CN115262986A - Installation method of long-span steel truss - Google Patents

Installation method of long-span steel truss Download PDF

Info

Publication number
CN115262986A
CN115262986A CN202210868970.8A CN202210868970A CN115262986A CN 115262986 A CN115262986 A CN 115262986A CN 202210868970 A CN202210868970 A CN 202210868970A CN 115262986 A CN115262986 A CN 115262986A
Authority
CN
China
Prior art keywords
steel truss
lower run
span steel
run
installation method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210868970.8A
Other languages
Chinese (zh)
Inventor
陈文才
吕玉玲
石和斌
贾迎冬
赵乙让
罗乙凯
王宁
姜博宇
刘瑞军
赵坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202210868970.8A priority Critical patent/CN115262986A/en
Publication of CN115262986A publication Critical patent/CN115262986A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C3/11Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal with non-parallel upper and lower edges, e.g. roof trusses
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/163Jacks specially adapted for working-up building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/165Tools or apparatus specially adapted for in situ prefabricated building elements to be tilted up in position

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a method for installing a large-span steel truss, which comprises the following steps: assembling on the ground to form a lower chord beam, placing the lower chord beam on the top of a jack, and pre-arching the lower chord beam by using the jack; hoisting the lower chord beam to a set position of the main body structure, and connecting an inclined pull rod between the lower chord beam and the main body structure on two sides of the lower chord beam; and a horizontal first connecting beam is connected between the lower chord beam and the main body structure, and then the upper chord beam is installed on the top of the lower chord beam, so that the upper chord beam and the lower chord beam are spliced to form a steel truss, and the pull rod is disassembled. The invention effectively solves the problem that the large-span steel truss is easy to bend downwards when being installed, reduces the deformation of the steel truss bending downwards under the action of gravity by optimizing the installation method of the large-span steel truss, improves the installation precision of the steel truss, ensures the construction quality and improves the construction efficiency.

Description

大跨度钢桁架的安装方法Installation method of long-span steel truss

技术领域technical field

本发明涉及建筑施工领域,特指一种大跨度钢桁架的安装方法。The invention relates to the field of building construction, in particular to a method for installing a large-span steel truss.

背景技术Background technique

在钢结构工程钢桁架吊装过程中,由于各构件现场拼装,使得桁架安装后的整体精度较难控制,造成桁架所在楼层的整体标高较设计值会产生较大偏差,传统的钢桁架吊装方法是在钢桁架下方搭设满堂脚手架支撑平台,使用塔吊或者汽车吊将各构件吊运至设计标高散拼安装,但由于钢桁架自重及上部构件传递的荷载,桁架中部会受拉向下弯曲产生一定挠度,使桁架所在楼层的整体标高较设计值产生较大偏差,且该方法只适用于桁架跨度较小、桁架自重较小和所处楼层较低的施工条件,对于面临大跨度、重型和处于高空等施工条件的钢桁架吊装不适用。In the process of hoisting steel trusses in steel structure engineering, due to the on-site assembly of various components, it is difficult to control the overall accuracy of the trusses after installation, resulting in a large deviation in the overall elevation of the floor where the trusses are located compared with the design value. The traditional hoisting method of steel trusses is Set up a full scaffolding support platform under the steel truss, and use a tower crane or a truck crane to lift each component to the design elevation and install it in bulk. However, due to the self-weight of the steel truss and the load transmitted by the upper component, the middle part of the truss will bend downward under tension to produce a certain deflection , so that the overall elevation of the floor where the truss is located has a large deviation from the design value, and this method is only applicable to the construction conditions of small truss span, small truss weight and low floor. The hoisting of steel trusses under other construction conditions is not applicable.

发明内容Contents of the invention

本发明的目的在于克服现有技术的缺陷,提供一种大跨度钢桁架的安装方法,解决了大跨度钢桁架安装时容易出现向下弯曲的问题,通过优化大跨度钢桁架的安装方法,以减小钢桁架受重力向下弯曲的变形量,提升钢桁架的安装精度,保证施工质量,提升施工效率。The purpose of the present invention is to overcome the defects of the prior art and provide a method for installing large-span steel trusses, which solves the problem of easy downward bending of large-span steel trusses during installation. By optimizing the installation method of large-span steel trusses, the Reduce the deformation of steel trusses bent downward by gravity, improve the installation accuracy of steel trusses, ensure construction quality, and improve construction efficiency.

实现上述目的的技术方案是:The technical scheme for realizing the above-mentioned purpose is:

本发明提供了一种大跨度钢桁架的安装方法,包括如下步骤:The invention provides a method for installing a large-span steel truss, comprising the following steps:

于地面拼装形成下弦梁,将下弦梁置于千斤顶的顶部,并利用千斤顶对下弦梁预起拱;Assemble on the ground to form the lower string beam, place the lower string beam on the top of the jack, and use the jack to pre-arch the lower string beam;

将下弦梁吊装至主体结构的设定位置,于下弦梁和下弦梁两侧的主体结构之间连接倾斜的拉杆;Hoist the lower string beam to the set position of the main structure, and connect the inclined tie rods between the lower string beam and the main structure on both sides of the lower string beam;

于下弦梁与主体结构之间连接水平状的第一连接梁,进而与下弦梁的顶部安装上弦梁,从而上弦梁和下弦梁拼合形成钢桁架,拆除拉杆。The horizontal first connecting beam is connected between the lower run beam and the main structure, and then the upper run girder is installed on the top of the lower run girder, so that the upper run girder and the lower run girder are combined to form a steel truss, and the tie rods are removed.

本发明采用大跨度钢桁架的安装方法,通过利用千斤顶于地面预先对下弦梁进行起拱,使得下弦梁的起拱高度能够与因重力而出现的向下弯曲量相抵消,进而将下弦梁安装于主体结构,并使用拉杆进一步固定下弦梁,防止上弦梁安装过程对下弦梁产生影响,且第一连接梁也对下弦梁提供了有力的支撑,解决了大跨度钢桁架安装时容易出现向下弯曲的问题,通过优化大跨度钢桁架的安装方法,以减小钢桁架受重力向下弯曲的变形量,提升钢桁架的安装精度,保证施工质量,提升施工效率。The present invention adopts the installation method of the large-span steel truss. By using the jack to arch the lower string beam in advance on the ground, the arching height of the lower string beam can be offset with the downward bending amount due to gravity, and then the lower string beam is installed. In the main structure, tie rods are used to further fix the lower string girder to prevent the impact of the upper string girder installation process on the lower string girder, and the first connecting beam also provides strong support for the lower string girder, which solves the problem that the large-span steel truss tends to fall downward during installation. For the bending problem, optimize the installation method of the long-span steel truss to reduce the deformation of the steel truss bent downward by gravity, improve the installation accuracy of the steel truss, ensure the construction quality, and improve the construction efficiency.

本发明大跨度钢桁架的安装方法的进一步改进在于,安装上弦梁时,还包括:The further improvement of the installation method of the large-span steel truss of the present invention is that when installing the upper string beam, it also includes:

于下弦梁的顶部间隔安装若干竖直杆,于竖直杆与主体结构之间连接水平状的第二连接梁,进而于相邻两个竖直杆之间安装上弦梁。A plurality of vertical rods are installed at intervals on the top of the lower string beam, a horizontal second connecting beam is connected between the vertical rods and the main structure, and an upper string beam is installed between two adjacent vertical rods.

本发明大跨度钢桁架的安装方法的进一步改进在于,竖直杆靠近顶部的位置固定有水平段;The further improvement of the installation method of the large-span steel truss of the present invention is that a horizontal section is fixed near the top of the vertical bar;

将上弦梁固定连接于相邻两个水平段之间。Fix the upper string beam between two adjacent horizontal sections.

本发明大跨度钢桁架的安装方法的进一步改进在于,安装上弦梁后,还包括:The further improvement of the installation method of the large-span steel truss of the present invention is that, after installing the upper string girder, it also includes:

于上弦梁和下弦梁之间倾斜地连接若干斜撑。Several diagonal braces are obliquely connected between the upper string beam and the lower string beam.

