CN115434305A - Steel pipe pile construction process - Google Patents

Steel pipe pile construction process Download PDF

Info

Publication number
CN115434305A
CN115434305A CN202211112801.8A CN202211112801A CN115434305A CN 115434305 A CN115434305 A CN 115434305A CN 202211112801 A CN202211112801 A CN 202211112801A CN 115434305 A CN115434305 A CN 115434305A
Authority
CN
China
Prior art keywords
pile
steel pipe
construction process
pipe pile
process according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211112801.8A
Other languages
Chinese (zh)
Inventor
尹学鑫
高晓刚
王忠钊
贺贤群
王强元
张洪江
周海波
李恒杰
胡卓
杜彬
吴伟强
许光耀
万振华
周汝德
杨建强
朱鸿博
谢玉珩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Guangdong Construction Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
China Railway Guangzhou Investment and Development Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Guangdong Construction Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
China Railway Guangzhou Investment and Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Guangdong Construction Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd, China Railway Guangzhou Investment and Development Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN202211112801.8A priority Critical patent/CN115434305A/en
Publication of CN115434305A publication Critical patent/CN115434305A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/08Removing obstacles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to the technical field of subway engineering, and provides a steel pipe pile construction process, which comprises the following steps: s1, testing a pile on the ground, wherein the pile is used for verifying stratum parameters; s2, drilling a grid in advance; s3, drilling; s4, cleaning holes; s5, placing a steel pipe; s6, pouring concrete; s8, grouting the pile bottom; s9, pile foundation detection, erection of the cross beam, connection of the cross beam and the pile, providing force far away from the pile foundation direction for the cross beam through the lifting device, and adjusting the lifting device to apply force to test the bearing capacity of the pile foundation. By taking the side piles as constraint ends and adopting the back pressure cross beams and the jacks to detect the bearing capacity, a method for detecting the static load test in a narrow space is provided, the problem that the static load test cannot be carried out in a narrow space is solved, and compared with the traditional test, the quality is more reliable; the mechanized construction and construction quality control in narrow and small space are realized, and the construction progress and construction quality of the miniature steel pipe pile in the narrow and small space are guaranteed.

Description

Steel pipe pile construction process
Technical Field
The invention belongs to the technical field of subway engineering, and particularly relates to a steel pipe pile construction process.
Background
At present, in the subway line construction process, because the space in the pilot tunnel is narrow, the large-scale equipment can not be used for construction, and the construction efficiency is lower.
Patent CN113481973A discloses a construction method of a steel pipe pile in a subway station, which comprises the following steps: s1, hardening and leveling a pilot hole; s2, positioning a pile and opening a hole; s3, coring the steel pipe pile; s4, drilling: after coring is finished, drilling by adopting a crawler-type drilling machine, checking the flatness of the drilling machine and the verticality of a driving drill rod in the drilling process, regularly checking a drill bit and a drill rod joint, drilling at low speed and low pressure in the drilling process, and controlling the verticality by arranging a hanging hammer on a drill boom; s5, primary hole cleaning; s6, measuring the hole depth and checking the hole; s7, placing a steel pipe; s8, hanging and placing the grouting pipe; s9, checking and checking the thickness; s10, pouring concrete; s11, pile splicing and filling test blocks and pile top longitudinal bar installation; and S12, grouting the pile bottom. Although this patent has been solved the drilling straightness that hangs down and has not conform to the difficult problem of design standard requirement, sediment thickness control and steel pipe pile concrete closely knit not enough a difficult problem, it is lower at the efficiency of construction, and quality testing still has certain difficulty, causes the time limit for a project extension easily, drags the construction progress slowly.
Disclosure of Invention
The invention provides a steel pipe pile construction process aiming at the problems of inconvenient steel pipe column construction, difficult quality detection, low construction efficiency and the like in a narrow space in the prior art. The technical scheme adopted by the invention is as follows:
a steel pipe pile construction process comprises the following steps:
s1, testing a pile on the ground, wherein the pile is used for verifying stratum parameters;
s2, drilling a grid in advance;
s3, drilling;
s4, cleaning holes;
s5, placing a steel pipe;
s6, pouring concrete;
s8, grouting the pile bottom;
s9, pile foundation detection, erection of the cross beam, connection of the cross beam and the pile, providing force far away from the pile foundation direction for the cross beam through the lifting device, and adjusting the lifting device to apply force to test the bearing capacity of the pile foundation.
Preferably, in step S8, the lifting device is a hydraulic jack.
Preferably, in step S6, grout holes are reserved during pouring, and in step S8, the connection mode of the beam and the pile foundation is as follows: and a steel wire rope penetrates through the grout overflow hole and then is connected with the cross beam.
Preferably, the lifting device sets up between two adjacent pile foundations, and two pile foundations of lifting device both sides are connected with the crossbeam through 2 wire rope respectively.
Preferably, the diameter of the grout overflow hole is 10-15% of the diameter of the pile foundation.
Preferably, the diameter of the steel wire rope is 60-80% of the diameter of the grout hole.
Preferably, after one priming at step S6, road cleaning is performed.
Preferably, step S8 further includes performing low strain detection on the pile foundation.
Preferably, a perfusion block is previously manufactured before step S6.
Compared with the prior art, the method is suitable for the construction of the steel pipe column in a narrow space such as a subway pilot tunnel, realizes the mechanized construction and the construction quality control in the narrow space, and ensures the construction progress and the construction quality of the miniature steel pipe pile in the narrow space; by taking the side piles as constraint ends and adopting the back pressure cross beams and the jacks to detect the bearing capacity, a method for detecting static load test in narrow space is provided, the problem that the static load test cannot be carried out in narrow space is solved, and compared with the traditional test, the quality is more reliable.
According to the construction method, the manual difficulty and risk are reduced in the construction process of the Guangzhou subway eleven-line scenic station, the construction quality is guaranteed, the construction progress is accelerated, the fund is saved by 110 ten thousand yuan, and the construction method is friendly to social environment.
Drawings
Fig. 1 is a schematic diagram of a simple process of the steel pipe pile construction process of the present application.
Fig. 2 is a detailed flow chart in the embodiment of the present application.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be obtained by a person skilled in the art without making any creative effort based on the embodiments in the present invention, belong to the protection scope of the present invention.
The specific embodiment is as follows:
as shown in fig. 1-2, a steel pipe pile construction process specifically includes:
preparing outside the pilot tunnel:
the ground pile test is used for verifying stratum parameters;
and a working step in the pilot tunnel:
step one, hardening and leveling a pilot hole: after the preliminary support of the pilot tunnel is finished, hardening C20 concrete with the thickness of 15cm at the bottom of the pilot tunnel to ensure that the ground is firm and flat, and building a drainage ditch, thereby facilitating the discharge of drilling slag and slurry in the drilling construction process;
step two, positioning and opening the pile by a bench drill: according to construction drawings and on-site lead control points, lofting the position of a steel pipe pile of an edge pile by using a total station, retesting the coordinates and the elevation of the pile position by adopting a point-changing application method, ensuring the accuracy of the coordinates and the elevation of the pile position, and after the lofting is measured, firstly aligning the hole position by using a bench drilling machine, removing a primary support at the bottom of a pilot tunnel and perforating, so that the advanced drilling of grids is realized, and the abrasion of a drill bit is prevented from being serious;
step three, coring the steel pipe pile: coring is carried out by adopting an XY-1A type geological drilling machine, and a pile bottom rock sample is recorded so as to ensure that a pile bottom stratum meets the design requirement;
fourthly, positioning and correcting the drilling machine; preferably a crawler type hydraulic jumbolter, model KS-800, is used.
Step five, drilling: drilling by using a crawler-type drilling machine after coring is finished, wherein the diameter of a drill bit is 330mm, and the specification of a drill rod is phi 89 multiplied by 1500mm;
step six, hole cleaning at one time: after drilling to the designed hole depth, stopping footage, blowing out sediments at the bottom of the hole by adopting high-pressure air circulation, and simultaneously, in order to ensure the maximum hole cleaning, injecting clear water into the hole to ensure that the sediment thickness can meet the design and standard requirements; the slurry is deposited and treated and discharged through a preset ditch, so that the adverse effect of environmental factors is reduced.
Seventhly, measuring the hole depth and checking the hole: after hole cleaning is finished, checking the aperture, the hole verticality, the hole depth and the sediment thickness, and if the sediment thickness at the bottom of the pile after hole cleaning is detected to be not in accordance with the requirement, arranging hole cleaning again until the detected sediment thickness is in accordance with the requirement;
step eight, placing steel pipes: when the drilling hole reaches the design depth and meets the requirements, hoisting the steel pipe by using a winch, fixing the steel pipe at the orifice by using a pipe clamp, exposing the length of the steel pipe by 50cm, hoisting the next section, and connecting the two sections together by using screw threads; when the pipe is lowered, the pipe joints in adjacent holes are staggered front and back, so that the stress of the joints on the same section is avoided; the number of joints in the same section is not more than 50% of the total number of steel pipes, and the joints of the two adjacent holes of steel pipes are staggered by at least 1m.
Step nine, checking and checking the thickness: checking the sediment thickness at the bottom of the hole, and entering the next procedure when the sediment thickness can meet the design and specification requirements; when the sediment thickness can not meet the design and specification requirements, secondary hole cleaning is carried out, and sediment at the bottom of the hole is blown out by adopting high-pressure air circulation until the sediment thickness can meet the design and specification requirements;
step ten, hanging and placing a grouting pipe: in order to ensure that the pile bottom of the steel pipe pile is compact, post-grouting construction needs to be carried out, grouting pipes are hung in the steel pipe pile before concrete is poured, the grouting pipes are arranged along the deep through length of the pile and are provided with 1 grouting pipe, and the grouting pipes need to extend out of the pile top by 20cm, so that later-stage grouting connection is facilitated; the pipe sections are connected by screw threads, and the pipe bottom is sealed by an adhesive tape, so that the grouting pipe is prevented from being blocked when test block concrete is poured; the grouting pipe is a galvanized steel pipe with the diameter of 21.3 multiplied by 2.8 mm.
And eleventh, installing a guide pipe, namely performing trial assembly and preparation on the guide pipe in advance, and then installing the guide pipe on the steel pipe pile.
And step twelve, installing a funnel, namely installing the funnel on the guide pipe to facilitate the concentration of concrete.
Thirteen steps, concrete pouring for the first time: draining accumulated water at the bottom of the hole before concrete pouring, pouring sufficient concrete by using a ground pump, and vibrating when the concrete is poured to the hole opening until fresh concrete returns out from the hole opening; the first pour is a pour of the subsurface portion.
And fourteen steps of welding the steel pipe column connection columns.
Step fifteen, pouring concrete for the second time: and pouring the column base part on the ground during the second pouring. Further, before the perfusion, a perfusion test block is prepared in advance. And after primary perfusion is carried out, dismantling a pump pipe and cleaning a road.
Sixthly, mounting the reserved steel bars at the top of the column.
Seventeen, post grouting at the pile bottom: the grouting operation is preferably carried out 2 days after the pile is formed and is not later than 30 days after the pile is formed; the distance between the grouting operation point and the hole forming operation point is not less than 8-10m; the water cement ratio of the grouting slurry is 0.5-0.6, the cement is ordinary portland cement, the grouting pressure is not lower than 1MPa, the pressure is ensured to crush the adhesive tape, the slurry is extruded out of the pipe, and the grouting flow is not more than 75L/min; stopping grouting when the grouting pressure reaches or exceeds the design requirement; when the grouting pressure is lower than the normal value for a long time or grout is blown out or surrounding pile holes are strung, intermittent grouting is changed, the intermittent time is 30-60 min, or the water-cement ratio of the grout is adjusted to be low.
Eighteen, column base detection: erect the crossbeam in the pilot tunnel, be connected crossbeam and post to provide the power of keeping away from the pile foundation direction for the crossbeam through the lifting device, adjust the lifting device and exert the power size test pile foundation bearing capacity for the crossbeam. And further, carrying out low strain detection on the pile foundation in the pilot tunnel.
Further, the lifting device is a hydraulic jack.
Furthermore, a grout overflow hole is reserved during pouring, and a steel wire rope penetrates through the grout overflow hole and then is connected with the cross beam to realize the connection of the cross beam and the pile foundation.
Further, the lifting device sets up between two adjacent pile foundations, and two pile foundations of lifting device both sides are connected with the crossbeam through 2 wire rope respectively.
Furthermore, the aperture of each single grout overflow hole is 10% -15% of the diameter of the pile foundation, and each pile foundation is provided with 2 grout overflow holes.
Further, the diameter of the steel wire rope is 60% -80% of the diameter of the grout overflow hole.
Furthermore, the aperture of the slurry overflow hole is 5cm, and the diameter of the steel wire rope is 3cm.
By taking the side piles (the edge piles) as the constraint ends and adopting the cross beams and the jacks to carry out bearing capacity detection, the method for detecting the static load test in the narrow space is provided, the problem that the static load test cannot be carried out in the narrow space is solved, and compared with the traditional test, the quality is more reliable.
The method is suitable for the construction of the steel pipe column in a narrow space such as a subway pilot tunnel, realizes the mechanized construction and the construction quality control in the narrow space, and ensures the construction progress and the construction quality of the miniature steel pipe pile in the narrow space; in the construction process of the Guangzhou subway eleven-line scenic station, the manual difficulty and risk are reduced, the construction quality is guaranteed, the construction progress is accelerated, the fund is saved by 110 ten thousand yuan, and the construction method is friendly to social environment.
Finally, it should be noted that the above-mentioned contents are only used for illustrating the technical solutions of the present invention, and not for limiting the protection scope of the present invention, and that the simple modifications or equivalent substitutions of the technical solutions of the present invention by those of ordinary skill in the art can be made without departing from the spirit and scope of the technical solutions of the present invention.

Claims (10)

1. A steel pipe pile construction process is characterized in that: the method comprises the following steps:
s1, testing a pile on the ground; verifying the formation parameters;
s2, drilling a grid in advance;
s3, drilling;
s4, cleaning holes;
s5, placing a steel pipe;
s6, pouring concrete;
s7, grouting the pile bottom;
s8, detecting a pile foundation; erect the crossbeam, be connected crossbeam and pile foundation to provide the power of keeping away from the pile foundation direction for the crossbeam through the lifting device, the adjustment lifting device exerts the power size test pile foundation bearing capacity.
2. The steel pipe pile construction process according to claim 1, characterized in that: in step S8, the lifting device is a hydraulic jack.
3. The steel pipe pile construction process according to claim 1, characterized in that: in the step S6, a grout overflow hole is reserved when a test block is poured, and in the step S8, the connection mode of the cross beam and the pile foundation is as follows: and a steel wire rope penetrates through the grout overflow hole and then is connected with the cross beam.
4. The steel pipe pile construction process according to claim 3, characterized in that: the lifting device sets up between two adjacent pile foundations, and two pile foundations of lifting device both sides are connected with the crossbeam through 2 wire rope respectively.
5. The steel pipe pile construction process according to claim 3, characterized in that: the aperture of the grout overflow hole is 10-15% of the diameter of the pile foundation.
6. The steel pipe pile construction process according to claim 3, characterized in that: the diameter of the steel wire rope is 60-80% of the diameter of the grout overflow hole.
7. The steel pipe pile construction process according to claim 3, characterized in that: the aperture of the slurry overflow hole is 5cm, and the diameter of the steel wire rope is 3cm.
8. The steel pipe pile construction process according to claim 1, characterized in that: after the completion of the first filling in step S6, the road is cleaned.
9. The steel pipe pile construction process according to claim 1, characterized in that: and step S8, low strain detection is carried out on the pile foundation.
10. The steel pipe pile construction process according to claim 1, characterized in that: before step S6, a perfusion test block is prepared in advance.
CN202211112801.8A 2022-09-14 2022-09-14 Steel pipe pile construction process Pending CN115434305A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211112801.8A CN115434305A (en) 2022-09-14 2022-09-14 Steel pipe pile construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211112801.8A CN115434305A (en) 2022-09-14 2022-09-14 Steel pipe pile construction process

Publications (1)

Publication Number Publication Date
CN115434305A true CN115434305A (en) 2022-12-06

Family

ID=84248150

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211112801.8A Pending CN115434305A (en) 2022-09-14 2022-09-14 Steel pipe pile construction process

Country Status (1)

Country Link
CN (1) CN115434305A (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000129677A (en) * 1998-10-28 2000-05-09 Komatsu Ltd Steel-pipe pile
CN104612134A (en) * 2014-12-16 2015-05-13 中铁建大桥工程局集团第五工程有限公司 Cast-in place pile post-grouting construction method for pouring construction
CN108612136A (en) * 2018-05-25 2018-10-02 深圳市岩土工程有限公司 A kind of the test pile structure and construction method of engineering pile pile extension
CN109505317A (en) * 2018-10-29 2019-03-22 建研地基基础工程有限责任公司 A kind of resistance to compression of high stake, resistance to plucking and horizontally loading test equipment
US20190249387A1 (en) * 2016-10-18 2019-08-15 ASAHI KASEl CONSTRUCTION MATERIALS CORPORATION Steel pipe coupling device for steel pipes
CN110468887A (en) * 2019-07-31 2019-11-19 青岛理工大学 A kind of miniature steel pipe stake body soil pressure and displacement monitoring method
CN210134410U (en) * 2019-03-06 2020-03-10 中交路桥建设有限公司 Grid type panel of drilling platform
CN111550180A (en) * 2020-05-11 2020-08-18 中铁十八局集团有限公司 Construction method and construction equipment for hard rock stratum pile foundation in low-clearance narrow space
CN113216840A (en) * 2021-05-18 2021-08-06 浙江交工集团股份有限公司 Impact pore-forming ultra-long bored pile and construction method
CN113322942A (en) * 2021-06-11 2021-08-31 中铁隧道集团三处有限公司 Construction method of soft stratum squeezing and expanding support disc cast-in-place pile
CN113481973A (en) * 2021-06-10 2021-10-08 中铁三局集团广东建设工程有限公司 Construction method of steel pipe pile of subway station

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000129677A (en) * 1998-10-28 2000-05-09 Komatsu Ltd Steel-pipe pile
CN104612134A (en) * 2014-12-16 2015-05-13 中铁建大桥工程局集团第五工程有限公司 Cast-in place pile post-grouting construction method for pouring construction
US20190249387A1 (en) * 2016-10-18 2019-08-15 ASAHI KASEl CONSTRUCTION MATERIALS CORPORATION Steel pipe coupling device for steel pipes
CN108612136A (en) * 2018-05-25 2018-10-02 深圳市岩土工程有限公司 A kind of the test pile structure and construction method of engineering pile pile extension
CN109505317A (en) * 2018-10-29 2019-03-22 建研地基基础工程有限责任公司 A kind of resistance to compression of high stake, resistance to plucking and horizontally loading test equipment
CN210134410U (en) * 2019-03-06 2020-03-10 中交路桥建设有限公司 Grid type panel of drilling platform
CN110468887A (en) * 2019-07-31 2019-11-19 青岛理工大学 A kind of miniature steel pipe stake body soil pressure and displacement monitoring method
CN111550180A (en) * 2020-05-11 2020-08-18 中铁十八局集团有限公司 Construction method and construction equipment for hard rock stratum pile foundation in low-clearance narrow space
CN113216840A (en) * 2021-05-18 2021-08-06 浙江交工集团股份有限公司 Impact pore-forming ultra-long bored pile and construction method
CN113481973A (en) * 2021-06-10 2021-10-08 中铁三局集团广东建设工程有限公司 Construction method of steel pipe pile of subway station
CN113322942A (en) * 2021-06-11 2021-08-31 中铁隧道集团三处有限公司 Construction method of soft stratum squeezing and expanding support disc cast-in-place pile

Similar Documents

Publication Publication Date Title
CN110056369B (en) Construction method for entrance and exit hole of tunnel
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN111576431A (en) Excavation method for foundation pit of four-layer subway station
WO2023066327A1 (en) Construction method for underground building consisting of sinking wall foundation
CN107326898B (en) I-shaped precast pile supporting structure with adjustable inserted rigidity in cement-soil wall and construction method thereof
CN107700479A (en) A kind of construction method of large diameter drill hole pile
CN114134928B (en) Construction method of steel pipe column tower crane foundation
CN109578035B (en) Steel pipe drainage lock foot pile and construction method
CN113481973A (en) Construction method of steel pipe pile of subway station
CN111472363A (en) Construction method of foundation pit enclosure structure located in underground space of existing building
CN218148483U (en) Tower crane foundation structure
CN115434305A (en) Steel pipe pile construction process
CN213448506U (en) Plugging structure arranged between foundation pit fender posts
CN114922195A (en) Construction method of soft soil deep and large foundation pit adjacent to protected object
CN113266019A (en) Construction method of foundation pit steel pipe support system
CN111676963A (en) Steel pipe upright post positioning device and positioning construction method thereof
CN113373915B (en) Method for reinforcing steel column pile structure
CN112359819B (en) Wall structure construction method for increasing depth of old diaphragm wall
JP7466044B1 (en) Installation method of underpinning piles and inspection anchor piles
CN114482079B (en) Construction method for deep foundation pit of pipe jacking well
CN115324106B (en) Construction method for optimizing intermittent stopping point of synchronous reverse construction technology
CN115821937B (en) Combined reinforcement method for foundation pit adjacent to unstable vertical shaft
CN212896374U (en) Foundation pit support structure located in underground space of existing building
CN116856462A (en) Construction method for deep foundation pit shaft structure in narrow space of proximity sensitive building
CN117166483A (en) Anti-disturbance support construction method for large deep foundation pit of subway station main body

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination