CN115450229A - Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry - Google Patents

Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry Download PDF

Info

Publication number
CN115450229A
CN115450229A CN202211051951.2A CN202211051951A CN115450229A CN 115450229 A CN115450229 A CN 115450229A CN 202211051951 A CN202211051951 A CN 202211051951A CN 115450229 A CN115450229 A CN 115450229A
Authority
CN
China
Prior art keywords
pipeline
slurry
groove
construction method
method based
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211051951.2A
Other languages
Chinese (zh)
Inventor
郭卓明
刘振兴
王洪江
肖粤秀
王晓彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Original Assignee
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Municipal Engineering Group Co Ltd filed Critical Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority to CN202211051951.2A priority Critical patent/CN115450229A/en
Publication of CN115450229A publication Critical patent/CN115450229A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/12Back-filling of foundation trenches or ditches
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/0075Uses not provided for elsewhere in C04B2111/00 for road construction
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0023Slurry
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0025Adhesives, i.e. glues

Abstract

The invention discloses a pipeline trench excavation backfill construction method based on retaining wall slurry in-situ curing, which comprises the following steps of: the method comprises the steps of excavating a groove on a current road, excavating, injecting slurry into the groove and enabling the slurry liquid level to be always located on the bottom surface of the pavement of the current road until the groove is excavated to a design elevation; hoisting and lowering the pipe section to a preset position in the groove, and enabling the slurry liquid level to be always positioned on the bottom surface of the pavement of the existing road; adding a curing agent into the slurry in the groove and stirring and mixing the curing agent and the slurry to form fluid cured soil; and after the fluid solidified soil is hardened and reaches the design strength, constructing a road restoration pavement on the hardened fluid solidified soil. The invention has the advantages that: the method has the characteristics of reducing the quantity of earthwork outward transportation engineering, being convenient and quick to construct, being reliable in groove backfill quality, saving engineering cost and the like.

Description

Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry
Technical Field
The invention relates to the technical field of pipeline groove excavation and backfilling, in particular to a pipeline groove excavation and backfilling construction method based on wall protection slurry in-situ curing.
Background
Along with the development and construction of cities, municipal pipeline is newly built and rebuilt increasingly, and pipeline groove excavation is everywhere visible. In the traditional pipeline groove excavation construction, a pile plate type supporting structure and an inner supporting system are adopted, the construction process is complicated, and the assembly, disassembly and disturbance of components are frequent; the quantity of earthwork external transportation engineering is large, the earthwork is difficult to place, and dust generated in the transportation process pollutes the environment; the grooves need to be compacted in a layering mode during backfilling, the processes are multiple, additional disturbance is easily caused to a newly-arranged pipeline, the construction speed is low, and the backfilling quality is difficult to guarantee.
Disclosure of Invention
The invention aims to provide a pipeline trench excavation backfill construction method based on wall protection slurry in-situ solidification, according to the defects of the prior art, slurry is injected into a trench while the trench is excavated, a pipeline is hoisted into the slurry in the trench, and a curing agent is added into the slurry to form hardened fluid-state solidified soil, so that the backfill quality of the trench can be effectively improved.
The purpose of the invention is realized by the following technical scheme:
a pipeline trench excavation backfill construction method based on wall protection slurry in-situ curing is characterized by comprising the following steps:
(S1) excavating a groove on a current road, and excavating, injecting slurry into the groove, and enabling the slurry liquid level to be always positioned on the bottom surface of the road surface of the current road until the groove is excavated to a designed elevation;
(S2) hoisting and lowering the pipe section to a preset position in the groove, and enabling the slurry liquid level to be always located on the bottom surface of the road surface of the existing road;
(S3) adding a curing agent into the slurry in the groove and stirring and mixing the curing agent and the slurry to form fluid cured soil;
and (S4) after the fluid solidified soil is hardened and reaches the designed strength, applying a road restoration pavement on the hardened fluid solidified soil.
Preparing the slurry by utilizing soil generated by excavating the groove, wherein the preparation proportion of the slurry is as follows: water to soil = 10.
The curing agent comprises the following components in percentage by weight: 40-60% of cement and 20-35% of Al rich in activity 2 O 3 And SiO 2 2 to 3 percent of surface modifier and 5 to 10 percent of activity excitant.
The preparation proportion of the flow state solidified soil is as follows: slurry curing agent =1, 0.5-0.7.
The pipeline section comprises pipeline and pipeline foundation just the pipeline passes through the pipeline staple bolt and the crab-bolt is fixed on the pipeline foundation, wherein, the pipeline foundation is followed the length direction interval arrangement of pipeline has a plurality of, seted up on the pipeline foundation with the arc recess of pipeline bottom looks adaptation, place the pipeline bottom in the arc recess, the pipeline staple bolt hug closely in pipeline top outer wall sets up and passes through the crab-bolt is fixed on the pipeline foundation.
The invention has the advantages that:
1. static pressure generated by slurry is utilized in the process of trench excavation, mud skin is formed on the trench wall, the trench wall can be prevented from collapsing, the water permeability of the trench wall is reduced, the problems that the construction process of the traditional pile-plate type enclosure structure and the inner support system is complicated, and the assembly and disassembly disturbance is frequent are effectively avoided, and the method has the advantage of convenient and rapid construction;
2. the earthwork excavated on site can be used as a preparation raw material of the breast wall slurry and the fluidized solidified soil, so that the external transportation engineering quantity of the earthwork is reduced, and the problems of difficult placement of the abandoned soil, dust emission, environmental pollution and the like are relieved to a certain extent;
3. after the pipeline is installed in place, curing agents are added into the groove retaining wall slurry and stirred to form fluid-state solidified soil, in-situ solidification backfilling is achieved, large tamping and rolling equipment is not needed on site, multiple procedures such as layering compaction backfilling and the like are not needed, additional damage to the pipeline in construction machines is reduced, the method has the advantages of being flexible and flexible in construction, high in construction speed, reliable in backfilling quality and the like, engineering quality can be guaranteed to the maximum extent, and engineering cost is reduced.
Drawings
FIG. 1 is a schematic diagram of the step S1 of the construction method for excavating and backfilling the pipeline trench according to the invention;
FIG. 2 is a schematic diagram of step S2 of the pipeline trench excavation and backfilling construction method of the invention;
FIG. 3 is a schematic diagram of the step S3 of the construction method for excavating and backfilling the pipeline trench according to the present invention;
FIG. 4 is a schematic diagram of the pipeline trench excavation backfill construction method of the invention in step S4;
FIG. 5 is a schematic cross-sectional view of a duct and duct foundation of the present invention;
FIG. 6 is a schematic longitudinal cross-section of the pipe and pipe foundation of the present invention;
FIG. 7 is a schematic flow chart of a backfill construction method for a premixed flow state solidified soil foundation trench in the prior art.
Detailed Description
The features of the present invention and other related features are described in further detail below by way of example in conjunction with the following drawings to facilitate understanding by those skilled in the art:
as shown in fig. 1 to 6, reference numerals 1 to 10 denote a current road pavement 1, a current road subgrade 2, a trench 3, slurry 4, a pipeline 5, a pipeline foundation 6, an anchor bolt 7, a pipeline anchor ear 8, fluid solidified soil 9 and a road restoration pavement 10, respectively.
As shown in fig. 7, the backfill construction method for the premixed flow state solidified soil foundation trench in the prior art mainly comprises the following steps:
s1: preparing solidified soil, namely determining a solidified soil feeding mode, and feeding by adopting a stirring station or building a station on site;
s2: cleaning a foundation trench, namely cleaning the bottom of the foundation trench;
s3: constructing a gravel drainage ditch;
s4: building templates in a layered and sectional manner according to a solidified soil filling process;
s5: pouring solidified soil in layers;
s6: and after the lower layer construction is finished, the surface is strickled off, when the strength of the solidified soil reaches the strength of the human body, the next layer of solidified soil construction is carried out, and after the surface layer construction is finished, the surface is strickled off by using a special tool.
S7: and (4) protecting a finished product on site.
S8: curing the solidified soil.
The construction method has the advantages that:
1. the characteristics of fluidity and self-sealing property of the fluidized solidified soil are utilized, the chute or the pumping is used for backfilling the foundation trench, vibration is not needed, the construction process is convenient, and the problems of high difficulty and long backfilling period of the traditional backfilling construction are solved;
2. the fluid-state solidified soil is constructed in a layering way, the layering construction joint surface can be well combined without chiseling, a construction joint cannot be formed, and the backfilling quality can be guaranteed through layering construction and maintenance.
The disadvantages of this method are:
1. the templates and the supporting system thereof need to be built layer by layer, and the building, the inspection, the removal and the like of the templates still need to occupy a certain time;
2. the fluidized solidified soil needs to be fed by a mixing station or a field station, so that the construction site is occupied, and the transportation and transfer cost is high;
3. before backfilling, a supporting structure is still required to excavate the trench.
The embodiment is as follows: as shown in fig. 1 to 6, the present embodiment relates to a pipeline trench excavation backfill construction method based on in-situ curing of retaining wall slurry, and the construction method includes the following steps:
(S1) as shown in figure 1, excavating a groove 3 on the current road from top to bottom, and injecting slurry 4 into the groove 3 while excavating the groove 3 until the groove 3 is excavated to the designed elevation. Specifically, according to the design pipe position, construction layout is performed on the current road surface 1, the trench excavation width is determined, a slurry pool is arranged, and slurry 4 is configured by using the trench excavation soil body, in this embodiment, the preparation proportion of the slurry 4 may be: soil =10, and the practical application determines a proper proportion according to soil layer properties after tests. The slurry 4 is adopted to protect the wall of the excavated groove 3, the slurry 4 is replenished and injected along with the increase of the excavation depth, the liquid level of the slurry is always positioned at the bottom surface of the current road pavement 1 (the top surface of the current road subgrade 2), the wall of the groove is prevented from peeling and collapsing, the seepage inside and outside the wall of the groove is cut off, and the stability of the wall of the groove is ensured until the groove 3 is excavated to the designed elevation.
(S2) after the groove 3 is excavated to the designed elevation, hoisting a pipe section consisting of a pipeline 5 and a pipeline foundation 6 and lowering the pipe section into the groove 3 filled with the slurry 4, slowly adjusting the position and the elevation of the pipeline, and avoiding collision and disturbance of the wall of the groove in the hoisting process to influence the overall stability of the groove 3, wherein the pipeline foundation 6 is positioned on the bottom surface of the groove 3 in the embodiment. In the process of lowering the pipe section, the redundant slurry 4 in the groove 3 is timely pumped out, so that the liquid level is always positioned on the bottom surface of the road surface 1 of the current situation. As shown in fig. 5 and 6, the pipeline 5 is fixed on the pipeline foundation 6 through the pipeline hoop 8 and the anchor bolt 7, wherein the pipeline foundation 6 is provided with a plurality of parts along the length direction of the pipeline 5 at intervals, the pipeline foundation 6 is provided with an arc-shaped groove matched with the bottom of the pipeline 5, the bottom of the pipeline 5 is placed in the arc-shaped groove, and the pipeline hoop 8 is tightly attached to the outer wall of the top of the pipeline 5 and is fixed on the pipeline foundation 6 through the anchor bolt 7 arranged on two sides of the arc-shaped groove. The pipe sections can be manufactured in factories and then transported to the site or assembled directly on the site, and the pipeline foundation 6 is of a concrete structure and can be prefabricated or cast in situ.
(S3) as shown in figure 3, after the pipe section is put down in place, adding a curing agent into the slurry 4 in the groove 3, fully stirring the curing agent and the slurry 4 to form fluid solidified soil 9, and rapidly filling a gap between the pipe section and the groove 3 by utilizing the fluidity and the self-sealing property of the fluid solidified soil 9 positioned at the bottom surface of the road surface 1 to finish the groove backfilling. The fluid solidified soil 9 should be pre-prepared, and the slurry solidification can be carried out according to the proportion after the proportion of the slurry 4, the solidifying agent and the water is determined. Wherein the curing agent is CaO and active Al 2 O 3 And SiO 2 The inorganic hydraulic cementing material as main component consists of the following components in proportion: 40-60% of cement and 20-35% of Al rich in activity 2 O 3 And SiO 2 2 to 3 percent of surface modifier, 5 to 10 percent of activity excitant and the like. The preparation proportion of the fluid solidified soil 9 can be as follows: the slurry and curing agent =1 and the ratio is 0.5-0.7, and the actual application needs to be determined according to soil layer properties after tests.
(S4) as shown in FIG. 4, after the fluid solidified soil 9 is gradually hardened and reaches the designed strength, a road restoration pavement 10 is constructed on the hardened fluid solidified soil 9.
The embodiment also has the following beneficial effects: the defects that in the traditional pipeline groove excavation and backfilling construction process, the construction process of a pile plate type enclosure structure and an inner support system is complex, the assembly and disassembly disturbance is frequent, the earthwork outward transport engineering quantity is large, the compaction quality is difficult to guarantee, the construction period is long, the environmental protection problem is obvious and the like are overcome, and the method has the characteristics of reducing the earthwork outward transport engineering quantity, being convenient and rapid to construct, being reliable in groove backfilling quality, saving the engineering cost and the like.
Although the conception and the embodiments of the present invention have been described in detail with reference to the drawings, those skilled in the art will recognize that various changes and modifications can be made therein without departing from the scope of the appended claims, and therefore, they are not to be considered repeated herein.

Claims (5)

1. A pipeline groove excavation backfill construction method based on wall protection slurry in-situ solidification is characterized by comprising the following steps:
(S1) excavating a groove on a current road, and excavating, injecting slurry into the groove, and enabling the slurry liquid level to be always positioned on the bottom surface of the road surface of the current road until the groove is excavated to a designed elevation;
(S2) hoisting and lowering the pipe section to a preset position in the groove, and enabling the slurry liquid level to be always located on the bottom surface of the road surface of the existing road;
(S3) adding a curing agent into the slurry in the groove and stirring and mixing the curing agent and the slurry to form fluid cured soil;
and (S4) after the fluid state solidified soil is hardened and reaches the design strength, constructing a road restoration pavement on the hardened fluid state solidified soil.
2. The pipeline trench excavation backfill construction method based on in-situ curing of the retaining wall slurry, as claimed in claim 1, wherein: preparing the slurry by utilizing soil generated by excavating the groove, wherein the preparation proportion of the slurry is as follows: water to soil = 10.
3. The pipeline trench excavation backfill construction method based on the in-situ curing of the retaining wall slurry as claimed in claim 1, characterized in that: the curing agent comprises the following components in percentage by weight: 40-60% of cement and 20-35% of Al rich in activity 2 O 3 And SiO 2 2 to 3 percent of surface modifier and 5 to 10 percent of activity excitant.
4. The pipeline trench excavation backfill construction method based on the in-situ curing of the retaining wall slurry as claimed in claim 1, characterized in that: the preparation proportion of the fluid solidified soil is as follows: slurry curing agent = 1.
5. The pipeline trench excavation backfill construction method based on the in-situ curing of the retaining wall slurry as claimed in claim 1, characterized in that: the pipeline section comprises pipeline and pipeline foundation just the pipeline passes through the pipeline staple bolt and the crab-bolt is fixed on the pipeline foundation, wherein, the pipeline foundation is followed the length direction interval arrangement of pipeline has a plurality of, seted up on the pipeline foundation with the arc recess of pipeline bottom looks adaptation, place the pipeline bottom in the arc recess, the pipeline staple bolt hug closely in pipeline top outer wall sets up and passes through the crab-bolt is fixed on the pipeline foundation.
CN202211051951.2A 2022-08-31 2022-08-31 Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry Pending CN115450229A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211051951.2A CN115450229A (en) 2022-08-31 2022-08-31 Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211051951.2A CN115450229A (en) 2022-08-31 2022-08-31 Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry

Publications (1)

Publication Number Publication Date
CN115450229A true CN115450229A (en) 2022-12-09

Family

ID=84301716

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211051951.2A Pending CN115450229A (en) 2022-08-31 2022-08-31 Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry

Country Status (1)

Country Link
CN (1) CN115450229A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4329083A (en) * 1977-01-26 1982-05-11 Societe Soletanche Methods of laying underground conduits
CN104895174A (en) * 2015-06-02 2015-09-09 杭州江润科技有限公司 Construction method of large-diameter rain sewage pipeline assembling type component structure
CN107572956A (en) * 2017-09-11 2018-01-12 王继忠 A kind of premixing fluidised form solidified earth
CN107816047A (en) * 2017-11-01 2018-03-20 王继忠 The method that backfill construction is carried out using premixing fluidised form solidified earth
CN207921480U (en) * 2017-12-27 2018-09-28 上海三凯建设管理咨询有限公司 A kind of fixing hoop for the fixed multi-pipeline for being embedded in underground
CN112359848A (en) * 2020-10-30 2021-02-12 北京住总第六开发建设有限公司 Construction method for backfilling fertilizer groove by using solidified soil
KR20210043402A (en) * 2019-10-13 2021-04-21 김건 The safty construction method of the side ditch using the hardening agent
CN114086539A (en) * 2021-11-24 2022-02-25 安徽理工大学环境友好材料与职业健康研究院(芜湖) Equipment and method for in-situ curing of building waste slurry
CN114411766A (en) * 2022-03-01 2022-04-29 中煤江南建设发展集团有限公司 Construction method of enclosure structure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4329083A (en) * 1977-01-26 1982-05-11 Societe Soletanche Methods of laying underground conduits
CN104895174A (en) * 2015-06-02 2015-09-09 杭州江润科技有限公司 Construction method of large-diameter rain sewage pipeline assembling type component structure
CN107572956A (en) * 2017-09-11 2018-01-12 王继忠 A kind of premixing fluidised form solidified earth
CN107816047A (en) * 2017-11-01 2018-03-20 王继忠 The method that backfill construction is carried out using premixing fluidised form solidified earth
CN207921480U (en) * 2017-12-27 2018-09-28 上海三凯建设管理咨询有限公司 A kind of fixing hoop for the fixed multi-pipeline for being embedded in underground
KR20210043402A (en) * 2019-10-13 2021-04-21 김건 The safty construction method of the side ditch using the hardening agent
CN112359848A (en) * 2020-10-30 2021-02-12 北京住总第六开发建设有限公司 Construction method for backfilling fertilizer groove by using solidified soil
CN114086539A (en) * 2021-11-24 2022-02-25 安徽理工大学环境友好材料与职业健康研究院(芜湖) Equipment and method for in-situ curing of building waste slurry
CN114411766A (en) * 2022-03-01 2022-04-29 中煤江南建设发展集团有限公司 Construction method of enclosure structure

Similar Documents

Publication Publication Date Title
CN108677924B (en) Double-row miniature steel pipe pile grouting wall-forming partition structure and method
CN101270579B (en) Foundation pit guard method for expansion construction from deep foundation pit to shallow foundation pit
CN109667985B (en) Method for butting pipe pushing jack and receiving well steel sleeve in pipe pushing construction
CN106884433A (en) Control vibrations pile pulling causes the structure of underground structure depression and control depression method
CN204059403U (en) A kind of low embankment existing gas pipeline insulation blocking structure
CN111119128B (en) Danger-removing, reinforcing and seepage-proofing method for natural rock-fill dam of barrier lake
CN112323560B (en) Roadbed construction settlement control system in complex soft foundation environment
CN112323819A (en) Soft soil foundation pit bottom in-situ curing method and soft soil foundation pit bottom curing structure
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN109706952A (en) Large-scale well-sinking construction method
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN111379253A (en) Construction method for high-speed railway expanded cement slurry post-grouting discrete material pile composite foundation
CN110512536A (en) Region of FuShui box culvert cracking comprehensive treatment construction
CN113445516A (en) Drilling and pouring type cement soil pile and construction method thereof
CN212837843U (en) IV-class and V-class surrounding rock tunnel concrete lining anti-cracking structure
CN110284432B (en) Construction method for filling bridge abutment in high-fill area after first construction
CN213897154U (en) Soft soil foundation pit bottom curing structure
CN206189430U (en) A escape canal for deep overburden ground
CN115450229A (en) Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry
CN210636441U (en) Guide partition wall
CN110792440B (en) Construction method of water-rich loess tunnel penetrating through loess towards valley
CN111734451A (en) IV-type and V-type surrounding rock tunnel concrete lining anti-cracking construction method and structure thereof
CN110344439A (en) A kind of construction method of rear-mounted retaining wall drain hole
CN212200440U (en) Water leakage prevention structure for bottom sealing concrete in deep and large foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination