CN115573582A - A method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses - Google Patents

A method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses Download PDF

Info

Publication number
CN115573582A
CN115573582A CN202211369630.7A CN202211369630A CN115573582A CN 115573582 A CN115573582 A CN 115573582A CN 202211369630 A CN202211369630 A CN 202211369630A CN 115573582 A CN115573582 A CN 115573582A
Authority
CN
China
Prior art keywords
steel
column
steel column
elevation
truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211369630.7A
Other languages
Chinese (zh)
Inventor
朱文峰
武文龙
申夏磊
王岩松
陈辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Baoye Steel Structure Co ltd
Shanghai Baoye Group Corp Ltd
Original Assignee
Zhengzhou Baoye Steel Structure Co ltd
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Baoye Steel Structure Co ltd, Shanghai Baoye Group Corp Ltd filed Critical Zhengzhou Baoye Steel Structure Co ltd
Priority to CN202211369630.7A priority Critical patent/CN115573582A/en
Publication of CN115573582A publication Critical patent/CN115573582A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses an unequal-height steel column elevation adjusting method for horizontal sliding construction of a steel truss, which comprises the following steps of: step 1: selecting a construction standard, and designing and installing other structures by taking a standard structure as a reference; step 2: install a plurality of adjusting shim plates 8 additional between the top of steel column and track 5 so that track 5 is the level setting, step 3: after the truss slides in place, measures are taken to remove the sliding shoes 6 at the bottom of the truss support 1, remove the rails 5, remove the adjusting shim plate 8, install the cast steel support 3, unload the truss 13 and finally remove the sliding steel beam; the invention has the advantages of ingenious design, simple operation, safety and stability, and wide application prospect in the sliding construction of the large-span steel truss.

Description

一种用于钢桁架水平滑移施工的不等高钢柱标高调整方法A method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses

技术领域technical field

本发明涉及钢桁架安装技术领域,具体涉及一种用于钢桁架水平滑移施工的不等高钢柱标高调整方法。The invention relates to the technical field of steel truss installation, in particular to a method for adjusting the elevation of unequal-height steel columns used in the horizontal sliding construction of steel trusses.

背景技术Background technique

随着建筑施工工艺的发展,钢结构因其具有自重轻、易安拆、精度高、周期短、残值高、抗震性能好、环境污染少等特点,日渐受市场青睐,被广泛地应用于各建筑结构领域,且随着很多机场、车站、体育馆等建筑的不断兴起,钢桁架结构得以迅速发展。该类型结构通常情况下跨度较大,能够满足建筑功能对空间的要求,钢桁架的滑移施工时,通常情况下,利用原有结构柱进行钢桁架的滑移施工,钢柱柱顶标高普遍是一致的,但是当遇到钢柱柱顶标高(也可以说是桁架支座底部标高)不一致时,这就给钢桁架水平直线滑移带来了很大的难题,甚至是无法采用滑移施工方案,使钢桁架水平直线移动,即使钢桁架移动的轨道在同一平面上,现有的方法是预埋临时支撑杆,支撑杆的顶部在同一平面,则轨道在同一平面,或者是采用起重设备支撑轨道,使轨道在同一平面,现有方法的缺点是:采用临时支撑杆支撑轨道,需要支撑架的安装和拆卸,且需要混凝土结构对临时支撑杆底部的加固,增加费用的支出,且拆除临时支撑杆时,增加拆装的难度,采用起重设备对轨道进行临时支撑时,收场地的限制,有些施工的场地不够大,起重设备无法进行场地进行长时间的支撑轨道,且设备一直在现场施工,费用较高,且对起重设备的起重高度和起重重量要求较高,例如申请号为201820335853 .4的中国专利公开了大跨度不等高支座钢桁架结构吊装滑移施工系统,包括起重设备,滑移结构、滑移支座和顶推系统,所述滑移结构包括轨道和滑靴,所述轨道上设置有滑槽,所述顶推系统包括滑移顶推器和液压输出系统,该专利起重设备支撑轨道,使轨道在同一平面上,以保证滑移支座沿直线移动,该专利的缺点是使用起重设备保证轨道在同一平面上,但是该专利的施工场地如果较小,仍然会是起重设备的使用受到限制,起重设备无法进行场地进行长时间的支撑轨道,且设备一直在现场施工,费用较高。With the development of building construction technology, steel structures are increasingly favored by the market and widely used in In various building structure fields, and with the continuous rise of many airports, stations, stadiums and other buildings, steel truss structures have developed rapidly. This type of structure usually has a large span, which can meet the space requirements of the building function. During the sliding construction of the steel truss, usually, the original structural column is used for the sliding construction of the steel truss, and the elevation of the top of the steel column is generally It is consistent, but when the elevation of the top of the steel column (it can also be said to be the elevation of the bottom of the truss support) is inconsistent, this brings great difficulties to the horizontal and linear sliding of the steel truss, and it is even impossible to use the sliding The construction plan is to make the steel truss move horizontally and straightly, even if the track of the steel truss is on the same plane, the existing method is to pre-bury the temporary support bar, and the top of the support bar is on the same plane, then the track is on the same plane, or adopt the lifting method The heavy equipment supports the track so that the track is on the same plane. The disadvantages of the existing method are: the use of temporary support rods to support the track requires the installation and disassembly of the support frame, and the reinforcement of the bottom of the temporary support rod by the concrete structure, which increases the expenditure. And when the temporary support rods are removed, the difficulty of disassembly and assembly will be increased. When the lifting equipment is used to temporarily support the track, the limitation of the site is limited. Some construction sites are not large enough, and the lifting equipment cannot support the track for a long time on the site, and The equipment has been being constructed on site, and the cost is high, and the lifting height and lifting weight of the lifting equipment are high. For example, the Chinese patent application number 201820335853 . The sliding construction system includes lifting equipment, a sliding structure, a sliding support and a pushing system. The sliding structure includes a track and a sliding shoe. Ejector and hydraulic output system, the patented lifting equipment supports the rails so that the rails are on the same plane to ensure that the sliding support moves along a straight line. The disadvantage of this patent is that the lifting equipment is used to ensure that the rails are on the same plane. But if the construction site of this patent is less, still can be that the use of hoisting equipment is restricted, and hoisting equipment can't carry out the long-time supporting track of site, and equipment is always on-site construction, and expense is higher.