本发明大跨度钢桁架的安装方法的进一步改进在于,还包括:The further improvement of the installation method of the large-span steel truss of the present invention is that it also includes:

拼装形成下弦梁时,于下弦梁的顶部间隔固设若干倾斜设置的第一倾斜段,拼装形成上弦梁时,于上弦梁的底部对应第一倾斜段固设若干第二倾斜段,待上弦梁安装完成后,将斜撑固定连接于相对的第一倾斜段和第二倾斜段之间。When assembling to form the lower run, a number of inclined first inclined sections are fixed on the top of the lower run at intervals; After the installation is completed, the braces are fixedly connected between the opposite first inclined section and the second inclined section.

本发明大跨度钢桁架的安装方法的进一步改进在于,安装上弦梁后,还包括:The further improvement of the installation method of the large-span steel truss of the present invention is that, after installing the upper string girder, it also includes:

于上弦梁和下弦梁之间竖直地连接若干支撑杆。A plurality of support rods are vertically connected between the upper string beam and the lower string beam.

本发明大跨度钢桁架的安装方法的进一步改进在于,还包括:The further improvement of the installation method of the large-span steel truss of the present invention is that it also includes:

拼装形成下弦梁时,于下弦梁的顶部间隔固设若干竖直设置的第一支撑段,拼装形成上弦梁时,于上弦梁的底部对应第一支撑段固设若干第二支撑段,待上弦梁安装完成后,将支撑杆固定连接于相对的第一支撑段和第二支撑段之间。When assembling to form the lower string beam, a number of vertically arranged first support sections are fixed at intervals on the top of the lower string beam; After the beam is installed, the support rod is fixedly connected between the opposite first support section and the second support section.

本发明大跨度钢桁架的安装方法的进一步改进在于,还包括:The further improvement of the installation method of the large-span steel truss of the present invention is that it also includes:

拼装形成下弦梁时,于下弦梁的顶部间隔固设若干竖直段,将竖直杆固定连接于竖直段。When assembling to form the lower run beam, several vertical sections are fixed at intervals on the top of the lower run beam, and the vertical rods are fixedly connected to the vertical sections.

本发明大跨度钢桁架的安装方法的进一步改进在于,下弦梁的起拱高度为15mm。The further improvement of the installation method of the large-span steel truss of the present invention lies in that the arching height of the lower string girder is 15 mm.

本发明大跨度钢桁架的安装方法的进一步改进在于,还包括:The further improvement of the installation method of the large-span steel truss of the present invention is that it also includes:

拼装下弦梁时,于下弦梁的侧部固定连接板,将下弦梁固定于主体结构后,将拉杆的一端固定于下弦梁侧部的主体结构,将拉杆的另一端通过螺栓与连接板固定连接。When assembling the lower string beam, fix the connecting plate on the side of the lower string beam, fix the lower string beam to the main structure, fix one end of the tie rod to the main structure on the side of the lower string beam, and fix the other end of the tie rod to the connecting plate through bolts .

附图说明Description of drawings

图1为本发明大跨度钢桁架的安装方法中下弦梁预起拱的示意图。Fig. 1 is a schematic diagram of the pre-arching of the lower string girder in the installation method of the large-span steel truss of the present invention.

图2为本发明大跨度钢桁架的安装方法中下弦梁安装的示意图。Fig. 2 is a schematic diagram of the installation of the lower string girder in the installation method of the large-span steel truss according to the present invention.

图3为本发明大跨度钢桁架的安装方法中上弦梁安装的示意图。Fig. 3 is a schematic diagram of the installation of the upper string girder in the installation method of the large-span steel truss according to the present invention.

具体实施方式Detailed ways

下面结合附图和具体实施例对本发明作进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

参阅图1,本发明提供了一种大跨度钢桁架的安装方法,通过利用千斤顶于地面预先对下弦梁进行起拱,使得下弦梁的起拱高度能够与因重力而出现的向下弯曲量相抵消,进而将下弦梁安装于主体结构,并使用拉杆进一步固定下弦梁,防止上弦梁安装过程对下弦梁产生影响,且第一连接梁也对下弦梁提供了有力的支撑,解决了大跨度钢桁架安装时容易出现向下弯曲的问题,通过优化大跨度钢桁架的安装方法,以减小钢桁架受重力向下弯曲的变形量,提升钢桁架的安装精度,保证施工质量,提升施工效率。下面结合附图对本发明大跨度钢桁架的安装方法进行说明。Referring to Fig. 1, the present invention provides a method for installing large-span steel trusses. By using jacks to arch the lower string beams on the ground in advance, the arching height of the lower string girders can be equal to the amount of downward bending due to gravity. offset, and then install the lower run beam on the main structure, and use tie rods to further fix the lower run girder to prevent the impact of the upper run girder installation process on the lower run girder, and the first connecting beam also provides strong support for the lower run girder, solving the problem of large-span steel The problem of downward bending is easy to occur when the truss is installed. By optimizing the installation method of the large-span steel truss, the deformation of the steel truss bent downward by gravity can be reduced, the installation accuracy of the steel truss can be improved, the construction quality can be guaranteed, and the construction efficiency can be improved. The installation method of the large-span steel truss of the present invention will be described below in conjunction with the accompanying drawings.

参阅图1,图1为本发明大跨度钢桁架的安装方法中下弦梁预起拱的示意图。下面结合图1,对本发明大跨度钢桁架的安装方法进行说明。Referring to Fig. 1, Fig. 1 is a schematic diagram of the pre-arching of the lower string girder in the installation method of the large-span steel truss according to the present invention. The installation method of the large-span steel truss of the present invention will be described below with reference to FIG. 1 .

结合图1~3所示,本发明大跨度钢桁架的安装方法,该方法包括如下步骤:Shown in conjunction with Figures 1 to 3, the installation method of the large-span steel truss of the present invention comprises the following steps:

于地面拼装形成下弦梁11,将下弦梁11置于千斤顶的顶部,并利用千斤顶对下弦梁11预起拱;Assemble the lower string 11 on the ground, place the lower string 11 on the top of the jack, and use the jack to pre-arch the lower string 11;

将下弦梁11吊装至主体结构的设定位置,于下弦梁11和下弦梁11两侧的主体结构之间连接倾斜的拉杆16;hoisting the lower run beam 11 to the set position of the main structure, and connecting the inclined tie rods 16 between the lower run beam 11 and the main structure on both sides of the lower run beam 11;

于下弦梁11与主体结构之间连接水平状的第一连接梁,进而与下弦梁11的顶部安装上弦梁12,从而上弦梁12和下弦梁11拼合形成钢桁架,拆除拉杆16。Connect the first horizontal connecting beam between the lower run 11 and the main structure, and then install the upper run 12 on the top of the lower run 11, so that the upper run 12 and the lower run 11 are combined to form a steel truss, and the tie rods 16 are removed.

具体的,下弦梁11的起拱高度为15mm。Specifically, the arching height of the lower string 11 is 15 mm.

具体的,还包括:Specifically, it also includes:

拼装下弦梁11时,于下弦梁11的侧部固定连接板114,将下弦梁11固定于主体结构后,将拉杆16的一端固定于下弦梁11侧部的主体结构,将拉杆16的另一端通过螺栓与连接板114固定连接。When assembling the lower run beam 11, fix the connecting plate 114 on the side of the lower run beam 11, fix the lower run beam 11 to the main structure, fix one end of the tie rod 16 to the main structure at the side of the lower run beam 11, and connect the other end of the tie rod 16 It is fixedly connected with the connecting plate 114 by bolts.

作为本发明的一较佳实施方式,安装上弦梁12时,还包括:As a preferred embodiment of the present invention, when installing the upper run girder 12, it also includes:

于下弦梁11的顶部间隔安装若干竖直杆13,于竖直杆13与主体结构之间连接水平状的第二连接梁,进而于相邻两个竖直杆13之间安装上弦梁12,由于第二连接梁和第一连接梁位于钢桁架的后侧,因此图中并未示出。A plurality of vertical rods 13 are installed at intervals on the top of the lower run beam 11, and a horizontal second connecting beam is connected between the vertical rods 13 and the main structure, and then the upper run beam 12 is installed between two adjacent vertical rods 13, Since the second connecting beam and the first connecting beam are located at the rear side of the steel truss, they are not shown in the figure.

具体的,竖直杆13靠近顶部的位置固定有水平段131;Specifically, a horizontal section 131 is fixed near the top of the vertical bar 13;

将上弦梁12固定连接于相邻两个水平段131之间。The upper run beam 12 is fixedly connected between two adjacent horizontal sections 131 .

进一步的,安装上弦梁12后,还包括:Further, after installing the top string 12, it also includes:

于上弦梁12和下弦梁11之间倾斜地连接若干斜撑14。Several diagonal braces 14 are obliquely connected between the upper run beam 12 and the lower run beam 11 .

具体的,还包括:Specifically, it also includes:

拼装形成下弦梁11时,于下弦梁11的顶部间隔固设若干倾斜设置的第一倾斜段111,拼装形成上弦梁12时,于上弦梁12的底部对应第一倾斜段111固设若干第二倾斜段121,待上弦梁12安装完成后,将斜撑14固定连接于相对的第一倾斜段111和第二倾斜段121之间。When assembling to form the lower run beam 11, a number of first inclined sections 111 are fixed at intervals on the top of the lower run beam 11; The inclined section 121 is fixedly connected between the first inclined section 111 and the second inclined section 121 after the top run 12 is installed.

进一步的,安装上弦梁12后,还包括:Further, after installing the top string 12, it also includes:

于上弦梁12和下弦梁11之间竖直地连接若干支撑杆15。Several support rods 15 are vertically connected between the upper run 12 and the lower run 11 .

具体的,还包括:Specifically, it also includes:

拼装形成下弦梁11时,于下弦梁11的顶部间隔固设若干竖直设置的第一支撑段112,拼装形成上弦梁12时,于上弦梁12的底部对应第一支撑段112固设若干第二支撑段122,待上弦梁12安装完成后,将支撑杆15固定连接于相对的第一支撑段112和第二支撑段122之间。When assembling the lower run beam 11, a number of vertically arranged first support sections 112 are fixed at intervals on the top of the lower run beam 11; For the second support section 122 , after the top string 12 is installed, the support rod 15 is fixedly connected between the opposite first support section 112 and the second support section 122 .

进一步的,还包括:Further, it also includes:

拼装形成下弦梁11时,于下弦梁11的顶部间隔固设若干竖直段113,将竖直杆13固定连接于竖直段113。When assembling the lower string 11 , several vertical sections 113 are fixed at intervals on the top of the lower string 11 , and the vertical rods 13 are fixedly connected to the vertical sections 113 .

本发明大跨度钢桁架的安装方法的具体施工方式如下:The concrete construction method of the installation method of long-span steel truss of the present invention is as follows:

于地面拼装形成下弦梁11,并在下弦梁11的顶部间隔固设若干竖直设置的第一支撑段112和竖直段113,且第一支撑段112与竖直段113交错设置,并在下弦梁11的顶部且位于竖直段113的两侧固设第一倾斜段11,在下弦梁11的侧部安装连接板114;Assembled on the ground to form the lower run beam 11, and a number of vertically arranged first support sections 112 and vertical sections 113 are fixed at intervals on the top of the lower run beam 11, and the first support sections 112 and the vertical sections 113 are arranged alternately, and The first inclined section 11 is fixed on the top of the lower string 11 and on both sides of the vertical section 113, and the connecting plate 114 is installed on the side of the lower string 11;

将下弦梁11置于千斤顶的顶部,利用千斤顶推顶下弦梁11靠近中部的位置,以对下弦梁11预起拱,使得下弦梁11具有一定的起拱高度;Place the lower string 11 on the top of the jack, and use the jack to push the lower string 11 near the middle to pre-arch the lower string 11, so that the lower string 11 has a certain arching height;

将下弦梁11吊装至主体结构的设定高度处,进而将拉杆16的一端与下弦梁11的连接板114通过螺栓固定连接,将拉杆16的另一端与主体结构固定连接,从而拉杆16倾斜地连接于主体结构与下弦梁11之间,以对下弦梁11提供斜向上的拉力;Hoist the lower string 11 to the set height of the main structure, and then connect one end of the tie rod 16 to the connecting plate 114 of the lower string 11 through bolts, and fix the other end of the pull rod 16 to the main structure, so that the pull rod 16 tilts It is connected between the main structure and the lower run beam 11 to provide an oblique upward tension to the lower run beam 11;

将第一连接梁水平地连接于下弦梁11与主体结构之间;connecting the first connecting beam horizontally between the lower run beam 11 and the main structure;

将竖直杆13固定连接于竖直段113的顶部,且将第二连接梁水平地连接于竖直杆13与主体结构之间;The vertical rod 13 is fixedly connected to the top of the vertical section 113, and the second connecting beam is horizontally connected between the vertical rod 13 and the main structure;

于地面拼装形成上弦梁12,并在上弦梁12的底部对应第一倾斜段111固设若干第二倾斜段121,在上弦梁12的底部对应第一支撑段112固设若干第二支撑段122;Assembled on the ground to form the upper run beam 12, and fixed a number of second inclined sections 121 at the bottom of the upper run beam 12 corresponding to the first inclined section 111, and fixed a number of second support sections 122 at the bottom of the upper run beam 12 corresponding to the first support section 112 ;

将上弦梁12固定连接于相邻两个竖直杆13的水平段131之间,在相对的第一倾斜段111和第二倾斜段121之间连接斜撑14,在相对的第一支撑段112和第二支撑段122之间连接支撑杆15,此时上弦梁12与下弦梁11拼合形成钢桁架,拆除拉杆16。The upper run beam 12 is fixedly connected between the horizontal sections 131 of two adjacent vertical rods 13, the diagonal brace 14 is connected between the opposite first inclined section 111 and the second inclined section 121, and the opposite first support section 112 and the second support section 122 are connected with the support rod 15. At this time, the upper run 12 and the lower run 11 are combined to form a steel truss, and the tie rod 16 is removed.

以上结合附图实施例对本发明进行了详细说明,本领域中普通技术人员可根据上述说明对本发明做出种种变化例。因而,实施例中的某些细节不应构成对本发明的限定,本发明将以所附权利要求书界定的范围作为本发明的保护范围。The present invention has been described in detail above with reference to the embodiments of the accompanying drawings, and those skilled in the art can make various changes to the present invention according to the above description. Therefore, some details in the embodiments should not be construed as limiting the present invention, and the present invention will take the scope defined by the appended claims as the protection scope of the present invention.

Claims (10)

1.一种大跨度钢桁架的安装方法,其特征在于,包括如下步骤:1. A method for installing a large-span steel truss, characterized in that it may further comprise the steps: 于地面拼装形成下弦梁,将所述下弦梁置于千斤顶的顶部,并利用千斤顶对所述下弦梁预起拱;Assembling on the ground to form the lower run beam, placing the lower run beam on the top of the jack, and using the jack to pre-arch the lower run beam; 将所述下弦梁吊装至主体结构的设定位置,于所述下弦梁和所述下弦梁两侧的主体结构之间连接倾斜的拉杆;hoisting the lower run beam to the set position of the main structure, and connecting inclined tie rods between the lower run beam and the main structure on both sides of the lower run beam; 于所述下弦梁与所述主体结构之间连接水平状的第一连接梁,进而于所述下弦梁的顶部安装上弦梁,从而所述上弦梁和所述下弦梁拼合形成钢桁架,拆除所述拉杆。A horizontal first connecting beam is connected between the lower run beam and the main structure, and an upper run beam is installed on the top of the lower run girder, so that the upper run beam and the lower run girder are combined to form a steel truss, and all Said tie rod. 2.如权利要求1所述的大跨度钢桁架的安装方法,其特征在于,安装所述上弦梁时,还包括:2. The installation method of the long-span steel truss as claimed in claim 1, characterized in that, when installing the upper string beam, it also includes: 于所述下弦梁的顶部间隔安装若干竖直杆,于所述竖直杆与所述主体结构之间连接水平状的第二连接梁,进而于相邻两个所述竖直杆之间安装所述上弦梁。A plurality of vertical rods are installed at intervals on the top of the lower chord beam, and a horizontal second connecting beam is connected between the vertical rods and the main structure, and then installed between two adjacent vertical rods The top string. 3.如权利要求2所述的大跨度钢桁架的安装方法,其特征在于,所述竖直杆靠近顶部的位置固定有水平段;3. the installation method of long-span steel truss as claimed in claim 2, is characterized in that, the position of described vertical bar near top is fixed with horizontal section; 将所述上弦梁固定连接于相邻两个所述水平段之间。The upper run beam is fixedly connected between two adjacent horizontal sections. 4.如权利要求1所述的大跨度钢桁架的安装方法,其特征在于,安装所述上弦梁后,还包括:4. The installation method of the long-span steel truss as claimed in claim 1, characterized in that, after installing the upper chord beam, further comprising: 于所述上弦梁和所述下弦梁之间倾斜地连接若干斜撑。A plurality of diagonal braces are obliquely connected between the upper run beam and the lower run beam. 5.如权利要求4所述的大跨度钢桁架的安装方法,其特征在于,还包括:5. The installation method of the long-span steel truss as claimed in claim 4, further comprising: 拼装形成所述下弦梁时,于所述下弦梁的顶部间隔固设若干倾斜设置的第一倾斜段,拼装形成所述上弦梁时,于所述上弦梁的底部对应所述第一倾斜段固设若干第二倾斜段,待所述上弦梁安装完成后,将所述斜撑固定连接于相对的所述第一倾斜段和所述第二倾斜段之间。When assembling the lower run beams, a number of first inclined sections are fixed at intervals on the top of the lower run beams; A plurality of second inclined sections are provided, and after the installation of the upper string girder is completed, the braces are fixedly connected between the opposite first inclined sections and the second inclined sections. 6.如权利要求1所述的大跨度钢桁架的安装方法,其特征在于,安装所述上弦梁后,还包括:6. The installation method of the long-span steel truss as claimed in claim 1, characterized in that, after installing the upper chord beam, further comprising: 于所述上弦梁和所述下弦梁之间竖直地连接若干支撑杆。A plurality of support rods are vertically connected between the upper run beam and the lower run beam. 7.如权利要求6所述的大跨度钢桁架的安装方法,其特征在于,还包括:7. The installation method of the long-span steel truss as claimed in claim 6, further comprising: 拼装形成所述下弦梁时,于所述下弦梁的顶部间隔固设若干竖直设置的第一支撑段,拼装形成所述上弦梁时,于所述上弦梁的底部对应所述第一支撑段固设若干第二支撑段,待所述上弦梁安装完成后,将所述支撑杆固定连接于相对的所述第一支撑段和所述第二支撑段之间。When assembling to form the lower run, a number of vertically arranged first support sections are fixed at intervals on the top of the lower run; when assembling to form the upper run, the bottom of the upper run corresponds to the first support section A plurality of second support sections are fixed, and after the installation of the upper string beam is completed, the support rods are fixedly connected between the opposite first support sections and the second support sections. 8.如权利要求1所述的大跨度钢桁架的安装方法,其特征在于,还包括:8. The installation method of the long-span steel truss according to claim 1, further comprising: 拼装形成所述下弦梁时,于所述下弦梁的顶部间隔固设若干竖直段,将所述竖直杆固定连接于所述竖直段。When assembling to form the lower run beam, several vertical sections are fixed at intervals on the top of the lower run beam, and the vertical rods are fixedly connected to the vertical sections. 9.如权利要求1所述的大跨度钢桁架的安装方法,其特征在于,所述下弦梁的起拱高度为15mm。9. The installation method of the long-span steel truss according to claim 1, wherein the arching height of the lower string girder is 15 mm. 10.如权利要求1所述的大跨度钢桁架的安装方法,其特征在于,还包括:10. The installation method of the long-span steel truss according to claim 1, further comprising: 拼装所述下弦梁时,于所述下弦梁的侧部固定连接板,将所述下弦梁固定于所述主体结构后,将所述拉杆的一端固定于所述下弦梁侧部的主体结构,将所述拉杆的另一端通过螺栓与所述连接板固定连接。When assembling the lower run beam, fix the connecting plate on the side of the lower run beam, fix the lower run beam to the main structure, and then fix one end of the tie rod to the main structure at the side of the lower run beam, The other end of the pull rod is fixedly connected with the connecting plate through bolts.
CN202210868970.8A 2022-07-22 2022-07-22 Installation method of long-span steel truss Pending CN115262986A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210868970.8A CN115262986A (en) 2022-07-22 2022-07-22 Installation method of long-span steel truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210868970.8A CN115262986A (en) 2022-07-22 2022-07-22 Installation method of long-span steel truss

Publications (1)

Publication Number Publication Date
CN115262986A true CN115262986A (en) 2022-11-01

Family

ID=83769482

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210868970.8A Pending CN115262986A (en) 2022-07-22 2022-07-22 Installation method of long-span steel truss

Country Status (1)

Country Link
CN (1) CN115262986A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4087437B1 (en) * 2007-12-12 2008-05-21 イシグロ農材株式会社 Truss beam assembly method
CN206616765U (en) * 2016-06-06 2017-11-07 中建钢构有限公司 Large span is without depending on huge bandy truss pull bar
CN107700360A (en) * 2017-09-19 2018-02-16 武船重型工程股份有限公司 A kind of assembling method of truss bridge section
JP2020118004A (en) * 2019-01-28 2020-08-06 三井住友建設株式会社 Truss beam
CN113685040A (en) * 2021-08-25 2021-11-23 中电建十一局工程有限公司 Large-span steel truss hoisting construction method
CN214940962U (en) * 2021-06-01 2021-11-30 中国建筑第二工程局有限公司 Large-span steel construction vestibule

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4087437B1 (en) * 2007-12-12 2008-05-21 イシグロ農材株式会社 Truss beam assembly method
CN206616765U (en) * 2016-06-06 2017-11-07 中建钢构有限公司 Large span is without depending on huge bandy truss pull bar
CN107700360A (en) * 2017-09-19 2018-02-16 武船重型工程股份有限公司 A kind of assembling method of truss bridge section
JP2020118004A (en) * 2019-01-28 2020-08-06 三井住友建設株式会社 Truss beam
CN214940962U (en) * 2021-06-01 2021-11-30 中国建筑第二工程局有限公司 Large-span steel construction vestibule
CN113685040A (en) * 2021-08-25 2021-11-23 中电建十一局工程有限公司 Large-span steel truss hoisting construction method

Similar Documents

Publication Publication Date Title
CN103243654B (en) Mounting method for steel anchor beam of cable-stayed bridge and assembly jig and cable bent tower mounting platform used in method
CN106759909B (en) A lower hanging and upper bearing structure system and its construction method
CN111101726A (en) An application method of structural underpinning technology in reinforcement engineering
CN108729640B (en) Mounting method of cantilever plate of assembled building
CN115492400B (en) Steel structure net frame lifting construction method
CN106836028A (en) The concrete continuous rigid structure beam bridge and construction method reinforced with steel truss girder jacking
CN115387245A (en) A method for cantilever erection of continuous steel truss girders
CN216999749U (en) Foundation pit supporting device convenient for subsequent construction of foundation pit
CN221810709U (en) A hanging basket exterior wall construction device
CN115262986A (en) Installation method of long-span steel truss
CN217732445U (en) Double-lifting-point lifting support attached to unequal-height concrete columns
CN217378583U (en) Crossbeam support structure with main tower column stull function
CN218667155U (en) Supporting platform structure
CN118390801A (en) A cantilevered inclined column reinforcement structure and construction method
CN218713234U (en) A assembled concrete truss for iron tower infrastructure
CN217028054U (en) Small-radius semicircular arch wall non-floor support device
CN114232498B (en) A multifunctional support erection method for construction of a mid-span steel tube concrete arch bridge
CN117145268A (en) Jig frame supporting system for steel structure sliding and steel structure construction method
CN116043719A (en) A No. 0 Block Support System Combining Triangular Brackets and Floor Steel Pipes and Its Construction Method
CN116122579A (en) Hoisting method for bidirectional bending dome bracket
CN210917011U (en) Cable tower structure and bridge
CN111172886A (en) Construction method of main arch and auxiliary arch of double-flying-wing arch bridge and temporary support used by same
CN220450682U (en) Temporary construction support based on new bridge tie beam
CN114592523B (en) Pit support without column support used in the foundation pit
CN114541270A (en) Cross beam support structure with main tower column cross bracing function and using method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20221101

RJ01 Rejection of invention patent application after publication