CN110130627A - Large Span Structure of Arch surface mesh roofing construction platform and construction method - Google Patents

Large Span Structure of Arch surface mesh roofing construction platform and construction method Download PDF

Info

Publication number
CN110130627A
CN110130627A CN201910435120.7A CN201910435120A CN110130627A CN 110130627 A CN110130627 A CN 110130627A CN 201910435120 A CN201910435120 A CN 201910435120A CN 110130627 A CN110130627 A CN 110130627A
Authority
CN
China
Prior art keywords
roofing
platform
grid
construction
installation unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910435120.7A
Other languages
Chinese (zh)
Inventor
王振波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201910435120.7A priority Critical patent/CN110130627A/en
Publication of CN110130627A publication Critical patent/CN110130627A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/08Vaulted roofs
    • E04B7/10Shell structures, e.g. of hyperbolic-parabolic shape; Grid-like formations acting as shell structures; Folded structures
    • E04B7/105Grid-like structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/18Scaffolds primarily resting on the ground adjustable in height
    • E04G1/22Scaffolds having a platform on an extensible substructure, e.g. of telescopic type or with lazy-tongs mechanism
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/36Scaffolds for particular parts of buildings or buildings of particular shape, e.g. for stairs, cupolas, domes

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The present invention relates to construction engineering technical field, specifically a kind of Large Span Structure of Arch surface mesh roofing construction platform.Including job platform, hydraulic lifting component and anti-sideslip component are provided on job platform.Multiple installation units are resolved into according to roofing truss, after the completion of installation on ground, it is installed from both ends to intermediate direction, calculates the prestressing force situation of each installation unit, setting installation supporting construction platform first in installation process, it often installs two and closes on unit, the connection between two units is first carried out, unloads the roofing installation unit stress of distal end after connection, removes supporting platform, it recycles and is installed to centre, be finally all installed roofing.The present invention has stronger specific aim in this structure type of steel arch curved surface network roofing, reduces waste of material, improves installation accuracy, construction operation platformization is safer, improves construction efficiency, reduces construction cost.

Description

Large Span Structure of Arch surface mesh roofing construction platform and construction method
Technical field
The present invention relates to construction engineering technical field, specifically a kind of Large Span Structure of Arch surface mesh roofing construction platform.
Background technique
Existing construction method is roofing truss to be decomposed into multiple installation units, and be arranged under entire roofing truss multiple The support bracket set by standard section of tower crane tower uses fashioned iron etc. after roofing truss installation unit reaches installation site on support bracket Supporting frame body is welded as a whole by material with roofing, and reaches stabilization, waits all roofing installation units in the sky The steel welded together with roofing are being cut away after the completion of assembled;Above-mentioned traditional construction method has the following insufficient: (1) There is a large amount of arch structure in this structure type of steel arch surface mesh roofing, does not allow in installation accuracy control easy to operate; It (2) is to need scene according to circumstances to wanting the materials such as last fashioned iron to carry out cutting guarantee when support frame is played a supporting role Bearing height meets the requirements, and the method is very big to technical measures material consumption, low in a little utilization rates after the cutting of the materials such as fashioned iron, needs Manually repeatedly to adjust can be only achieved requirement, and construction speed is slow;(3) need to be arranged a large amount of scaffold as the work of construction personnel Industry platform, measure circulation material is expensive, higher cost;(4) support frame is welded with roofing in the construction process, can be to room Surface member appearance is damaged, and finally also needs to carry out repair constructing, and the use paint in repair process, fire prevention apply The generations such as material, which are largely constructed, draws rubbish, increases the costs such as the artificial, material of construction.
Summary of the invention
Present invention seek to address that the above problem, to provide, a kind of structure is simple, and construction operation is convenient, can be improved construction Safety zone, control quality problems, and reduce waste of material, the Large Span Structure of Arch surface mesh roofing truss construction for saving cost is flat Platform and construction method.
The present invention solves described problem, the technical solution adopted is that:
A kind of Large Span Structure of Arch surface mesh roofing construction platform, including job platform are provided with hydraulic lifting group on job platform Part and anti-sideslip component, hydraulic lifting component include two hydraulic jacks, lifting support and conduit saddle, and lifting support is arranged two It in platform hydraulic jack, is realized and is gone up and down by hydraulic jack, conduit saddle is arranged on lifting support by support plate, is used for support The cast loose mail of roofing, anti-sideslip component include four spacing columns for preventing lifting support from shaking in lifting process, Four spacing columns in pairs and are respectively placed in the both ends of lifting support, and the both ends of lifting support are respectively placed in corresponding two In gap between spacing column.
Preferably, job platform is by two girders and four secondary beams and the riffled iron board group being laid on girder and secondary beam At.
Preferably, the girder lower end of job platform is provided with leg structure, and leg structure includes being welded on master in symmetry shape Four steel columns of beam lower end are respectively welded bearing diagonal, the lower end welding of every steel column between the two sides and girder of every steel column There is bottom plate.
Preferably, hydraulic lifting component and anti-sideslip component are correspondingly arranged and are respectively set two groups.
A kind of Large Span Structure of Arch surface mesh roof construction method is applied using Large Span Structure of Arch surface mesh roofing as described above Work platform carries out, and includes the following steps:
(1) entire arching surface grids roofing is designed decomposition, splits into multiple grid roofing truss installation units.
(2) each grid roofing truss installation unit is calculated using midas GEN calculating.
(3) erection sequence of grid roofing truss installation unit is to be installed from both ends to centre.
(4) six arching surface grids roofing constructions need to be set under grid roofing truss installation unit to be mounted each Platform.
(5) after the arrangement foundation midas GEN software for calculation Stress calculation of arching surface grids roofing construction platform, Determine that stress point is distributed.
(6) it acts as stress support platform, each bases for two arching surface grids roofing construction platforms of intermediate arrangement Progress position is calculated accordingly to move.
(7) it acts as installation and weld job platforms for two, the every end in both ends arching surface grids roofing construction platform.
(8) it is standard section of tower crane that each arching surface grids roofing construction platform, which is lower part, and top is arching surface grids roofing Operation platform.
(9) after the completion of arching surface grids roofing construction platform arrangement, the arching surface grids roofing construction platform at both ends is made It is attached with the operation platform that girder steel is arranged with Turbogrid plates, is connected as four arching surface grids roofing construction platforms at both ends One entirety.
(10) the good grid roofing truss installation unit of installation on ground is hung to six arching surface grids roofing construction platforms Conduit saddle on.
(11) adjust separately hydraulic jack (the hydraulic jack adjustment model of six arching surface grids roofing construction platforms Rising is trapped among to fall after rise in 100mm), it is adjusted to the position after the design of grid roofing truss installation unit calculates.
(12) construction personnel girder steel and Turbogrid plates setting operation platform on by grid roofing truss installation unit with Roof girder is welded.
(13) repeat the 4th to the 12nd step;
(14) are by first grid roofing truss installation unit and second grid roofing truss installation unit in girder steel and grid It is welded to connect on the operation platform of panel setting.
(15) are single by first grid roofing truss installation after the completion of two grid roofing truss installation units weld The hydraulic jack progress of two arching surface grids roofing construction platforms of the centre below member falls operation after rise, makes conduit saddle and grid Roofing truss installation unit is kept completely separate.
(16) first four, grid roofing truss installation unit both ends arching surface grids roofing construction platform is fallen after rise Hydraulic jack is kept completely separate conduit saddle with grid roofing truss installation unit.
(17) first remove the girder steel below first piece of grid roofing truss installation unit and the construction of Turbogrid plates setting Platform, then remove six arching surface grids roofing construction platforms connecting by girder steel with the operation platform that Turbogrid plates are arranged.
(18) repeat the 14th to the 17th step;
(19) are removed last girder steel and are applied with what Turbogrid plates were arranged after most latter two grid roofing truss installation unit closes up Work platform and arching surface grids roofing construction platform.
The present invention by adopting the above technical scheme, compared with prior art, the feature protruded is:
Structure is simple, eliminates the welding cutting operation of support construction, and construction operation is convenient, ensure that construction safety, improves Construction quality can reuse, and reduce waste of material, save cost.
Detailed description of the invention
Fig. 1 is the schematic perspective view of arching surface grids roofing construction platform of the embodiment of the present invention;
Fig. 2 is the schematic view of the front view of arching surface grids roofing construction platform of the embodiment of the present invention;
Fig. 3 is the side structure schematic view of arching surface grids roofing construction platform of the embodiment of the present invention;
Fig. 4 is the overlooking structure diagram of arching surface grids roofing construction platform of the embodiment of the present invention;
Fig. 5 is that arching surface grids roofing construction platform of the embodiment of the present invention installs layout drawing;
Fig. 6 is that arching surface grids roofing construction platform of the embodiment of the present invention is connect with girder steel with the operation platform that Turbogrid plates are arranged Structural schematic diagram;
Fig. 7 is the plane of grid roofing truss installation unit of the embodiment of the present invention with regard to bitmap;
Fig. 8 is the facade stress support figure in place of grid roofing truss installation unit of the embodiment of the present invention;
Fig. 9 is the attachment structure schematic diagram of two pieces of grid roofing truss installation units of the embodiment of the present invention;
Figure 10 is the stress unloading figure of first piece of grid roofing truss installation unit of the embodiment of the present invention;
Figure 11 is the structural schematic diagram after first piece of grid roofing truss installation unit operation platform of the embodiment of the present invention is removed;
Figure 12 is the perspective view of grid roofing truss installation unit of the embodiment of the present invention;
Figure 13 is the elevation after grid roofing truss installation unit of the embodiment of the present invention is installed;
Figure 14 is the plan view after grid roofing truss installation unit of the embodiment of the present invention is installed;
In figure: roof girder 1;Arching surface grids roofing construction platform 2;Conduit saddle 2-1;Hydraulic jack 2-2;Lifting support 2-3;Branch Fagging 2-4;Spacing column 2-5;Job platform 2-6;Leg structure 2-7;The operation platform 3 of girder steel and Turbogrid plates setting;Grid Roofing truss installation unit 4.
Specific embodiment:
Below with reference to embodiment, the invention will be further described, and purpose, which is only that, more fully understands the content of present invention, therefore, institute The example of act is not intended to limit protection scope of the present invention.
It is a kind of referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9, Figure 10, Figure 11, Figure 12, Figure 13, Figure 14 Large Span Structure of Arch surface mesh roofing construction platform, including hydraulic lifting component is provided on job platform 2-6, job platform 2-6 With anti-sideslip component, hydraulic lifting component includes two hydraulic jack 2-2, lifting support 2-3 and conduit saddle 2-1, lifting support 2-3 is arranged on two hydraulic jack 2-2, is realized and is gone up and down by hydraulic jack 2-2, and conduit saddle 2-1 is set by support plate 2-4 It sets on lifting support 2-3, for the cast loose mail of support roofing, anti-sideslip component includes four for preventing lifting support 2- The 3 spacing column 2-5, four spacing column 2-5 shaken in lifting process in pairs and are respectively placed in lifting support 2-3's Both ends, the both ends of lifting support 2-3 are respectively placed in the gap between corresponding two spacing column 2-5.
Job platform 2-6 by two H200mm × 200mm × 12mm × 12mm girder and four mm of 200mm × 200 × Based on the secondary beam of 8mm × 12, the upper anti-skid design steel plate for being laid with 6mm thickness is welded.
The girder lower end of job platform 2-6 is provided with leg structure 2-7, and leg structure 2-7 includes being welded in symmetry shape Four H200mm × 200mm × 12mm × 12mm steel columns of girder lower end, are welded respectively between the two sides and girder of every steel column It is connected to H100mm × 100mm × 6mm × 8mm bearing diagonal, the lower end of every steel column is welded with the bottom 250mm × 250mm × 10mm Plate.
Hydraulic lifting component and anti-sideslip component are correspondingly arranged and are respectively set two groups, and hydraulic lifting component is divided into two groups, Every component is the hydraulic jack 2-2 of lower part two, and top is lifting support 2-3, support plate 2-4 and conduit saddle 2-1, lifting support 2- 3 be H100mm × 100mm × 6mm × 8mm girder steel, support plate 2-4 be 10mm thick steel plate, conduit saddle 2-1 with a thickness of 6mm, diameter 300mm, hydraulic jack 2-2 and lifting support 2-3 can be replaced without welding for different structural points.
Anti- sideslip component includes four spacing column 2-5, and spacing column 2-5 is made for channel steel.
Production method: leg structure 2-7 is weldingly fixed on four sides below job platform 2-6, is pacified on job platform 2-6 Fill hydraulic lifting component, installation site according to actual needs supporting steel structural roof determine, after hydraulic lifting component is in place will Anti- sideslip component is located in the two sides of hydraulic lifting component, and welds to job platform 2-6, prevents hydraulic lifting component from shaking It is dynamic.
A kind of Large Span Structure of Arch surface mesh roof construction method is applied using Large Span Structure of Arch surface mesh roofing as described above Work platform carries out, and includes the following steps:
(1) entire arching surface grids roofing is designed decomposition, splits into multiple grid roofing truss installation units 4.
(2) each grid roofing truss installation unit 4 is calculated using midas GEN calculating.
(3) erection sequence of grid roofing truss installation unit 4 is to be installed from both ends to centre.
(4) six arching surface grids roofing constructions need to be set under grid roofing truss installation unit 4 to be mounted each Platform 2.
(5) after the arrangement foundation midas GEN software for calculation Stress calculation of arching surface grids roofing construction platform 2, Determine that stress point is distributed.
(6) it acts as stress support platform, each roots for two arching surface grids roofing construction platforms 2 of intermediate arrangement It is accordingly moved according to progress position is calculated.
(7) it acts as installation and weld job platforms for two, the every end in both ends arching surface grids roofing construction platform 2.
(8) it is standard section of tower crane that each arching surface grids roofing construction platform 2, which is lower part, and top is arching surface grids room Surface construction platform.
(9) after the completion of arching surface grids roofing construction platform 2 is arranged, by the arching surface grids roofing construction platform 2 at both ends The operation platform 3 being arranged using girder steel with Turbogrid plates is attached, and four arching surface grids roofing construction platforms 2 at both ends are connected It is connected in an entirety.
(10) the good grid roofing truss installation unit 4 of installation on ground is hung to six arching surface grids roofing construction platforms On 2 conduit saddle 2-1.
(11) adjust separately the hydraulic jack 2-2(hydraulic jack 2- of six arching surface grids roofing construction platforms 2 2 adjusting ranges are rising in falling 100mm), it is adjusted to the position after the design of grid roofing truss installation unit 4 calculates.
(12) construction personnel is on girder steel and the operation platform 3 of Turbogrid plates setting by grid roofing truss installation unit 4 It is welded with roof girder 1.
(13) repeat the 4th to the 12nd step;
(14) by first grid roofing truss installation unit 4 and second grid roofing truss installation unit 4 girder steel with It is welded to connect on the operation platform 3 of Turbogrid plates setting.
(15) install first grid roofing truss after the completion of two grid roofing truss installation units 4 weld The hydraulic jack 2-2 progress of two arching surface grids roofing construction platforms 2 of the centre below unit 4 falls operation after rise, makes pipe Support 2-1 is kept completely separate with grid roofing truss installation unit 4.
(16) first four, 4 both ends of grid roofing truss installation unit arching surface grids roofing construction platform 3 is fallen after rise Hydraulic jack 2-2, be kept completely separate conduit saddle 2-1 with grid roofing truss installation unit 4.
(17) first remove the girder steel below first piece of grid roofing truss installation unit 4 and the construction of Turbogrid plates setting Platform 3, then remove six arching surface grids roofing construction platforms 2 connecting by girder steel with the operation platform 3 that Turbogrid plates are arranged.
(18) repeat the 14th to the 17th step;
(19) remove last girder steel and Turbogrid plates setting after most latter two grid roofing truss installation unit 4 closes up Operation platform 3 and arching surface grids roofing construction platform 2.
Support component of the present invention eliminates the welded connecting of support and truss, and the welding cutting for eliminating support construction is made Industry improves construction safety, exempts scaffold building and removes work, significantly reduces the workload of construction personnel, tradition branch Recycling rate of waterused is low after support cutting, and needs to modify and could use, and the present invention is reusable, reduces the wave of material Take, reduces engineering cost and building waste (oil paint coating after roofing truss and support cutting).
The present invention resolves into multiple installation units according to roofing truss, after the completion of installation on ground, from both ends to third side To being installed, the prestressing force situation of each installation unit is calculated first in installation process, supporting construction platform is installed in setting, Often install two and close on unit, first carry out two units between connection, after connection by the roofing installation unit stress of distal end into Row unloading, removes supporting platform, recycles and installed to centre, be finally all installed roofing, in steel arch curved surface network There is stronger specific aim in this structure type of roofing, structure is simple, eliminates the welding cutting operation of support construction, and construction is made Industry is convenient, and construction operation platformization is safer, improves installation accuracy and construction quality, can reuse, reduce material Material waste, improves construction efficiency, reduces construction cost.
The foregoing is merely preferably feasible embodiment of the invention, not thereby limiting the scope of the invention, It is all to use equivalence changes made by description of the invention and its accompanying drawing content, it is intended to be included within the scope of the present invention.

Claims (5)

1. a kind of Large Span Structure of Arch surface mesh roofing construction platform, including job platform, it is characterised in that: be arranged on job platform There are hydraulic lifting component and anti-sideslip component, hydraulic lifting component includes two hydraulic jacks, lifting support and conduit saddle, lifting Support is arranged in two hydraulic jacks, is realized and is gone up and down by hydraulic jack, and conduit saddle is arranged by support plate in lifting branch On seat, for the cast loose mail of support roofing, anti-sideslip component includes four for preventing lifting support from shaking in lifting process Dynamic spacing column, four spacing columns in pairs and are respectively placed in the both ends of lifting support, the both ends difference of lifting support It is placed in the gap between corresponding two spacing columns.
2. Large Span Structure of Arch surface mesh roofing construction platform according to claim 1, it is characterised in that: job platform is by two Root girder and four secondary beams and the checkered steel plate being laid on girder and secondary beam composition.
3. Large Span Structure of Arch surface mesh roofing construction platform according to claim 2, it is characterised in that: the master of job platform Beam lower end is provided with leg structure, and leg structure includes four steel columns that girder lower end is welded in symmetry shape, every steel column Bearing diagonal is respectively welded between two sides and girder, the lower end of every steel column is welded with bottom plate.
4. Large Span Structure of Arch surface mesh roofing construction platform according to claim 1, it is characterised in that: hydraulic lifting component It is correspondingly arranged with anti-sideslip component and is respectively set two groups.
5. a kind of Large Span Structure of Arch surface mesh roof construction method, using Large Span Structure of Arch according to any one of claims 1-4 Surface mesh roofing construction platform carries out, which comprises the steps of:
(1) entire arching surface grids roofing is designed decomposition, splits into multiple grid roofing truss installation units;
(2) each grid roofing truss installation unit is calculated using midas GEN calculating;
(3) erection sequence of grid roofing truss installation unit is to be installed from both ends to centre;
(4) six arching surface grids roofing construction platforms need to be set under grid roofing truss installation unit to be mounted each;
(5) arrangement of arching surface grids roofing construction platform is determined according to after midas GEN software for calculation Stress calculation Stress point is distributed;
(6) it acts as stress support platforms for two arching surface grids roofing construction platforms of intermediate arrangement, every time according to calculating Position is carried out accordingly to move;
(7) it acts as installation and weld job platforms for two, the every end in both ends arching surface grids roofing construction platform;
(8) it is standard section of tower crane that each arching surface grids roofing construction platform, which is lower part, and top is arching surface grids roofing construction Platform;
(9) after the completion of arching surface grids roofing construction platform arrangement, the arching surface grids roofing construction platform at both ends is used into steel The operation platform that beam is arranged with Turbogrid plates is attached, and four arching surface grids roofing construction platforms at both ends is made to be connected as one It is whole;
(10) the good grid roofing truss installation unit of installation on ground is hung to the pipe of six arching surface grids roofing construction platforms In support;
(11) adjust separately the hydraulic jacks of six arching surface grids roofing construction platforms, and (hydraulic jack adjusting range exists Rise and fall after rise in 100mm), it is adjusted to the position after the design of grid roofing truss installation unit calculates;
(12) construction personnel is on girder steel and the operation platform of Turbogrid plates setting by grid roofing truss installation unit and roofing Beam is welded;
(13) repeat the 4th to the 12nd step;
(14) are by first grid roofing truss installation unit and second grid roofing truss installation unit in girder steel and grid It is welded to connect on the operation platform of panel setting;
(15), will be under first grid roofing truss installation unit after the completion of two grid roofing truss installation units weld The hydraulic jack progress of two arching surface grids roofing construction platforms of the centre in face falls operation after rise, makes conduit saddle and grid roofing Truss installa-tion unit is kept completely separate;
(16) the hydraulic of first four, grid roofing truss installation unit both ends arching surface grids roofing construction platform is fallen after rise Jack is kept completely separate conduit saddle with grid roofing truss installation unit;
(17) first remove the girder steel below first piece of grid roofing truss installation unit and the operation platform of Turbogrid plates setting, Six arching surface grids roofing construction platforms connecting by girder steel with the operation platform that Turbogrid plates are arranged are removed again;
(18) repeat the 14th to the 17th step;
(19) are removed last girder steel and are applied with what Turbogrid plates were arranged after most latter two grid roofing truss installation unit closes up Work platform and arching surface grids roofing construction platform.
CN201910435120.7A 2019-05-23 2019-05-23 Large Span Structure of Arch surface mesh roofing construction platform and construction method Pending CN110130627A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910435120.7A CN110130627A (en) 2019-05-23 2019-05-23 Large Span Structure of Arch surface mesh roofing construction platform and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910435120.7A CN110130627A (en) 2019-05-23 2019-05-23 Large Span Structure of Arch surface mesh roofing construction platform and construction method

Publications (1)

Publication Number Publication Date
CN110130627A true CN110130627A (en) 2019-08-16

Family

ID=67572746

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910435120.7A Pending CN110130627A (en) 2019-05-23 2019-05-23 Large Span Structure of Arch surface mesh roofing construction platform and construction method

Country Status (1)

Country Link
CN (1) CN110130627A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112796528A (en) * 2021-02-23 2021-05-14 中冶建工集团重庆钢结构有限公司 Construction method for high-altitude in-situ splicing of large-span steel truss
CN115404994A (en) * 2022-10-21 2022-11-29 中建八局第二建设有限公司 Construction method of irregular curve space three-dimensional truss system of super-large-span building

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002030803A (en) * 2000-07-13 2002-01-31 Shikoku Electric Power Co Inc Scaffold in boiler and installing method therefor
US20070264110A1 (en) * 2006-05-09 2007-11-15 Rhodes Design And Development Corporation Building transport device
CN201835509U (en) * 2010-07-22 2011-05-18 胡约民 Supporting platform for closing of large-span building roof
CN102661054A (en) * 2012-05-23 2012-09-12 中建二局第三建筑工程有限公司 Lateral reinforcing structure in whole lifting of plane steel truss and whole lifting method
CN104929375A (en) * 2015-07-20 2015-09-23 中国二十二冶集团有限公司 Large-span truss short-stroke hydraulic jack synchronous slide method and device
CN105003080A (en) * 2015-05-06 2015-10-28 上海绿地建设(集团)有限公司 Construction technique of sector steel-structured building
CN106836498A (en) * 2016-12-28 2017-06-13 郑州工业应用技术学院 A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN210002824U (en) * 2019-05-23 2020-01-31 中国二十二冶集团有限公司 Large-span arch curved surface grid roof construction platform

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002030803A (en) * 2000-07-13 2002-01-31 Shikoku Electric Power Co Inc Scaffold in boiler and installing method therefor
US20070264110A1 (en) * 2006-05-09 2007-11-15 Rhodes Design And Development Corporation Building transport device
CN201835509U (en) * 2010-07-22 2011-05-18 胡约民 Supporting platform for closing of large-span building roof
CN102661054A (en) * 2012-05-23 2012-09-12 中建二局第三建筑工程有限公司 Lateral reinforcing structure in whole lifting of plane steel truss and whole lifting method
CN105003080A (en) * 2015-05-06 2015-10-28 上海绿地建设(集团)有限公司 Construction technique of sector steel-structured building
CN104929375A (en) * 2015-07-20 2015-09-23 中国二十二冶集团有限公司 Large-span truss short-stroke hydraulic jack synchronous slide method and device
CN106836498A (en) * 2016-12-28 2017-06-13 郑州工业应用技术学院 A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN210002824U (en) * 2019-05-23 2020-01-31 中国二十二冶集团有限公司 Large-span arch curved surface grid roof construction platform

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112796528A (en) * 2021-02-23 2021-05-14 中冶建工集团重庆钢结构有限公司 Construction method for high-altitude in-situ splicing of large-span steel truss
CN115404994A (en) * 2022-10-21 2022-11-29 中建八局第二建设有限公司 Construction method of irregular curve space three-dimensional truss system of super-large-span building

Similar Documents

Publication Publication Date Title
CN103556823B (en) The construction method of lamina tecti form bracing system made by silo sliding formwork operating platform
CN109914244B (en) Weak bracket system suitable for high-tower reinforced concrete combined beam steel structure installation and bottom and top plate concrete pouring and operation method thereof
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN110130627A (en) Large Span Structure of Arch surface mesh roofing construction platform and construction method
CN204531469U (en) A kind of steel work overhanging component temporary support of tool-type and discharge mechanism
CN110821159A (en) Steel-structure large-span adjustable floor support plate supporting structure and construction method thereof
CN204753397U (en) Gallows is installed to steel case bridge temporarily
CN213953189U (en) Supporting device for ensuring smooth surface of lower cone shell of prefabricated water tank
CN113914223A (en) High-pier arc-shaped upper cross beam light-weight bracket system and mounting method thereof
CN211647306U (en) Floor carrier plate bearing structure with adjustable steel construction large-span
CN211572504U (en) Aerial work platform
CN105370027A (en) Construction method for integrally lifted and supported steel platform structure in high-rise suspended structure
CN202220439U (en) Combined steel template of integral stair plate
CN215212427U (en) Adjustable unloading platform with steel structure for building
CN107237515A (en) The support meanss and its application method of circular steel truss structure
CN211201112U (en) Sectional steel tower mounted assembly type construction platform
CN209941512U (en) Supporting shear part for lower cross beam of inclined tower of cable-stayed bridge
CN110468960B (en) Supporting structure capable of adjusting node displacement of net rack and construction method
CN206844680U (en) Steel vestibule installation on ground load transfer device
CN102787717A (en) Self-supporting combined steel template construction method
CN110952765A (en) Formwork supporting platform for shear wall high-altitude concrete cantilever structure and assembling method of formwork supporting platform
CN219973885U (en) Hyperboloid roofing template braced system
CN114214968B (en) Bridge No. 0 block bottom plate dismantling-free construction method
CN113059317B (en) Manufacturing method of integral node type box-type rod piece of steel truss arch bridge
CN218988724U (en) Integrated mounting platform for purlines of roof of large-scale steel structure factory building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190816