CN115492353A - An assembled operating platform attached to the top of a steel pipe column and its attachment method - Google Patents

An assembled operating platform attached to the top of a steel pipe column and its attachment method Download PDF

Info

Publication number
CN115492353A
CN115492353A CN202211189132.4A CN202211189132A CN115492353A CN 115492353 A CN115492353 A CN 115492353A CN 202211189132 A CN202211189132 A CN 202211189132A CN 115492353 A CN115492353 A CN 115492353A
Authority
CN
China
Prior art keywords
steel pipe
pipe column
shaped
attached
groined
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211189132.4A
Other languages
Chinese (zh)
Inventor
栾蔚
栗泽
刘智勇
崔泽海
于浩
许迁迁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northwest Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Northwest Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northwest Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Northwest Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202211189132.4A priority Critical patent/CN115492353A/en
Publication of CN115492353A publication Critical patent/CN115492353A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • E04G3/243Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons following the outside contour of a building
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

本发明公开了一种附着于钢管柱柱顶的装配式操作平台及其附着方法,所述装配式操作平台包括:由两根横杆和两根纵杆搭设形成的井字形附着底架、以及覆盖并铺设在所述井字形附着底架顶部的平台板,所述平台板上对应所述井字形附着底架的井字口区域设有开口;两根所述横杆之间连接有第一伸缩件,两根所述纵杆之间连接有第二伸缩件,两根所述横杆和两根所述纵杆上均活动装设有用于连接至钢管柱顶沿的连接件。本发明适配多种管径的钢管柱,更加具有实用性。

Figure 202211189132

The invention discloses an assembled operating platform attached to the top of a steel pipe column and an attaching method thereof. The assembled operating platform includes: a well-shaped attachment chassis formed by erecting two horizontal bars and two longitudinal bars; and Covering and laying on the platform plate on the top of the well-shaped attachment chassis, the platform plate is provided with an opening corresponding to the well-shaped area of the well-shaped attachment chassis; a first cross-bar is connected between the two cross bars. As for the telescopic element, a second telescopic element is connected between the two longitudinal bars, and a connecting piece for connecting to the top edge of the steel pipe column is movably installed on the two horizontal bars and the two longitudinal bars. The invention is suitable for steel pipe columns with various pipe diameters, and has more practicability.

Figure 202211189132

Description

一种附着于钢管柱柱顶的装配式操作平台及其附着方法An assembled operating platform attached to the top of a steel pipe column and its attachment method

技术领域technical field

本发明涉建筑施工领域,尤其涉及一种附着于钢管柱柱顶的装配式操作平台及其附着方法。The invention relates to the field of building construction, in particular to an assembled operating platform attached to the top of a steel pipe column and an attachment method thereof.

背景技术Background technique

由于钢管混凝土柱普遍较为高大,在钢管柱安装完成后再进行钢管柱内混凝土的浇筑通常较为困难,需要围绕钢管柱搭设脚手架等操作平台以便在柱顶进行混凝土浇筑及振捣操作,施工过程繁琐,成本较高,且存在安全隐患等。Since steel pipe concrete columns are generally tall, it is usually difficult to pour concrete inside the steel pipe column after the steel pipe column is installed. Scaffolding and other operating platforms need to be erected around the steel pipe column to perform concrete pouring and vibration operations on the top of the column. The construction process is cumbersome , high cost, and potential safety hazards.

发明内容Contents of the invention

本发明的目的在于克服现有技术的缺陷,提供附着于钢管柱柱顶的装配式操作平台及其附着方法,用以进行钢管柱内的混凝土浇筑振捣等施工作业,该装置由可调附着底架、防护栏和平台板组装而成,制作简单,装配方便、快捷,可适用于不同直径的钢管柱顶安装使用,安全、可靠,现场使用效果良好。The purpose of the present invention is to overcome the defects of the prior art, and provide an assembled operating platform attached to the top of the steel pipe column and its attachment method, which are used for construction operations such as concrete pouring and vibration in the steel pipe column. The bottom frame, guard rail and platform board are assembled, and the manufacture is simple, and the assembly is convenient and quick, and it is suitable for installation and use on steel pipe column tops of different diameters, safe and reliable, and has a good effect on site.

为实现上述目的,本发明采用的技术方案为包括:由两根横杆和两根纵杆搭设形成的井字形附着底架、以及覆盖并铺设在所述井字形附着底架顶部的平台板,所述平台板上对应所述井字形附着底架的井字口区域设有开口;In order to achieve the above object, the technical solution adopted by the present invention is to include: a well-shaped attachment chassis formed by erecting two horizontal bars and two longitudinal bars, and a platform plate covered and laid on the top of the well-shaped attachment chassis, Openings are provided on the platform plate corresponding to the well-shaped area of the well-shaped attachment chassis;

两根所述横杆之间连接有第一伸缩件,两根所述纵杆之间连接有第二伸缩件,两根所述横杆和两根所述纵杆上均活动装设有用于连接至钢管柱顶沿的连接件。A first telescopic member is connected between the two horizontal bars, a second telescopic member is connected between the two longitudinal bars, and the two horizontal bars and the two longitudinal bars are movably equipped with A connector that attaches to the top edge of a steel pipe column.

本发明附着于钢管柱柱顶的装配式操作平台进一步的改进在于,还包括两根外纵杆和两根外横杆,两根所述外纵杆分别活动串接两根所述横杆的两个端部,两根所述外横杆分别活动串接两根所述纵杆的两个端部,两根所述外横杆和两根所述外纵杆搭接连接成围设所述井字形附着底架的矩形边框。The further improvement of the assembled operating platform attached to the top of the steel pipe column in the present invention is that it also includes two outer longitudinal bars and two outer transverse bars, and the two outer longitudinal bars are respectively movably connected to the two outer transverse bars. The two ends, the two outer horizontal bars are respectively movable in series with the two ends of the two longitudinal bars, and the two outer transverse bars and the two outer longitudinal bars are overlapped and connected to form a surrounding The rectangular frame of the well-shaped attachment chassis.

本发明附着于钢管柱柱顶的装配式操作平台进一步的改进在于,两根所述外纵杆的相对两侧和两根所述外横杆的相对内侧均设有供相应所述横杆和所述纵杆滑动连接的滑轨。The further improvement of the assembled operating platform attached to the top of the steel pipe column in the present invention lies in that the opposite sides of the two outer longitudinal bars and the inner sides of the two outer transverse bars are provided with the corresponding transverse bars and The longitudinal rod is slidably connected to a slide rail.

本发明附着于钢管柱柱顶的装配式操作平台进一步的改进在于,所述滑轨为通长开设于相应所述外纵杆或相应所述外横杆的滑槽,所述滑槽的侧壁上通长开设有条形通槽,所述横杆和所述纵杆的两端均连接有用于插入相应所述条形通槽的插挡件。The further improvement of the assembled operating platform attached to the top of the steel pipe column in the present invention lies in that the slide rail is a chute opened on the corresponding outer longitudinal bar or the corresponding outer cross bar, and the side of the chute A strip-shaped through-slot is opened on the wall, and both ends of the horizontal bar and the longitudinal bar are connected with inserting pieces for inserting into the corresponding strip-shaped through-slot.

本发明附着于钢管柱柱顶的装配式操作平台进一步的改进在于,所述外横杆的两端开设有第一螺纹孔,所述外纵杆的两端开设有与所述第一螺纹孔的孔径相适配的第二螺纹孔,所述第一螺纹孔和相应所述第二螺纹孔通过螺栓螺合连接。The further improvement of the assembled operating platform attached to the top of the steel pipe column in the present invention is that the two ends of the outer cross bar are provided with first threaded holes, and the two ends of the outer longitudinal bar are provided with first threaded holes. A second threaded hole matching the hole diameter of the first threaded hole and the corresponding second threaded hole are connected by bolts.

本发明附着于钢管柱柱顶的装配式操作平台进一步的改进在于,所述连接件包括倒U型板、以及用于将所述倒U型板固定至所述钢管柱顶沿的螺栓,所述倒U型板的一侧翼缘板以及所述钢管柱的顶沿上均开设有供所述螺栓穿过并固定的连接孔。A further improvement of the assembled operating platform attached to the top of the steel pipe column in the present invention is that the connecting piece includes an inverted U-shaped plate and bolts for fixing the inverted U-shaped plate to the top edge of the steel pipe column. Both the side flange plate of the inverted U-shaped plate and the top edge of the steel pipe column are provided with connecting holes for the bolts to pass through and be fixed.

本发明附着于钢管柱柱顶的装配式操作平台进一步的改进在于,所述平台板底部连接有平台板卡扣,所述平台板卡扣扣接在所述井字形附着底架上。The further improvement of the assembled operating platform attached to the top of the steel pipe column in the present invention is that the bottom of the platform plate is connected with a platform plate buckle, and the platform plate buckle is fastened to the well-shaped attachment chassis.

本发明附着于钢管柱柱顶的装配式操作平台进一步的改进在于,所述矩形边框四周还围接有防护栏。A further improvement of the assembled operating platform attached to the top of the steel pipe column in the present invention is that the rectangular frame is surrounded by guardrails.

本发明还提供附着于钢管柱柱顶的装配式操作平台的附着方法,包括步骤:The present invention also provides an attachment method for an assembled operating platform attached to the top of a steel pipe column, comprising the steps of:

提供上述的附着于钢管柱柱顶的装配式操作平台;Provide the above-mentioned prefabricated operating platform attached to the top of the steel pipe column;

将所述装配式操作平台吊装至钢管柱的上方,并使井字形附着底架的井字口正对所述钢管柱;hoisting the fabricated operating platform above the steel pipe column, and making the well-shaped opening attached to the underframe face the steel pipe column;

调节第一伸缩件和第二伸缩件的长度,使两根横杆和两根纵杆相对移动,进而使所述井字口的大小适配于所述钢管柱的外径;Adjusting the length of the first telescopic member and the second telescopic member, so that the two horizontal bars and the two longitudinal bars move relatively, so that the size of the well-shaped opening is adapted to the outer diameter of the steel pipe column;

将所述井字形附着底架下移至所述钢管柱的顶端,利用连接件将所述井字形附着底架连接至所述钢管柱的顶沿。The well-shaped attachment base is moved down to the top of the steel pipe column, and the well-shaped attachment base is connected to the top edge of the steel pipe column by using a connector.

与现有技术相比,本发明的优势在于:Compared with the prior art, the present invention has the advantages of:

1.通过将网格型附着底架分割成上下搭接的井字型附着底架,并在所述井字型附着底架上连接伸缩件,适配多种管径的钢管柱。1. By dividing the grid-shaped attachment base frame into a well-shaped attachment base frame overlapping up and down, and connecting telescopic parts to the well-shaped attachment base frame, it can adapt to steel pipe columns of various pipe diameters.

2.通过设置所述倒U型板,将所述井字型附着底架固定在所述钢管柱侧壁顶部。2. By setting the inverted U-shaped plate, the well-shaped attachment chassis is fixed on the top of the side wall of the steel pipe column.

附图说明Description of drawings

为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings that need to be used in the description of the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present invention. For those skilled in the art, other drawings can also be obtained based on these drawings without creative effort.

图1为本发明附着于钢管柱柱顶的装配式操作平台的剖面示意图。Fig. 1 is a schematic cross-sectional view of an assembled operating platform attached to the top of a steel pipe column according to the present invention.

图2为本发明附着于钢管柱柱顶的装配式操作平台的附着底架俯视图。Fig. 2 is a top view of the attachment base of the assembled operating platform attached to the top of the steel pipe column according to the present invention.

图3为本发明附着于钢管柱柱顶的装配式操作平台的防护栏示意图。Fig. 3 is a schematic diagram of the protective fence of the assembled operating platform attached to the top of the steel pipe column according to the present invention.

图4为本发明附着于钢管柱柱顶的装配式操作平台的平面板铺设状态示意图。Fig. 4 is a schematic diagram of the laying state of the flat plate of the assembled operating platform attached to the top of the steel pipe column according to the present invention.

图中:1、钢管柱;2、井字形附着底架;3、倒U型板;4、防护栏;5、第一伸缩件;6、第二伸缩件;7、外横杆;8、外纵杆;9、平台板。In the figure: 1. steel pipe column; 2. well-shaped attachment chassis; 3. inverted U-shaped plate; 4. guardrail; 5. first expansion part; 6. second expansion part; Outer longitudinal rod; 9. Platform board.

具体实施方式detailed description

以下通过特定的具体实例说明本发明的实施方式,本领域技术人员可由本说明书所揭露的内容轻易地了解本发明的其他优点与功效。本发明还可以通过另外不同的具体实施方式加以实施或应用,本说明书中的各项细节也可以基于不同观点与应用,在没有背离本发明的精神下进行各种修饰或改变。Embodiments of the present invention are described below through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the content disclosed in this specification. The present invention can also be implemented or applied through other different specific implementation modes, and various modifications or changes can be made to the details in this specification based on different viewpoints and applications without departing from the spirit of the present invention.

下面结合附图和具体实施例对本发明附着于钢管柱1柱顶的装配式操作平台及其附着方法做进一步详细说明。The prefabricated operating platform attached to the top of the steel pipe column 1 and its attachment method of the present invention will be further described in detail in conjunction with the accompanying drawings and specific embodiments.

请参阅图1~图4所示,附着于钢管柱1柱顶的装配式操作平台,包括:由两根横杆和两根纵杆搭设形成的井字形附着底架2、以及覆盖并铺设在该井字形附着底架2顶部的平台板,该平台板上对应该井字形附着底架2的井字口区域设有开口;Please refer to Figures 1 to 4, the assembled operating platform attached to the top of the steel pipe column 1 includes: a well-shaped attachment chassis 2 formed by erecting two horizontal bars and two vertical bars, and covering and laying on the The platform plate on the top of the well-shaped attachment base frame 2 is provided with an opening corresponding to the well-shaped area of the well-shaped attachment base frame 2 on the platform plate;

两根该横杆之间连接有第一伸缩件5,两根该纵杆之间连接有第二伸缩件6,两根该横杆和两根该纵杆上均活动装设有用于连接至钢管柱1顶沿的连接件。A first telescopic member 5 is connected between the two cross bars, and a second telescopic member 6 is connected between the two longitudinal bars. Both the cross bars and the two longitudinal bars are movably equipped with a device for connecting to A connecting piece for the top edge of the steel pipe column 1.

较佳地,还包括两根外纵杆8和两根外横杆7,两根该外纵杆8分别活动串接两根该横杆的两个端部,两根该外横杆7分别活动串接两根该纵杆的两个端部,两根该外横杆7和两根该外纵杆8搭接连接成围设该井字形附着底架2的矩形边框。Preferably, it also includes two outer longitudinal bars 8 and two outer cross bars 7, the two outer longitudinal bars 8 are respectively movable in series with the two ends of the two outer bars, and the two outer bars 7 are respectively The two ends of the two longitudinal bars are connected in series, and the two outer transverse bars 7 and the two outer longitudinal bars 8 are overlapped and connected to form a rectangular frame surrounding the well-shaped attachment chassis 2 .

较佳地,两根该外纵杆8的相对两侧和两根该外横杆7的相对内侧均设有供相应该横杆和该纵杆滑动连接的滑轨。Preferably, the opposite sides of the two outer longitudinal bars 8 and the inner sides of the two outer transverse bars 7 are provided with sliding rails for sliding connection between the corresponding transverse bars and the longitudinal bars.

较佳地,该滑轨为通长开设于相应该外纵杆8或相应该外横杆7的滑槽,该滑槽的侧壁上通长开设有条形通槽,该横杆和该纵杆的两端均连接有用于插入相应该条形通槽的插挡件。Preferably, the slide rail is a chute opened on the corresponding outer longitudinal bar 8 or the corresponding outer cross bar 7, and a bar-shaped through groove is opened on the side wall of the chute. Both ends of the longitudinal rod are connected with inserting pieces for inserting into the corresponding bar-shaped through groove.

具体地,该插挡件为紧固螺栓,该紧固螺栓包括沿该条形通槽滑动的螺杆以及螺合套设在该螺杆上用于限制该横杆和该纵杆滑动的螺母。Specifically, the blocking member is a fastening bolt, and the fastening bolt includes a screw rod sliding along the bar-shaped channel and a nut screwed on the screw rod for limiting the sliding of the cross bar and the longitudinal bar.

较佳地,该外横杆7的两端开设有第一螺纹孔,该外纵杆8的两端开设有与该第一螺纹孔的孔径相适配的第二螺纹孔,该第一螺纹孔和相应该第二螺纹孔通过螺栓螺合连接。Preferably, the two ends of the outer cross bar 7 are provided with a first threaded hole, and the two ends of the outer longitudinal bar 8 are provided with a second threaded hole matching the diameter of the first threaded hole. The hole and the corresponding second threaded hole are connected by bolt threading.

较佳地,该连接件包括倒U型板3、以及用于将该倒U型板3固定至该钢管柱1顶沿的螺栓,该倒U型板3的一侧翼缘板以及该钢管柱1的顶沿上均开设有供该螺栓穿过并固定的连接孔。Preferably, the connecting piece includes an inverted U-shaped plate 3 and bolts for fixing the inverted U-shaped plate 3 to the top edge of the steel pipe column 1, one side flange plate of the inverted U-shaped plate 3 and the steel pipe column 1 are provided with connecting holes for the bolts to pass through and be fixed on the top edge.

较佳地,该平台板底部连接有平台板卡扣,该平台板卡扣扣接在该井字形附着底架2上。Preferably, the platform board buckle is connected to the bottom of the platform board, and the platform board buckle is fastened to the well-shaped attachment chassis 2 .

具体地,该平台板的尺寸不一,在装设该平台板时将相应尺寸的平台板扣接在该井字形附着底架2的相应位置。Specifically, the size of the platform board is different, and the platform board of the corresponding size is fastened to the corresponding position of the well-shaped attachment chassis 2 when the platform board is installed.

较佳地,该矩形边框四周还围接有防护栏4。Preferably, the rectangular frame is surrounded by guardrails 4 .

具体地,所诉防护栏4包括围接在该矩形框架四周的固定杆,固定在该固定杆上的多根立杆,以及连接在相邻两个该立杆之间的安全立网。Specifically, the said guardrail 4 includes a fixed bar surrounding the rectangular frame, a plurality of uprights fixed on the fixed bar, and a safety vertical net connected between two adjacent uprights.

具体地,相邻两个该立杆之间还连接有加固斜撑,通过设置该加固斜撑加强了该安全立网的稳定性。Specifically, a reinforcing diagonal brace is also connected between two adjacent vertical poles, and the stability of the safety vertical net is enhanced by arranging the reinforcing diagonal brace.

一种附着于钢管柱柱顶的装配式操作平台的附着方法,包括步骤:A method for attaching an assembled operating platform attached to the top of a steel pipe column, comprising steps:

步骤1,提供上述的附着于钢管柱1柱顶的装配式操作平台;Step 1, providing the above-mentioned assembled operating platform attached to the top of the steel pipe column 1;

步骤2,将该装配式操作平台吊装至钢管柱1的上方,并使井字形附着底架2的井字口正对该钢管柱1;Step 2, hoisting the prefabricated operating platform above the steel pipe column 1, and making the well-shaped mouth of the well attached to the chassis 2 face the steel pipe column 1;

步骤3,调节第一伸缩件5和第二伸缩件6的长度,使两根横杆和两根纵杆相对移动,进而使该井字口的大小适配于该钢管柱1的外径;Step 3, adjusting the length of the first telescopic member 5 and the second telescopic member 6, so that the two horizontal bars and the two longitudinal bars move relatively, so that the size of the well-tac-toe is adapted to the outer diameter of the steel pipe column 1;

步骤4,将该井字形附着底架2下移至该钢管柱1的顶端,利用连接件将该井字形附着底架2连接至该钢管柱1的顶沿。Step 4, move the well-shaped attachment base 2 down to the top of the steel pipe column 1, and connect the well-shaped attachment base 2 to the top edge of the steel pipe column 1 by using connectors.

需要说明的是,本说明书所附图式所绘示的结构、比例、大小等,均仅用以配合说明书所揭示的内容,以供熟悉此技术的人士了解与阅读,并非用以限定本发明可实施的限定条件,故不具技术上的实质意义,任何结构的修饰、比例关系的改变或大小的调整,在不影响本发明所能产生的功效及所能达成的目的下,均应仍落在本发明所揭示的技术内容得能涵盖的范围内。同时,本说明书中所引用的如“上”、“下”、“左”、“右”、“中间”及“一”等的用语,亦仅为便于叙述的明了,而非用以限定本发明可实施的范围,其相对关系的改变或调整,在无实质变更技术内容下,当亦视为本发明可实施的范畴。It should be noted that the structures, proportions, sizes, etc. shown in the drawings attached to this specification are only used to match the content disclosed in the specification, for those who are familiar with this technology to understand and read, and are not intended to limit the present invention Therefore, it has no technical substantive meaning, and any modification of structure, change of proportional relationship or adjustment of size shall still fall into the within the scope covered by the technical content disclosed in the present invention. At the same time, terms such as "upper", "lower", "left", "right", "middle" and "one" quoted in this specification are only for the convenience of description and are not used to limit this specification. The practicable scope of the invention and the change or adjustment of its relative relationship shall also be regarded as the practicable scope of the present invention without any substantial change in the technical content.

以上所述仅是本发明的较佳实施例而已,并非对本发明做任何形式上的限制,虽然本发明已以较佳实施例揭露如上,然而并非用以限定本发明,任何熟悉本专业的技术人员,在不脱离本发明技术方案的范围内,当可利用上述揭示的技术内容作出些许更动或修饰为等同变化的等效实施例,但凡是未脱离本发明技术方案的内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化与修饰,均仍属于本发明技术方案的范围内。The above descriptions are only preferred embodiments of the present invention, and do not limit the present invention in any form. Although the present invention has been disclosed as above with preferred embodiments, it is not intended to limit the present invention. Anyone familiar with this professional technology Personnel, without departing from the scope of the technical solution of the present invention, when the technical content disclosed above can be used to make some changes or modifications to equivalent embodiments with equivalent changes, but all the content that does not depart from the technical solution of the present invention, according to the present invention Any simple modifications, equivalent changes and modifications made to the above embodiments by the technical essence still belong to the scope of the technical solution of the present invention.

Claims (9)

1. An assembled operation platform attached to the top of a steel pipe column is characterized by comprising: the device comprises a groined attachment underframe formed by erecting two cross rods and two longitudinal rods and a platform plate covering and laying the top of the groined attachment underframe, wherein an opening is formed in the platform plate corresponding to a groined mouth area of the groined attachment underframe;
two be connected with first extensible member between the horizontal pole, two be connected with the second extensible member between the vertical pole, two horizontal pole and two equal activity has been installed and is used for being connected to the connecting piece on steel-pipe column top edge on the vertical pole.
2. The assembly type operating platform attached to the top of the steel pipe column according to claim 1, further comprising two outer longitudinal rods and two outer transverse rods, wherein the two outer longitudinal rods are respectively and movably connected with two end portions of the two transverse rods in series, the two outer transverse rods are respectively and movably connected with two end portions of the two longitudinal rods in series, and the two outer transverse rods and the two outer longitudinal rods are connected in a lap joint mode to form a rectangular frame surrounding the groined type attached underframe.
3. The fabricated operation platform attached to the top of the steel pipe column according to claim 2, wherein slide rails for slidably connecting the corresponding cross bars and the longitudinal bars are provided on opposite sides of the two outer longitudinal bars and on opposite inner sides of the two outer cross bars.
4. The assembly type operating platform attached to the top of the steel pipe column according to claim 3, wherein the slide rail is a slide groove which is formed in the corresponding outer vertical rod or the corresponding outer transverse rod in a full length mode, a strip-shaped through groove is formed in the side wall of the slide groove in a full length mode, and insertion stoppers which are used for being inserted into the corresponding strip-shaped through grooves are connected to two ends of each of the transverse rod and the longitudinal rod.
5. The assembly type operation platform attached to the top of the steel pipe column according to claim 2, wherein first threaded holes are formed in two ends of the outer cross rod, second threaded holes matched with the first threaded holes are formed in two ends of the outer longitudinal rod, and the first threaded holes and the corresponding second threaded holes are in threaded connection through bolts.
6. The assembly type operation platform attached to the top of the steel pipe column according to claim 1, wherein the connecting piece comprises an inverted U-shaped plate and a bolt for fixing the inverted U-shaped plate to the top edge of the steel pipe column, and a connecting hole for the bolt to pass through and be fixed is formed in each of a side flange plate of the inverted U-shaped plate and the top edge of the steel pipe column.
7. The assembly type operation platform attached to the top of the steel pipe column according to claim 1, wherein a platform plate buckle is connected to the bottom of the platform plate, and the platform plate buckle is buckled on the groined attachment base frame.
8. The assembly type operating platform attached to the top of the steel pipe column according to claim 2, wherein guard rails are further arranged around the rectangular frame.
9. An attachment method for a fabricated operation platform, comprising the steps of:
providing the fabricated operation platform attached to the top of the steel pipe column according to any one of claims 1 to 7;
hoisting the assembled operating platform above the steel pipe column, and enabling the # -shaped opening of the # -shaped attached bottom frame to face the steel pipe column;
adjusting the lengths of the first telescopic piece and the second telescopic piece to enable the two cross rods and the two longitudinal rods to move relatively, so that the size of the # -shaped opening is adapted to the outer diameter of the steel pipe column;
and moving the groined attaching bottom frame downwards to the top end of the steel pipe column, and connecting the groined attaching bottom frame to the top edge of the steel pipe column by using a connecting piece.
CN202211189132.4A 2022-09-28 2022-09-28 An assembled operating platform attached to the top of a steel pipe column and its attachment method Pending CN115492353A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211189132.4A CN115492353A (en) 2022-09-28 2022-09-28 An assembled operating platform attached to the top of a steel pipe column and its attachment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211189132.4A CN115492353A (en) 2022-09-28 2022-09-28 An assembled operating platform attached to the top of a steel pipe column and its attachment method

Publications (1)

Publication Number Publication Date
CN115492353A true CN115492353A (en) 2022-12-20

Family

ID=84471452

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211189132.4A Pending CN115492353A (en) 2022-09-28 2022-09-28 An assembled operating platform attached to the top of a steel pipe column and its attachment method

Country Status (1)

Country Link
CN (1) CN115492353A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000054617A (en) * 1998-08-12 2000-02-22 Nippon Steel Corp Work scaffold for tubular structure, method of assembling tubular structure using scaffold, and method of removing scaffold
CN201738560U (en) * 2010-09-02 2011-02-09 中建三局建设工程股份有限公司 Adjustable operating platform for pouring concrete into steel column
CN103526918A (en) * 2013-10-18 2014-01-22 中国建筑第八工程局有限公司 Adjustable steel pipe operation platform
CN203514789U (en) * 2013-09-24 2014-04-02 浙江省建工集团有限责任公司 Steel platform for concrete pouring construction in ultra-high-rise steel pipe column
CN204662926U (en) * 2015-04-21 2015-09-23 中建六局建设发展有限公司 A kind of operating platform for steel pipe column top construction operation
CN107060309A (en) * 2017-05-15 2017-08-18 中国十七冶集团有限公司 A kind of hanging type steel structure high-altitude operation mobile platform fast construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000054617A (en) * 1998-08-12 2000-02-22 Nippon Steel Corp Work scaffold for tubular structure, method of assembling tubular structure using scaffold, and method of removing scaffold
CN201738560U (en) * 2010-09-02 2011-02-09 中建三局建设工程股份有限公司 Adjustable operating platform for pouring concrete into steel column
CN203514789U (en) * 2013-09-24 2014-04-02 浙江省建工集团有限责任公司 Steel platform for concrete pouring construction in ultra-high-rise steel pipe column
CN103526918A (en) * 2013-10-18 2014-01-22 中国建筑第八工程局有限公司 Adjustable steel pipe operation platform
CN204662926U (en) * 2015-04-21 2015-09-23 中建六局建设发展有限公司 A kind of operating platform for steel pipe column top construction operation
CN107060309A (en) * 2017-05-15 2017-08-18 中国十七冶集团有限公司 A kind of hanging type steel structure high-altitude operation mobile platform fast construction method

Similar Documents

Publication Publication Date Title
CN103452311B (en) A kind of erection method of shaped steel suspended structural support frame
CN208518307U (en) A kind of fast pylon easy to install of adjustable platform width
CN115492353A (en) An assembled operating platform attached to the top of a steel pipe column and its attachment method
CN203347205U (en) Overhung scaffold
CN105822076A (en) Construction edge safety protection warning fence
CN205637641U (en) Limit safety protection warning rail is faced in construction
JP5152768B2 (en) Roof structure for temporary scaffold and method for assembling structure using the same
CN201439636U (en) Door type scaffold
CN104195954B (en) Overhead column erection without scaffolding platform and erection method thereof
CN107587708B (en) Foldable high-altitude construction platform and high-altitude construction method
CN205476389U (en) High altitude portable passes through bridge
CN220768786U (en) Movable scaffold with liftable guard rail
CN203701567U (en) Steel pipe scaffold provided with safety facility
CN209908385U (en) Electric power integration multipurpose ladder
CN208702123U (en) A kind of outer protective net of rotation fixed chute formula steel
KR200340325Y1 (en) Bridge inspection
CN205421892U (en) Even wall scaffold for building
CN219158611U (en) Assembled safety protection railing
CN215760608U (en) Stair guard rail
CN214062567U (en) Telescopic assembled guardrail
CN214576205U (en) Protector for construction
CN222184226U (en) Building floor opening protection device
CN217233005U (en) Reusable guardrail based on building economy
CN217782828U (en) Device for pre-connecting horizontal rod of scaffold
CN218950883U (en) Foldable protective railing for tower crane operation platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20221220