大小,确定“Y”型桩钉式加固结构(桩钉组合结构6)在坡脚处的具体位置,并计算桩钉嵌入潜在滑动体4以下稳定土层中的所需长度;(2) According to the design requirements of slope anti-slide piles in the Technical Code for Slope Engineering (GB 50330-2013), the pile spacing is determined in combination with the size of the prefabricated piles and the construction requirements. Then, based on the slope stability evaluation method recommended by the code and the safety factor required for slope stability, the specific position of the "Y"-shaped pile reinforcement structure (pile combination structure 6) at the slope foot is determined, and the required length of the pile embedded in the stable soil layer below the potential sliding body 4 is calculated;
(3)从边坡潜在滑动体两侧周边稳定土体开始逐渐向潜在滑动体中部来开展“Y”型桩钉式加固结构施作,采取逐步施工方式(即完成一个“Y”型桩钉式加固结构后再接续下一个“Y”型桩钉式加固结构),并按照桩钉施工工序来布置桩钉,即如图10所示,局部开挖→管桩定位→锤击打入管桩→放入管桩内嵌套骨架→施作砂垫层和边坡排水管→浇筑混凝土管桩和连梁→回填原状土;(3) The Y-shaped pile-nail reinforcement structure is constructed starting from the stable soil around the potential sliding body on both sides of the slope and gradually moving toward the middle of the potential sliding body. A step-by-step construction method is adopted (i.e., one Y-shaped pile-nail reinforcement structure is completed before the next Y-shaped pile-nail reinforcement structure is constructed). The piles are arranged according to the pile-nail construction process, as shown in Figure 10: local excavation → pipe pile positioning → hammering into the pipe pile → inserting the nested skeleton into the pipe pile → constructing the sand cushion layer and slope drainage pipe → pouring concrete pipe piles and connecting beams → backfilling the original soil;
(4)“Y”型桩钉式加固结构中连梁间断处(即连梁混凝土非连续浇筑而形成的施工接头) 留置在桩钉内,并预留搭接钢筋,然后继续下个桩钉施工,直到联排“Y”型桩钉式加固结构施作完成;(4) The discontinuity of the coupling beam in the “Y” type pile-nail reinforcement structure (i.e. the construction joint formed by the non-continuous pouring of the coupling beam concrete) is left in the pile, and the lap steel bars are reserved, and then the next pile construction is continued until the row of “Y” type pile-nail reinforcement structures is completed;
(5)联排“Y”型桩钉式加固结构完成施作后,在边坡以及桩钉上设置位移监测点,持续观察加固后边坡位移变化,并判别其稳定状况以及评价“Y”型桩钉式结构加固的有效性与可靠性。(5) After the construction of the row "Y"-shaped pile-type reinforcement structure is completed, displacement monitoring points are set up on the slope and the piles to continuously observe the displacement changes of the slope after reinforcement, determine its stability, and evaluate the effectiveness and reliability of the "Y"-shaped pile-type structure reinforcement.
以上所述,仅为本发明的具体实施方案,但本发明的保护范围不限于此,任何熟悉本领域的技术人员,在不脱离本发明技术方案范围的情况下,都可利用上述揭示的技术内容对本发明技术方案做出许多可能的变动和修饰,或修改为等同变化的等效实施例。因此,凡是未脱离本发明技术方案的内容,依据本发明技术实质对以上实施例所做的任何简单修改、等同变化及修饰,均应落在本发明技术方案保护的范围内。The above is only a specific implementation scheme of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the art can make many possible changes and modifications to the technical scheme of the present invention by using the technical content disclosed above without departing from the scope of the technical scheme of the present invention, or modify it into an equivalent embodiment of equivalent changes. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical scheme of the present invention should fall within the protection scope of the technical scheme of the present invention.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211277421.XA CN115627781B (en) | 2022-10-19 | 2022-10-19 | A slope reinforcement structure and construction method for rapid treatment of existing slope collapse |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211277421.XA CN115627781B (en) | 2022-10-19 | 2022-10-19 | A slope reinforcement structure and construction method for rapid treatment of existing slope collapse |
Publications (2)
Publication Number | Publication Date |
---|---|
CN115627781A CN115627781A (en) | 2023-01-20 |
CN115627781B true CN115627781B (en) | 2024-06-04 |
Family
ID=84905686
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211277421.XA Active CN115627781B (en) | 2022-10-19 | 2022-10-19 | A slope reinforcement structure and construction method for rapid treatment of existing slope collapse |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115627781B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116290021A (en) * | 2023-03-27 | 2023-06-23 | 中建安装集团南方建设有限公司 | Novel side slope network type anti-slip row pile |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100543799B1 (en) * | 2005-09-26 | 2006-01-23 | 주식회사 장원기술단 | Road slope reinforcement retaining wall structure |
KR100766859B1 (en) * | 2006-09-19 | 2007-10-15 | 김원철 | Method of constructing cast-in-placement pile using factory-installed pile-pile plant that can separate and inject concrete |
CN110670598A (en) * | 2019-07-24 | 2020-01-10 | 青岛理工大学 | A cold joint treatment structure and method for occlusal pile construction |
CN113463666A (en) * | 2021-07-12 | 2021-10-01 | 中国电建集团成都勘测设计研究院有限公司 | Row pile structure for soil cutting slope and construction method thereof |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103233473B (en) * | 2013-04-18 | 2016-05-25 | 河南博特工程防护有限公司 | Many ribs of high polymer stake grouting method |
-
2022
- 2022-10-19 CN CN202211277421.XA patent/CN115627781B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100543799B1 (en) * | 2005-09-26 | 2006-01-23 | 주식회사 장원기술단 | Road slope reinforcement retaining wall structure |
KR100766859B1 (en) * | 2006-09-19 | 2007-10-15 | 김원철 | Method of constructing cast-in-placement pile using factory-installed pile-pile plant that can separate and inject concrete |
CN110670598A (en) * | 2019-07-24 | 2020-01-10 | 青岛理工大学 | A cold joint treatment structure and method for occlusal pile construction |
CN113463666A (en) * | 2021-07-12 | 2021-10-01 | 中国电建集团成都勘测设计研究院有限公司 | Row pile structure for soil cutting slope and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN115627781A (en) | 2023-01-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103452147B (en) | Self-balancing anchor counterweight broken pile forced-landing tilt correcting method | |
CN110017144B (en) | Loess tunnel three-step construction method considering substrate reinforcement treatment | |
CN104264688A (en) | Manual hole digging non-uniform pile support construction technology | |
CN103306289A (en) | Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof | |
CN111851597B (en) | Penetration protection structure of pipe jacking close-distance downward-penetrating pipe gallery and construction method | |
CN211006756U (en) | Interface structure of open cut station and large-span duplex arch buried tunnel | |
CN206034454U (en) | Supporting construction | |
CN115627781B (en) | A slope reinforcement structure and construction method for rapid treatment of existing slope collapse | |
CN101153494A (en) | Underground Beam-Pile Frame Structure for Slope Reinforcement | |
CN204000925U (en) | Prefabricated diaphragm wall | |
CN113417300B (en) | Slope support system and construction method thereof | |
CN108035360A (en) | A kind of method for pattern foundation pit supporting structure | |
CN104005414A (en) | Method for constructing large-diameter reinforced concrete cast-in-place pile supporting stand column | |
CN212294705U (en) | Inflation dirt road moat slope reinforced structure | |
CN211174126U (en) | Open cut tunnel structure | |
CN211285658U (en) | Structure capable of carrying out deep water area hollowing repair in rapid stream state | |
CN105696701B (en) | A kind of suitable slope shear wall building development platform and its construction method | |
CN210459232U (en) | Soil nailing wall supporting structure for pure sand area | |
CN209211459U (en) | Skirt piles are gone along with sb. to guard him in a kind of buried subway station PBA | |
CN210104765U (en) | High and large retaining structure of soft geological side slope | |
CN203270588U (en) | Mini-pile antiskid structure | |
CN111074916A (en) | Retaining structure of anti-slide pile and structural pile and construction method | |
CN203373753U (en) | Pile anchor retaining wall concrete anchor cable top beam structure of foundation ditches | |
CN215801664U (en) | Rigid rib wall type pile wall foundation pit supporting structure | |
CN215441915U (en) | Foundation pit supporting structure and foundation pit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |