CN115196492A - Vertical transportation and hoisting device for arc-shaped prefabricated parts in super-large-diameter shield tunnel - Google Patents
Vertical transportation and hoisting device for arc-shaped prefabricated parts in super-large-diameter shield tunnel Download PDFInfo
- Publication number
- CN115196492A CN115196492A CN202210787817.2A CN202210787817A CN115196492A CN 115196492 A CN115196492 A CN 115196492A CN 202210787817 A CN202210787817 A CN 202210787817A CN 115196492 A CN115196492 A CN 115196492A
- Authority
- CN
- China
- Prior art keywords
- arc
- lifting
- shield tunnel
- body frame
- hoisting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/22—Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
- B66C1/28—Duplicate, e.g. pivoted, members engaging the loads from two sides
Abstract
The invention relates to a vertical transportation and hoisting device for an arc-shaped prefabricated part in an oversized-diameter shield tunnel, which consists of a main body frame structure and a hoisting structure, wherein the main body frame structure comprises main cross beams, stand columns and transverse supports, and the stand columns are fixedly connected through the main cross beams and the transverse supports to form a main body frame of a hoisting tool; a lifting lug is welded at the upper end of the lifting appliance main body frame; hoisting structure includes lifting hook, pivot, locating pin, spacing steel sheet passes through connecting plate and stand welding, with pivot connection between spacing steel sheet and the lifting hook, as the axis of rotation, two spacing holes are opened on the spacing steel sheet, through the different positions of locating pin control lifting hook. According to the invention, the problems that the arc-shaped prefabricated part in the shield tunnel with the super-large diameter is difficult to hoist and the lifting appliance is difficult to fix are effectively solved by combining the height difference between the human body and the member according to the structural form of the arc-shaped member.
Description
Technical Field
The invention relates to a hoisting device for an arc-shaped prefabricated part in an oversized-diameter shield tunnel, in particular to a vertical transportation hoisting device.
Background
With the continuous development of the shield method technology, the application of the shield tunnel is more and more extensive, and the shield tunnel is developed from an early highway tunnel and a railway tunnel to a water taking and draining tunnel, a nuclear power tunnel, a subway tunnel and the like. At present, underground high-speed rail tunnels are built, the use functions of the tunnels are continuously updated, and the construction method of the internal structure of the tunnels is also continuously updated.
A14 m-grade large shield machine is adopted for tunnel engineering construction in multiple sections of the winding yard connecting line of the Shanghai rail transit urban area, so that the quantity of components in a tunnel is very large, and the construction difficulty is increased. How to guarantee the safe and convenient hoisting and transportation of the internal components with the ultra-large volume becomes a big problem in construction. Because the lower part of the arc-shaped component is arc-shaped, lifting appliances such as steel wire ropes and lifting belts cannot be directly used, the arc-shaped component is large in size, the top height is high, and the clamp cannot be directly fixed on the top manually.
Disclosure of Invention
The invention provides a vertical transportation and hoisting device for an arc-shaped prefabricated part in an oversized-diameter shield tunnel, which effectively solves the problems that the arc-shaped prefabricated part in the oversized-diameter shield tunnel is difficult to hoist and a hoisting tool is difficult to fix by combining the height difference between a human body and the prefabricated part according to the structural form of the arc-shaped part.
In order to achieve the purpose, the technical scheme of the invention is as follows: a vertical transportation and hoisting device for an arc-shaped prefabricated part in an oversized-diameter shield tunnel comprises a main body frame structure and a hoisting structure, wherein the main body frame structure comprises main cross beams, stand columns and transverse supports, and the stand columns are fixedly connected through the main cross beams and the transverse supports to form a main body frame of a hoisting tool; a lifting lug is welded at the upper end of the lifting appliance main body frame; hoisting structure includes lifting hook, pivot, locating pin, spacing steel sheet passes through connecting plate and stand welding, with the pivot connection between spacing steel sheet and the lifting hook, as the axis of rotation, two spacing holes are opened on the spacing steel sheet, through the different positions of locating pin control lifting hook.
Furthermore, the number of the lifting lugs is 4, the direction of the lifting lugs and the main beam form 45 degrees, and the lifting lugs (1) are made of steel plates with the height of 267.6mm and the thickness of 30mm.
Furthermore, 2.16m 4 pieces of 20# section steel are adopted for the main cross beams, 1.86m 4 pieces of 20# section steel are adopted for the upright columns, and 2.16m 4 pieces of 20# section steel are adopted for the transverse support.
Furthermore, two crossbeam supports are located main beam below 400mm department, and two other crossbeam supports are located main beam below 1310mm department, reinforcing hoist stability.
Further, the web size is 240mm 30mm.
Furthermore, the thickness of the limiting steel plate is 40mm, the thickness of the lifting hook is 55mm, and the diameters of the shaft pin and the positioning pin are 55mm.
The invention has the beneficial effects that:
the vertical transportation and hoisting device for the arc-shaped prefabricated part in the shield tunnel with the ultra-large diameter, disclosed by the invention, has the advantages that the safety of hoisting large-scale parts is improved, meanwhile, the problem that the construction of a hoisting worker is difficult due to the overlarge size of the arc-shaped part is also solved, the working efficiency is greatly improved, and manpower and material resources are saved. The hoisting device can be suitable for hoisting other large-scale components after being modified.
Drawings
FIG. 1 is a front view of a vertical transportation and hoisting device for an arc-shaped prefabricated part inside an ultra-large diameter shield tunnel according to the invention;
FIG. 2 is a side view of the vertical transportation and hoisting device for the arc-shaped prefabricated part in the ultra-large diameter shield tunnel;
FIG. 3 is a top view of the vertical transportation and hoisting device for the arc-shaped prefabricated part inside the super-large diameter shield tunnel according to the invention;
fig. 4 is a side view of the present invention when hoisted.
Detailed Description
The invention is further illustrated by the following specific examples in conjunction with the accompanying drawings.
The invention relates to a vertical transportation and hoisting device for an arc-shaped prefabricated part in an oversized-diameter shield tunnel, which is characterized in that the lower part of the arc-shaped part is arc-shaped, so that a steel wire rope, a sling and other hoisting tools cannot be directly used, the size of the arc-shaped part is large, the height of the top is high, and a clamp cannot be directly fixed on the top manually.
As shown in fig. 1 to 4, the vertical transportation and hoisting device for the arc-shaped prefabricated part in the ultra-large diameter shield tunnel comprises the following parts: the lifting lug comprises a lifting lug 1, a main beam 2, a stand column 3, a transverse support I4, a transverse support II 5, a connecting plate 6, a lifting hook 7, a shaft pin 8, a shoe plate 9, a positioning pin 10 and a limiting steel plate 11.
A main frame structure is formed by the main beam 2, the upright post 3, the transverse support I4 and the transverse support II 5, and a hoisting structure of an arc-shaped component is formed by the lifting hook 7, the shaft pin 8, the positioning pin 10 and the limiting steel plate 11 and is also a main working position of the whole lifting appliance. Be connected with pivot 8 between spacing steel sheet 11 and the lifting hook 7, as the axis of rotation, open two spacing holes on the spacing steel sheet 11, open and close through locating pin 10 control lifting hook, be fixed in the spacing hole in below with lifting hook 7 during lifting by crane, make the lifting hook be in the closure state, after the hoist and mount, be fixed in the spacing hole in top with lifting hook 7, make lifting hook 7 be in the state of opening, the arc can freely come in and go out the hoist.
The number of the lifting lugs 1 is 4, the direction of the lifting lugs 1 and the main beam 2 form a 45-degree angle, and the lifting lugs 1 are made of steel plates with the height of 267.6mm and the thickness of 30mm. The main beam 2 adopts 2.16m × 4 pieces of 20# section steel, the upright column 3 adopts 1.86m × 4 pieces of 20# section steel, the first transverse support 4 adopts 2.16m × 2 pieces of 20# section steel, and the second transverse support 5 adopts 2.16m × 2 pieces of 20# section steel. The crossbeam supports one 4 and the crossbeam supports two 5's position, and crossbeam supports one 4 and is located main beam 2 below 400mm, and crossbeam supports two 5 and is located main beam 2 below 1310mm, reinforcing hoist stability.
Before hoisting, the crane is connected with the hoisting tool through the steel wire rope, 4 hoisting lugs 1 are connected with 4 steel wire ropes, and at the moment, the state of the lifting hook 7 is in an open state, namely the lifting hook 7 is fixed in an upper limit hole through a positioning pin 10. Then after the lifting appliance is lifted to the upper part of the arc-shaped part, the lifting hook 7 is adjusted to be in a closed state, namely the positioning pin 10 in the upper limiting hole is pulled out, and the lifting hook 7 is fixed in the lower limiting hole. The arc-shaped piece can be lifted after the operation is completed.
The method is applied to vertical transportation and hoisting of the arc-shaped prefabricated part in the shield tunnel with the ultra-large diameter. The safety of hoisting the large arc-shaped component is improved, the problem that a hoisting worker is difficult to construct due to the overlarge size of the arc-shaped component is solved, the working efficiency is greatly improved, and manpower and material resources are saved. The hoisting device can be suitable for hoisting other large-scale components after being modified.
Claims (6)
1. The utility model provides a perpendicular transportation hoist device of inside arc prefabricated component of super large diameter shield tunnel, its characterized in that: the lifting appliance comprises a main body frame structure and a lifting structure, wherein the main body frame structure comprises main cross beams, stand columns and transverse supports, and the stand columns are fixedly connected through the main cross beams and the transverse supports to form a lifting appliance main body frame; lifting lugs are welded at the upper end of the lifting appliance main body frame; hoisting structure includes lifting hook, pivot, locating pin, spacing steel sheet passes through connecting plate and stand welding, with pivot connection between spacing steel sheet and the lifting hook, as the axis of rotation, two spacing holes are opened on the spacing steel sheet, through the different positions of locating pin control lifting hook.
2. The vertical transportation and hoisting device for the arc-shaped prefabricated parts in the shield tunnel according to claim 1, characterized in that: the total number of the lifting lugs is 4, the direction of the lifting lugs and the main beam form 45 degrees, and the lifting lugs (1) are made of steel plates with the height of 267.6mm and the thickness of 30mm.
3. The vertical transportation and hoisting device for the arc-shaped prefabricated parts in the shield tunnel according to claim 1, characterized in that: the main cross beams adopt 2.16m 4 pieces of 20# section steel, the upright posts adopt 1.86m 4 pieces of 20# section steel, and the transverse supports adopt 2.16m 4 pieces of 20# section steel.
4. The vertical transportation and hoisting device for the arc-shaped prefabricated parts in the shield tunnel according to claim 3, characterized in that: two crossbeam supports are located main beam below 400mm department, and two other crossbeam supports are located main beam below 1310mm department, reinforcing hoist stability.
5. The vertical transportation and hoisting device for the arc-shaped prefabricated parts in the shield tunnel according to claim 1, characterized in that: the web size was 240mm 30mm.
6. The vertical transportation and hoisting device for the arc-shaped prefabricated parts in the shield tunnel according to claim 1, characterized in that: the thickness of the limiting steel plate is 40mm, the thickness of the lifting hook is 55mm, and the diameters of the shaft pin and the positioning pin are 55mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210787817.2A CN115196492A (en) | 2022-07-06 | 2022-07-06 | Vertical transportation and hoisting device for arc-shaped prefabricated parts in super-large-diameter shield tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210787817.2A CN115196492A (en) | 2022-07-06 | 2022-07-06 | Vertical transportation and hoisting device for arc-shaped prefabricated parts in super-large-diameter shield tunnel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115196492A true CN115196492A (en) | 2022-10-18 |
Family
ID=83578142
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210787817.2A Pending CN115196492A (en) | 2022-07-06 | 2022-07-06 | Vertical transportation and hoisting device for arc-shaped prefabricated parts in super-large-diameter shield tunnel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115196492A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116239000A (en) * | 2022-12-24 | 2023-06-09 | 安徽华兴管业有限责任公司 | Lifting appliance for transferring steel building upright post |
-
2022
- 2022-07-06 CN CN202210787817.2A patent/CN115196492A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116239000A (en) * | 2022-12-24 | 2023-06-09 | 安徽华兴管业有限责任公司 | Lifting appliance for transferring steel building upright post |
CN116239000B (en) * | 2022-12-24 | 2023-10-20 | 安徽华兴管业有限责任公司 | Lifting appliance for transferring steel building upright post |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN115196492A (en) | Vertical transportation and hoisting device for arc-shaped prefabricated parts in super-large-diameter shield tunnel | |
CN208202586U (en) | Conduit lifting device for the perfusion of power transmission tower concrete filled steel tube high-altitude | |
CN206110133U (en) | A device for cutting underwater concrete steel -pipe pile | |
CN206590793U (en) | Connect arm assembly and the movable arm tower crane comprising the device in the air | |
CN208858357U (en) | A kind of adjustable builder's staging for heavy grade tunnel | |
CN206874293U (en) | Subway tunnel soft oil support device | |
CN206680096U (en) | One kind is used for restricted clearance hanging apparatus | |
CN203334186U (en) | A wheel type device for cable-stayed bridge floor press anchoring | |
CN212101659U (en) | Clamping device for hoisting reinforcement cage | |
CN206156638U (en) | Swing arm tower crane top ping lift prevents kinking device | |
CN214780276U (en) | Lifting machine for unloading, overturning and lifting reinforced concrete pipe | |
CN208473293U (en) | Narrow deformation joint easy-dismount template system | |
CN206188260U (en) | Hoist top ping lift prevents kinking device and hoist | |
CN206553111U (en) | One kind balance arm brace installs auxiliary body | |
CN111498672A (en) | Hoisting system and construction method for large bridge crane heavy workpiece | |
CN208037877U (en) | A kind of portable small-sized electrical equipment lifting auxiliary tool | |
CN205990200U (en) | 360 ° of luffing independent hoist device | |
CN110821264A (en) | Holding pole lifting frame and holding pole assembling method thereof | |
CN212269239U (en) | City narrow district foundation ditch jack-up hoist and mount auxiliary device | |
CN217903849U (en) | Movable power transmission power cable erecting device | |
CN216141911U (en) | Material lifting device for mountainous large-height bridge cylindrical pier slip form construction platform | |
CN215479309U (en) | A hoist and mount manhole device for side slope stock construction | |
CN202227349U (en) | Device for assembling and disassembling concrete conduit of cast-in-place pile | |
CN218598224U (en) | Portable movable underground cavern crown anchor cable lowering device | |
CN213710366U (en) | Integral steel mould structure of stand |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |