CN113123469A - Method for constructing complex curved surface modeling roof grid structure - Google Patents

Method for constructing complex curved surface modeling roof grid structure Download PDF

Info

Publication number
CN113123469A
CN113123469A CN202110312186.4A CN202110312186A CN113123469A CN 113123469 A CN113123469 A CN 113123469A CN 202110312186 A CN202110312186 A CN 202110312186A CN 113123469 A CN113123469 A CN 113123469A
Authority
CN
China
Prior art keywords
frame
grid
steel
ball
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110312186.4A
Other languages
Chinese (zh)
Inventor
赵恒�
伏海奎
罗力夫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN202110312186.4A priority Critical patent/CN113123469A/en
Publication of CN113123469A publication Critical patent/CN113123469A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional [3D] framework structures
    • E04B1/1903Connecting nodes specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional [3D] framework structures
    • E04B1/1903Connecting nodes specially adapted therefor
    • E04B1/1906Connecting nodes specially adapted therefor with central spherical, semispherical or polyhedral connecting element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3511Lift-slab; characterised by a purely vertical lifting of floors or roofs or parts thereof
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/08Vaulted roofs
    • E04B7/10Shell structures, e.g. of hyperbolic-parabolic shape; Grid-like formations acting as shell structures; Folded structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional [3D] framework structures
    • E04B2001/1957Details of connections between nodes and struts
    • E04B2001/1972Welded or glued connection
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3577Extraordinary methods of construction, e.g. lift-slab, jack-block prefabricating a building and moving it as a whole to the erection site

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to the field of building construction, aims to solve the problems that the assembly operation of a steel net rack is complex and the quality and the effect of a finished product cannot be guaranteed in the prior art, and provides a method for constructing a net rack structure of a complex curved surface modeling roof, which comprises the following steps: the steel mesh frame is split and assembled, the assembling sequence is from far to near, and the steel mesh frame is symmetrically installed; in the process of hoisting the steel mesh frame, hoisting the mesh frame to a to-be-installed position by using a crane, arranging a temporary support frame in advance at the projection position of the mesh frame ball node, and positioning and paying off the temporary support frame to ensure that the elevation and the position of a lower welding ball arranged on a support frame steel pipe are accurate; the rod pieces between any two net rack units are connected through welding, and in the step, when the ball nodes between the net racks need to be welded, an adjustable support frame is arranged below the ball nodes to support the ball nodes. The invention has the advantages of safe construction, high efficiency and ensured quality.

Description

Method for constructing complex curved surface modeling roof grid structure
Technical Field
The invention relates to the field of building construction, in particular to a method for constructing a complex curved surface modeling roof grid structure.
Background
Because of the advantages of large span, reliable structure and light total mass, the steel structure net rack has more and more roof structures in the form adopted by domestic buildings, and the traditional net rack hoisting mainly comprises processes of sectional hoisting, high-altitude bulk loading and the like, but both the processes have certain defects. The net rack sectional hoisting is that a moulding bed is manufactured on a ground scattered assembly field according to the shape of a roof, temporary supports are arranged, a lower chord, a web member, an upper chord and mutual ball joints are connected one by one to form a hoisting unit whole, and hoisting machinery and a support are utilized to hoist and install. The method has the disadvantages that a steel pipe scaffold supporting platform needs to be erected, a formwork is fully paved on the top of the platform, and the enclosure guard rails are arranged, so that a large amount of steel pipes and wood are input, the cost is high, the site pressure is high, and the hoisting machinery occupies a large area and has long influence time; the high-altitude bulk method is directly jointed and assembled at high altitude, and has the defects of high construction difficulty, great potential safety hazard, difficult control of construction quality and low construction speed. Especially for the roof grid structure with complex curved surface modeling, the quality and the effect of the finished product are not easy to be ensured.
Disclosure of Invention
The invention aims to provide a complex curved surface modeling roof grid structure, which solves the problems that the assembly operation of a steel grid in the prior art is complex and the quality and the effect of a finished product cannot be guaranteed.
The embodiment of the invention is realized by the following steps:
a method for constructing a complex curved surface modeling roof grid structure is characterized in that the grid structure is a free hyperboloid grid and is a roof grid consisting of a plurality of steel grids, each steel grid is formed by splicing a plurality of quadrangular pyramid units consisting of upper chord members, web members and lower chord members, and all the members are connected through welding balls; the welding balls are divided into upper welding balls and lower welding balls, the upper welding balls are connected with the web members and the upper chord members, and the lower welding balls are connected with the web members and the lower chord members;
the construction method comprises the following steps:
the steel mesh frame is split and assembled, the assembling sequence is from far to near, and the steel mesh frame is symmetrically installed;
in the steel truss hoist and mount process, suspend the net rack unit through the crane and stagnate empty, the net rack construction is carried out to the mode of artifical assistance-localization real-time installation, promptly: hoisting the net rack to a to-be-installed position by using a crane, arranging a temporary support frame in advance at the projection position of the net rack ball node, and ensuring the elevation and the position of a lower welding ball arranged on a support frame steel pipe to be accurate through positioning and paying off the temporary support frame; two workers are borne on the platform of the temporary support and are matched with the crawler crane to adjust and fix the position of the net rack;
the rod pieces between any two net rack units are connected by welding, and in the step, when the ball nodes between the net racks need to be welded, an adjustable support frame is arranged below the ball nodes to support the ball nodes;
and repeating the installation until the hoisting and positioning of the last net rack are completed, namely completing the construction of the whole steel net rack.
In one embodiment:
when each steel net frame is manufactured, selecting a proper place and position as an assembling place, and arranging a jig frame according to the net frame shape and the structural design; the setting method of the jig frame comprises the following steps:
planning a single assembly field, which can meet the integral assembly of two small hoisting units or the assembly of one large hoisting unit;
the assembly field is tamped to the field in advance, a steel plate is fully paved to serve as a bed jig bottom plate, profile steel is combined to form a supporting base, the nodes are lofted to support coordinates, welding balls of the nodes are fixed, rod pieces are connected among the welding balls to form steel net racks serving as net rack hoisting units.
In one embodiment:
the bed-jig bottom plate is made of steel plates with the thickness of more than 20cm, and the supporting base is formed by welding I-shaped steel; and the welding balls are supported at the required height through the supporting structures with the set heights.
In one embodiment:
the supporting structure comprises an embedded steel plate, and the embedded steel plate is fixed on the supporting base through embedded ribs welded below the embedded steel plate;
an adjustable seat is arranged on the embedded steel plate, a support column is arranged on the adjustable seat, and the welding ball is supported at the top of the support column; the adjustable seat comprises a fixed part at the lower part and a movable part which is in ball joint with the fixed part, and the support is connected with the movable part, so that the movable part and the support thereon can rotate relative to the fixed part to adjust the supporting angle.
In one embodiment:
the method for assembling the net rack hoisting unit on the ground comprises the following steps:
1) paying off and inspecting; placing a lower chord node base plate; completing the installation and positioning of 4 lower chord bolt ball nodes and lower chords among the nodes, so that the lower chords are in a square shape;
2) continuously installing a lower chord bolt ball and a lower chord, and connecting 7 lower chords into a 'ri' shape;
3) installing an upper chord bolt ball joint and a web member; connecting the upper bolt ball with the web member to form a regular rectangular pyramid;
4) and (5) repeating the steps 2) and 3), connecting the upper chord and the bolt ball joint, and installing the steel net rack.
In one embodiment:
the steel net frame is assembled on the jig frame by adopting a horizontal station, when the net frame is lifted, the lengths of 4 hoisting point steel wire ropes are adjusted according to the positions of the lifting lugs, so that the 4 hoisting points on the jig frame can be lifted basically and simultaneously under stress, the net frame member is kept stable when being separated from the jig frame, and after the member is integrally separated from the jig frame, the minimum distance between the net frame member and the ground is kept to be not more than 30 cm;
when the component is lifted by 30cm by using the arranged adjusting hoist, the hoist is adjusted to form a certain angle on the component, and meanwhile, the minimum distance between the steel net rack and the ground is kept not to exceed 30 cm; and finally, adjusting the hoist to enable the net rack to form an attitude angle in place at last, and when the net rack is transferred to the position above the temporary support frame, accurately positioning and welding installation are carried out through manual assistance.
In one embodiment:
and a crawler crane is arranged in the plane of the roof net rack and is used for hoisting each steel net rack.
The embodiment has the following beneficial effects due to the adoption of the construction technical scheme:
1. the construction cost, the construction period, the construction safety, the convenient installation and operation and the combination of the actual conditions on site are comprehensively considered, an integral hoisting and integral lifting method is dispatched, and a combined assembling method of sectional hoisting and air butt joint is adopted, so that the high-altitude operation time is reduced, the auxiliary material cost is reduced, and the construction period is saved;
2. the crane is used for staying empty, so that the convenience of installation and operation is improved, the precise positioning is facilitated, the quality of finished products is improved, the unfavorable condition of erecting a large number of construction platforms is avoided, the operation can be flexibly carried out only by a small number of workers, the construction speed is high, and the occupied area is small;
drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings referred to in the embodiments will be briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present invention and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings may be obtained from these drawings without inventive effort.
FIG. 1 is a top view of a steel lattice roof in an embodiment of the present invention;
FIG. 2 is a cross-sectional view taken along line 1-1 of FIG. 1;
FIG. 3 is a cross-sectional view taken along line 2-2 of FIG. 1;
FIG. 4 is a schematic diagram of the steel grid segment splicing according to an embodiment of the present invention;
FIG. 5 is a schematic view of an assembled steel grid frame assembly according to an embodiment of the present invention;
FIG. 6 is a schematic view of a steel truss segment hoisting according to an embodiment of the present invention;
FIG. 7 is an enlarged view of an adjustable mount of an embodiment of the present invention.
Icon: 1-lower welding ball, 2-lower chord, 3-steel support, 4-web member, 5-upper welding ball, 6-upper chord, 7-jig, 8-Zhongting crawler crane, 9-northern crawler crane, 10-temporary support frame, 11-steel support embedded part, 12-stiffening rib and 13-support.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. The components of embodiments of the present invention generally described and illustrated in the figures herein may be arranged and designed in a wide variety of different configurations.
Thus, the following detailed description of the embodiments of the present invention, presented in the figures, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, it need not be further defined and explained in subsequent figures.
Examples
The embodiment provides a method for constructing a complex curved surface modeling roof truss structure, and particularly refers to fig. 1 to 7.
The net rack structure is a free hyperboloid net rack and a roof net rack consisting of a plurality of steel net racks, each steel net rack is formed by splicing a plurality of quadrangular pyramid units consisting of upper chord members 6, web members 4 and lower chord members 2, and all the members are connected through welding balls; the welding ball is divided into an upper welding ball 5 and a lower welding ball 1, the upper welding ball is connected with the web member and the upper chord member, and the lower welding ball is connected with the web member and the lower chord member. The upper solder ball may be supported by a steel support 3.
The method for constructing the complex curved surface modeling roof truss structure in the embodiment comprises the following steps:
1. arranging crawler cranes in the plane of the roof steel net rack, wherein the hoisting capacity of cranes 8 distributed in the structural atrium open space is 320 tons, the hoisting capacity of cranes 9 on the north side and the hoisting capacity of cranes 9 on the south side are 300 tons, different cranes cover different areas, the net rack hoisting is mainly completed by an atrium crane, and the side zones on the north side and the south side are respectively hoisted by the cranes in the areas;
2. selecting a proper place and position as an assembling place, arranging a jig frame 7 according to the net rack shape and the structural design, and accurately positioning by means of instruments such as a total station instrument, a level instrument and the like to ensure that the assembled net rack is consistent with the actual position of a roof;
3. the steel net frame is divided into two parts and assembled into sections, the assembling sequence is comprehensively considered according to the axis, the position of a supporting point, the lifting capacity of a crane and the like, in the step, the heaviest part of the steel net frame is M30# (M is the code of the building net frame, 30# is the number, and the balance is the same), the lifting weight is 23.6 tons, the height is 15M, (the weight of the rest of the parts exceeds 23 tons, and the rest of the parts are installed in two parts), and the farthest lifting part of the M5# is 21.4 tons, and the height is 16M. The assembly sequence is in a symmetrical installation form from far to near;
4. in order to save the field, after the previous net rack is hoisted, the next net rack is assembled, the construction methods of different areas are the same, in order to ensure the stress safety and accurate positioning of the net rack, the first net rack starts from a support at a symmetrical position, the support 13 is connected with a pre-buried rib 11 which is pre-buried in advance by welding, a steel pipe of the support is provided with a steel rib 12 to improve the rigidity, the reliability of the structure is ensured, and other net racks are sequentially hoisted and connected with the previous net rack into a whole;
5. because this engineering rack space span is great, for reducing the cost, improves the efficiency of construction, and zhongting crawler crane adopts great hoisting capacity crane, and the rack unit stagnates in the rack hoist and mount in-process, suspends in midair through the crane, and the rack construction is carried out to the mode of artifical supplementary location installation, promptly: the net rack is lifted to a mounting position by a crane, a temporary support frame 10 is arranged in advance at the projection position of the net rack ball joint, and the elevation and the position of the net rack lower chord ball arranged on the support frame steel pipe are ensured to be accurate through positioning and paying off of the support frame. Two workers can be borne on the platform of the temporary support to adjust and fix the position of the net rack by matching with the crawler crane;
6. the member between two arbitrary rack units is connected and is passed through welded joint, the workman can directly be in the operation on the passageway of setting up on the rack, also can go on ascending a height the frame, to when needing the ball joint between the welded rack in this step, set up an adjustable support frame under the ball joint, the support is by steel pipe scaffold, the top holds in the palm and the connection of platform steel sheet, bolt connection for shore and steel sheet platform, form removable supporting platform frame, set up the cylindrical support steel pipe of profile modeling on the platform steel sheet, be used for supporting the ball joint. The adjusting mechanism is fixed on the working platform, the horizontal position of the spherical node can be adjusted by adjusting the elevations of the four jacking supports and moving the position of the profiling support, so that the adjusting mechanism can be used as a supporting point when the net rack is installed, bear construction load and adjust the coordinate of the net rack spherical node;
7. and repeating the steps 4 and 5 until the hoisting and positioning of the last net rack are completed, namely completing the construction of the whole steel net rack. In the process, the total station is kept in real-time detection, and three to five cases are assembled and then subjected to full-range reinspection once, so that problems can be found and timely processed. After the whole assembly, one-time comprehensive inspection and measurement are carried out, so that any deviation and quality problems are avoided;
preferably, the specific method for setting the jig frame in the step 2 is as follows:
a single assembly site of 12 m x30 m is planned, and the integral assembly of two small hoisting units or the assembly of one large hoisting unit can be met. The assembly site is leveled and tamped in advance, steel plates with the thickness of more than 20mm are fully paved to serve as a jig frame plane, H250mm steel is combined to form a supporting base, lofting nodes support coordinates, fixed nodes are welded with balls in a spot mode, and then rod pieces are connected between the balls to form a net rack hoisting unit;
preferably, the method for assembling the net rack assembling units on the ground comprises the following steps:
1) paying off and inspecting; placing a lower chord node base plate; the installation and positioning of the 4 lower chord bolt ball nodes 1 and the lower chord 2 among the nodes are completed, so that the lower chord is in a 'mouth' shape;
2) continuously installing a lower chord bolt ball and a lower chord, and connecting 7 lower chords into a day;
3) installing an upper chord bolt ball joint 5 and a web member 4; connecting the upper bolt ball with the web member to form a regular rectangular pyramid;
4) repeating the processes 2) to 3), connecting the upper chord 6 with the bolt ball joint, and mounting the steel net rack.
Preferably, the specific method for supporting the temporary support frame in the hoisting of the net frame in the step 5 is as follows:
the support frame adopts lattice formula 10, and bottom surface size 1.5X1.5m highly confirms according to concrete position lofting, and the support frame is arranged in rack piecemeal butt joint mouth position, and the connection that the support frame relates is except that marking for bolted connection, all the other are the welding, and the leg size is not less than 8mm, and the support frame stand all falls on the frame roof beam with the lower part, and the support point that individually can not fall on the frame roof beam, the lower part will set up the conversion roof beam and carry out the conversion. The support frame is divided into 3 types according to different use heights, and each type is divided into a combination of standard sections of 3 meters and 4 meters. The type of the section H100 multiplied by 6 multiplied by 8 of the upright post is used for a support frame with the height within 10 meters, the type of the section H150 multiplied by 7 multiplied by 10 of the upright post is used for a support frame with the height of 10 meters to 15 meters, and the type of the section P180 multiplied by 6 of the upright post is used for a support frame with the height above 15 meters. The web members and the horizontal rods are supported by L75 multiplied by 5mm angle steel, and the connection is realized by M16 bolts. The material is Q235.
Preferably, the specific method for hoisting and positioning the net rack in the step 5 is as follows:
the net rack is assembled on the jig frame by adopting a horizontal station, when the net rack is lifted, the length of each lifting point steel wire rope of 4 is adjusted according to the position of a lifting lug, so that 4 lifting points on the frame can be lifted basically and simultaneously under stress, the net rack is kept stable when being separated from the jig frame, and after the whole frame is separated from the jig frame, the minimum distance between the net rack and the ground is kept to be not more than 30 cm. By utilizing the arranged regulating hoist (the specification of the regulating hoist in the project is 20t), when the component is lifted by 30cm, the 15 and 16 hoists are regulated, so that the component forms a certain angle, and meanwhile, the minimum distance between the net frame component and the ground is kept not to exceed 30 cm. And the adjustment is performed by analogy. And in the same way, the 14 and 15 hoists are finally adjusted, so that the net rack is finally formed into an attitude angle when in position, and when the net rack is transferred to the upper part of the temporary support frame, the net rack is accurately positioned and welded and installed through manual assistance. The welding quality is directly related to the overall performance of the grid structure, and meanwhile, the positioning of the rod piece meets the requirement of deformation coordination, so that the generation of internal stress is reduced.
According to the invention, a welded ball grid is adopted for roof design, the effective coverage area of the grid is 23000 square meters, the design height of the grid is 4m, the total weight is about 1853.2 tons, the installation height is 2 m-23.5 m, the longitudinal span of the grid is 168 x 102m, and the large-span steel structure grid splicing structure belongs to.
The embodiment has the following beneficial effects due to the adoption of the construction technical scheme:
1. the construction cost, the construction period, the construction safety, the convenient installation and operation and the combination of the actual conditions on site are comprehensively considered, an integral hoisting and integral lifting method is dispatched, and a combined assembling method of sectional hoisting and air butt joint is adopted, so that the high-altitude operation time is reduced, the auxiliary material cost is reduced, and the construction period is saved;
2. the crane is used for staying empty, so that the convenience of installation and operation is improved, the precise positioning is facilitated, the quality of finished products is improved, the unfavorable condition of erecting a large number of construction platforms is avoided, the operation can be flexibly carried out only by a small number of workers, the construction speed is high, and the occupied area is small;
the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1.一种复杂曲面造型屋面网架结构施设方法,其特征在于:1. a complex curved surface modeling roof grid structure construction method is characterized in that: 网架结构为自由双曲面网架,由多榀钢网架组成的屋面网架,每一榀钢网架由上弦杆、腹杆和下弦杆组成的若干个四角锥单元拼接而成,各杆间通过焊接球连结;所述焊接球分为上焊接球和下焊接球,上焊接球连接腹杆和上弦杆,下焊接球连接腹杆与下弦杆;The grid structure is a free hyperboloid grid, which is a roof grid composed of multiple steel grids. They are connected by welding balls; the welding balls are divided into upper welding balls and lower welding balls, the upper welding balls connect the web rod and the upper chord, and the lower welding balls connect the web rod and the lower chord; 所述施设方法包括以下步骤:The installation method includes the following steps: 将钢网架进行分榀拼装,拼装顺序为由远及近,对称安装;Assemble the steel mesh frame separately, the assembly order is from far to near, and the installation is symmetrical; 钢网架吊装过程中,通过吊车悬吊网架单元滞空、人工辅助定位安装的方式进行网架施工,即:利用吊车吊运网架至拟安装位置,在网架球节点的投影位置提前设置临时支撑架,临时支撑架通过定位放线,保证置于支撑架钢管上的下焊接球的标高和位置准确无误;临时支架的平台上承载两名工人,配合履带吊对网架位置进行调整和固定;During the hoisting process of the steel grid frame, the grid frame construction is carried out by suspending the grid frame unit by a crane and manually assisted positioning and installation. Temporary support frame, the temporary support frame is positioned and laid out to ensure that the elevation and position of the lower welding ball placed on the steel pipe of the support frame are accurate; the platform of the temporary support frame carries two workers, and the position of the grid frame is adjusted and adjusted with the crawler crane. fixed; 任意两块网架单元之间的杆件连结通过焊接连结,该步骤中对于需要焊接网架之间的球节点时,在球节点下设置一可调的支撑架,用以支撑球节点;The rods between any two grid units are connected by welding. In this step, when the ball joint between the grid frames needs to be welded, an adjustable support frame is arranged under the ball joint to support the ball joint; 重复前述安装,直到完成最后一榀网架的吊装定位,即完成了整个钢网架的施工完成。Repeat the aforementioned installation until the hoisting and positioning of the last grid frame is completed, that is, the construction of the entire steel grid frame is completed. 2.根据权利要求1所述的复杂曲面造型屋面网架结构施设方法,其特征在于:2. the complex curved surface modeling roof grid structure construction method according to claim 1, is characterized in that: 各榀钢网架制作时,选择合适的场地和位置作为拼装场地,根据网架造型和结构设计设置胎架;胎架的设置方法为:When making each steel grid frame, select the appropriate site and position as the assembly site, and set the tire frame according to the shape and structural design of the grid frame; the setting method of the tire frame is as follows: 规划单个拼装场地,其能够满足两个小吊装单元的整体拼装或一个大吊装单元的拼装;Plan a single assembly site, which can meet the overall assembly of two small hoisting units or the assembly of one large hoisting unit; 拼装场地事先对场地平整夯实,满铺一钢板作为胎架底板,用型钢组合成支撑底座,放样节点支撑坐标,固定各节点的焊接球,并在焊接球之间连接杆件形成各榀钢网架,作为网架吊装单元。The assembly site is leveled and compacted in advance, and a steel plate is fully covered as the bottom plate of the tire frame, and the support base is combined with profiled steel. frame, as a grid hoisting unit. 3.根据权利要求2所述的复杂曲面造型屋面网架结构施设方法,其特征在于:3. the complex curved surface modeling roof grid structure construction method according to claim 2, is characterized in that: 所述胎架底板采用厚度20cm以上的钢板,所述支撑底座采用工字钢焊接而成;各焊接球分别通过设定高度的支撑结构支撑于所需高度。The base plate of the tire frame is made of a steel plate with a thickness of more than 20 cm, and the support base is welded by I-beam; each welding ball is respectively supported at a required height by a support structure with a set height. 4.根据权利要求3所述的复杂曲面造型屋面网架结构施设方法,其特征在于:4. the complex curved surface modeling roof grid structure construction method according to claim 3, is characterized in that: 所述支撑结构包括预埋钢板,所述预埋钢板通过焊接于其下的预埋筋固定于支撑底座上;The support structure includes a pre-embedded steel plate, and the pre-embedded steel plate is fixed on the support base through the pre-embedded rib welded thereunder; 所述预埋钢板上设置可调座,可调座上设置支柱,焊接球支撑于支柱的顶部;所述可调座包括下部的固定部和球接于所述固定部上的可动部,所述支柱连接于所述可动部,以使所述可动部和其上的支柱能够相对固定部转动,以调节其支撑角度。An adjustable seat is arranged on the embedded steel plate, a pillar is arranged on the adjustable seat, and the welding ball is supported on the top of the pillar; the adjustable seat includes a lower fixed part and a movable part connected to the fixed part by the ball, The strut is connected to the movable part, so that the movable part and the strut thereon can rotate relative to the fixed part to adjust the supporting angle thereof. 5.根据权利要求3所述的复杂曲面造型屋面网架结构施设方法,其特征在于:5. the complex curved surface modeling roof grid structure construction method according to claim 3, is characterized in that: 网架吊装单元在地面拼装方法为:The method of assembling the grid hoisting unit on the ground is as follows: 1)放线、验线;放置下弦节点垫板;完成4个下弦螺栓球节点及节点间的下弦杆安装定位,使得下弦杆成“口”形;1) Paying off and checking the line; placing the bottom chord joint pad; completing the installation and positioning of the four bottom chord bolt ball nodes and the bottom chord between the nodes, so that the bottom chord has a "mouth" shape; 2)继续安装下弦螺栓球及下弦杆,用7根下弦杆组接成“日”形;2) Continue to install the lower chord bolt ball and lower chord, and use 7 lower chords to form a "sun" shape; 3)安装上弦螺栓球节点和腹杆;使得上螺栓球和腹杆连结,形成正四棱锥;3) Install the upper chord bolt ball node and the web rod; connect the upper bolt ball and the web rod to form a regular quadrangular pyramid; 4)重复步骤2)和3),并连结上弦杆和螺栓球节点,进行钢网架安装。4) Repeat steps 2) and 3), and connect the upper chord and bolt ball joints to install the steel grid. 6.根据权利要求2所述的复杂曲面造型屋面网架结构施设方法,其特征在于:6. the complex curved surface modeling roof grid structure construction method according to claim 2, is characterized in that: 钢网架在胎架上拼装是采取的水平工位,网架起吊时,根据吊耳位置调整4个吊点钢丝绳长度,使得构架上4个吊点能基本同时受力起吊,保持网架构件在脱离工装胎架的时候是平稳的,当构件整体脱离工装胎架后,保持网架构件与地面最小距离不超过30cm;The steel mesh frame is assembled on the tire frame in a horizontal position. When the mesh frame is hoisted, the length of the wire rope of the 4 lifting points is adjusted according to the position of the lifting lugs, so that the 4 lifting points on the frame can basically be lifted by force at the same time, keeping the mesh frame components. It is stable when it is separated from the tooling frame. When the component is separated from the tooling frame as a whole, keep the minimum distance between the grid member and the ground not exceeding 30cm; 利用设置的调节葫芦在起吊构件30cm时,调整葫芦,使得构件形成一定角度,同时保持钢网架与地面最小距离不超过30cm;最后调整葫芦,使得网架最后形成就位时的姿态角度,当网架被调运至临时支撑架上方时,通过人工辅助准确定位并焊接安装。Use the set adjustment hoist to lift the component by 30cm, adjust the hoist to make the component form a certain angle, and keep the minimum distance between the steel grid and the ground not more than 30cm; finally adjust the hoist, so that the grid finally forms the attitude angle when the grid is in place. When the grid is transported to the top of the temporary support frame, it is accurately positioned and welded and installed with manual assistance. 7.根据权利要求2所述的复杂曲面造型屋面网架结构施设方法,其特征在于:7. The complex curved surface modeling roof grid structure construction method according to claim 2 is characterized in that: 在屋面网架的平面内布置履带吊,用作各榀钢网架的吊装工作。The crawler cranes are arranged in the plane of the roof grid, which is used for the hoisting work of each steel grid.
CN202110312186.4A 2021-03-24 2021-03-24 Method for constructing complex curved surface modeling roof grid structure Pending CN113123469A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110312186.4A CN113123469A (en) 2021-03-24 2021-03-24 Method for constructing complex curved surface modeling roof grid structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110312186.4A CN113123469A (en) 2021-03-24 2021-03-24 Method for constructing complex curved surface modeling roof grid structure

Publications (1)

Publication Number Publication Date
CN113123469A true CN113123469A (en) 2021-07-16

Family

ID=76774070

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110312186.4A Pending CN113123469A (en) 2021-03-24 2021-03-24 Method for constructing complex curved surface modeling roof grid structure

Country Status (1)

Country Link
CN (1) CN113123469A (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112267568A (en) * 2020-11-06 2021-01-26 中铁二十局集团市政工程有限公司 A construction method for segmented hoisting of steel grid structure
CN113415714A (en) * 2021-07-23 2021-09-21 中国二十二冶集团有限公司 Quick installation construction device of steel construction large-span net rack starting frame
CN114086669A (en) * 2021-11-30 2022-02-25 中国五冶集团有限公司 A modular and rapid construction method for large-scale space special-shaped curved steel grid frame
CN114722472A (en) * 2022-04-15 2022-07-08 中建科工集团有限公司 Method for analyzing batch hoisting weight of steel members
CN114922435A (en) * 2022-05-17 2022-08-19 山东电力工程咨询院有限公司 Construction method of bolt-sphere joint net rack of garbage power station
CN115075383A (en) * 2022-08-04 2022-09-20 上海市机械施工集团有限公司 Assembling method and assembling support for grid structure
CN115404994A (en) * 2022-10-21 2022-11-29 中建八局第二建设有限公司 Construction method of irregular curve space three-dimensional truss system of super-large-span building
CN115538682A (en) * 2022-10-10 2022-12-30 中国十九冶集团有限公司 Installation method of arched bolt spherical reticulated shell
CN115788065A (en) * 2022-11-30 2023-03-14 中铁四局集团建筑工程有限公司 Steel net rack installation construction method
CN115898027A (en) * 2023-02-13 2023-04-04 浙江中南绿建科技集团有限公司 Sectional lifting and assembling method for large-span roof structure
CN115897802A (en) * 2022-10-31 2023-04-04 山西一建集团有限公司 Construction method of single-layer round-hub steel reticulated shell structure with special-shaped curved surface
CN116480157A (en) * 2023-04-28 2023-07-25 中建八局发展建设有限公司 Hoisting method for large-span roof steel structure
CN116876833A (en) * 2023-07-25 2023-10-13 中冶(上海)钢结构科技有限公司 Large-span large-drop curved steel net frame outward expanding assembling accumulating lifting method
CN117166624A (en) * 2023-09-01 2023-12-05 中冶(上海)钢结构科技有限公司 A construction method for ground jacking to assemble space curved grid structure
CN117684751A (en) * 2023-12-28 2024-03-12 四川攀钢钢构有限公司 A kind of installation and construction method of modeling grid structure
CN118390823A (en) * 2024-04-11 2024-07-26 中建八局华中建设有限公司 Cross-floor assembled grid construction platform and construction method thereof
CN119531503A (en) * 2024-10-31 2025-02-28 中铁第一勘察设计院集团有限公司 A construction method for station roof grid support structure
CN120465648A (en) * 2025-05-09 2025-08-12 中国五冶集团有限公司 A hidden drainage construction method in steel structure flower pipe columns

Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291147A (en) * 1999-04-06 2000-10-17 Takenaka Komuten Co Ltd Dome roof construction method without timbering
JPWO2008102429A1 (en) * 2007-02-20 2010-05-27 東急建設株式会社 Construction method of large space building
CN101988308A (en) * 2010-09-30 2011-03-23 中国华西企业有限公司 Non-support installation method of long-span spatial bolt ball steel reticulated shell dome
CN102168490A (en) * 2011-03-09 2011-08-31 中国建筑第八工程局有限公司 Partition direct hoisting construction method for hyperboloidal welded ball net rack
CN102635162A (en) * 2012-04-09 2012-08-15 浙江东南网架股份有限公司 Combined torsional reticulated shell and construction method thereof
CN103628570A (en) * 2013-11-05 2014-03-12 陕西建工机械施工集团有限公司 Installation method for welding ball node grid structure
CN103883131A (en) * 2014-03-31 2014-06-25 中国建筑第八工程局有限公司 Connecting structure for roof truss tube and steel tube column and construction method thereof
CN104453248A (en) * 2013-09-24 2015-03-25 上海宝冶集团有限公司 Complex irregular-shaped multi-layer net rack construction method based on layered modular assembling technology
CN204370833U (en) * 2014-12-19 2015-06-03 山西四建集团有限公司 Elements of Space Grid Truss supporting apparatus
CN104831939A (en) * 2015-05-22 2015-08-12 常州第一建筑集团有限公司 Bolt ball welding ball mixed node large span cantilever grid structure construction method
CN105089152A (en) * 2015-07-10 2015-11-25 中铁十八局集团建筑安装工程有限公司 Reverse installation and construction method for large bifurcated column and complex curved net rack
CN105468796A (en) * 2014-08-13 2016-04-06 青岛百键城环保科技有限公司 Method for establishing temporary support moulding bed system for steel structure assembly
CN107386460A (en) * 2017-07-18 2017-11-24 江苏绿色辉煌节能科技有限公司 A kind of large-span shell bolted spherical node installation method
CN107524261A (en) * 2017-09-14 2017-12-29 中铁上海工程局集团第五工程有限公司 A kind of construction method of roofing Elements of Space Grid Truss
CN108612187A (en) * 2018-03-28 2018-10-02 中建钢构有限公司 A kind of welding ball grid assembling and construction method
CN110185138A (en) * 2019-04-24 2019-08-30 中建八局第二建设有限公司 A kind of welding ball grid and its method for assembling and welding
CN110499921A (en) * 2019-09-04 2019-11-26 中亿丰建设集团股份有限公司 Multilayer space curved surface reticulated shell skeletal support formula film structure roof construction method
CN110528891A (en) * 2019-09-06 2019-12-03 成都建工第一建筑工程有限公司 Large-span Spherical rack integral hoisting method
CN110805138A (en) * 2019-11-29 2020-02-18 中国二十冶集团有限公司 Construction method for jacking two sides of large-span net rack
CN111218987A (en) * 2020-01-10 2020-06-02 河南宏程工程建设有限责任公司 Bearing type net rack construction method
CN112267568A (en) * 2020-11-06 2021-01-26 中铁二十局集团市政工程有限公司 A construction method for segmented hoisting of steel grid structure

Patent Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291147A (en) * 1999-04-06 2000-10-17 Takenaka Komuten Co Ltd Dome roof construction method without timbering
JPWO2008102429A1 (en) * 2007-02-20 2010-05-27 東急建設株式会社 Construction method of large space building
CN101988308A (en) * 2010-09-30 2011-03-23 中国华西企业有限公司 Non-support installation method of long-span spatial bolt ball steel reticulated shell dome
CN102168490A (en) * 2011-03-09 2011-08-31 中国建筑第八工程局有限公司 Partition direct hoisting construction method for hyperboloidal welded ball net rack
CN102635162A (en) * 2012-04-09 2012-08-15 浙江东南网架股份有限公司 Combined torsional reticulated shell and construction method thereof
CN104453248A (en) * 2013-09-24 2015-03-25 上海宝冶集团有限公司 Complex irregular-shaped multi-layer net rack construction method based on layered modular assembling technology
CN103628570A (en) * 2013-11-05 2014-03-12 陕西建工机械施工集团有限公司 Installation method for welding ball node grid structure
CN103883131A (en) * 2014-03-31 2014-06-25 中国建筑第八工程局有限公司 Connecting structure for roof truss tube and steel tube column and construction method thereof
CN105468796A (en) * 2014-08-13 2016-04-06 青岛百键城环保科技有限公司 Method for establishing temporary support moulding bed system for steel structure assembly
CN204370833U (en) * 2014-12-19 2015-06-03 山西四建集团有限公司 Elements of Space Grid Truss supporting apparatus
CN104831939A (en) * 2015-05-22 2015-08-12 常州第一建筑集团有限公司 Bolt ball welding ball mixed node large span cantilever grid structure construction method
CN105089152A (en) * 2015-07-10 2015-11-25 中铁十八局集团建筑安装工程有限公司 Reverse installation and construction method for large bifurcated column and complex curved net rack
CN107386460A (en) * 2017-07-18 2017-11-24 江苏绿色辉煌节能科技有限公司 A kind of large-span shell bolted spherical node installation method
CN107524261A (en) * 2017-09-14 2017-12-29 中铁上海工程局集团第五工程有限公司 A kind of construction method of roofing Elements of Space Grid Truss
CN108612187A (en) * 2018-03-28 2018-10-02 中建钢构有限公司 A kind of welding ball grid assembling and construction method
CN110185138A (en) * 2019-04-24 2019-08-30 中建八局第二建设有限公司 A kind of welding ball grid and its method for assembling and welding
CN110499921A (en) * 2019-09-04 2019-11-26 中亿丰建设集团股份有限公司 Multilayer space curved surface reticulated shell skeletal support formula film structure roof construction method
CN110528891A (en) * 2019-09-06 2019-12-03 成都建工第一建筑工程有限公司 Large-span Spherical rack integral hoisting method
CN110805138A (en) * 2019-11-29 2020-02-18 中国二十冶集团有限公司 Construction method for jacking two sides of large-span net rack
CN111218987A (en) * 2020-01-10 2020-06-02 河南宏程工程建设有限责任公司 Bearing type net rack construction method
CN112267568A (en) * 2020-11-06 2021-01-26 中铁二十局集团市政工程有限公司 A construction method for segmented hoisting of steel grid structure

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
中国土木工程学会: "《土木工程5 应用技术》", 30 December 2017 *
孟文清等: "《现代建筑施工新技术》", 30 June 2010 *
孟萍等: "《建筑结构体系》", 31 October 2018 *
季豪等: "《建筑工程创优实用新技术及应用》", 30 November 2016 *

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112267568A (en) * 2020-11-06 2021-01-26 中铁二十局集团市政工程有限公司 A construction method for segmented hoisting of steel grid structure
CN113415714A (en) * 2021-07-23 2021-09-21 中国二十二冶集团有限公司 Quick installation construction device of steel construction large-span net rack starting frame
CN114086669B (en) * 2021-11-30 2024-03-19 中国五冶集团有限公司 A modular rapid construction method for large space special-shaped curved surface steel grids
CN114086669A (en) * 2021-11-30 2022-02-25 中国五冶集团有限公司 A modular and rapid construction method for large-scale space special-shaped curved steel grid frame
CN114722472A (en) * 2022-04-15 2022-07-08 中建科工集团有限公司 Method for analyzing batch hoisting weight of steel members
CN114922435A (en) * 2022-05-17 2022-08-19 山东电力工程咨询院有限公司 Construction method of bolt-sphere joint net rack of garbage power station
CN115075383A (en) * 2022-08-04 2022-09-20 上海市机械施工集团有限公司 Assembling method and assembling support for grid structure
CN115075383B (en) * 2022-08-04 2024-04-26 上海市机械施工集团有限公司 Assembling method and assembling bracket for grid structure
CN115538682A (en) * 2022-10-10 2022-12-30 中国十九冶集团有限公司 Installation method of arched bolt spherical reticulated shell
CN115404994A (en) * 2022-10-21 2022-11-29 中建八局第二建设有限公司 Construction method of irregular curve space three-dimensional truss system of super-large-span building
CN115897802A (en) * 2022-10-31 2023-04-04 山西一建集团有限公司 Construction method of single-layer round-hub steel reticulated shell structure with special-shaped curved surface
CN115788065A (en) * 2022-11-30 2023-03-14 中铁四局集团建筑工程有限公司 Steel net rack installation construction method
CN115898027A (en) * 2023-02-13 2023-04-04 浙江中南绿建科技集团有限公司 Sectional lifting and assembling method for large-span roof structure
CN116480157A (en) * 2023-04-28 2023-07-25 中建八局发展建设有限公司 Hoisting method for large-span roof steel structure
CN116480157B (en) * 2023-04-28 2025-09-19 中建八局发展建设有限公司 Hoisting method for large-span roof steel structure
CN116876833A (en) * 2023-07-25 2023-10-13 中冶(上海)钢结构科技有限公司 Large-span large-drop curved steel net frame outward expanding assembling accumulating lifting method
CN116876833B (en) * 2023-07-25 2025-08-22 中冶(上海)钢结构科技有限公司 Cumulative lifting method for outward expansion assembly of large-span and large-drop curved steel grid
CN117166624A (en) * 2023-09-01 2023-12-05 中冶(上海)钢结构科技有限公司 A construction method for ground jacking to assemble space curved grid structure
CN117684751A (en) * 2023-12-28 2024-03-12 四川攀钢钢构有限公司 A kind of installation and construction method of modeling grid structure
CN118390823A (en) * 2024-04-11 2024-07-26 中建八局华中建设有限公司 Cross-floor assembled grid construction platform and construction method thereof
CN119531503A (en) * 2024-10-31 2025-02-28 中铁第一勘察设计院集团有限公司 A construction method for station roof grid support structure
CN120465648A (en) * 2025-05-09 2025-08-12 中国五冶集团有限公司 A hidden drainage construction method in steel structure flower pipe columns

Similar Documents

Publication Publication Date Title
CN113123469A (en) Method for constructing complex curved surface modeling roof grid structure
CN114086669B (en) A modular rapid construction method for large space special-shaped curved surface steel grids
CN112343233B (en) Circular roof space tube truss structure and its construction method
CN106836498B (en) Hoisting construction method for steel truss of grand stand roof of super-large span stadium
CN114439249B (en) Construction method for lifting large-span triangular truss through air swivel
CN103410322B (en) The parallel Truss Steel corridor construction method of large span
CN111270852A (en) Construction method of a new formwork support system for reinforced concrete silo domes
CN102296858B (en) Cement production line clinker storage warehouse roof steel structure and construction method thereof
CN112663927B (en) Steel structure dome aerial work stepped operation platform and construction method thereof
CN113356597A (en) Lifting process of large-span net rack and truss combined roof
CN207079729U (en) Steel structure net rack jacking apparatus
CN105569358A (en) Construction method of special-shaped curved surface roof with large span and multiple curvatures
CN101440667A (en) Installation method of large-span single-layer canopy latticed shell structure
CN111395532B (en) Installation and construction method for large-span half-opening elliptical spherical reticulated shell
CN111980165A (en) Large-span net rack external-expanding splicing integral jacking construction method
CN106812236A (en) A kind of construction technology of large-span shell steel structural roof
CN114703956A (en) Construction process method for double-layer large-span steel structure corridor
CN114622726A (en) Installation and construction method for top inhaul cable of high-rise building
CN110130627A (en) Large Span Structure of Arch surface mesh roofing construction platform and construction method
CN116791760A (en) Construction method of large-span multi-curved-surface single-layer intersecting circular pipe network shell
CN115288449A (en) Construction method of middle support installation of large-span grid frame
CN116752638B (en) Construction method of super-span multi-angle special-shaped composite steel structure in restricted space of large complex
CN108842954A (en) Installation and construction method of huge different-section honeycomb beam structure system of wing-shaped roof
CN118128188A (en) A method for overall lifting of a high-altitude steel corridor with a bottom suspended ceiling
CN103711322A (en) Construction method for mounting large-span semispherical reticulated shell through overhanging

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210716

RJ01 Rejection of invention patent application after publication