CN115404994A - Construction method of irregular curve space three-dimensional truss system of super-large-span building - Google Patents

Construction method of irregular curve space three-dimensional truss system of super-large-span building Download PDF

Info

Publication number
CN115404994A
CN115404994A CN202211292857.6A CN202211292857A CN115404994A CN 115404994 A CN115404994 A CN 115404994A CN 202211292857 A CN202211292857 A CN 202211292857A CN 115404994 A CN115404994 A CN 115404994A
Authority
CN
China
Prior art keywords
truss
dimensional
trusses
space
hoisted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211292857.6A
Other languages
Chinese (zh)
Inventor
刘凯
李锰
张志腾
高远
张广臣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202211292857.6A priority Critical patent/CN115404994A/en
Publication of CN115404994A publication Critical patent/CN115404994A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/342Structures covering a large free area, whether open-sided or not, e.g. hangars, halls
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Theoretical Computer Science (AREA)
  • Electromagnetism (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种超大跨度建筑不规则曲线空间立体桁架体系施工方法,其包括在计算机内构建不规则曲线桁架模型,完成桁架杆件的加工制作;确定胎架位置,对胎架进行拼装;将空间立体桁架分成三组;根据不规则曲线桁架模型对空间立体桁架分段吊装。本发明解决了大直径大壁厚杆件在桁架在拼装过程中预起拱困难的情况,并通过选择合理的拼装场地位置及吊装施工顺序,解决了传统施工过程中拼装胎架跟随吊装施工过程反复移动拼装的难题,提高了施工效率,节省施工工期。且每榀桁架分两段吊装,中间位置采用“井字”支撑作为临时支撑胎架,整个桁架体系吊装过程中挠度变形最小,最大程度的保证了屋盖钢结构不规则曲线形造型。

Figure 202211292857

The invention relates to a construction method of a three-dimensional truss system in an irregularly curved space of a super-large-span building, which comprises the steps of constructing an irregularly curved truss model in a computer, completing the processing and manufacture of truss members; determining the position of the tire frame, and assembling the tire frame; The three-dimensional trusses are divided into three groups; the three-dimensional trusses are hoisted in sections according to the irregular curve truss model. The invention solves the problem that the large-diameter and thick-walled rods are difficult to pre-arch during the assembly process of the truss, and solves the problem that the assembly tire frame follows the hoisting construction process in the traditional construction process by selecting a reasonable assembly site location and hoisting construction sequence The difficulty of repeatedly moving and assembling improves the construction efficiency and saves the construction period. In addition, each truss is hoisted in two sections, and the middle position is supported by a "square" as a temporary support tire frame. The deflection and deformation of the entire truss system are minimized during the hoisting process, and the irregular curved shape of the roof steel structure is guaranteed to the greatest extent.

Figure 202211292857

Description

一种超大跨度建筑不规则曲线空间立体桁架体系施工方法A Construction Method of Irregular Curved Space Three-dimensional Truss System for Super-Large-span Buildings

技术领域technical field

本发明涉及钢结构工程的技术领域,尤其是涉及一种超大跨度建筑不规则曲线空间立体桁架体系施工方法。The invention relates to the technical field of steel structure engineering, in particular to a construction method for a three-dimensional truss system in an irregular curved space of a super-large-span building.

背景技术Background technique

随着社会经济水平的提高,大型会馆、体育中心、大型机场需求量越来越多,超大跨度、造型复杂不规则线型桁架越来越广泛的应用到建筑设计中,大跨度桁架具有自重轻、承载性能好、强度高,且能提供超大空间,节省材料,同时能满足各种造型需要。但是超大跨度不规则曲线桁架空间立体桁架在场地受限的情况下拼装困难、且跟随桁架吊装进进度,拼装胎架需要反复移动,吊装难度巨大,且桁架安装完成后保证桁架本身不规则曲线造型困难,如何科学、有序、合理、经济的组织超大跨度桁架吊装将对这个施工的质量、进度把控、工期要求以及施工成本控制起到关键性的作用。With the improvement of social and economic level, there are more and more demands for large-scale clubhouses, sports centers, and large-scale airports. Super-long-span, complex-shaped and irregular-line trusses are more and more widely used in architectural design. Long-span trusses have light weight. , good load-bearing performance, high strength, and can provide a large space, save materials, and can meet various modeling needs. However, the super-large-span irregular curved truss space three-dimensional truss is difficult to assemble when the site is limited, and it follows the progress of the truss hoisting. The assembled tire frame needs to be moved repeatedly, and the hoisting is extremely difficult. After the truss is installed, the irregular curve shape of the truss itself is guaranteed. Difficulties, how to scientifically, orderly, rationally and economically organize the hoisting of super-large-span trusses will play a key role in the construction quality, progress control, construction period requirements and construction cost control.

发明内容Contents of the invention

为了解决以上存在的技术问题,本发明提供一种超大跨度建筑不规则曲线空间立体桁架体系施工方法。In order to solve the above existing technical problems, the present invention provides a construction method of a three-dimensional truss system in an irregular curved space of a super-large-span building.

本发明提供的一种超大跨度建筑不规则曲线空间立体桁架体系施工方法采用如下的技术方案:The construction method of a three-dimensional truss system with irregular curved space for a super-large-span building provided by the present invention adopts the following technical scheme:

一种超大跨度建筑不规则曲线空间立体桁架体系施工方法,包括以下步骤:A construction method for a three-dimensional truss system with an irregular curved space in a super-large-span building, comprising the following steps:

S1.在计算机内构建不规则曲线桁架模型,完成桁架杆件的加工制作;S1. Construct the irregular curve truss model in the computer, and complete the processing and production of the truss members;

S2.根据计算机内构建的不规则曲线桁架模型确定胎架位置,对所述胎架进行拼装;S2. Determine the tire frame position according to the irregular curve truss model built in the computer, and assemble the tire frame;

S3. 将所述空间立体桁架分成北侧桁架、中间桁架和南侧桁架三组,其中,每榀所述桁架包括为两段对称分布的上弦杆、两段对称分布的下弦杆及若干桁架间连杆;S3. Divide the three-dimensional space trusses into three groups of north side trusses, middle trusses and south side trusses, wherein each truss includes two symmetrically distributed upper chords, two symmetrically distributed lower chords and several truss spaces link;

S4.根据所述不规则曲线桁架模型对所述空间立体桁架分段吊装;S4. hoisting the space three-dimensional truss in sections according to the irregular curve truss model;

a1.吊装拼接北侧桁架及北侧桁架间连杆,所述北侧桁架及北侧桁架连杆由北向南依次吊装,每榀桁架分两段吊装;a1. Hoisting and splicing the north truss and the connecting rod between the north trusses, the north truss and the north truss connecting rod are hoisted sequentially from north to south, and each truss is hoisted in two sections;

a2.吊装拼接南侧桁架及南侧桁架间连杆,所述南侧桁架及南侧桁架连杆由南向北依次吊装,每榀桁架分两段吊装;a2. Hoisting and splicing the south truss and the connecting rod between the south trusses, the south truss and the south truss connecting rod are hoisted sequentially from south to north, and each truss is hoisted in two sections;

a3.将中间桁架移到施工厂区的空地备用,拆除拼装左右两侧的胎架;a3. Move the middle truss to the open space in the construction factory area for standby, and remove and assemble the tire frames on the left and right sides;

a4.吊装中间桁架,其中,中间桁架为三榀桁架,先吊装左右两侧的两榀桁架及连杆。a4. Hoist the middle truss, wherein the middle truss is three trusses, and the two trusses and connecting rods on the left and right sides are hoisted first.

通过采用上述技术方案,解决了大直径大壁厚杆件在桁架在拼装过程中预起拱困难的情况,并通过选择合理的拼装场地位置及吊装施工顺序,解决了传统施工过程中拼装胎架跟随吊装施工过程反复移动拼装的难题,提高了施工效率,节省施工工期。By adopting the above-mentioned technical scheme, the difficult situation of pre-arching of large-diameter and thick-walled rods during the truss assembly process is solved, and by selecting a reasonable assembly site location and hoisting construction sequence, it solves the problem of assembling tire frames in the traditional construction process. Follow the lifting construction process to repeatedly move and assemble the problem, which improves the construction efficiency and saves the construction period.

优选的,在所述步骤S1中包括:Preferably, the step S1 includes:

根据设计图利用CAD完成桁架三维线型模型建立;According to the design drawing, use CAD to complete the establishment of the three-dimensional linear model of the truss;

导入结构计算软件MIDAS中,计算得到所述空间立体桁架每个节点位置的竖向位移值,所述位移值为所述空间立体桁架节点位置的起拱值;Into the structural calculation software MIDAS, calculate the vertical displacement value of each node position of the space three-dimensional truss, and the displacement value is the camber value of the node position of the space three-dimensional truss;

通过深化设计软件TEKLA完成所述空间立体桁架模型的建立,将所述起拱值反向施加到所述空间立体桁架的每个节点的位置,完成桁架杆件加工图纸,最终完成桁架各组成杆件的加工制作。The establishment of the spatial three-dimensional truss model is completed through the detailed design software TEKLA, and the arching value is reversely applied to the position of each node of the spatial three-dimensional truss, the processing drawings of the truss rods are completed, and the components of the truss are finally completed The processing and production of parts.

优选的,在所述步骤S2中包括:Preferably, said step S2 includes:

所述胎架设置在两个相邻的所述空间立体桁架之间。The tire frame is arranged between two adjacent three-dimensional trusses.

优选的,在所述步骤S4中包括:Preferably, the step S4 includes:

先吊装每榀所述桁架的第一段,根据所述不规则曲线桁架模型确定桁架位置固定;First hoist the first section of each truss, and determine that the position of the truss is fixed according to the irregular curve truss model;

安装“井”字支撑架对第一段桁架进行支撑;Install the "well" support frame to support the first section of the truss;

吊装每榀桁架的第二段,对所述空间立体桁架进行高空焊接。The second section of each truss is hoisted, and the space three-dimensional truss is welded at high altitude.

通过采用上述技术方案,桁架吊装过程中每榀桁架分两段吊装,中间位置采用“井字”支撑作为临时支撑胎架,整个桁架体系吊装过程中挠度变形最小,最大程度的保证了屋盖钢结构不规则曲线形造型。By adopting the above-mentioned technical scheme, each truss is hoisted in two sections during the hoisting process of the trusses, and the "well-shaped" support is used as the temporary support tire frame in the middle position. Structural irregular curved shape.

优选的,焊接每段桁架的步骤包括:Preferably, the step of welding each section of truss includes:

将所述下弦杆吊装至所述胎架,控制好每一节点标高位置后点焊固定;Lift the lower chord to the tire frame, control the elevation of each node and fix it by spot welding;

然后拼装固定上弦杆,再安装桁架间连杆,确认拼装尺寸后进行全方位高空焊接。Then assemble and fix the upper chord, then install the connecting rods between the trusses, and carry out all-round high-altitude welding after confirming the assembly size.

优选的,所述高空焊接的步骤包括:Preferably, the step of high-altitude welding comprises:

计算机内测量所述胎架与所述空间立体桁架的特征点的相对定位尺寸,根据数值对超差部分进行调整;Measure the relative positioning dimensions of the tire frame and the feature points of the space three-dimensional truss in the computer, and adjust the out-of-tolerance part according to the value;

调整完毕后,对所述空间异形钢管桁架进行焊接;After the adjustment is completed, the space special-shaped steel pipe truss is welded;

焊接完后,对焊缝进行100%超声波探伤检测。After welding, 100% ultrasonic flaw detection is carried out on the weld.

综上所述,本发明具有如下的有益技术效果:In summary, the present invention has the following beneficial technical effects:

本发明所述的一种超大跨度建筑不规则曲线空间立体桁架体系施工方法,解决了大直径大壁厚杆件在桁架在拼装过程中预起拱困难的情况,并通过选择合理的拼装场地位置及吊装施工顺序,解决了传统施工过程中拼装胎架跟随吊装施工过程反复移动拼装的难题,提高了施工效率,节省施工工期。且桁架吊装过程中每榀桁架分两段吊装,中间位置采用“井字”支撑作为临时支撑胎架,整个桁架体系吊装过程中挠度变形最小,最大程度的保证了屋盖钢结构不规则曲线形造型。The construction method of the three-dimensional truss system in the irregular curved space of the super-large-span building described in the present invention solves the difficulty of pre-arching the large-diameter and thick-walled rods during the assembling process of the truss, and selects a reasonable location for the assembling site. And the hoisting construction sequence, which solves the problem of repeated movement and assembly of the assembled tire frame following the hoisting construction process in the traditional construction process, improves the construction efficiency and saves the construction period. In addition, during the hoisting process of the trusses, each truss is hoisted in two sections, and the middle position is supported by a "square" as a temporary support tire frame. The deflection and deformation of the entire truss system are minimized during the hoisting process, and the irregular curved shape of the roof steel structure is guaranteed to the greatest extent. modeling.

附图说明Description of drawings

图1是本发明中桁架吊装顺序示意图。Fig. 1 is a schematic diagram of the hoisting sequence of the truss in the present invention.

具体实施方式Detailed ways

以下结合附图1对本发明作进一步详细说明。The present invention will be described in further detail below in conjunction with accompanying drawing 1 .

本发明实施例公开一种超大跨度建筑不规则曲线空间立体桁架体系施工方法。参照图1,包括以下步骤:The embodiment of the invention discloses a construction method of a three-dimensional truss system in an irregular curved space of a super-large-span building. Referring to Figure 1, the following steps are included:

S1.在计算机内构建不规则曲线桁架模型,完成桁架杆件的加工制作;S1. Construct the irregular curve truss model in the computer, and complete the processing and production of the truss members;

具体的,根据设计图利用CAD完成桁架三维线型模型建立;Specifically, use CAD to complete the establishment of the three-dimensional line model of the truss according to the design drawing;

导入结构计算软件MIDAS中,计算得到空间立体桁架每个节点位置的竖向位移值,位移值为空间立体桁架节点位置的起拱值,其中,按照桁架的施工工艺流程及桁架要承受荷载施加金属屋面自重荷载、桁架本体自重荷载、屋面活荷载、雪荷载、风荷载,计算得到桁架上、下弦每个节点位置的竖向位移值,此位移值为桁架节点位置的起拱值;Imported into the structural calculation software MIDAS, the vertical displacement value of each node position of the spatial three-dimensional truss is calculated, and the displacement value is the arching value of the node position of the spatial three-dimensional truss. Roof self-weight load, truss body self-weight load, roof live load, snow load, wind load, calculate the vertical displacement value of each node position of the upper and lower chords of the truss, and this displacement value is the arching value of the truss node position;

通过深化设计软件TEKLA完成桁架模型的建立,将起拱值反向施加到桁架的每个节点的位置,完成桁架杆件加工图纸,最终完成桁架各组成杆件的加工制作。The establishment of the truss model is completed through the detailed design software TEKLA, the camber value is reversely applied to the position of each node of the truss, the processing drawings of the truss members are completed, and finally the processing and manufacture of each component member of the truss is completed.

S2.根据计算机内构建的不规则曲线桁架模型确定胎架位置,对胎架进行拼装;S2. Determine the position of the tire frame according to the irregular curve truss model built in the computer, and assemble the tire frame;

具体的,胎架设置在两个相邻的空间立体桁架之间。Specifically, the tire frame is arranged between two adjacent three-dimensional trusses.

需要说明的是,为保证结构拼装施工安全可靠,对拼装胎架需要场地进行整平处理,并进行渣石填放压实,立杆局部部位设置1.5m*1.5m*0.01m混凝土找平,便于拼装。由于场地受限,桁架不能整榀拼装,每榀桁架分两段进行拼装,拼装场地设置在场地中间位置,需要布置两组胎架,每组拼装胎架能够拼装两个半榀桁架,两组胎架能够同时同时拼装2榀桁架。进行胎架拼装时,结合吊装顺序,先拼装北侧4榀桁架,然后拼装南侧4榀桁架,最后拼装中间位置3榀桁架。It should be noted that in order to ensure the safety and reliability of the structural assembly construction, the site for the assembled tire frame needs to be leveled, and the slag should be filled and compacted. The local parts of the poles are leveled with 1.5m*1.5m*0.01m concrete leveling, which is convenient assembled. Due to the limited space, the trusses cannot be assembled as a whole. Each truss is assembled in two sections. The assembly site is set in the middle of the field. The tire frame can assemble 2 trusses at the same time. When assembling the tire frame, according to the hoisting order, first assemble the 4 trusses on the north side, then assemble the 4 trusses on the south side, and finally assemble the 3 trusses in the middle.

S3. 将空间立体桁架分成北侧桁架、中间桁架和南侧桁架三组,其中,每榀桁架包括为两段对称分布的上弦杆、两段对称分布的下弦杆及若干桁架间连杆;S3. Divide the three-dimensional space trusses into three groups of north trusses, middle trusses and south trusses, where each truss includes two symmetrically distributed top chords, two symmetrically distributed bottom chords and several connecting rods between trusses;

需要说明的是,桁架结构为不规则曲线空间立体倒三角形桁架,跨度达到117米,自重为128吨到240吨不等,共计11榀桁架,桁架上、下弦主弦杆高度为6米,上弦杆宽度为4米,腹杆间距为7.5米。It should be noted that the truss structure is an irregular curved space three-dimensional inverted triangular truss with a span of 117 meters and a dead weight ranging from 128 tons to 240 tons. There are 11 trusses in total. The pole width is 4 meters, and the distance between the web poles is 7.5 meters.

S4.根据不规则曲线桁架模型对空间立体桁架分段吊装;S4. According to the irregular curve truss model, the space three-dimensional truss is hoisted in sections;

具体的,先吊装每榀桁架的第一段,根据不规则曲线桁架模型确定桁架位置固定;Specifically, the first section of each truss is hoisted first, and the position of the truss is fixed according to the irregular curve truss model;

安装“井”字支撑架对第一段桁架进行支撑;其中,每榀桁架分两段进行吊装,第一段安装时,需要设置临时支撑进行支撑。临时井字支撑采用塔吊标准节作为支撑,每个标准节的尺寸为1.8米*1.8米*2.8米。标准节采用方管塔吊标准节作为支撑,塔吊每个标准节长宽高为1.8米*1.8米*2.8米。标准节四支主杆为方管135*135*12,直腹杆为方管50*50*5,斜腹杆为方管80*80*6及方管70*70*6.标准节与标准节之间通过M36大六角螺栓连接。根据每榀主桁架上弦杆的实际标高,通过在支撑顶部加设顶部转换工装支撑立管,支撑立管顶面与弦杆接触部位切为圆弧状,与上弦杆能够有效贴合,防止滑动造成危险。Install the "well" support frame to support the first section of the truss; among them, each truss is hoisted in two sections, and when the first section is installed, it is necessary to set up temporary supports for support. The temporary well support is supported by tower crane standard sections, and the size of each standard section is 1.8m*1.8m*2.8m. The standard section is supported by the square tube tower crane standard section, and the length, width and height of each standard section of the tower crane are 1.8m*1.8m*2.8m. The four main bars of the standard section are square tubes 135*135*12, the straight web bars are square tubes 50*50*5, the oblique web bars are square tubes 80*80*6 and square tubes 70*70*6. The standard section and The standard sections are connected by M36 large hexagonal bolts. According to the actual elevation of the upper chord of each main truss, by adding a top conversion tooling support standpipe on the top of the support, the top surface of the support riser and the contact part of the chord are cut into an arc shape, which can effectively fit with the upper chord and prevent sliding cause danger.

吊装每榀桁架的第二段,对空间立体桁架进行高空焊接。Lift the second section of each truss, and perform high-altitude welding on the three-dimensional truss.

a1.吊装拼接北侧桁架及北侧桁架间连杆,北侧桁架及北侧桁架连杆由北向南依次吊装,每榀桁架分两段吊装;a1. Hoisting and splicing the north truss and the connecting rod between the north trusses, the north truss and the north truss connecting rod are hoisted sequentially from north to south, and each truss is hoisted in two sections;

a2.吊装拼接南侧桁架及南侧桁架间连杆,南侧桁架及南侧桁架连杆由南向北依次吊装,每榀桁架分两段吊装;a2. Hoisting and splicing the south truss and the connecting rod between the south trusses, the south truss and the south truss connecting rod are hoisted sequentially from south to north, and each truss is hoisted in two sections;

a3.将中间桁架移到施工厂区的空地备用,拆除拼装左右两侧的胎架;a3. Move the middle truss to the open space in the construction factory area for standby, and remove and assemble the tire frames on the left and right sides;

a4.吊装中间桁架,其中,中间桁架为三榀桁架,先吊装左右两侧的两榀桁架及连杆。a4. Hoist the middle truss, wherein the middle truss is three trusses, and the two trusses and connecting rods on the left and right sides are hoisted first.

最优的吊装顺序能够最大程度的降低施工成本,加快施工进度,确保施工安全。首先采用350吨履带吊吊装北侧4榀桁架及桁架间连杆,4榀桁架及连杆由北向南依次吊装,每榀桁架分2段吊装;再次用350吨履带吊吊装南侧4榀桁架及连杆,4榀桁架及连杆由南向北依次吊装,每榀桁架分两段吊装;再次拼装完成中间部位3榀桁架,共计6段,移到施工厂区的空地备用,拆除拼装胎架;再次用350吨履带吊吊装中间桁架左侧、右侧两榀桁架及连杆,吊装完成后拆除履带吊,最后中间位置桁架吊装每段用两台500t汽车吊进行抬吊。The optimal hoisting sequence can minimize construction costs, speed up construction progress, and ensure construction safety. First, use a 350-ton crawler crane to hoist the 4 trusses on the north side and the connecting rods between the trusses. The 4 trusses and connecting rods are hoisted sequentially from north to south, and each truss is hoisted in two sections; again, use a 350-ton crawler crane to hoist the 4 trusses on the south side. And connecting rods, 4 trusses and connecting rods are hoisted sequentially from south to north, and each truss is hoisted in two sections; the 3 trusses in the middle part are assembled again, with a total of 6 sections, and they are moved to the open space of the construction plant for standby, and the assembled tire frame is removed ; Use a 350-ton crawler crane to hoist the two trusses and connecting rods on the left and right sides of the middle truss again. After the hoisting is completed, remove the crawler crane, and finally use two 500-ton truck cranes to lift each section of the middle truss.

具体的,焊接每段桁架的步骤包括:Specifically, the steps of welding each truss include:

将下弦杆吊装至胎架,控制好每一节点标高位置后点焊固定;Hoist the lower chord to the tire frame, control the elevation of each node and fix it by spot welding;

然后拼装固定上弦杆,再安装桁架间连杆,确认拼装尺寸后进行全方位高空焊接。Then assemble and fix the upper chord, then install the connecting rods between the trusses, and carry out all-round high-altitude welding after confirming the assembly size.

需要说明的是,桁架拼装过程中,利用50t汽车吊先将下弦杆件吊运至拼装胎架,测量节点部位每一点的标高值,控制好分段对接的位置并临时点焊固定,然后用汽车吊依次吊运上弦主杆并定位,上、下弦杆采用经纬仪、全站仪、水准仪等尺寸标高、位置复测尺寸无误后进行腹杆的拼装,确认桁架拼装尺寸无误后,从中间向两侧对称平衡进行施焊,使焊接引起的变形降到最小。It should be noted that during the assembly process of the truss, the lower chord members are hoisted to the assembled tire frame by using a 50t truck crane, the elevation value of each point of the node is measured, and the position of the segmented butt joint is controlled and temporarily fixed by spot welding. The truck crane lifts and positions the upper chord main rod in turn. The upper and lower chord rods are re-measured with theodolite, total station, level and other dimensions, elevations, and positions. After the size is correct, the web rods are assembled. Welding is carried out with lateral symmetrical balance to minimize the deformation caused by welding.

在本发明的描述中,需要说明的是,术语“中心”、“上”、“下”、“左”、“右”、“竖直”、“水平”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制;术语“第一”、“第二”、“第三”仅用于描述目的,而不能理解为指示或暗示相对重要性,此外,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer" etc. The indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, or in a specific orientation. construction and operation, and therefore should not be construed as limiting the present invention; the terms "first", "second", and "third" are used for descriptive purposes only, and should not be construed as indicating or implying relative importance, and unless otherwise Clearly stipulated and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or a Electrical connection; it can be directly connected or indirectly connected through an intermediary, and it can be the internal communication of two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.

以上均为本发明的较佳实施例,并非依此限制本发明的保护范围,故:凡依本发明的结构、形状、原理所做的等效变化,均应涵盖于本发明的保护范围之内。The above are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention, so: all equivalent changes made according to the structure, shape and principle of the present invention should be covered by the protection scope of the present invention Inside.

Claims (6)

1.一种超大跨度建筑不规则曲线空间立体桁架体系施工方法,其特征在于:包括以下步骤:1. A method for construction of a three-dimensional truss system with irregular curves in a super-large-span building, characterized in that: comprising the following steps: S1.在计算机内构建不规则曲线桁架模型,完成桁架杆件的加工制作;S1. Construct the irregular curve truss model in the computer, and complete the processing and production of the truss members; S2.根据计算机内构建的不规则曲线桁架模型确定胎架位置,对所述胎架进行拼装;S2. Determine the tire frame position according to the irregular curve truss model built in the computer, and assemble the tire frame; S3. 将所述空间立体桁架分成北侧桁架、中间桁架和南侧桁架三组,其中,每榀所述桁架包括为两段对称分布的上弦杆、两段对称分布的下弦杆及若干桁架间连杆;S3. Divide the three-dimensional space trusses into three groups of north side trusses, middle trusses and south side trusses, wherein each truss includes two symmetrically distributed upper chords, two symmetrically distributed lower chords and several truss spaces link; S4.根据所述不规则曲线桁架模型对所述空间立体桁架分段吊装;S4. hoisting the space three-dimensional truss in sections according to the irregular curve truss model; a1.吊装拼接北侧桁架及北侧桁架间连杆,所述北侧桁架及北侧桁架连杆由北向南依次吊装,每榀桁架分两段吊装;a1. Hoisting and splicing the north truss and the connecting rod between the north trusses, the north truss and the north truss connecting rod are hoisted sequentially from north to south, and each truss is hoisted in two sections; a2.吊装拼接南侧桁架及南侧桁架间连杆,所述南侧桁架及南侧桁架连杆由南向北依次吊装,每榀桁架分两段吊装;a2. Hoisting and splicing the south truss and the connecting rod between the south trusses, the south truss and the south truss connecting rod are hoisted sequentially from south to north, and each truss is hoisted in two sections; a3.将中间桁架移到施工厂区的空地备用,拆除拼装左右两侧的胎架;a3. Move the middle truss to the open space in the construction factory area for standby, and remove and assemble the tire frames on the left and right sides; a4.吊装中间桁架,其中,中间桁架为三榀桁架,先吊装左右两侧的两榀桁架及连杆。a4. Hoist the middle truss, wherein the middle truss is three trusses, and the two trusses and connecting rods on the left and right sides are hoisted first. 2.根据权利要求1所述的一种超大跨度建筑不规则曲线空间立体桁架体系施工方法,其特征在于:在所述步骤S1中包括:2. The construction method of a three-dimensional truss system with irregular curved spaces for super-large-span buildings according to claim 1, characterized in that: in the step S1, it includes: 根据设计图利用CAD完成桁架三维线型模型建立;According to the design drawing, use CAD to complete the establishment of the three-dimensional linear model of the truss; 导入结构计算软件MIDAS中,计算得到所述空间立体桁架每个节点位置的竖向位移值,所述位移值为所述空间立体桁架节点位置的起拱值;Into the structural calculation software MIDAS, calculate the vertical displacement value of each node position of the space three-dimensional truss, and the displacement value is the camber value of the node position of the space three-dimensional truss; 通过深化设计软件TEKLA完成所述空间立体桁架模型的建立,将所述起拱值反向施加到所述空间立体桁架的每个节点的位置,完成桁架杆件加工图纸,最终完成桁架各组成杆件的加工制作。The establishment of the spatial three-dimensional truss model is completed through the detailed design software TEKLA, and the arching value is reversely applied to the position of each node of the spatial three-dimensional truss, the processing drawings of the truss rods are completed, and the components of the truss are finally completed The processing and production of parts. 3.根据权利要求1所述的一种超大跨度建筑不规则曲线空间立体桁架体系施工方法,其特征在于:在所述步骤S2中包括:3. The construction method of a three-dimensional truss system with irregular curved spaces for super-large-span buildings according to claim 1, characterized in that: in the step S2, it includes: 所述胎架设置在两个相邻的所述空间立体桁架之间。The tire frame is arranged between two adjacent three-dimensional trusses. 4.根据权利要求1所述的一种超大跨度建筑不规则曲线空间立体桁架体系施工方法,其特征在于:在所述步骤S4中包括:4. The construction method of a three-dimensional truss system with irregular curved spaces for super-large-span buildings according to claim 1, characterized in that: in the step S4, it includes: 先吊装每榀所述桁架的第一段,根据所述不规则曲线桁架模型确定桁架位置固定;First hoist the first section of each truss, and determine that the position of the truss is fixed according to the irregular curve truss model; 安装“井”字支撑架对第一段桁架进行支撑;Install the "well" support frame to support the first section of the truss; 吊装每榀桁架的第二段,对所述空间立体桁架进行高空焊接。The second section of each truss is hoisted, and the space three-dimensional truss is welded at high altitude. 5.根据权利要求4所述的一种超大跨度建筑不规则曲线空间立体桁架体系施工方法,其特征在于:焊接每段桁架的步骤包括:5. The construction method of a three-dimensional truss system in an irregularly curved space in a super-large-span building according to claim 4, wherein the step of welding each truss comprises: 将所述下弦杆吊装至所述胎架,控制好每一节点标高位置后点焊固定;Lift the lower chord to the tire frame, control the elevation of each node and fix it by spot welding; 然后拼装固定上弦杆,再安装桁架间连杆,确认拼装尺寸后进行全方位高空焊接。Then assemble and fix the upper chord, then install the connecting rods between the trusses, and carry out all-round high-altitude welding after confirming the assembly size. 6.根据权利要求5所述的一种超大跨度建筑不规则曲线空间立体桁架体系施工方法,其特征在于:所述高空焊接的步骤包括:6. The construction method of a three-dimensional truss system with irregular curves in super-large-span buildings according to claim 5, wherein the high-altitude welding step comprises: 计算机内测量所述胎架与所述空间立体桁架的特征点的相对定位尺寸,根据数值对超差部分进行调整;Measure the relative positioning dimensions of the tire frame and the feature points of the space three-dimensional truss in the computer, and adjust the out-of-tolerance part according to the value; 调整完毕后,对所述空间异形钢管桁架进行焊接;After the adjustment is completed, the space special-shaped steel pipe truss is welded; 焊接完后,对焊缝进行100%超声波探伤检测。After welding, 100% ultrasonic flaw detection is carried out on the weld.
CN202211292857.6A 2022-10-21 2022-10-21 Construction method of irregular curve space three-dimensional truss system of super-large-span building Pending CN115404994A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211292857.6A CN115404994A (en) 2022-10-21 2022-10-21 Construction method of irregular curve space three-dimensional truss system of super-large-span building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211292857.6A CN115404994A (en) 2022-10-21 2022-10-21 Construction method of irregular curve space three-dimensional truss system of super-large-span building

Publications (1)

Publication Number Publication Date
CN115404994A true CN115404994A (en) 2022-11-29

Family

ID=84168327

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211292857.6A Pending CN115404994A (en) 2022-10-21 2022-10-21 Construction method of irregular curve space three-dimensional truss system of super-large-span building

Country Status (1)

Country Link
CN (1) CN115404994A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116984787A (en) * 2023-08-17 2023-11-03 上海建工(江苏)钢结构有限公司 Construction process of rectangular frame with super-long cross-diamond rods
CN117605287A (en) * 2023-10-17 2024-02-27 中铁建工集团有限公司 A wind-resistant lifting construction method for ultra-high heavy-duty connecting trusses

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104847017A (en) * 2015-05-25 2015-08-19 中国航空规划建设发展有限公司 Novel prestress industrial stockyard canopy structure and method for constructing same
WO2017121315A1 (en) * 2016-01-12 2017-07-20 广州机施建设集团有限公司 Construction method for building truss and floor slab
CN107524261A (en) * 2017-09-14 2017-12-29 中铁上海工程局集团第五工程有限公司 A kind of construction method of roofing Elements of Space Grid Truss
CN108894496A (en) * 2018-07-19 2018-11-27 中铁城建集团北京工程有限公司 A kind of over-the-counter construction method of Large-span Truss String Structure beam
CN109025286A (en) * 2018-07-20 2018-12-18 中建三局第三建设工程有限责任公司 A kind of construction method of large span high-altitude three-dimensional canopy of the heavens steel construction
CN110130627A (en) * 2019-05-23 2019-08-16 中国二十二冶集团有限公司 Large Span Structure of Arch surface mesh roofing construction platform and construction method
CN110259145A (en) * 2019-06-28 2019-09-20 中冶建工集团有限公司 A kind of arch tubular truss rapid constructing method
CN113123469A (en) * 2021-03-24 2021-07-16 中国五冶集团有限公司 Method for constructing complex curved surface modeling roof grid structure
CN113719139A (en) * 2021-10-13 2021-11-30 中建八局第二建设有限公司 Construction method for hoisting irregular space net rack of stadium

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104847017A (en) * 2015-05-25 2015-08-19 中国航空规划建设发展有限公司 Novel prestress industrial stockyard canopy structure and method for constructing same
WO2017121315A1 (en) * 2016-01-12 2017-07-20 广州机施建设集团有限公司 Construction method for building truss and floor slab
CN107524261A (en) * 2017-09-14 2017-12-29 中铁上海工程局集团第五工程有限公司 A kind of construction method of roofing Elements of Space Grid Truss
CN108894496A (en) * 2018-07-19 2018-11-27 中铁城建集团北京工程有限公司 A kind of over-the-counter construction method of Large-span Truss String Structure beam
CN109025286A (en) * 2018-07-20 2018-12-18 中建三局第三建设工程有限责任公司 A kind of construction method of large span high-altitude three-dimensional canopy of the heavens steel construction
CN110130627A (en) * 2019-05-23 2019-08-16 中国二十二冶集团有限公司 Large Span Structure of Arch surface mesh roofing construction platform and construction method
CN110259145A (en) * 2019-06-28 2019-09-20 中冶建工集团有限公司 A kind of arch tubular truss rapid constructing method
CN113123469A (en) * 2021-03-24 2021-07-16 中国五冶集团有限公司 Method for constructing complex curved surface modeling roof grid structure
CN113719139A (en) * 2021-10-13 2021-11-30 中建八局第二建设有限公司 Construction method for hoisting irregular space net rack of stadium

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116984787A (en) * 2023-08-17 2023-11-03 上海建工(江苏)钢结构有限公司 Construction process of rectangular frame with super-long cross-diamond rods
CN117605287A (en) * 2023-10-17 2024-02-27 中铁建工集团有限公司 A wind-resistant lifting construction method for ultra-high heavy-duty connecting trusses

Similar Documents

Publication Publication Date Title
CN114086669B (en) A modular rapid construction method for large space special-shaped curved surface steel grids
CN115506604B (en) Method for installing first truss of large-span steel structure
WO2024148715A1 (en) Method for erecting continuous steel truss bridge
CN111809528B (en) A pier column vertical cage platform channel construction method and cage platform channel device
CN107100309A (en) A kind of construction method for the large-scale multi-angular cantilever frame of integral hoisting
CN108049666B (en) A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction
CN114263114A (en) Construction system and construction method of large-section steel box girder
CN116446530A (en) High-rise umbrella-shaped eccentric overhanging steel structure and construction method thereof
CN115404994A (en) Construction method of irregular curve space three-dimensional truss system of super-large-span building
CN108678181A (en) Silo roof steel truss and concrete combined structure high-altitude construction method
CN117027183A (en) Pistil steel structure and construction method thereof
CN116770980A (en) Extra-long variable-height V-shaped large-span steel structure corridor and its construction method
CN109653517B (en) Multidirectional unloading system and construction method for assembling steel corridor by using same
CN209457263U (en) An assembled steel structure beam-slab connection structure
CN100366855C (en) Inclined triangular pyramid truss frame structure and its fabrication, installation and measurement methods
CN209686923U (en) Round tube combined support device and steel construction temporary construction support device
CN112240006A (en) Construction method for constructing large-span non-support steel box girder by cantilever process
CN109252590B (en) Super-long super-high giant diagonal brace and climbing type construction method thereof
CN118958695A (en) A method for assembling and constructing a large steel structure roof
CN205276472U (en) Large -span steel truss structure
CN118007799A (en) A method for assembling and lifting a large-span grid dome in circles and stages
CN213896812U (en) Temporary support for construction of large-span non-support steel box girder by cantilever process
CN116856298A (en) Construction technology of wide-width and large-tonnage swivel T-structure
CN211922324U (en) Prefabricated bent cap wet joint construction hangs mould system
CN103243927A (en) Double pole reverse operation combined hoisting construction method and double pole

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20221129