因此,提供一种利用原结构的钢柱且通过对原结构的钢柱高度进行调整而是轨道处于水平面的用于钢桁架水平滑移施工的不等高钢柱标高调整方法,已是一个值得研究的问题。Therefore, it is worth studying to provide a method for adjusting the height of steel columns with different heights for the horizontal sliding construction of steel trusses by adjusting the height of the steel columns of the original structure so that the rails are in the horizontal plane. question.

发明内容Contents of the invention

本发明的目的是提供一种利用原结构的钢柱且通过对原结构的钢柱高度进行调整而是轨道处于水平面的用于钢桁架水平滑移施工的不等高钢柱标高调整方法。The object of the present invention is to provide a steel column elevation adjustment method for steel truss horizontal sliding construction using the steel column of the original structure and adjusting the height of the steel column of the original structure so that the track is in the horizontal plane.

本发明的目的是这样实现的:The purpose of the present invention is achieved like this:

一种用于钢桁架水平滑移施工的不等高钢柱标高调整方法,包括以下步骤:步骤1:选取施工的基准,以基准结构为参照,设计并安装其他的结构;步骤2:在钢柱的顶部和轨道5之间加装若干调节垫板8以使轨道5呈水平设置,具体操作如下:钢柱2上部的桁架支座1底部设置滑靴6,滑靴6下设置滑移的轨道5,在轨道5底部设置钢柱间的滑移钢梁4,钢柱2的顶部与轨道5之间的间隙采用多层调节垫板8垫设;步骤3:桁架滑移到位后,采取措施拆除桁架支座1底部的滑靴6,拆除轨道5,拆除调节垫板8,安装铸钢支座3,桁架13卸载,最后拆除滑移钢梁4。A method for adjusting the elevation of unequal-height steel columns for the horizontal sliding construction of steel trusses, comprising the following steps: Step 1: Select a construction datum, and use the datum structure as a reference to design and install other structures; Add some adjusting pads 8 between the top and the track 5 so that the track 5 is set horizontally. The specific operation is as follows: the bottom of the truss support 1 on the upper part of the steel column 2 is provided with a sliding shoe 6, and the sliding track 5 is arranged under the sliding shoe 6. , the sliding steel beam 4 between the steel columns is set at the bottom of the track 5, and the gap between the top of the steel column 2 and the track 5 is set with a multi-layer adjusting backing plate 8; Step 3: After the truss slides in place, take measures to remove it The sliding shoe 6 at the bottom of the truss support 1, remove the track 5, remove the adjustment backing plate 8, install the cast steel support 3, unload the truss 13, and finally remove the sliding steel beam 4.

所述步骤1的具体操作如下:选取柱顶标高最低的第一钢柱2-1为基准,第一钢柱2-1的柱顶标高9-1为基准,与第一钢柱2-1的柱顶标高相差不大的钢柱为第三钢柱2-3,且H3 <h1-h2,H3为第三钢柱2-3与第一钢柱2-1之间的柱顶标高差,h1铸钢支座高度,h2为轨道高度;与第一钢柱2-1柱顶标高相差大的为第二钢柱2-2,H1>h1-h2;H1为与第一钢柱2-1柱顶标高相差较大的第二钢柱2-2的顶段2-2-U高度,h1铸钢支座高度,h2为轨道高度。The specific operation of said step 1 is as follows: select the first steel column 2-1 with the lowest column top elevation as a benchmark, the column top elevation 9-1 of the first steel column 2-1 as a benchmark, and the first steel column 2-1 The steel column with little difference in column top elevation is the third steel column 2-3, and H3<h1-h2, H3 is the column top elevation difference between the third steel column 2-3 and the first steel column 2-1 , h1 is the height of the cast steel support, h2 is the height of the track; the height difference from the top of the first steel column 2-1 is the second steel column 2-2, H1>h1-h2; H1 is the same as the first steel column 2 -1 The height of the top section 2-2-U of the second steel column 2-2 with a large difference in column top elevation, h1 is the height of the cast steel support, and h2 is the height of the track.

当与第一钢柱2-1的柱顶标高相差不大的钢柱为第三钢柱2-3,且H3 <h1-h2时,步骤2的具体操作如下:在第一钢柱2-1上部的第一桁架支座1-1底部设置正常滑靴6-1,滑靴厚度20~30mm也相当于滑移施工时,桁架13整体抬高20~30mm,便于在桁架13滑移完成后安装铸钢支座3;第三钢柱2-3的柱顶标高高于第一钢柱2-1柱顶标高,第三桁架支座1-3也同样会抬高,抬高部分采用加厚的滑靴6-3处理,轨道5底部与第一钢柱2-1柱顶的间隙采用调节垫板8垫设,轨道5底部与第三钢柱2-3柱顶的间隙采用调节垫板8垫设,直至第一钢柱2-1的调节垫板(8)的上表面与第三钢柱2-3的调节垫板8的上表面在同一平面上。When the steel column that is not much different from the column top elevation of the first steel column 2-1 is the third steel column 2-3, and H3<h1-h2, the specific operation of step 2 is as follows: in the first steel column 2- 1. The bottom of the first truss support 1-1 on the upper part is equipped with normal sliding shoes 6-1. The thickness of the sliding shoes is 20~30mm, which is equivalent to the overall elevation of the truss 13 by 20~30mm during the sliding construction, which is convenient for sliding on the truss 13. Install the cast steel support 3 afterwards; the column top elevation of the third steel column 2-3 is higher than the column top elevation of the first steel column 2-1, and the third truss support 1-3 will also be raised, and the raised part adopts Thickened sliding shoe 6-3 treatment, the gap between the bottom of the track 5 and the top of the first steel column 2-1 is set by adjusting the backing plate 8, and the gap between the bottom of the track 5 and the top of the third steel column 2-3 is adjusted The backing plate 8 is laid until the upper surface of the adjusting backing plate (8) of the first steel column 2-1 and the upper surface of the adjusting backing plate 8 of the third steel column 2-3 are on the same plane.

当与第一钢柱2-1的柱顶标高相差不大的钢柱为第三钢柱2-3,且H3 <h1-h2时,步骤3的具体操作如下:桁架13滑移到位后,采取措施拆除第三铸钢支座1-3底部的加厚滑靴6-3和第一铸钢支座1-1底部的正常滑靴6-1,拆除轨道5,拆除第三钢柱2-3顶部调节垫板8和第一钢柱2-1顶部调节垫板8,安装铸钢支座3,桁架13卸载,最后拆除滑移钢梁4。When the steel column with the same elevation as the first steel column 2-1 is the third steel column 2-3, and H3<h1-h2, the specific operation of step 3 is as follows: After the truss 13 slides into place, Take measures to remove the thickened sliding shoe 6-3 at the bottom of the third cast steel support 1-3 and the normal sliding shoe 6-1 at the bottom of the first cast steel support 1-1, remove the track 5, and remove the third steel column 2 -3 top adjustment backing plate 8 and the first steel column 2-1 top adjustment backing plate 8, install the cast steel support 3, unload the truss 13, and finally remove the sliding steel beam 4.

当与第一钢柱2-1柱顶标高相差大的为第二钢柱2-2,H1>h1-h2时,步骤2的具体操作如下:将第二钢柱2-2临时分成两段,滑移施工时只安装底段2-2-D,上段2-2-U待滑移完成后,轨道5拆除后再安装;分段位置在轨道5底部的第二标高9-2;第二桁架支座1-2底部与轨道5之间的高度通过加高滑靴6-2实现,且加高滑靴6-2与桁架支座1-1增设水平连杆7。When the height difference from the top of the first steel column 2-1 is the second steel column 2-2, H1>h1-h2, the specific operation of step 2 is as follows: temporarily divide the second steel column 2-2 into two sections , only the bottom section 2-2-D is installed during the sliding construction, and the upper section 2-2-U is installed after the sliding is completed, and the track 5 is dismantled; The height between the bottom of the two truss supports 1-2 and the track 5 is realized by increasing the slide shoe 6-2, and the heightening slide shoe 6-2 and the truss support 1-1 are provided with a horizontal connecting rod 7.

当与第一钢柱2-1柱顶标高相差大的为第二钢柱2-2,H1>h1-h2时,步骤3的具体操作如下:桁架13滑移到位后,采取措施拆除第二铸钢支座1-2底部的加高滑靴6-2和第一铸钢干支座1-1底部的正常滑靴6-1,拆除轨道5,拆除第二钢柱2-2顶部调节垫板8和第一钢柱2-1顶部调节垫板8,安装铸钢支座3,桁架13卸载,最后拆除滑移钢梁4。When the height difference from the top of the first steel column 2-1 is the second steel column 2-2, H1>h1-h2, the specific operation of step 3 is as follows: After the truss 13 slides into place, take measures to remove the second steel column 2-2. The heightened sliding shoe 6-2 at the bottom of the cast steel support 1-2 and the normal sliding shoe 6-1 at the bottom of the first cast steel dry support 1-1, remove the track 5, and remove the top adjustment pad of the second steel column 2-2 The plate 8 and the top of the first steel column 2-1 adjust the backing plate 8, install the cast steel support 3, unload the truss 13, and finally remove the sliding steel beam 4.

所述正常滑靴的厚度20~30mm。The thickness of the normal sliding shoe is 20-30mm.

积极有益效果:本发明通过对原有结构钢柱柱顶标高进行处理,保证上部钢桁架沿着水平直线滑移,有效解决了利用原有不等高钢柱进行直线滑移的难题;本发明设计巧妙,操作简单,安全稳定,在大跨度钢桁架滑移施工上有着广泛的应用前景。Positive and beneficial effects: the present invention ensures that the upper steel truss slides along a horizontal straight line by processing the height of the original structural steel column top, effectively solving the problem of using the original unequal-height steel columns for linear sliding; the design of the present invention is ingenious , easy to operate, safe and stable, and has broad application prospects in the sliding construction of large-span steel trusses.

附图说明Description of drawings

图1为本发明适用条件的结构示意图;Fig. 1 is the structural representation of applicable condition of the present invention;

图2为本发明钢柱标高调整方法的结构示意图;Fig. 2 is the structural representation of steel column elevation adjustment method of the present invention;

图3为本发明钢桁架安装后的结构示意图;Fig. 3 is the structural representation after steel truss installation of the present invention;

图中:桁架支座1,第一桁架支座1-1,第二桁架支座1-2,第三桁架支座1-3,钢柱2,第一钢柱2-1,第二钢柱2-2,第三钢柱2-3,铸钢支座3,滑移钢梁4,轨道5,滑靴6,正常滑靴6-1,加高滑靴6-2,加厚滑靴6-3,水平连杆7,调节垫板8,标高9,第一钢柱2-1柱顶标高9-1,滑移钢梁顶面标高9-2,轨道顶标高9-3,与第一钢柱2-1柱顶标高相差较大的第二钢柱2-2之间的高差H1,与第一钢柱2-1柱顶标高相差较大的第二钢柱2-2的顶段2-2-U高度H2,与第一钢柱2-1柱顶标高相差较小的第三钢柱2-3之间的高差H3。In the figure: truss support 1, first truss support 1-1, second truss support 1-2, third truss support 1-3, steel column 2, first steel column 2-1, second steel column Column 2-2, third steel column 2-3, cast steel support 3, sliding steel beam 4, track 5, sliding shoe 6, normal sliding shoe 6-1, heightened sliding shoe 6-2, thickened sliding Boot 6-3, horizontal connecting rod 7, adjusting backing plate 8, elevation 9, first steel column 2-1 column top elevation 9-1, sliding steel beam top elevation 9-2, track top elevation 9-3, The height difference H1 between the second steel column 2-2 which is quite different from the top elevation of the first steel column 2-1, and the second steel column 2-2 which is quite different from the top elevation of the first steel column 2-1 The height H2 of the top section 2-2-U of 2, and the height difference H3 between the third steel column 2-3 which has a small difference in elevation from the top of the first steel column 2-1.

具体实施方式detailed description

以下结合附图和实施例对本发明作进一步说明。The present invention will be further described below in conjunction with drawings and embodiments.

一种用于钢桁架水平滑移施工的不等高钢柱标高调整方法,包括以下步骤:步骤1:选取施工的基准,以基准结构为参照,设计并安装其他的结构,选取柱顶标高最低的第一钢柱2-1为基准,第一钢柱2-1的柱顶标高9-1为基准,与第一钢柱2-1的柱顶标高相差不大的钢柱为第三钢柱2-3,且H3 <h1-h2,H3为第三钢柱2-3与第一钢柱2-1之间的柱顶标高差,h1铸钢支座高度,h2为轨道高度;与第一钢柱2-1柱顶标高相差大的为第二钢柱2-2,H1>h1-h2;H1为与第一钢柱2-1柱顶标高相差较大的第二钢柱2-2的顶段2-2-U高度,h1铸钢支座高度,h2为轨道高度。A method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses, comprising the following steps: Step 1: Select a construction datum, use the datum structure as a reference, design and install other structures, and select the first column with the lowest elevation A steel column 2-1 is used as the reference, the column top elevation 9-1 of the first steel column 2-1 is used as the reference, and the steel column with the same elevation as the first steel column 2-1 is the third steel column 2 -3, and H3<h1-h2, H3 is the column top elevation difference between the third steel column 2-3 and the first steel column 2-1, h1 is the height of the cast steel support, h2 is the track height; The steel column 2-1 with a large difference in the top elevation is the second steel column 2-2, H1>h1-h2; H1 is the second steel column 2-2 with a large difference in the top elevation of the first steel column 2-1 The height of the top section of the 2-2-U, h1 is the height of the cast steel support, and h2 is the height of the track.

步骤2:在钢柱的顶部和轨道5之间加装若干调节垫板8以使轨道5呈水平设置,具体操作如下:钢柱2上部的桁架支座1底部设置滑靴6,滑靴6下设置滑移的轨道5,在轨道5底部设置钢柱间的滑移钢梁4,钢柱2的顶部与轨道5之间的间隙采用多层调节垫板8垫设。Step 2: Add some adjusting pads 8 between the top of the steel column and the track 5 to make the track 5 horizontal. The specific operation is as follows: set the sliding shoe 6 at the bottom of the truss support 1 on the upper part of the steel column 2, and the sliding shoe 6 The sliding track 5 is arranged below, the sliding steel beam 4 between the steel columns is set at the bottom of the track 5, and the gap between the top of the steel column 2 and the track 5 is provided with a multi-layer adjusting backing plate 8.

步骤3:桁架滑移到位后,采取措施拆除桁架支座1底部的滑靴6,拆除轨道5,拆除调节垫板8,安装铸钢支座3,桁架13卸载,最后拆除滑移钢梁4。Step 3: After the truss slides in place, take measures to remove the sliding shoe 6 at the bottom of the truss support 1, remove the track 5, remove the adjustment pad 8, install the cast steel support 3, unload the truss 13, and finally remove the sliding steel beam 4 .

实施例1Example 1

屋面桁架13通过桁架支座1及铸钢支座3支撑在钢柱2柱顶;The roof truss 13 is supported on the top of the steel column 2 through the truss support 1 and the cast steel support 3;

选取第一钢柱2-1为基准,第一钢柱2-1柱顶标高9-1为基准;Select the first steel column 2-1 as the benchmark, and the first steel column 2-1 column top elevation 9-1 as the benchmark;

当与第一钢柱2-1的柱顶标高相差不大的钢柱为第三钢柱2-3,且H3 <h1-h2时,具体操作如下:When the steel column with the same elevation as the first steel column 2-1 is the third steel column 2-3, and H3<h1-h2, the specific operation is as follows:

