CN115341542A - Breaking hammer with annular clamp and construction method for supporting steel pipe in pit area in deep foundation pit - Google Patents

Breaking hammer with annular clamp and construction method for supporting steel pipe in pit area in deep foundation pit Download PDF

Info

Publication number
CN115341542A
CN115341542A CN202211095224.6A CN202211095224A CN115341542A CN 115341542 A CN115341542 A CN 115341542A CN 202211095224 A CN202211095224 A CN 202211095224A CN 115341542 A CN115341542 A CN 115341542A
Authority
CN
China
Prior art keywords
pit
steel pipe
construction
foundation pit
pipe support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211095224.6A
Other languages
Chinese (zh)
Inventor
董传艺
郗骁
商和松
郭腾
杜纪强
孙远磊
吕军强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202211095224.6A priority Critical patent/CN115341542A/en
Publication of CN115341542A publication Critical patent/CN115341542A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/18Placing by vibrating
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention mainly relates to the field of buildings, in particular to a breaking hammer with an annular hoop and a construction method for supporting a steel pipe in a pit area in a deep foundation pit; the method comprises the following five steps of S1.BIM modeling, S2. Construction environment and stress calculation simulation analysis, S3. Thin-wall steel pipe supporting pile penetration into S4. Pit-in-pit earthwork excavation, and S5. Foundation pit side wall retaining wall construction; the method comprises the following steps of simulating the pit-in-pit construction environment of a deep foundation pit by adopting a BIM modeling method, and ensuring the construction safety and economy of the foundation pit through stress calculation analysis and supporting pile type selection; on the premise of ensuring the construction safety, the construction period of the support is greatly reduced, a stable support system of the foundation pit is formed more quickly, and the construction operation risk of the deep foundation pit is reduced; the retaining wall of the side wall of the foundation pit is used for reinforcing the support once more, all the support steel pipes are integrally formed, a good operation environment is provided for subsequent raft construction, the construction safety is guaranteed, and the construction quality is guaranteed.

Description

Breaking hammer with annular clamp and deep foundation pit in-pit area steel pipe support construction method
Technical Field
The invention mainly relates to the field of buildings, in particular to a breaking hammer with an annular hoop and a construction method for supporting a steel pipe in a pit area in a deep foundation pit.
Background
In the building construction, as for the construction method of the pit in the deep foundation pit, the traditional method is a cement-soil gravity type retaining wall or a method of adopting a profile steel cement-soil mixing wall, an underground continuous wall and the like for supporting, and the construction methods need to be invested into large-scale construction machinery, have large disturbance to the foundation during construction, and have long construction period and high cost. Therefore, under the working condition that the large foundation pit is excavated, when the pit area in the pit is supported, the disturbance to the foundation is reduced as much as possible, and a quick, safe and economic supporting method needs to be selected.
Disclosure of Invention
In order to solve the problems, the invention adopts the following technical scheme.
The breaking hammer with the annular hoop comprises a breaking hammer and the annular hoop, wherein the annular hoop is arranged on the end head of the breaking hammer;
the base of annular clamp is fixed in afterbody in the end, the annular clamp is in the end below is provided with the ring perpendicular with the end axis, the ring pass through the telescopic link with the pedestal connection.
Furthermore, an elastic ring is arranged inside the circular ring.
A construction method for supporting and protecting a steel pipe in a pit area in a deep foundation pit comprises the following steps:
s1.BIM modeling
The BIM software is used for carrying out integral modeling on the whole foundation pit supporting system, and the structural stress form of the pit-in-pit system is determined;
s2, stress calculation simulation analysis
Carrying out construction environment simulation analysis by using Midas software, and carrying out stress and deformation simulation on a supporting structure, so as to select the type of the steel pipe supporting pile and determine the construction parameters of the steel pipe supporting pile;
s3, steel pipe support pile injection
Measuring and positioning the outer side of a pit area in the pre-excavated pit, reserving the position of the side wall of the pit, and arranging a piling center line of the steel pipe support pile along the side wall of the pit; installing a breaking hammer on an engineering truck, stretching a telescopic rod to the longest, placing a steel pipe support pile into an annular hoop by using the engineering truck, sleeving the upper part of the steel pipe support pile into an elastic ring, erecting the steel pipe support pile, righting the steel pipe support pile in place through a binding belt and starting to inject, injecting the steel pipe pile to the depth of 100-200 mm, removing the binding belt, and hammering the rest part of the steel pipe support pile downwards at the top by using the breaking hammer installed on the engineering truck until the steel pipe support pile is injected to the designed elevation; repeatedly injecting steel pipe supporting piles along the side wall of the pit, attaching the steel pipe supporting piles to the side wall of the whole pit, welding two sides of the top of each steel pipe supporting pile by using connecting steel bars, connecting the steel pipe supporting piles into a whole, and pouring concrete into the steel pipe supporting piles;
s4. Pit-in-pit earthwork excavation
Excavating earth in the pit; adopting a layered and segmented excavation form, reserving pit-in-pit foundation pit deformation monitoring points on the steel pipe support piles, monitoring horizontal displacement data of soil bodies, transporting earthwork to a pit-out safety position for storage and timely transporting the earthwork out of a field during excavation; after digging the soil to the designed elevation, carrying out concrete bottom sealing treatment;
s5. Foundation pit side wall retaining wall construction
And pouring a foundation pit side wall retaining wall on the inner side of the integral structure formed by connecting the steel pipe support piles.
Further, the step S5 includes:
s5.1, binding a steel bar net piece on the outer wall of the steel pipe support pile on the inner side of the foundation pit, and welding and fixing the steel bar net piece on the steel pipe support pile;
s5.2, welding tie bars, and connecting the reinforcing mesh and the steel pipe support piles into a whole;
s5.3, erecting a concrete template, reinforcing the template by using a water stop screw rod, pouring the concrete for the side wall of the foundation pit in a layered and sectional manner after the erecting of the template is completed, removing the template and the water stop screw rod after the concrete reaches the designed strength, and continuously keeping monitoring on the deformation of the supporting structure in subsequent construction.
Furthermore, the deformation monitoring point is located at the center of the top of the steel pipe support pile.
Further, in the step S3, when the breaking hammer performs the last 200mm to 600mm of the penetration of the remaining part, the telescopic rod of claim 2 is retracted.
The invention has the following beneficial effects:
the method is novel in scheme and clear in thought arrangement, full life cycle informatization management and control is adopted from foundation pit design, design and construction are integrated, modular construction is achieved, the construction period can be shortened, the construction progress is accelerated, and a good economic effect is achieved; and Midas software is adopted to carry out simulation analysis on the construction process of the supporting system, the stress and deformation of the supporting structure are simulated, monitoring points are arranged on the supporting structure, the safety condition of the supporting is monitored in real time, the construction safety is ensured, and the operation risk of pit-in-pit is reduced.
The light thin-wall steel pipe is used for a pit-in-pit supporting structure, has the characteristics of large lateral rigidity resistance, strong bearing capacity, small disturbance effect on a clay foundation during construction and the like, is easy to carry and stack, has light dead weight, does not need to worry about damage, can be connected into a whole after construction is completed, has good supporting integrity, is simple and easy to operate in a construction method, and has small deformation of a supporting system. Therefore, the light thin-wall steel pipe support is adopted, so that the cost can be obviously saved, the construction period is shortened, the support quality is easy to control, the support integrity is good, the safety of later construction is ensured, and the support can be popularized in the same type of engineering.
Annular clamp can erect and be spacing to steel pipe fender pile in the work progress, has improved convenience and construction quality's stability, uses manpower sparingly.
Drawings
FIG. 1 is a flow chart of the construction method of the present invention;
FIG. 2 is a schematic view of the construction structure of the steel pipe support pile;
FIG. 3 is a schematic view of a demolition hammer with an annular clamp;
fig. 4 is a partial view of fig. 3 at a.
1. Pile central line, 2, steel pipe fender pile, 3, connecting reinforcement, 4, reinforcing bar net piece, 5, drawknot reinforcing bar, 6, foundation ditch lateral wall barricade, 7, destruction hammer, 8, annular clamp, 9, elastic ring.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
A breaking hammer with an annular clamp comprises a breaking hammer 7 and the annular clamp 8, wherein the annular clamp 8 is arranged on the end of the breaking hammer 7, a base of the annular clamp 8 is welded on the tail of the end, a ring perpendicular to the axis of the end is arranged below the end of the annular clamp 8, and the ring is connected with the base through a telescopic rod 801; the inside elastic ring 9 that is provided with of ring prevents to destroy the hammer during operation and produces destruction to steel pipe fender pile 2 lateral wall.
A construction method for supporting and protecting a steel pipe in a pit area in a deep foundation pit comprises the following steps:
s1.BIM modeling
The BIM software is used for carrying out integral modeling on the whole foundation pit supporting system, and the structural stress form of the pit-in-pit system is determined;
s2, stress calculation simulation analysis
Carrying out construction environment simulation analysis by using Midas software, and carrying out stress and deformation simulation on a supporting structure, so as to select the type of the steel pipe supporting pile 2 and determine the construction parameters of the steel pipe supporting pile 2;
s3, steel pipe support pile injection
Measuring and positioning the outer side of a pit area in the pre-excavated pit, reserving the position of the side wall of the pit, and arranging a piling center line 1 of a steel pipe support pile 2 along the side wall of the pit; the method comprises the steps of installing a breaking hammer 7 on an engineering truck, stretching a telescopic rod 801 to the longest, placing a steel pipe supporting pile 2 into an annular hoop 8 by using the engineering truck, enabling the upper portion of the steel pipe supporting pile 2 to be sleeved into an elastic ring 9, erecting the steel pipe supporting pile 2, keeping the steel pipe supporting pile 2 sleeved in the annular hoop 8, feeding the breaking hammer 7 installed on the engineering truck one over the other, hammering the top of the steel pipe supporting pile 2, righting the steel pipe supporting pile 2 in place through a binding belt, starting injection, removing the binding belt after the steel pipe pile is injected to the depth of 100-200 mm, continuing feeding the breaking hammer 7 one over the other, hammering the top of the steel pipe supporting pile 2, injecting the rest of the steel pipe supporting pile 2, wherein when the glass breaking hammer 7 is fed up and down, the telescopic rod 801 is always at the longest position, and keeping the steel pipe supporting pile 2 always located in the annular hoop 8.
Wherein, when the last 200 mm-600 mm of the rest part of the breaking hammer 7 is penetrated, the telescopic rod 801 is retracted to ensure that the rest part is penetrated; until the steel pipe support pile 2 is penetrated to the designed elevation; repeatedly penetrate steel pipe fender pile 2 to steel pipe fender pile 2 along the pit lateral wall and attach whole pit lateral wall in the pit, use connecting reinforcement 3 to weld in 2 top both sides of steel pipe fender pile, with steel pipe fender pile 2 and be linked into whole to at the inside concrete placement of steel pipe fender pile 2.
S4. Pit-in-pit earthwork excavation
Excavating earth in the pit; adopting a layered and segmented excavation form, reserving a pit foundation pit deformation monitoring point in a pit at the center position of the top of the steel pipe support pile 2, monitoring horizontal displacement data of a soil body, transporting the earthwork to a safe position outside the pit for storage and timely transporting the earthwork out of the field during excavation; after digging to the designed elevation, carrying out concrete bottom sealing treatment;
s5. Foundation pit side wall retaining wall construction
S5.1, binding a steel bar net piece 4 on the outer wall of the steel pipe support pile 2 on the inner side of the foundation pit, and welding and fixing the steel bar net piece on the steel pipe support pile 2;
s5.2, welding tie bars 5, and connecting a steel bar net piece 4 and the steel pipe support pile 2 into a whole;
s5.3, erecting a concrete template, reinforcing the template by using the water stop screw rod, pouring concrete for the side wall retaining wall 6 of the foundation pit in a layered and sectional manner after the erecting of the template is completed, removing the template and the water stop screw rod after the concrete reaches the design strength, and continuously monitoring the deformation of the supporting structure in the subsequent construction.
The whole life cycle informatization management and control is adopted in the process, and the construction flow cycle and the specific construction progress are managed.
The present invention can be easily implemented by those skilled in the art from the above detailed description. It should be understood, however, that the intention is not to limit the invention to the particular embodiments described. On the basis of the disclosed embodiments, a person skilled in the art can combine different technical features at will, thereby implementing different technical solutions.

Claims (6)

1. The utility model provides a quartering hammer with annular clamp which characterized in that: the device comprises a breaking hammer (7) and an annular hoop (8), wherein the annular hoop (8) is arranged on the end head of the breaking hammer (7);
the base of annular clamp (8) is fixed in afterbody in the end, annular clamp (8) are in the end below is provided with the ring perpendicular with the end axis, the ring pass through telescopic link (801) with the pedestal connection.
2. The demolition hammer with annular clamp of claim 1 wherein: an elastic ring (9) is arranged in the circular ring.
3. A construction method for supporting and protecting a steel pipe in a pit area in a deep foundation pit is characterized by comprising the following steps:
s1.BIM modeling
The BIM software is used for carrying out integral modeling on the whole foundation pit supporting system, and the structural stress form of the pit-in-pit system is determined;
s2, stress calculation simulation analysis
Carrying out construction environment simulation analysis by using Midas software, and carrying out stress and deformation simulation on a supporting structure, so as to select the type of the steel pipe supporting pile (2) and determine the construction parameters of the steel pipe supporting pile (2);
s3, steel pipe support pile injection
Measuring and positioning the outer side of a pit area in the pre-excavated pit, reserving the position of the side wall of the pit, and arranging a piling center line (1) of a steel pipe support pile (2) along the side wall of the pit; installing the breaking hammer (7) of claim 2 on a engineering truck, stretching the telescopic rod (801) to the longest, and placing the steel pipe support pile (2) into the annular hoop (8) of claim 2 by using the engineering truck, so that the upper part of the steel pipe support pile (2) is sleeved into the elastic ring (9); erecting the steel pipe support piles (2), righting the steel pipe support piles (2) in place through binding bands, starting to penetrate into the steel pipe piles to the depth of 100-200 mm, removing the binding bands, and hammering the steel pipe support piles (2) downwards into the rest part at the top by using a breaking hammer (7) which is arranged on a engineering truck and is described in claim 2 until the steel pipe support piles (2) penetrate into the designed elevation; repeatedly injecting steel pipe supporting piles (2) to the steel pipe supporting piles (2) along the side wall of the pit, attaching the side wall of the whole pit to the side wall of the pit, welding two sides of the top of the steel pipe supporting piles (2) by using connecting steel bars (3), connecting the steel pipe supporting piles (2) into a whole, and pouring concrete into the steel pipe supporting piles (2);
s4. Pit-in-pit earthwork excavation
Excavating earth in the pit; adopting a layered and segmented excavation form, reserving pit-in-pit foundation pit deformation monitoring points on the steel pipe support piles (2), monitoring horizontal displacement data of a soil body, transporting earthwork to a pit-out safety position for storage and timely transporting the earthwork out of a field during excavation; after digging the soil to the designed elevation, carrying out concrete bottom sealing treatment;
s5. Foundation pit side wall retaining wall construction
And pouring a foundation pit side wall retaining wall (6) at the inner side of the integral structure formed by connecting the steel pipe support piles (2).
4. The construction method for supporting the steel pipe in the pit area of the deep foundation pit as claimed in claim 3, wherein: the step S5 includes:
s5.1, binding a steel bar net piece (4) on the outer wall of the steel pipe support pile (2) on the inner side of the foundation pit, and welding and fixing the steel bar net piece on the steel pipe support pile (2);
s5.2, welding tie bars (5), and connecting a bar net piece (4) and the steel pipe support pile (2) into a whole;
s5.3, erecting a concrete template, reinforcing the template by using the water stop screw rod, pouring concrete on the side wall of the foundation pit (6) in a layered and sectional manner after the erecting of the template is finished, removing the template and the water stop screw rod after the concrete reaches the design strength, and continuously monitoring the deformation of the supporting structure in the subsequent construction.
5. The construction method for the steel pipe support of the pit area in the deep foundation pit according to claim 3, characterized in that: the deformation monitoring point is located at the center of the top of the steel pipe support pile (2).
6. The construction method for the steel pipe support of the pit area in the deep foundation pit according to claim 3, characterized in that: in the step S3, when the breaking hammer 7 performs the last 200mm to 600mm of the remaining part penetration, the telescopic rod 801 according to claim 2 is retracted.
CN202211095224.6A 2022-09-08 2022-09-08 Breaking hammer with annular clamp and construction method for supporting steel pipe in pit area in deep foundation pit Pending CN115341542A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211095224.6A CN115341542A (en) 2022-09-08 2022-09-08 Breaking hammer with annular clamp and construction method for supporting steel pipe in pit area in deep foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211095224.6A CN115341542A (en) 2022-09-08 2022-09-08 Breaking hammer with annular clamp and construction method for supporting steel pipe in pit area in deep foundation pit

Publications (1)

Publication Number Publication Date
CN115341542A true CN115341542A (en) 2022-11-15

Family

ID=83956258

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211095224.6A Pending CN115341542A (en) 2022-09-08 2022-09-08 Breaking hammer with annular clamp and construction method for supporting steel pipe in pit area in deep foundation pit

Country Status (1)

Country Link
CN (1) CN115341542A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118531810A (en) * 2024-07-23 2024-08-23 山东大学 Construction method of permanent supporting wall of whole row of piles

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107090837A (en) * 2017-06-29 2017-08-25 中国建筑第二工程局有限公司 Pit-in-pit reinforced concrete retaining wall composite supporting structure and construction method thereof
CN108914942A (en) * 2018-06-28 2018-11-30 上海建工五建集团有限公司 A kind of system of deep foundation pit support and its construction method
CN112813984A (en) * 2020-12-31 2021-05-18 攀钢集团工程技术有限公司 Deep foundation pit construction method under complex geological condition
CN214245799U (en) * 2020-11-12 2021-09-21 蒲树珍 Pile foundation connecting device convenient to dismantle and install
DE202022104117U1 (en) * 2022-07-21 2022-08-25 China Railway Liuyuan Group Co., Ltd. An underground mine support structure combined with piles and pipes, which can take into account the treatment of voids
CN115012429A (en) * 2022-06-29 2022-09-06 中交上海航道局有限公司 Supporting structure for exposing foundation pit for long time and construction method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107090837A (en) * 2017-06-29 2017-08-25 中国建筑第二工程局有限公司 Pit-in-pit reinforced concrete retaining wall composite supporting structure and construction method thereof
CN108914942A (en) * 2018-06-28 2018-11-30 上海建工五建集团有限公司 A kind of system of deep foundation pit support and its construction method
CN214245799U (en) * 2020-11-12 2021-09-21 蒲树珍 Pile foundation connecting device convenient to dismantle and install
CN112813984A (en) * 2020-12-31 2021-05-18 攀钢集团工程技术有限公司 Deep foundation pit construction method under complex geological condition
CN115012429A (en) * 2022-06-29 2022-09-06 中交上海航道局有限公司 Supporting structure for exposing foundation pit for long time and construction method thereof
DE202022104117U1 (en) * 2022-07-21 2022-08-25 China Railway Liuyuan Group Co., Ltd. An underground mine support structure combined with piles and pipes, which can take into account the treatment of voids

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118531810A (en) * 2024-07-23 2024-08-23 山东大学 Construction method of permanent supporting wall of whole row of piles

Similar Documents

Publication Publication Date Title
CN212426780U (en) Double-walled steel cofferdam and short pile casing crowd integrated positioning mounting structure
CN106522242B (en) For soft stratum close to underground structure foundation pit supporting system construction method
CN106638640B (en) Construction method without bottom concrete combined type cofferdam under the conditions of formation geology
CN206467667U (en) Suspended net shotcrete building enclosure between a kind of stake of use expansion type fixation reinforced mesh
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN109356169A (en) Foundation pit row pile supporting system and construction method thereof
CN214530750U (en) Bridge pile foundation structure suitable for rock mass abrupt slope
CN111576247A (en) Double-wall steel cofferdam and short pile casing group integral positioning and mounting structure and construction method
CN113216832A (en) Water-mill drilling construction method for pile hole in karst area
CN211340800U (en) Super dark foundation ditch earthwork excavation platform structure
CN115341542A (en) Breaking hammer with annular clamp and construction method for supporting steel pipe in pit area in deep foundation pit
CN113482011B (en) Large-diameter PHC pipe pile and cast-in-situ bored pile combined foundation pit supporting structure and method
CN214245694U (en) Pile forming system for large-diameter cast-in-situ bored pile in karst area
CN211006702U (en) Inclined strut underground structure is thrown in soft soil foundation double-deck
CN105064334A (en) Construction method for cast-in-situ bored pile
CN212052780U (en) Oblique supporting type deep foundation pit supporting structure
CN112482367A (en) Foundation pit support pile for replacing cast-in-place pile rock-socketed with steel pipe pile
CN114250784A (en) Foundation pit enclosure system combining piles with inclined piles in support-first and excavation-later construction method
CN217378907U (en) Deep soft soil pool foundation pit support system for complex land storage yard
CN110847188A (en) Ultra-deep foundation pit earth excavation platform structure and construction method thereof
CN113585272B (en) Pile repairing construction method for pipeline influence position by reverse construction method
CN214832726U (en) Supporting structure for pipe-jacking working well in deep soft soil area
CN115506807A (en) Supporting structure crossing karst cave below tunnel and construction method thereof
CN103015433A (en) Method for constructing super-large diameter round and square combination deep foundation pit
CN210530848U (en) Large-span small-clear-distance asymmetric section tunnel supporting structure in loess region

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20221115