CN107816047A - The method that backfill construction is carried out using premixing fluidised form solidified earth - Google Patents

The method that backfill construction is carried out using premixing fluidised form solidified earth Download PDF

Info

Publication number
CN107816047A
CN107816047A CN201711060680.6A CN201711060680A CN107816047A CN 107816047 A CN107816047 A CN 107816047A CN 201711060680 A CN201711060680 A CN 201711060680A CN 107816047 A CN107816047 A CN 107816047A
Authority
CN
China
Prior art keywords
backfill
slurries
earthwork
fluidised form
solidified earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711060680.6A
Other languages
Chinese (zh)
Inventor
王继忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711060680.6A priority Critical patent/CN107816047A/en
Publication of CN107816047A publication Critical patent/CN107816047A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

A kind of method that backfill construction is carried out using premixing fluidised form solidified earth, this method are comprised the following steps:The earthwork is backfilling into the construction part for needing to carry out backfill with nature;Then to the curing agent slurries that premixing is poured into backfill, slurries are higher by backfill earthwork certain altitude and form the gravity impetus so that the slurries are infiltrated through in the earthwork of backfill in the presence of self gravitation;Whether detection slurries have penetrated into earthwork bottom, be at the position do not permeated completely if the earthwork is not completely by slurry infiltration, and supplement is poured into curing agent slurries and continues to permeate and/or be stirred using agitating device at the position.Or this method comprises the following steps:The soil body is inputted in mixer, while the curing agent slurries mixed are also added in mixer in ratio set in advance and is sufficiently mixed, crushed and stirred, forms premixing fluidised form solidified earth;Premixing fluidised form solidified earth is delivered to backfill job site by pump or tank car, and carries out backfill operation;In backfilling operation process big aggregate is being thrown into premixing fluidised form solidified earth.Using two method can most efficiently utilizing works excavate to greatest extent the earthwork in itself, speed of application is fast, and cost is low, reliable in quality.