步骤1:选取施工的基准,以基准结构为参照,设计并安装其他的结构,选取柱顶标高最低的第一钢柱2-1为基准,第一钢柱2-1的柱顶标高9-1为基准,与第一钢柱2-1的柱顶标高相差不大的钢柱为第三钢柱2-3,且H3 <h1-h2,H3为第三钢柱2-3与第一钢柱2-1之间的柱顶标高差,h1铸钢支座高度,h2为轨道高度;步骤2:在第一钢柱2-1上部的第一桁架支座1-1底部设置正常滑靴6-1,正常滑靴6-1的厚度20~30mm,相当于滑移施工时,桁架13整体抬高20~30mm,便于在桁架13滑移完成后安装铸钢支座3;第三钢柱2-3的柱顶标高高于第一钢柱2-1柱顶标高,第三桁架支座1-3也同样会抬高,抬高部分采用加厚的滑靴6-3处理,轨道5底部与第一钢柱2-1柱顶的间隙采用调节垫板8垫设,轨道5底部与第三钢柱2-3柱顶的间隙采用调节垫板8垫设,直至第一钢柱2-1的调节垫板8的上表面与第三钢柱2-3的调节垫板8的上表面在同一平面上;Step 1: Select the construction datum, use the datum structure as a reference, design and install other structures, select the first steel column 2-1 with the lowest column top elevation as the datum, and the column top elevation of the first steel column 2-1 is 9- 1 as the benchmark, the steel column with the same elevation as the first steel column 2-1 is the third steel column 2-3, and H3<h1-h2, H3 is the third steel column 2-3 and the first steel column The elevation difference of the top of the steel column 2-1, h1 is the height of the cast steel support, and h2 is the height of the track; Step 2: Set a normal slide at the bottom of the first truss support 1-1 on the upper part of the first steel column 2-1 The shoe 6-1, the thickness of the normal sliding shoe 6-1 is 20~30mm, which is equivalent to the overall elevation of the truss 13 by 20~30mm during the sliding construction, which is convenient for installing the cast steel support 3 after the sliding of the truss 13 is completed; the third The column top elevation of the steel column 2-3 is higher than the column top elevation of the first steel column 2-1, and the third truss support 1-3 will also be raised, and the raised part is treated with a thicker sliding shoe 6-3, The gap between the bottom of the track 5 and the top of the first steel column 2-1 is set with an adjusting backing plate 8, and the gap between the bottom of the track 5 and the top of the third steel column 2-3 is set with an adjusting backing plate 8 until the first steel column The upper surface of the adjustment backing plate 8 of the column 2-1 is on the same plane as the upper surface of the adjustment backing plate 8 of the third steel column 2-3;

步骤3:桁架13滑移到位后,采取措施拆除第三铸钢支座1-3底部的加厚滑靴6-3和第一铸钢干支座1-1底部的正常滑靴6-1,拆除轨道5,拆除第三钢柱2-3顶部调节垫板8和第一钢柱2-1顶部调节垫板8,安装铸钢支座3,桁架13卸载。Step 3: After the truss 13 slides into place, take measures to remove the thickened sliding shoe 6-3 at the bottom of the third cast steel support 1-3 and the normal sliding shoe 6-1 at the bottom of the first cast steel dry support 1-1, Remove the track 5, remove the top adjustment pad 8 of the third steel column 2-3 and the top adjustment pad 8 of the first steel column 2-1, install the cast steel support 3, and unload the truss 13.

实施例2Example 2

面桁架13通过桁架支座1及铸钢支座3支撑在钢柱2柱顶;The surface truss 13 is supported on the top of the steel column 2 through the truss support 1 and the cast steel support 3;

选取第一钢柱2-1为基准,第一钢柱2-1柱顶标高9-1为基准;Select the first steel column 2-1 as the benchmark, and the first steel column 2-1 column top elevation 9-1 as the benchmark;

当与第一钢柱2-1柱顶标高相差大的为第二钢柱2-2,H1>h1-h2;The second steel column 2-2 is the second steel column 2-2 when the height difference from the top of the first steel column 2-1 is large, H1>h1-h2;

具体步骤如下:Specific steps are as follows:

步骤1:选取施工的基准,以基准结构为参照,设计并安装其他的结构,选取柱顶标高最低的第一钢柱2-1为基准,第一钢柱2-1柱顶标高9-1为基准,与第一钢柱2-1柱顶标高相差大的为第二钢柱2-2,H1>h1-h2;H1为与第一钢柱2-1柱顶标高相差较大的第二钢柱2-2的顶段2-2-U高度,h1铸钢支座高度,h2为轨道高度。Step 1: Select the construction datum and use the datum structure as a reference to design and install other structures. Select the first steel column 2-1 with the lowest column top elevation as the datum, and the first steel column 2-1 column top elevation 9-1 As a benchmark, the second steel column 2-2 is the one with the largest difference in elevation from the top of the first steel column 2-1, H1>h1-h2; H1 is the second steel column with a large difference in elevation from the top of the first steel column 2-1 The height of the top section 2-2-U of the second steel column 2-2, h1 is the height of the cast steel support, and h2 is the height of the track.

步骤2:在第一钢柱2-1上部的第一桁架支座1-1底部设置正常滑靴6-1,正常滑靴6-1厚度20~30mm也相当于滑移施工时,桁架13整体抬高20~30mm,便于在桁架13滑移完成后安装铸钢支座3;第三钢柱2-3的柱顶标高高于第一钢柱2-1柱顶标高,第三桁架支座1-3也同样会抬高,将第二钢柱2-2临时分成两段,滑移施工时只安装底段2-2-D,上段2-2-U待滑移完成后,轨道5拆除后再安装;分段位置在轨道5底部标高9-2;第二桁架支座1-2底部与轨道5之间的高度通过加高滑靴6-2实现,且加高滑靴6-2与桁架支座1-1增设水平连杆7。Step 2: Set the normal sliding shoe 6-1 at the bottom of the first truss support 1-1 on the upper part of the first steel column 2-1. The overall elevation is 20~30mm, which is convenient for installing the cast steel support 3 after the sliding of the truss 13 is completed; the column top elevation of the third steel column 2-3 is higher than that of the first steel column 2-1, and the third The seat 1-3 will also be raised, and the second steel column 2-2 is temporarily divided into two sections. During the sliding construction, only the bottom section 2-2-D is installed. After the upper section 2-2-U is finished sliding, the track 5 Reinstall after dismantling; the subsection position is at the bottom elevation 9-2 of the track 5; -2 and truss support 1-1 add horizontal connecting rod 7.

步骤3:桁架13滑移到位后,采取措施拆除第二铸钢支座1-2底部的加高滑靴6-2和第一铸钢干支座1-1底部的正常滑靴6-1,拆除轨道5,拆除第二钢柱2-2顶部调节垫板8和第一钢柱2-1顶部调节垫板8,安装铸钢支座3,桁架13卸载。Step 3: After the truss 13 slides into place, take measures to remove the heightened sliding shoe 6-2 at the bottom of the second cast steel support 1-2 and the normal sliding shoe 6-1 at the bottom of the first cast steel dry support 1-1, Remove the track 5, remove the top adjustment pad 8 of the second steel column 2-2 and the top adjustment pad 8 of the first steel column 2-1, install the cast steel support 3, and unload the truss 13.

本发明通过对原有结构钢柱柱顶标高进行处理,保证上部钢桁架沿着水平直线滑移,有效解决了利用原有不等高钢柱进行直线滑移的难题;本发明设计巧妙,操作简单,安全稳定,在大跨度钢桁架滑移施工上有着广泛的应用前景。The present invention ensures that the upper steel truss slides along a horizontal straight line by processing the height of the original structural steel column top, effectively solving the problem of using the original unequal-height steel columns for linear sliding; the present invention is ingenious in design and simple in operation. It is safe and stable, and has broad application prospects in the sliding construction of large-span steel trusses.

Claims (7)

1.一种用于钢桁架水平滑移施工的不等高钢柱标高调整方法,其特征在于:包括以下步骤:步骤1:选取施工的基准,以基准结构为参照,设计并安装其他的结构;步骤2:在钢柱的顶部和轨道(5)之间加装若干调节垫板8以使轨道(5)呈水平设置,具体操作如下:钢柱(2)上部的桁架支座(1)底部设置滑靴(6),滑靴(6)下设置滑移的轨道(5),在轨道(5)底部设置钢柱间的滑移钢梁(4),钢柱(2)的顶部与轨道(5)之间的间隙采用多层调节垫板8垫设;步骤3:桁架滑移到位后,采取措施拆除桁架支座(1)底部的滑靴(6),拆除轨道(5),拆除调节垫板(8),安装铸钢支座(3),桁架(13)卸载,最后拆除滑移钢梁(4)。1. A method for adjusting the elevation of unequal-height steel columns for steel truss horizontal sliding construction, characterized in that: comprise the following steps: Step 1: choose the benchmark of construction, take the benchmark structure as a reference, design and install other structures; step 2: Add some adjusting pads 8 between the top of the steel column and the track (5) to make the track (5) horizontal, the specific operation is as follows: the bottom of the truss support (1) on the upper part of the steel column (2) is set Sliding shoe (6), sliding track (5) is set under the sliding shoe (6), the sliding steel beam (4) between the steel columns is set at the bottom of the track (5), the top of the steel column (2) and the track ( 5) The gap between them is set with multi-layer adjustment backing plate 8; Step 3: After the truss slides in place, take measures to remove the sliding shoe (6) at the bottom of the truss support (1), remove the track (5), and remove the adjustment Install the backing plate (8), install the cast steel support (3), unload the truss (13), and finally remove the sliding steel beam (4). 2.根据权利要求1所述的用于钢桁架水平滑移施工的不等高钢柱标高调整方法,其特征在于:所述步骤1的具体操作如下:选取柱顶标高最低的第一钢柱(2-1)为基准,第一钢柱(2-1)柱顶标高(9-1)为基准,与第一钢柱(2-1)的柱顶标高相差不大的钢柱为第三钢柱(2-3),且H3 <h1-h2,H3为第三钢柱2-3与第一钢柱2-1之间的柱顶标高差,h1铸钢支座高度,h2为轨道高度;与第一钢柱(2-1)柱顶标高相差大的为第二钢柱(2-2),H1>h1-h2;H1为与第一钢柱(2-1)柱顶标高相差较大的第二钢柱(2-2)的顶段(2-2-U)高度,h1铸钢支座高度,h2为轨道高度。2. The method for adjusting the elevation of unequal-height steel columns for steel truss horizontal sliding construction according to claim 1, characterized in that: the specific operation of the step 1 is as follows: select the first steel column with the lowest column top elevation (2 -1) as the benchmark, the first steel column (2-1) column top elevation (9-1) as the benchmark, the steel column with the same column top elevation as the first steel column (2-1) is the third steel column Column (2-3), and H3<h1-h2, H3 is the elevation difference between the third steel column 2-3 and the first steel column 2-1, h1 is the height of the cast steel support, and h2 is the height of the track ; The height difference from the top of the first steel column (2-1) is the second steel column (2-2), H1>h1-h2; H1 is the difference in height from the top of the first steel column (2-1) The height of the top section (2-2-U) of the larger second steel column (2-2), h1 is the height of the cast steel support, and h2 is the height of the track. 3.根据权利要求2所述的用于钢桁架水平滑移施工的不等高钢柱标高调整方法,其特征在于:当与第一钢柱(2-1)的柱顶标高相差不大的钢柱为第三钢柱(2-3),且H3 <h1-h2时,步骤2的具体操作如下:在第一钢柱(2-1)上部的第一桁架支座(1-1)底部设置正常滑靴(6-1),便于在桁架(13)滑移完成后安装铸钢支座(3);第三钢柱(2-3)的柱顶标高高于第一钢柱(2-1)柱顶标高,第三桁架支座(1-3)也同样会抬高,抬高部分采用加厚的滑靴(6-3)处理,轨道(5)底部与第一钢柱(2-1)柱顶的间隙采用调节垫板(8)垫设,轨道(5)底部与第三钢柱(2-3)柱顶的间隙采用调节垫板(8)垫设,直至第一钢柱(2-1)的调节垫板(8)的上表面与第三钢柱(2-3)的调节垫板(8)的上表面在同一平面上。3. The method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses according to claim 2, characterized in that: when the steel column with the same elevation as the top of the first steel column (2-1) is the third steel column (2-3), and H3<h1-h2, the specific operation of step 2 is as follows: set The normal sliding shoe (6-1) is convenient for installing the cast steel support (3) after the truss (13) slides; the column top elevation of the third steel column (2-3) is higher than that of the first steel column (2- 1) The elevation of the top of the column, the third truss support (1-3) will also be raised, and the raised part shall be treated with thickened sliding shoes (6-3), and the bottom of the track (5) and the first steel column (2 -1) The gap at the top of the column is set with the adjusting backing plate (8), and the gap between the bottom of the track (5) and the top of the third steel column (2-3) is set with the adjusting backing plate (8) until the first steel column The upper surface of the adjusting backing plate (8) of the column (2-1) is on the same plane as the upper surface of the adjusting backing plate (8) of the third steel column (2-3). 4.根据权利要求2所述的用于钢桁架水平滑移施工的不等高钢柱标高调整方法,其特征在于:当与第一钢柱(2-1)的柱顶标高相差不大的钢柱为第三钢柱(2-3),且H3 <h1-h2时,步骤3的具体操作如下:桁架13滑移到位后,采取措施拆除第三铸钢支座(1-3)底部的加厚滑靴(6-3)和第一铸钢干支座(1-1)底部的正常滑靴(6-1),拆除轨道(5),拆除第三钢柱(2-3)顶部调节垫板(8)和第一钢柱(2-1)顶部调节垫板(8),安装铸钢支座(3),桁架(13)卸载,最后拆除滑移钢梁(4)。4. The method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses according to claim 2, characterized in that: when the steel column with the same elevation as the top of the first steel column (2-1) is the third steel column (2-3), and H3<h1-h2, the specific operation of step 3 is as follows: After the truss 13 slides into place, take measures to remove the reinforcement at the bottom of the third cast steel support (1-3). Thick sliding shoe (6-3) and normal sliding shoe (6-1) on the bottom of the first cast steel dry support (1-1), remove the track (5), remove the adjustment pad on the top of the third steel post (2-3) Plate (8) and the top of the first steel column (2-1) adjust the backing plate (8), install the cast steel support (3), unload the truss (13), and finally remove the sliding steel beam (4). 5.根据权利要求2所述的用于钢桁架水平滑移施工的不等高钢柱标高调整方法,其特征在于:当与第一钢柱(2-1)柱顶标高相差大的为第二钢柱(2-2),H1>h1-h2时,步骤2的具体操作如下:在第一钢柱(2-1)上部的第一桁架支座(1-1)底部设置正常滑靴(6-1),便于在桁架(13)滑移完成后安装铸钢支座(3);第二钢柱(2-2)的柱顶标高高于第一钢柱(2-1)柱顶标高,第二桁架支座(1-2)也同样会抬高,将第二钢柱(2-2)临时分成两段,滑移施工时只安装底段(2-2-D),上段(2-2-U)待滑移完成后,轨道(5)拆除后再安装;分段位置在轨道(5)底部标高(9-2);第二桁架支座(1-2)底部与轨道(5)之间的高度通过加高滑靴(6-2)实现,且加高滑靴(6-2)与桁架支座(1-1)增设水平连杆(7)。5. The method for adjusting the elevation of unequal-height steel columns for the horizontal sliding construction of steel trusses according to claim 2, characterized in that: when the elevation of the top of the first steel column (2-1) differs greatly from that of the first steel column (2-1), it is the second steel column Column (2-2), when H1>h1-h2, the specific operation of step 2 is as follows: set normal sliding shoes (6 -1), it is convenient to install the cast steel support (3) after the truss (13) slides; the column top elevation of the second steel column (2-2) is higher than the column top elevation of the first steel column (2-1) , the second truss support (1-2) will also be raised, and the second steel column (2-2) will be temporarily divided into two sections. During the sliding construction, only the bottom section (2-2-D) will be installed, and the upper section ( 2-2-U) After the sliding is completed, remove the track (5) and install it again; the subsection position is at the bottom elevation (9-2) of the track (5); the bottom of the second truss support (1-2) is in contact with the track The height between (5) is realized by heightening the sliding shoe (6-2), and a horizontal connecting rod (7) is added to the heightening sliding shoe (6-2) and the truss support (1-1). 6.根据权利要求2所述的用于钢桁架水平滑移施工的不等高钢柱标高调整方法,其特征在于:当与第一钢柱(2-1)柱顶标高相差大的为第二钢柱(2-2),H1>h1-h2时,步骤3的具体操作如下:桁架13滑移到位后,采取措施拆除第二铸钢支座(1-2)底部的加高滑靴(6-2)和第一铸钢干支座(1-1)底部的正常滑靴(6-1),拆除轨道(5),拆除第二钢柱(2-2)顶部调节垫板(8)和第一钢柱(2-1)顶部调节垫板(8),安装铸钢支座(3),桁架(13)卸载,最后拆除滑移钢梁(4)。6. The method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses according to claim 2, characterized in that: when the elevation difference between the first steel column (2-1) and the top elevation of the first steel column (2-1) is large, it is the second steel column For the column (2-2), when H1>h1-h2, the specific operation of step 3 is as follows: after the truss 13 slides into place, take measures to remove the heightening shoe (6 -2) and the normal sliding shoe (6-1) at the bottom of the first cast steel dry support (1-1), remove the track (5), remove the top adjustment backing plate (8) of the second steel column (2-2) and Adjust the backing plate (8) on the top of the first steel column (2-1), install the cast steel support (3), unload the truss (13), and finally remove the sliding steel beam (4). 7.根据权利要求2所述的用于钢桁架水平滑移施工的不等高钢柱标高调整方法,其特征在于:所述正常滑靴(6-1)的厚度20~30mm。7. The method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses according to claim 2, characterized in that: the normal sliding shoe (6-1) has a thickness of 20-30mm.
CN202211369630.7A 2022-11-03 2022-11-03 A method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses Pending CN115573582A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211369630.7A CN115573582A (en) 2022-11-03 2022-11-03 A method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211369630.7A CN115573582A (en) 2022-11-03 2022-11-03 A method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses

Publications (1)

Publication Number Publication Date
CN115573582A true CN115573582A (en) 2023-01-06

Family

ID=84588070

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211369630.7A Pending CN115573582A (en) 2022-11-03 2022-11-03 A method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses

Country Status (1)

Country Link
CN (1) CN115573582A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117536457A (en) * 2023-12-22 2024-02-09 广州五羊建设机械有限公司 Anti-overturning device and method for sliding construction of planar structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105421771A (en) * 2015-09-30 2016-03-23 浙江精工钢结构集团有限公司 Accumulated slip construction method for unequal-elevation string truss with columns
CN107013038A (en) * 2017-05-08 2017-08-04 福建省涵城建设工程有限公司 A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN108468430A (en) * 2018-03-12 2018-08-31 成都建筑工程集团总公司 The not contour bearing steel truss structure hoisting slide construction of large span
CN207932919U (en) * 2018-03-12 2018-10-02 成都建筑工程集团总公司 The not contour bearing steel truss structure hoisting slide construction system of large span
CN112392261A (en) * 2020-10-20 2021-02-23 中冶(上海)钢结构科技有限公司 Construction method for stably converting support system after slippage of large-span steel roof is completed
WO2021174481A1 (en) * 2020-03-05 2021-09-10 广州建筑股份有限公司 Construction method for accumulative sliding of single-side subsection orbital transfer of unequal-span structure
CN114525846A (en) * 2021-12-09 2022-05-24 北京建工集团有限责任公司 Mounting method of unequal-elevation steel truss structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105421771A (en) * 2015-09-30 2016-03-23 浙江精工钢结构集团有限公司 Accumulated slip construction method for unequal-elevation string truss with columns
CN107013038A (en) * 2017-05-08 2017-08-04 福建省涵城建设工程有限公司 A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN108468430A (en) * 2018-03-12 2018-08-31 成都建筑工程集团总公司 The not contour bearing steel truss structure hoisting slide construction of large span
CN207932919U (en) * 2018-03-12 2018-10-02 成都建筑工程集团总公司 The not contour bearing steel truss structure hoisting slide construction system of large span
WO2021174481A1 (en) * 2020-03-05 2021-09-10 广州建筑股份有限公司 Construction method for accumulative sliding of single-side subsection orbital transfer of unequal-span structure
CN112392261A (en) * 2020-10-20 2021-02-23 中冶(上海)钢结构科技有限公司 Construction method for stably converting support system after slippage of large-span steel roof is completed
CN114525846A (en) * 2021-12-09 2022-05-24 北京建工集团有限责任公司 Mounting method of unequal-elevation steel truss structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨向阳;王金辉;刘帅;刘汇东;桑晓景;: "不等高张弦三角管桁架带柱累积滑移施工技术", 施工技术, no. 20, 25 October 2016 (2016-10-25) *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117536457A (en) * 2023-12-22 2024-02-09 广州五羊建设机械有限公司 Anti-overturning device and method for sliding construction of planar structure
CN117536457B (en) * 2023-12-22 2024-04-12 广州五羊建设机械有限公司 Anti-overturning device and method for sliding construction of planar structure

Similar Documents

Publication Publication Date Title
CN106869489A (en) Super High Core Walls Structure level and vertical synchronous construction top module system and construction method
CN102619309A (en) Reinforced concrete stair provided with local supporting type efficient sliding support
CN115573582A (en) A method for adjusting the elevation of unequal-height steel columns for horizontal sliding construction of steel trusses
CN207567961U (en) Steel structure support suitable for sliding construction
CN111945881B (en) Adjustable connecting joint for prefabricated building and construction method of adjustable connecting joint
CN108560330B (en) Secondary pouring type upgradeable general ballast bed and construction method thereof
CN111173313A (en) Strutting arrangement is used in construction of large-span steel construction entrance hall
CN103343626A (en) Method for mounting plate type steel net racks with T-shaped support net rack in sliding mode and T-shaped support net rack structure
CN220434210U (en) Sliding pouring template for side wall of underground space structure
CN208964324U (en) A fully modular assembled elevator shaft
CN218091892U (en) Portable Scaffolding for Restoration of Ancient Buildings
CN205100543U (en) A New Construction System for Commercial Buildings
CN222632535U (en) Precast beam and precast column connection structure
CN206842780U (en) Elevator attaches support of wall frame and attaches system
CN219586572U (en) Steel box girder installing support
CN221855834U (en) Drainage device is drawn to movement joint
CN111705932A (en) Large-span structure overhanging structure and curtain wall sliding construction method
CN218623253U (en) Outer scaffold is wall spare even
CN219726670U (en) Adjustable prefabricated stair mould
CN104947836B (en) Construction method of cast-in-place floor slab without support in high-rise steel structure residence
CN222456569U (en) Floor thickness and protective layer thickness control device
CN216640294U (en) Steel supporting platform for bearing bridge construction foundation
CN210066812U (en) Reinforced earth retaining wall panel pouring template
CN211472210U (en) Large-tonnage prestressed concrete continuous beam pushing bench
CN214272570U (en) A splicing structure between curtain wall decorative panels

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination