CN115492055A - Method for building dam by arranging waste rocks on dumping machine - Google Patents

Method for building dam by arranging waste rocks on dumping machine Download PDF

Info

Publication number
CN115492055A
CN115492055A CN202211185725.3A CN202211185725A CN115492055A CN 115492055 A CN115492055 A CN 115492055A CN 202211185725 A CN202211185725 A CN 202211185725A CN 115492055 A CN115492055 A CN 115492055A
Authority
CN
China
Prior art keywords
dam
soil
waste rocks
discharging
dumper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211185725.3A
Other languages
Chinese (zh)
Inventor
王斌
李建成
马跃林
王海林
冷明军
刘春�
张招荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tisco Lanxian Mining Co ltd
Original Assignee
Tisco Lanxian Mining Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tisco Lanxian Mining Co ltd filed Critical Tisco Lanxian Mining Co ltd
Priority to CN202211185725.3A priority Critical patent/CN115492055A/en
Publication of CN115492055A publication Critical patent/CN115492055A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/06Earth-fill dams; Rock-fill dams

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明属于矿山尾矿库废石筑坝技术领域,具体涉及一种排土机上排废石筑坝的方法。该方法是采用排土机上排废石直接堆筑坝体或者采用排土机上排废石备料,再利用挖机和汽车倒堆筑坝。区别于传统尾矿库废石筑坝采用汽车单一运输排弃筑坝的方法,本发明充分利用排土机上排功能实现上排废石筑坝,大大提高废石筑坝的效率,缩短了筑坝周期,降低了筑坝施工成本,使矿山全寿命周期内整体效益得到明显增益,在矿山尾矿库废石筑坝领域有着较好的推广前景。

Figure 202211185725

The invention belongs to the technical field of damming waste rocks in mine tailing ponds, and in particular relates to a method for damming waste rocks on a soil dumper. In this method, the dam body is directly stacked by discharging waste rocks on the soil dumper, or the waste rocks are discharged on the soil dumper to prepare materials, and then the excavator and the automobile are used to stack upside down to build the dam. Different from the traditional method of damming waste rocks in tailings dams by single transportation and discarding by automobiles, the present invention makes full use of the up-discharging function of the earthmover to realize the damming of waste rocks, which greatly improves the efficiency of damming waste rocks and shortens the construction time. The dam cycle reduces the cost of dam construction, and the overall benefit of the mine life cycle is significantly improved. It has a good promotion prospect in the field of mine tailings pond waste rock dam construction.

Figure 202211185725

Description

一种排土机上排废石筑坝的方法A method for building a dam by discharging waste rocks on a soil dumper

技术领域technical field

本发明属于矿山尾矿库废石筑坝技术领域,具体涉及一种排土机上排废石筑坝的方法。The invention belongs to the technical field of damming waste rocks in mine tailing ponds, and in particular relates to a method for damming waste rocks on a soil dumper.

背景技术Background technique

尾矿库筑坝按照选取的筑坝材料可分为尾矿堆积坝和废石筑坝;按照堆坝形式又可分为上游式堆坝法、下游式堆坝法、中线式堆坝法、高浓度尾矿堆坝法和水库式尾矿堆坝法;按照是否透水又可分为透水坝和不透水坝。采用尾矿旋流器分级水力堆积形成尾矿堆积坝是目前行业内较为常用的筑坝方法,且经济性高。但根据国内尾矿筑坝的工程实践经验,利用尾砂筑坝尾矿砂的粒级分布应不具有如下特征:Tailings reservoir dams can be divided into tailings accumulation dams and waste rock dams according to the selected dam materials; according to the dam formation form, it can be divided into upstream dams, downstream dams, midline dams, High-concentration tailings dam method and reservoir-type tailings dam method; according to whether it is permeable, it can be divided into permeable dams and impermeable dams. The formation of tailings accumulation dam by graded hydraulic accumulation of tailings cyclone is a relatively common dam construction method in the industry at present, and has high economic efficiency. However, according to the domestic engineering experience of tailings dam construction, the size distribution of tailings sand should not have the following characteristics:

尾矿平均粒径dp<30μm;Tailings average particle size dp<30μm;

-19μm含量多,一般>50%;-19μm has a lot of content, generally >50%;

+74μm含量少,一般<10%;+74μm content is less, generally <10%;

可用于筑坝的粒径+37μm含量≤30%Can be used for damming particle size +37μm content ≤30%

太钢袁家村铁矿作为国内目前最大的露天铁矿山,由于铁矿物嵌布粒度微细,细磨尾矿中+74μm含量仅为7.25%,尾矿的力学特性和渗透特性不满足筑坝安全性的要求,因此设计时采用废石筑坝工艺,废石来源为采场剥离的废石,废石平均运距7km。汽车从采场拉运废石分层填筑尾矿坝体,运输成本高,经济性差。尤其是后期随着尾矿坝逐渐升高,坝体长度不断增加,筑坝所需要的岩石量和筑坝废石费用不断增长,各分期坝筑坝所需要的废石量如表1所示。鉴于此,亟待开发一种降低废石筑坝施工费用的方法。Yuanjiacun Iron Mine of Taiyuan Iron and Steel Co., Ltd. is currently the largest open-pit iron mine in China. Due to the fine particle size of the iron minerals, the content of +74μm in the finely ground tailings is only 7.25%. Safety requirements, so waste rock dam construction technology is adopted in the design, the source of waste rock is the waste rock stripped from the stope, and the average transportation distance of waste rock is 7km. Cars pull waste rock from the stope to fill the tailings dam in layers, which has high transportation costs and poor economic efficiency. Especially in the later period, as the tailings dam gradually rises, the length of the dam body increases continuously, and the amount of rocks required for dam construction and the cost of dam waste rock continue to increase. The amount of waste rock required for dam construction in each stage is shown in Table 1 . In view of this, it is urgent to develop a method for reducing the cost of waste rock dam construction.

表1太钢袁家村铁矿尾矿各期坝筑坝岩石量Table 1. Taigang Yuanjiacun iron mine tailings dam rock volume in each stage

Figure BDA0003867596250000021
Figure BDA0003867596250000021

发明内容Contents of the invention

本发明为降低废石筑坝的施工成本,提供了一种排土机上排废石筑坝的方法。In order to reduce the construction cost of building a dam with waste rock, the invention provides a method for building a dam by discharging waste rock on an excavator.

为实现上述目的,本发明是通过以下技术方案来实现:To achieve the above object, the present invention is achieved through the following technical solutions:

一种排土机上排废石筑坝的方法,其包括排土模式一和排土模式二,所述排土模式一为采用排土机上排废石直接堆筑坝体,所述排土模式二为采用排土机上排废石备料,再利用挖机和汽车倒堆筑坝。A method for building a dam by discharging waste rocks on a soil-discharging machine, which includes a soil-discharging mode 1 and a soil-discharging mode 2. The soil-discharging mode 1 is to use waste rocks discharged from a soil-discharging machine to directly pile up a dam body, and the soil-discharging mode The second is to use the dumper to discharge the waste rock to prepare materials, and then use the excavator and the car to pile up the dam.

进一步地,所述排土机上排直接堆筑坝体的作业方式包括上排作业方式一和上排作业方式二;所述上排作业方式一为将排土机置于胶带机上游与坝体下游之间,排土机上排筑坝排岩;所述上排作业方式二为排土机位于胶带机的下游,排料臂旋转并穿过胶带机上部上排筑坝排岩。Further, the operation mode of directly stacking the dam body by the upper row of the earth-moving machine includes the first operation mode of the upper row and the second operation mode of the upper row; Between the downstream, the soil dumper discharges dams and discharges rocks; the second operation mode of the upper discharge is that the soil discharger is located downstream of the belt conveyor, and the discharge arm rotates and passes through the upper part of the belt conveyor to discharge rocks for dam construction.

进一步地,所述上排作业方式一的工艺参数为:排土机上排直接堆筑坝体的上排高度为12m,排土机与胶带机中心的安全距离为10-15m,胶带机中心与上排台阶坡脚的安全距离为30-35m,排土机与上排台阶坡脚的安全距离为5-10m。Further, the process parameters of the upper row operation mode one are: the upper row height of the upper row of the earth-moving machine directly stacking the dam body is 12m, the safety distance between the earth-moving machine and the center of the belt conveyor is 10-15m, and the center of the belt conveyor and the center of the belt conveyor are 12m. The safety distance between the slope toe of the upper row of steps is 30-35m, and the safety distance between the earth dumper and the slope toe of the upper row of steps is 5-10m.

进一步地,所述上排作业方式二的工艺参数为:排土机上排直接堆筑坝体的上排高度为12-15m,排土机与胶带机中心的安全距离为10-15m,胶带机中心与上排台阶坡脚的安全距离为5-10m。Further, the process parameters of the upper row operation mode two are: the upper row height of the upper row of the earth-moving machine directly stacking the dam body is 12-15m, the safety distance between the earth-moving machine and the belt conveyor center is 10-15m, and the belt conveyor The safe distance between the center and the foot of the upper row of steps is 5-10m.

与现有技术相比,本发明的有益效果如下:Compared with the prior art, the beneficial effects of the present invention are as follows:

本发明利用排土机上排功能进行矿山尾矿库废石筑坝,提供了一种排土机上排废石堆筑坝体的方法,有益于提高废石筑坝的效率,缩短了筑坝周期,降低了废石筑坝施工成本,使矿山全寿命周期内整体效益得到明显增益,在矿山尾矿库废石筑坝领域有着姣好的推广前景。The present invention utilizes the up-discharging function of the earth-moving machine to build a dam with waste rocks in mine tailing ponds, and provides a method for stacking waste rocks on the earth-moving machine to build a dam body, which is beneficial to improving the efficiency of damming waste rocks and shortening the dam-building period , reduces the construction cost of waste rock dam construction, and makes the overall benefit of the mine life cycle significantly increased, and has a good promotion prospect in the field of waste rock dam construction of mine tailings ponds.

附图说明Description of drawings

图1为本发明排土机上排作业方式一(跟随式上排筑坝)的示意图;Fig. 1 is the schematic diagram of the upper row operation mode one (following type upper row dam building) of the earth dumper of the present invention;

图2为本发明排土机上排作业方式一的现场照片(太重排土机,箭头代表料流方向);Fig. 2 is the on-the-spot photograph (too heavy earth-moving machine, the arrow represents the material flow direction) of the present invention's upper row operation mode one;

图3为本发明排土机上排作业方式一的现场照片(山特维克排土机,箭头代表料流方向);Fig. 3 is the on-the-spot photograph (Sandvik earthmoving machine, arrow represents material flow direction) of the present invention's earthmoving machine upper row operation mode one;

图4为本发明排土机上排作业方式二的示意图;Fig. 4 is the schematic diagram of the second row operation mode of the earth moving machine of the present invention;

图5为本发明排土机上排作业方式二的现场照片(箭头代表料流方向);Fig. 5 is the on-the-spot photograph (arrow represents material flow direction) of the present invention's earthmoving machine upper row operation mode two;

图6为本发明太钢袁家村铁矿尾矿采用排土机上排作业方式一筑四期坝的示意图;Fig. 6 is a schematic diagram of building a four-stage dam in the first stage of the Taiyuan Iron and Steel Co., Ltd. Yuanjiacun iron ore tailings using the upper discharge operation mode of the earth dumper;

图7为本发明太钢袁家村铁矿尾矿采用排土机上排作业方式二筑四期坝的示意图;Fig. 7 is the schematic diagram of the second construction of the fourth-phase dam in the method of discharging the tailings of the Yuanjiacun Iron Mine of Taiyuan Iron and Steel Co.

图8为本发明太钢袁家村铁矿尾矿矿采用第二种排土模式筑四期坝的示意图。Fig. 8 is a schematic diagram of building the fourth-stage dam by adopting the second earth-discharging mode in the Yuanjiacun iron ore tailings mine of Taiyuan Iron and Steel Co., Ltd. according to the present invention.

(图中①为第一种排土模式下采用排土机上排作业方式一排弃形成的坝体范围;②为第一种排土模式下采用排土机上排作业方式二排弃形成的坝体范围;③第二种排土模式下排弃形成的坝体范围。)(In the figure ① is the range of the dam body formed by using the up-discharging operation method of the soil-discharging machine in the first type of soil-discharging mode; ② is the range of the dam formed by using the up-discharging operation method of the soil-discharging machine in the second type of disposal under the first type of soil-discharging mode body range; ③The range of the dam body formed by the discharge under the second soil discharge mode.)

具体实施方式detailed description

为了便于理解本发明,下面将对本发明进行更全面的描述。但是,本发明可以以许多不同的形式来实现,并不限于本文所描述的实施例。相反地,提供这些实施例的目的是使对本发明的公开内容的理解更加透彻全面。In order to facilitate the understanding of the present invention, the following will describe the present invention more fully. However, the present invention can be embodied in many different forms and is not limited to the embodiments described herein. On the contrary, these embodiments are provided to make the understanding of the disclosure of the present invention more thorough and comprehensive.

不同于单一汽车开拓运输方式,本发明采用汽车—半移动破碎—胶带机联合开拓运输方式进行废石筑坝,提供了一种利用排土机上排功能堆筑废石坝体的方法,具体包括:两种排土模式,第一种排土模式即排土机直接上排筑坝,第二种排土模式,即排土机就近落料,再利用挖机和汽车二次倒运填筑坝体。Different from the single vehicle development and transportation mode, the present invention adopts the vehicle-semi-mobile crushing-belt machine combined development and transportation mode to carry out waste rock dam building, and provides a method for stacking waste rock dams by using the up-discharging function of the soil dumper, which specifically includes : Two dumping modes, the first dumping mode is that the dumping machine directly lifts up the dam to build the dam, and the second dumping mode is that the dumping machine dumps the material nearby, and then uses the excavator and the car to carry it back to fill the dam body.

进一步地,排土机上排直接堆筑坝体的作业方式包括上排作业方式一和上排作业方式二;所述上排作业方式一为排土机位于胶带机上游与坝体下游之间,排土机跟随式上排筑坝排岩,排土机排岩方向与坝体发展方向整体一致(参见图1与图2);所述上排作业方式二为排土机位于胶带机的下游,排料臂旋转并穿过胶带机上部上排筑坝排岩(参见图4)。Further, the operation mode of directly stacking the dam body by the upper row of the earth-moving machine includes the first operation mode of the upper row and the second operation mode of the upper row; The soil dumper follows the upper row of the dam to discharge rocks, and the direction of the rock removal by the soil dumper is generally consistent with the development direction of the dam body (see Figure 1 and Figure 2); , the discharge arm rotates and passes through the upper part of the belt conveyor to discharge rocks (see Figure 4).

以下将结合具体示例,对本发明提供的排土机上排废石筑坝的方法进行详细阐述。太钢袁家村铁矿采用废石下游式筑坝工艺,尾矿库与排土场毗邻布置,排土场位于尾矿坝下游。初期坝于2012年8月建成投用,2018年开始建设四期坝(坝顶标高1690m)。下盘排土场胶带排岩系统于2017年建成投用,采用矩形排土工艺,其中尾段P01胶带机平行于坝轴线布置。以太钢袁家村铁矿尾矿四期坝筑坝为例,具体示例如下:In the following, the method for damming the waste rock on the earth moving machine provided by the present invention will be described in detail in conjunction with specific examples. Taiyuan Iron and Steel Yuanjiacun Iron Mine adopts waste rock downstream dam construction technology, and the tailings pond is adjacent to the dump site, and the dump site is located downstream of the tailings dam. The initial dam was completed and put into use in August 2012, and the construction of the fourth phase dam (dam crest elevation 1690m) began in 2018. The rubber belt rock drainage system of the footwall dump site was completed and put into use in 2017, using a rectangular soil drainage process, in which the P01 belt conveyor at the tail section is arranged parallel to the axis of the dam. Taking the dam construction of the fourth-stage dam of iron mine tailings in Yuanjiacun, Taiyuan Iron and Steel Co., Ltd. as an example, the specific examples are as follows:

基准例Benchmark example

采用传统单一汽车直排废石的方式堆筑四期坝,共需要排弃岩石630万t,汽车运输的距离为7km,四期坝筑坝岩石所需要的运输费用共计4021.81万元。The fourth phase of the dam needs to be piled up in the traditional single-vehicle direct discharge of waste rocks. A total of 6.3 million tons of rocks need to be discharged, and the transportation distance by car is 7km.

实施例Example

采用排土机上排废石的方法堆筑四期坝,包括以下步骤:The fourth phase of the dam is built by using the method of discharging waste rocks on the soil dumper, including the following steps:

步骤1:采用排土机按照上排作业方式一进行上排废石筑坝,达到排土机上排高度12m时,停止筑坝,形成的坝体轮廓参见图6,具体排土工艺参数及安全距离参见表2;Step 1: Use the earth dumper to carry out the waste rock dam construction according to the upper row operation mode 1. When the upper row height of the earth dumper reaches 12m, stop the dam construction. The outline of the formed dam body is shown in Figure 6. The specific soil removal process parameters and safety See Table 2 for the distance;

步骤2:采用排土机按照上排作业方式二继续进行上排废石筑坝,达到排土机上排高度12m时,停止筑坝,形成的坝体轮廓参见图7,具体排土工艺参数及安全距离参见表2;Step 2: Use the soil dumper to continue to discharge waste rocks according to the operation method 2 of the top row, and stop damming when the top row height of the soil dumper reaches 12m. The outline of the formed dam body is shown in Figure 7. The specific soil discharge process parameters and See Table 2 for safety distance;

步骤3:超出排土机上排高度或最大排弃宽度的堆筑工作采用第二种排土模式,即采用排土机就近落料,再利用挖机和汽车二次倒运,最终形成四期坝(参见图8)。Step 3: For the stacking work that exceeds the upper row height of the dumper or the maximum dumping width, the second dumping mode is adopted, that is, the dumper is used to drop the material nearby, and then the excavator and the car are used for secondary transportation, and finally the fourth-stage dam is formed (See Figure 8).

与基准例相比,四期坝废石筑坝所需要的岩石量约有41%可通过排土机上排作业方式一直接排弃形成,18%的岩石量可通过排土机上排作业方式二直接排弃形成,剩余41%的岩石量通过挖机和汽车倒堆完成。Compared with the reference example, about 41% of the rock volume required for the waste rock dam construction of the fourth-stage dam can be directly discharged through the first discharge operation of the soil dumper, and 18% of the rock can be formed through the second discharge operation of the soil dumper. The remaining 41% of the rock volume was formed by direct discharge, and the remaining 41% of the rock volume was completed by dumping machines and cars.

本实施例排土机上排废石筑坝过程中岩石运输费用可降低1920.2万元,费用降低率为47.73%。相比传统单一汽车直排废石筑坝施工工法,废石筑坝岩石运输费用降低接近一半。In this embodiment, the cost of rock transportation can be reduced by 19.202 million yuan during the process of discharging waste rocks on the earth-moving machine to build a dam, and the cost reduction rate is 47.73%. Compared with the traditional single-vehicle direct discharge waste rock dam construction method, the cost of waste rock dam rock transportation is reduced by nearly half.

表2排土机两种上排作业方式的排土工艺参数及安全距离Table 2. The technological parameters and safety distances of the two types of top-discharging operation methods of the soil-discharging machine

Figure BDA0003867596250000051
Figure BDA0003867596250000051

Figure BDA0003867596250000061
Figure BDA0003867596250000061

以上所述实施例的各技术特征可以进行任意的组合,为使描述简洁,未对上述实施例中的各个技术特征所有可能的组合都进行描述,然而,只要这些技术特征的组合不存在矛盾,都应当认为是本说明书记载的范围。The various technical features of the above-mentioned embodiments can be combined arbitrarily. To make the description concise, all possible combinations of the various technical features in the above-mentioned embodiments are not described. However, as long as there is no contradiction in the combination of these technical features, should be considered as within the scope of this specification.

以上所述实施例仅表达了本发明的几种实施方式,其描述较为具体和详细,但并不能因此而理解为对发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。因此,本发明专利的保护范围应以所附权利要求为准。The above-mentioned embodiments only express several implementation modes of the present invention, and the descriptions thereof are relatively specific and detailed, but should not be construed as limiting the patent scope of the invention. It should be pointed out that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent for the present invention should be based on the appended claims.

Claims (4)

1.一种排土机上排废石筑坝的方法,其特征在于:包括排土模式一和排土模式二,所述排土模式一为采用排土机上排废石直接堆筑坝体,所述排土模式二为采用排土机上排废石备料,再利用挖机和汽车倒堆筑坝。1. A method for building a dam by discharging waste rocks on a soil-discharging machine, characterized in that: it comprises a soil-discharging mode one and a soil-discharging mode two, and the described soil-discharging mode one is to directly pile up a dam body by means of discharging waste rocks on the soil-discharging machine, The second soil discharge mode is to use a soil dumper to discharge waste rocks to prepare materials, and then use an excavator and a car to stack upside down to build a dam. 2.根据权利要求1所述的一种排土机上排废石筑坝的方法,其特征在于:所述排土机上排废石直接堆筑坝体的作业方式包括上排作业方式一和上排作业方式二;所述上排作业方式一为排土机位于胶带机上游与坝体下游之间,排土机跟随式上排筑坝排岩;所述上排作业方式二为排土机位于胶带机的下游,排料臂旋转并穿过胶带机上部上排筑坝排岩。2. A method for building a dam by discharging waste rocks on the earthmoving machine according to claim 1, characterized in that: the operation mode of directly stacking the dam body by discharging waste rocks on the earth moving machine includes upper row operation mode one and upper The second row operation method; the first operation method of the upper row is that the soil dumper is located between the upstream of the belt conveyor and the downstream of the dam body, and the soil dumper follows the upper row of the dam to discharge rocks; the second operation method of the upper row is the soil dumper Located downstream of the belt conveyor, the discharge arm rotates and passes through the upper part of the belt conveyor to discharge the dam and discharge rock. 3.根据权利要求2所述的一种排土机上排废石筑坝的方法,其特征在于:所述上排作业方式一的工艺参数为:排土机上排直接堆筑坝体的上排高度为12m,排土机与胶带机中心的安全距离为10-15m,胶带机中心与上排台阶坡脚的安全距离为30-35m,排土机与上排台阶坡脚的安全距离为5-10m。3. The method for constructing a dam by discharging waste rocks on the top of the earth-moving machine according to claim 2, characterized in that: the process parameters of the first row operation mode are: the top row of the top row of the earth-moving machine directly stacks the top row of the dam body The height is 12m, the safety distance between the earthmoving machine and the center of the belt conveyor is 10-15m, the safety distance between the center of the belt conveyor and the foot of the upper step is 30-35m, and the safety distance between the earthmoving machine and the foot of the upper step is 5 -10m. 4.根据权利要求2所述的一种排土机上排废石筑坝的方法,其特征在于:所述上排作业方式二的工艺参数为:排土机上排直接堆筑坝体的上排高度为12m,排土机与胶带机中心的安全距离为10-15m,胶带机中心与上排台阶坡脚的安全距离为5-10m。4. The method for building a dam by discharging waste rocks on the top of the earth-moving machine according to claim 2, characterized in that: the process parameters of the second operation mode of the upper row are: the upper row of the upper row of the earth-moving machine directly piles up the dam body The height is 12m, the safety distance between the dumper and the center of the belt conveyor is 10-15m, and the safety distance between the center of the belt conveyor and the slope foot of the upper row of steps is 5-10m.
CN202211185725.3A 2022-09-27 2022-09-27 Method for building dam by arranging waste rocks on dumping machine Pending CN115492055A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211185725.3A CN115492055A (en) 2022-09-27 2022-09-27 Method for building dam by arranging waste rocks on dumping machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211185725.3A CN115492055A (en) 2022-09-27 2022-09-27 Method for building dam by arranging waste rocks on dumping machine

Publications (1)

Publication Number Publication Date
CN115492055A true CN115492055A (en) 2022-12-20

Family

ID=84473093

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211185725.3A Pending CN115492055A (en) 2022-09-27 2022-09-27 Method for building dam by arranging waste rocks on dumping machine

Country Status (1)

Country Link
CN (1) CN115492055A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004031493A1 (en) * 2002-10-02 2004-04-15 Vasilios Stenos Machinery for ejection of soil
CN101929160A (en) * 2009-06-24 2010-12-29 鞍钢集团矿业公司 Method for building impermeable tailings dams with high scattered piles by waste rocks
CN204999164U (en) * 2015-09-28 2016-01-27 云南省小龙潭矿务局机修总厂 On -vehicle portable sealing -tape machine
CN110984182A (en) * 2019-12-10 2020-04-10 太原钢铁(集团)有限公司 Operation method of dumping machine
CN113047840A (en) * 2021-04-27 2021-06-29 车兆学 Stripping semi-continuous reverse stacking process for open pit coal mine

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004031493A1 (en) * 2002-10-02 2004-04-15 Vasilios Stenos Machinery for ejection of soil
CN101929160A (en) * 2009-06-24 2010-12-29 鞍钢集团矿业公司 Method for building impermeable tailings dams with high scattered piles by waste rocks
CN204999164U (en) * 2015-09-28 2016-01-27 云南省小龙潭矿务局机修总厂 On -vehicle portable sealing -tape machine
CN110984182A (en) * 2019-12-10 2020-04-10 太原钢铁(集团)有限公司 Operation method of dumping machine
CN113047840A (en) * 2021-04-27 2021-06-29 车兆学 Stripping semi-continuous reverse stacking process for open pit coal mine

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
沃廷枢: "《尾矿库手册》", 31 August 2013, 冶金工业出版社, pages: 55 - 56 *
贺茂坤,张伟,徐利辉: "露天矿山联合排土应用研究", 中国矿山工程, vol. 48, no. 1, pages 12 - 15 *

Similar Documents

Publication Publication Date Title
CN101632993B (en) Method for building tailings dam through adoption of mine dumping
CN101215976B (en) Down-hole gangue pump packing system and method
CN201606111U (en) Crushing, pumping and filling system under gangue mine
CN103216238B (en) A kind of Opencut coal mine mining technique
CN103397645B (en) A kind of dry heap arranges with wet the tailings pile discharge method combined
CN108941146B (en) Waste rock and full tailings mixing and stacking method
CN105735238A (en) Dump safety control method under collapsible loess foundation condition
CN105780784A (en) Method suitable for conducting dry heaping on fine grained tailings on flat ground or beside mountain
CN110107298A (en) Coal mine selecting, which is filled, stays integrated mining system
CN105672318B (en) A fine-grained tailings mold bag classification filling system
CN115492055A (en) Method for building dam by arranging waste rocks on dumping machine
CN112682042A (en) Method for transporting and dumping open pit coal mine
CN1952349A (en) Mining method for replacement of pressed coal under village by waste rock
CN114294056B (en) Method for combined disposal of waste stone and dry tailings in open pit
CN104763467B (en) Obturation and its placement method and system for Hazard in Deep Metal Mines goaf
CN105626076B (en) It is a kind of to draw bucket shovel zigzag working berm high-efficiency mining method
CN110984182B (en) Operation method of dumping machine
CN201165881Y (en) Downhole gangue pumping and filling system
CN104475215B (en) A kind of integral manufacturing technique of rock-fill dams high standard Transition Materials
CN203783634U (en) Mineral powder recycling structure for underground mine
CN217712669U (en) Fill support and add high pressure and fill thick liquid and jointly fill structure
CN202544921U (en) Gangue discharging device in rock gangway rapid tunneling process
CN114704257A (en) A continuous stripping process for open-pit coal mines under the loess mao landform
CN205591225U (en) Grading filling system for fine-grained tailing mould bags
CN219260872U (en) Tailing pond structure capable of guaranteeing length of dry beach

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20221220