Description

The method that backfill construction is carried out using premixing fluidised form solidified earth
Technical field
The present invention relates to a kind of method that backfill construction is carried out using premixing fluidised form solidified earth.
Background technology
The construction for largely needing backfill in fields such as construction, road construction, water conservancy construction, mining industry goafs be present Operating mode.The conventional method backfilled mostly using dirt segmentation branch in the prior art, this method speed of application is slow, human factor More, construction quality is unstable, and many hidden danger are brought to construction quality;With expanding economy, some engineerings use low grade Concrete replaces dirt to carry out backfill construction, and this method speed of application is fast, reliable in quality, but cost is too high, and the later stage Such as need to excavate and will bring very big inconvenience.
Engineers and technicians have carried out many practices and invention for backfill, occur in recent years using traditional backfill Layer, bed course is provided with the upper surface of the back fill course, through hole is offered on the bed course, is worn in the through hole for cement The Grouting Pipe of slurries water conservancy diversion, the Grouting Pipe are worn to back fill course, are condensed into after cement grout solidification with back fill course One induration, the intensity of back fill course is improved, prevents the sedimentation of back fill course.Also just like Chinese patent CN104963349 Disclosed in backfill construction method, methods described be on the place of former deep pit digging, by interim excavation soil sorting accumulation On the ground near deep basal pit, then excavation soil is again returned in a manner of mud in former deep basal pit using filling technique, Make the soil property after backfill closely knit by draining in backfilling process, and be allowed to same layer soil balanced Matching regulation and control appropriateness, thus successively Backfill untill the terrace absolute altitude of design control.
Engineering also uses the method that water sinks, and adds water in the earthwork of backfill, passes through the induced effect soil of water Fang Mishi, but often due to the dosage control of water is bad and causes spongy soil or land subsidence.
A kind of method that backfill construction is carried out using premixing fluidised form solidified earth of present invention offer, premixing fluidised form solidified earth, Premixing can be formed in mixer, can also at the construction field (site) in be separately added into the earthwork and hardening slurry stirs to be formed.The party Method can most efficiently utilizing works excavate to greatest extent the earthwork in itself, speed of application is fast, and cost is low, reliable in quality.
The content of the invention
A kind of method that backfill construction is carried out using premixing fluidised form solidified earth, this method are comprised the following steps:By the earthwork The construction part for needing to carry out backfill is backfilling into nature;Then to the curing agent slurries that premixing is poured into backfill, Slurries are higher by backfill earthwork certain altitude and form the gravity impetus so that the slurries infiltrate through backfill in the presence of self gravitation In cubic metre of earth;Whether detection slurries have penetrated into earthwork bottom, be incomplete if the earthwork is not completely by slurry infiltration The position of infiltration, supplement are poured into curing agent slurries and continue to permeate and/or be stirred using agitating device at the position.
Cubic metre of earth use the natural earth excavated in engineering, loose condition (of surface) when keeping during backfill it to be dug out, do not spend Except bulky grain therein.Backfill substep backfills, and does not backfill i.e. progress slurries after completing a step and pours into, pours into and be verified Afterwards, next step backfill construction is carried out, the thickness of substep is often to walk 50-150cm.According to condition of construction, plug-in type can be used Agitator is stirred mix to the soil body for penetrating into slurries.
When the slurries once poured into are excessive, the appropriate backfill earthwork is inserted wherein to absorb slurries.
Big aggregate can be added in the backfill earthwork, big aggregate is concrete block, fragment of brick, stone or clinker.
The soil body can also be inputted in mixer, while the curing agent slurries mixed also are added in ratio set in advance It is sufficiently mixed, crushed and stirred into mixer, forms premixing fluidised form solidified earth;By premixing fluidised form solidified earth by pump or Tank car is delivered to backfill job site, and carries out backfill operation;Thrown in backfilling operation process into premixing fluidised form solidified earth Enter big aggregate;Big aggregate is concrete block, fragment of brick, stone, clinker etc..
After backfilling job execution in two methods, on premixing fluidised form solidified earth surface, cover film is conserved.
In two method that curing agent is levigate by GZM resonance grinders, curing agent granularity is not more than 80 μm.
Horizontal or vertical mixer is used in latter method, mixer has the function of broken soil block, finally mixed and stirred Solidified earth maximum soil particle is not more than 20mm.The slump for the fluidised form solidified earth mixed and stirred is 8-20mm.Premixing fluidised form solidified earth Intensity is 0.5-1.5MPa.
The place for needing to backfill is cleaned out before backfill operation is carried out in latter method, and moistening of watering.Backfilling process It is middle that symmetry operation is carried out according to project situation.
The premixing fluidised form solidified earth that the first step is poured in latter method is highly no more than 50cm.
In latter method in premixing fluidised form solidifies earthen backfill operation process, large granular materials, particle are thrown into thereto Footpath is not less than 50mm, to prevent premixing fluidised form solidified earth from ftractureing.
In two methods after solidified earth final step is constructed, in the uniform spreading granule materials in its surface, grain diameter 15-30mm.
Curing agent slurries can be replaced with cement grout in two methods.
Curing agent is can to permeate to fill and promote or control the material or mixture of curing reaction with soil particle, and it is wrapped Active silica-alumina material and exciting agent are included, it improves soil by the plural gel effect after the aquation in the soil body and fill strengthening effect Intensity, consistency, the stability of body.
Using this method can most efficiently utilizing works excavate to greatest extent the earthwork in itself, speed of application is fast, cost It is low, reliable in quality.
Embodiment
Construction embodiment 1, a foundation ditch for needing to backfill, foundation ditch most 12 meters of deep position, base widths are average 3 meters, and foundation ditch is about 45 degree of slopes.The backfill earthwork is poured into foundation ditch using navy barrow, height 80cm is put into every time, is then put into by tank car and chute Curing agent slurries, the proportionings of curing agent slurries are that the weight ratio of curing agent and water is 1:2, the proportion of curing agent slurries is 1.25; The slurries being put into every time are higher by backfill face 50cm, and when slurry surface does not have bubble to emerge, detector bar is inserted into the soil body, when When slurries penetrate into uneven, stirred with plug-in type agitator.After final step is constructed, particulate matter is uniformly added on surface Expect and addition plastic foil is conserved thereon, until test cube in the same condition reaches intensity requirement.
Construction embodiment 2, in a piping lane engineering, 18 meters of buried depth, the equal gunite concrete bank protection of bilateral slope, piping lane bottom Bed course stretches out, and connects with double-sided bevel bank protection.Fertile groove is cleaned out, backfill premixing fluidised form is used as using the earthwork that piping lane is dug out The material of solidified earth, is delivered in horizontal mixer with conveyer belt, and curing agent is prepared into slurries is also delivered in mixer, Gu The addition of agent be final products weight than 22%;It is sufficiently mixed after adding curing agent slurries, mixer crushes The earthwork is crushed and is sufficiently stirred to form premixing fluidised form solidified earth by device.Premixing fluidised form solidified earth is poured into fertile groove by chute Interior, fluidised form solidified earth is poured simultaneously in piping lane both sides, and it is 50cm that first layer, which pours height, after the first laminar flow regime solidified earth initial set Continue to pour.Slump control is not less than 1.5MPa in 10mm, 60 days intensity of premixing fluidised form solidified earth.In premixing fluidised form solidified earth In be thrown into the building wastes such as fragment of brick, its particle diameter is 80-150mm, with being thrown into pouring.After the completion of premixing fluidised form solidified earth is poured, Particle diameter 15-30mm granule materials are uniformly sprinkled on its surface, treat that the initial set of fluidised form solidified earth is spread plastic sheeting backward and supported thereon Shield 28 days.
Construction embodiment 3, a coal mine gob, 15 meters of tunnel buried depth, 5 meters of Breadth Maximum, 2.5 meters of height.The earthwork is defeated Vertical mixer is delivered to, while curing agent is prepared into slurries and is also delivered in mixer, the addition of curing agent is final production Product weight than 14%;It is sufficiently mixed after adding curing agent slurries, the breaker of mixer is broken and abundant by the earthwork Stirring forms premixing fluidised form solidified earth.The discharging opening of ground pump and mixer is connected, collapses and send fluidised form solidified earth to enter goaf, is flowed The slump of state solidified earth is 18mm, and 60 days intensity of premixing fluidised form solidified earth is not less than 0.5MPa.

Claims (10)

  1. A kind of 1. method that backfill construction is carried out using premixing fluidised form solidified earth, it is characterised in that this method includes following step Suddenly:The earthwork is backfilling into the construction part for needing to carry out backfill with nature;Then to pouring into consolidating for premixing in backfill Agent slurries, slurries are higher by backfill earthwork certain altitude and form the gravity impetus so that the slurries ooze in the presence of self gravitation Penetrate in the earthwork of backfill;Whether detection slurries have penetrated into earthwork bottom, if the earthwork is not completely by slurry infiltration At the position do not permeated completely, supplement is poured into curing agent slurries and continues to permeate and/or carried out using agitating device at the position Stirring.
  2. 2. the method as described in claim 1, it is characterised in that the earthwork uses the natural earth excavated in engineering, during backfill Keep its loose condition (of surface) after being dug out;Backfill substep backfills, and carrying out slurries after one step of often backfill completion pours into, and pours into simultaneously After being verified, next step backfill construction is carried out, the thickness of substep is often to walk 50-150cm.
  3. 3. method as claimed in claim 1 or 2, it is characterised in that according to condition of construction, plug-in type agitator pair can be used The soil body for penetrating into slurries is stirred mix.
  4. 4. method as claimed in claim 1 or 2, it is characterised in that big aggregate can be added in the backfill earthwork, big aggregate is concrete Block, fragment of brick, stone or clinker.
  5. A kind of 5. method that backfill construction is carried out using premixing fluidised form solidified earth, it is characterised in that this method includes following step Suddenly:The soil body is inputted in mixer, while the curing agent slurries mixed are also added in mixer in ratio set in advance It is sufficiently mixed, crushed and stirred, forms premixing fluidised form solidified earth;Premixing fluidised form solidified earth is delivered to by pump or tank car Backfill job site, and carry out backfill operation;Big aggregate is being thrown into premixing fluidised form solidified earth in backfilling operation process, greatly Aggregate is concrete block, fragment of brick, stone or clinker.
  6. 6. the method as described in claim 1 or 5, it is characterised in that after backfill job execution, in premixing fluidised form solidified earth Surface cover film is conserved.
  7. 7. the method as described in claim 1 or 5, it is characterised in that it is wherein that curing agent is levigate by GZM resonance grinders, Curing agent granularity is not more than 80 μm.
  8. 8. method as claimed in claim 5, it is characterised in that wherein have broken using horizontal or vertical mixer, mixer The function of soil crushing, the solidified earth maximum soil particle finally mixed and stirred are not more than 20mm;The slump for the fluidised form solidified earth mixed and stirred It is 0.5-1.5MPa to spend for 8-20mm, premixing fluidised form solidified earth intensity.
  9. 9. the method as described in claim 1 or 5, it is characterised in that curing agent slurries can be replaced with cement grout.
  10. 10. the method as described in claim 1 or 5, it is characterised in that after the final step of fluidised form solidified earth is constructed, The uniform spreading granule materials in its surface, grain diameter 15-30mm.
CN201711060680.6A 2017-11-01 2017-11-01 The method that backfill construction is carried out using premixing fluidised form solidified earth Pending CN107816047A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711060680.6A CN107816047A (en) 2017-11-01 2017-11-01 The method that backfill construction is carried out using premixing fluidised form solidified earth

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711060680.6A CN107816047A (en) 2017-11-01 2017-11-01 The method that backfill construction is carried out using premixing fluidised form solidified earth

Publications (1)

Publication Number Publication Date
CN107816047A true CN107816047A (en) 2018-03-20

Family

ID=61604611

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711060680.6A Pending CN107816047A (en) 2017-11-01 2017-11-01 The method that backfill construction is carried out using premixing fluidised form solidified earth

Country Status (1)

Country Link
CN (1) CN107816047A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111676987A (en) * 2020-06-02 2020-09-18 北京建材地质工程有限公司 Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN112252336A (en) * 2020-10-16 2021-01-22 中建八局发展建设有限公司 Construction method for backfilling foundation trench of premixed fluidized solidified soil
CN112359848A (en) * 2020-10-30 2021-02-12 北京住总第六开发建设有限公司 Construction method for backfilling fertilizer groove by using solidified soil
CN112695772A (en) * 2021-01-18 2021-04-23 北京建材地质工程有限公司 Construction method for backfilling construction of construction fertilizer groove by slurry filling interlayer method
CN112813993A (en) * 2021-01-04 2021-05-18 上海市城市建设设计研究总院(集团)有限公司 Backfill construction method for grooving and pipe burying foundation trench by adopting self-compacting backfill
CN113006090A (en) * 2021-03-01 2021-06-22 北京建材地质工程有限公司 Self-compacting filling method for top of pipe gallery or ground reservoir by using slurry
CN113089747A (en) * 2021-02-25 2021-07-09 中建三局第二建设工程有限责任公司 Fertilizer groove backfilling construction method based on self-compacting backfilled soil
CN115403352A (en) * 2022-09-16 2022-11-29 蒋黔湘 Method for preparing fluid solidified soil by using building residue soil
CN115450229A (en) * 2022-08-31 2022-12-09 上海城建市政工程(集团)有限公司 Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015037249A1 (en) * 2013-09-12 2015-03-19 Oya Yohei Civil engineering improvement method and modifying paper powder material
CN104863113A (en) * 2015-06-04 2015-08-26 杭州特诚地基工程有限公司 Method for curing in-situ soil in situ and stirring device
CN105969367A (en) * 2016-05-13 2016-09-28 王继忠 Pre-mixed high-strength cement soil
CN106994741A (en) * 2017-05-12 2017-08-01 王继忠 A kind of curable native mixer of premixing fluidised form
JP6174280B1 (en) * 2017-02-07 2017-08-02 三和石産株式会社 Fluid backfill material
CN107020692A (en) * 2017-05-26 2017-08-08 王继忠 It is a kind of to prepare curable native complete set of equipments
CN107299637A (en) * 2017-07-11 2017-10-27 江苏坤泽科技股份有限公司 A kind of solidified earth for possessing mobility pours backfill handling process

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015037249A1 (en) * 2013-09-12 2015-03-19 Oya Yohei Civil engineering improvement method and modifying paper powder material
CN104863113A (en) * 2015-06-04 2015-08-26 杭州特诚地基工程有限公司 Method for curing in-situ soil in situ and stirring device
CN105969367A (en) * 2016-05-13 2016-09-28 王继忠 Pre-mixed high-strength cement soil
JP6174280B1 (en) * 2017-02-07 2017-08-02 三和石産株式会社 Fluid backfill material
CN106994741A (en) * 2017-05-12 2017-08-01 王继忠 A kind of curable native mixer of premixing fluidised form
CN107020692A (en) * 2017-05-26 2017-08-08 王继忠 It is a kind of to prepare curable native complete set of equipments
CN107299637A (en) * 2017-07-11 2017-10-27 江苏坤泽科技股份有限公司 A kind of solidified earth for possessing mobility pours backfill handling process

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111676987A (en) * 2020-06-02 2020-09-18 北京建材地质工程有限公司 Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN112252336A (en) * 2020-10-16 2021-01-22 中建八局发展建设有限公司 Construction method for backfilling foundation trench of premixed fluidized solidified soil
CN112359848A (en) * 2020-10-30 2021-02-12 北京住总第六开发建设有限公司 Construction method for backfilling fertilizer groove by using solidified soil
CN112813993A (en) * 2021-01-04 2021-05-18 上海市城市建设设计研究总院(集团)有限公司 Backfill construction method for grooving and pipe burying foundation trench by adopting self-compacting backfill
CN112695772A (en) * 2021-01-18 2021-04-23 北京建材地质工程有限公司 Construction method for backfilling construction of construction fertilizer groove by slurry filling interlayer method
CN113089747A (en) * 2021-02-25 2021-07-09 中建三局第二建设工程有限责任公司 Fertilizer groove backfilling construction method based on self-compacting backfilled soil
CN113006090A (en) * 2021-03-01 2021-06-22 北京建材地质工程有限公司 Self-compacting filling method for top of pipe gallery or ground reservoir by using slurry
CN115450229A (en) * 2022-08-31 2022-12-09 上海城建市政工程(集团)有限公司 Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry
CN115403352A (en) * 2022-09-16 2022-11-29 蒋黔湘 Method for preparing fluid solidified soil by using building residue soil
CN115403352B (en) * 2022-09-16 2023-09-05 蒋黔湘 Method for preparing fluid solidified soil by using building slag soil

Similar Documents

Publication Publication Date Title
CN107816047A (en) The method that backfill construction is carried out using premixing fluidised form solidified earth
CN104863113B (en) The method and mixing plant of original place curing process are carried out to in-situ soil
CN105887837A (en) On-site ground cemented soil stirring pile construction method
CN109940755A (en) A kind of sorting and preparation method of filling material
CN108150179B (en) High osmosis bad ground shield pressure chamber sediment improvement method
CN205297580U (en) Soft rock bate distension control structure
CN102080381B (en) Method for managing landslip of side slope landslide for transformer substation
CN101008178B (en) Soft base processing construction process using excavating and stirring method
CN201598610U (en) Face plate rock-fill dam structure reasonably utilizing gravel sand
CN103242009A (en) Water permeable material non-fine concrete block for bridge abutment and manufacturing process for non-fine concrete block
CN110080232A (en) A kind of deep basal pit earth-filling method of underground high water level
KR100421540B1 (en) VCPS : Process for Treating Weak Soil with Vibrated Crushed Stone Compaction Pile Reinforced with Sand
CN108439867A (en) Using the rock-fill dams and its construction method of seamless panel
CN110984065B (en) Hydraulic structure of red-bed soft rock
CN104695455B (en) High-flow and high-head antiscour and anti-seepage overflow cofferdam structure and construction method thereof
CN107513992A (en) A kind of shallow surface solidifying agent consolidation continuous construction method of mud
NO760636L (en)
JPH0828200A (en) Filling of space part
JPH0452327A (en) Stabilized soil and construction method using this soil
CN100425555C (en) Pipeline sludge solidification treatment method
CN107859042A (en) A kind of moist expansion cubic metre of earth and stone earth-filling method
Tojik Techno-economic Assessment Study for Rogun Hydroelectric Construction Project
JPH02263890A (en) Quick ground-preventing method and soil-coagulant
JP6654772B1 (en) Fluidized soil slope protection structure
CN115504723B (en) Plastic slurry suitable for anti-seepage grouting of karst development stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180320

RJ01 Rejection of invention patent application after publication