CN115186349A - Method and system for building bridge model based on BIM technology - Google Patents
Method and system for building bridge model based on BIM technology Download PDFInfo
- Publication number
- CN115186349A CN115186349A CN202210854411.1A CN202210854411A CN115186349A CN 115186349 A CN115186349 A CN 115186349A CN 202210854411 A CN202210854411 A CN 202210854411A CN 115186349 A CN115186349 A CN 115186349A
- Authority
- CN
- China
- Prior art keywords
- bim
- framework
- bridge
- construction
- model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 26
- 238000005516 engineering process Methods 0.000 title claims abstract description 19
- 238000010276 construction Methods 0.000 claims abstract description 128
- 238000004088 simulation Methods 0.000 claims abstract description 36
- 238000006243 chemical reaction Methods 0.000 claims abstract description 8
- 239000007787 solid Substances 0.000 claims abstract description 8
- 238000013461 design Methods 0.000 claims description 16
- 238000004458 analytical method Methods 0.000 claims description 10
- 229910000831 Steel Inorganic materials 0.000 claims description 8
- 239000010959 steel Substances 0.000 claims description 8
- 238000012423 maintenance Methods 0.000 claims description 7
- 238000012545 processing Methods 0.000 claims description 7
- 238000003860 storage Methods 0.000 claims description 7
- 238000009440 infrastructure construction Methods 0.000 claims description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 8
- 230000008569 process Effects 0.000 description 6
- 238000004519 manufacturing process Methods 0.000 description 5
- 230000008859 change Effects 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 3
- 238000005266 casting Methods 0.000 description 3
- 239000009096 changqing Substances 0.000 description 3
- 239000004927 clay Substances 0.000 description 3
- 239000010410 layer Substances 0.000 description 3
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 3
- 239000004576 sand Substances 0.000 description 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000003292 glue Substances 0.000 description 2
- 230000010354 integration Effects 0.000 description 2
- 239000000843 powder Substances 0.000 description 2
- 238000009417 prefabrication Methods 0.000 description 2
- 238000011144 upstream manufacturing Methods 0.000 description 2
- 238000013459 approach Methods 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2111/00—Details relating to CAD techniques
- G06F2111/20—Configuration CAD, e.g. designing by assembling or positioning modules selected from libraries of predesigned modules
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Theoretical Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Architecture (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention provides a method and a system for constructing a bridge model based on a BIM technology, wherein the method comprises the following steps: constructing a large temporary facility model; establishing a bridge structure framework by adopting Midas Civil software based on a construction drawing, deriving bridge structure framework and bridge structure parameters, carrying out format conversion, and inputting the parameters into a BIM (building information modeling) model to serve as a basic framework and framework parameters; building a trestle BIM submodel based on the bridge structure framework in the BIM model, building a cofferdam BIM submodel based on the trestle BIM submodel, carrying out solid modeling on the cofferdam structure, and measuring the size and the spatial position of a detail component in the cofferdam BIM submodel; constructing a main bridge BIM sub-model on the upper part of the bridge structure framework based on the bridge structure framework; and (5) performing construction simulation.
Description
Technical Field
The invention relates to the technical field of bridge model construction based on a BIM (building information modeling) technology, in particular to a method and a system for constructing a bridge model based on the BIM technology.
Background
The span of a main bridge of the Changqing yellow river grand bridge of Zhengji railway is (108 +4 × 216+ 108m), the Changqing yellow river grand bridge is a first long-united multi-tower large-span cable-stayed bridge with the speed per hour of 350km in China, fills the domestic blank, and is the only controllable project of the whole Zhengji railway (Shandong segment). The glued continuous beam related to the bridge approach of the Changqing yellow river super bridge is a non-wet seam glued continuous beam structure with the largest railway scale in China at present.
Engineering features and difficulties include:
the main bridge is a multi-tower cable-stayed bridge of a kilometric long-link ballastless track of a first 350km/h high-speed railway in the world and is also the only controllable project in the whole Zhengjie high-speed railway work period.
The main bridge construction technology difficulty is as follows:
(1) Pile foundation grow up: the main bridge pile foundations are all large-diameter deep-hole drilled piles (the pile diameter is 2m, the maximum hole depth is 142 m), particularly the 249 pier riverbed surface layer is deposited silt, and the plasticity is poor; the cementing layer, the sand layer and the silty clay layer are alternately arranged within the range of 30m of the pile tip, the geological complex pore-forming is difficult, the concrete pouring volume is large, the settlement observation period is long, and the like.
(2) A bearing platform: the foundation pits of the main bridge bearing platform are all deep foundation pits with the depth of more than 11 meters, the underground water level is high, the geological condition is poor, particularly, the No. 249 water pier is located in the main river channel of the yellow river, the excavation depth is 16m, the water flow change is influenced by upstream water and sand adjustment and flood season, the short-time water level and flow rate change is obvious, and the river bed is scoured greatly. The 5m range of the bottom of the cofferdam is hard plastic, dry strength is medium powder clay, and foundation pit excavation construction organization difficulty is large.
(3) Main beam of the short-tower cable-stayed bridge: the main beam is a multi-tower long-span kilometer long-connected concrete short-tower cable-stayed bridge, the self weight of the bridge is large, and the vertical residual creep deformation of the beam is controlled within 20 mm. By adopting a cantilever casting method, the maximum cantilever casting section is 8m, the weight of a single section is 690t, the cantilever casting linearity control standard is high, the system conversion is complex, the construction period is short, and the safety risk is high.
The 3 x 56m section prefabricated assembled continuous beam is a 350km/h high-speed rail span-by-span full-rubber assembled continuous beam bridge which is firstly constructed in a large scale in the world, and a CRTSIII type slab ballastless track is adopted; a new technology of full-glue splicing and a new structure of a shear key are explored for a new technology of high-speed rail construction. The construction difficulty of the bridge is as follows:
(1) In the bridge 22, 19 links are connected on a circular curve, 2 links are connected on a gentle curve, 1 link is connected on a gentle straight line, and the difficulty in controlling the prefabrication of the beam type is high.
(2) The full-connection glue splicing has no wet joint, and has high requirements on the prefabrication precision of the beam and the linear control of splicing.
(3) The experience and the specification of the reference which can be borrowed at present are few.
Disclosure of Invention
In view of the above, the main objective of the present invention is to provide a method and a system for constructing a bridge model based on the BIM technology.
The technical scheme adopted by the invention is as follows:
the method for constructing the bridge model based on the BIM technology comprises the following steps:
step 1): establishing a temporary facility model by adopting Revit software, and setting the spatial structure relationship and the time flow relationship of each functional area in the temporary facility model to construct the continuous construction auxiliary design of the bridge;
step 2): building a bridge structure framework by using Midas Civil software based on a construction drawing, and performing stress analysis in the Midas Civil software based on the bridge structure framework to verify the structure framework; exporting a bridge structure framework and bridge structure parameters, carrying out format conversion, and inputting the converted parameters into a BIM (building information modeling) model to serve as a basic framework and framework parameters;
step 3): building a trestle BIM submodel based on the bridge structure framework in the BIM model, building a cofferdam BIM submodel based on the trestle BIM submodel, carrying out solid modeling on the cofferdam structure, and measuring the size and the spatial position of a detail component in the cofferdam BIM submodel; constructing a main bridge BIM sub-model on the upper part of the bridge structure framework based on the bridge structure framework;
step 4): compiling foundation framework construction files based on foundation frameworks and framework parameters, compiling trestle construction files based on a trestle BIM submodel, compiling cofferdam construction files based on a cofferdam BIM submodel and compiling main bridge construction files based on a main bridge BIM submodel; and respectively inputting the bridge structure framework and a foundation framework construction file corresponding to the bridge structure framework, a trestle BIM sub-model and a trestle construction file corresponding to the trestle BIM sub-model, a cofferdam BIM sub-model and a cofferdam construction file corresponding to the cofferdam BIM sub-model, a main bridge BIM sub-model and a main bridge BIM sub-model main bridge construction file into a simulation model for simulation, and performing construction simulation according to the simulation model based on the foundation parts constructed by the large temporary facility model.
In the step 1), modeling simulation construction is carried out on a steel bar processing area, a binding area, a beam manufacturing area, a maintenance area, a beam storage area and a beam lifting area of a beam yard in a large temporary facility model according to the construction requirements of continuous beams, and the spatial structure relation and the time flow relation of the processing area, the binding area, the beam manufacturing area, the maintenance area, the beam storage area and the beam lifting area are determined.
In the step 4), the foundation framework construction file, the trestle construction file, the cofferdam construction file and the main bridge construction file correspond to the time flow relation in the step 1).
The invention also provides a system for constructing a bridge model based on the BIM technology, which comprises the following steps:
setting a temporary facility model for establishing the temporary facility model by Revit software, and setting the spatial structure relationship and the time flow relationship of each functional area in the temporary facility model to construct a bridge continuous construction auxiliary design;
the basic framework construction module is used for establishing a bridge structure framework on a construction drawing by adopting Midas Civil software, and carrying out stress analysis in the Midas Civil software based on the bridge structure framework so as to verify the structure framework; exporting a bridge structure framework and bridge structure parameters, carrying out format conversion, and inputting the converted parameters into a BIM (building information modeling) model as a basic framework and framework parameters;
the bridge BIM submodel is established in the BIM model on the basis of the bridge structure framework;
the cofferdam BIM sub-model is constructed based on the trestle BIM sub-model; carrying out solid modeling on the cofferdam structure, and measuring the size and the spatial position of a detail component in a cofferdam BIM submodel;
the main bridge BIM submodel is constructed on the upper part of the bridge structure framework based on the bridge structure framework;
the simulation module is used for compiling a foundation framework construction file based on a foundation framework and framework parameters, a trestle bridge construction file based on a trestle BIM submodel, a cofferdam construction file based on a cofferdam BIM submodel and a main bridge construction file based on a main bridge BIM submodel; and respectively inputting the bridge structure framework and a foundation framework construction file corresponding to the bridge structure framework, a trestle BIM sub-model and a trestle construction file corresponding to the trestle BIM sub-model, a cofferdam BIM sub-model and a cofferdam construction file corresponding to the cofferdam BIM sub-model, a main bridge BIM sub-model and a main bridge BIM sub-model main bridge construction file into a simulation model for simulation, and performing construction simulation according to the simulation model based on the foundation parts constructed by the large temporary facility model.
Further, the basic skeleton building module comprises:
the Midas Civil software is used for establishing a structural framework in the Midas Civil software based on a construction drawing, and performing stress analysis in the Midas Civil software based on the structural framework to verify the structural framework;
the deriving unit is used for deriving the structural skeleton and skeleton parameters corresponding to the structural skeleton from the Midas Civil software;
and the importing unit is used for converting the format of the structural framework and the framework parameters corresponding to the structural framework to form a basic framework and framework parameters accepted by the BIM, and importing the basic framework and the framework parameters into the BIM.
In the application, the design and construction integration application based on the BIM is adopted, the BIM design standard and the construction application standard are determined, and the refined BIM model of the whole structure is established. A BIM model of a design end is carried from a construction end, BIM modeling is adopted for auxiliary design, modeling simulation construction is carried out on six functional areas such as a reinforcing steel bar processing area, a binding area, a beam manufacturing area (a long and short line method is combined with a pedestal), a maintenance area, a beam storage area (128 sections), a beam lifting area and the like of a beam yard according to the construction requirements of continuous beams, and the spatial structure relation and the time flow relation of each functional area are visually analyzed.
Drawings
The invention is illustrated and described only by way of example and not by way of limitation in the scope of the invention as set forth in the following drawings, in which:
FIG. 1 is a diagram of the method of the present invention;
fig. 2 is a schematic diagram of the system framework of the present invention.
Detailed Description
In order to make the objects, technical solutions, design methods, and advantages of the present invention more apparent, the present invention will be further described in detail by specific embodiments with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Referring to fig. 1 to 2, the present invention provides a system for constructing a bridge model based on BIM technology, including:
setting a temporary facility model for establishing the temporary facility model by adopting Revit software, and setting the spatial structure relationship and the time flow relationship of each functional area in the temporary facility model to construct the continuous construction auxiliary design of the bridge;
the infrastructure construction module is used for establishing a bridge structure framework in a construction drawing by adopting Midas Civil software, and carrying out stress analysis in the Midas Civil software based on the bridge structure framework so as to verify the structure framework; exporting a bridge structure framework and bridge structure parameters, carrying out format conversion, and inputting the converted parameters into a BIM (building information modeling) model to serve as a basic framework and framework parameters;
the bridge BIM submodel is established in the BIM model on the basis of the bridge structure framework;
the cofferdam BIM submodel is constructed based on the trestle BIM submodel; carrying out solid modeling on the cofferdam structure, and measuring the size and the spatial position of a detail component in a cofferdam BIM submodel;
the main bridge BIM submodel is constructed on the upper part of the bridge structure framework based on the bridge structure framework;
the simulation module is used for compiling foundation framework construction files based on a foundation framework and framework parameters, compiling trestle construction files based on a trestle BIM submodel, compiling cofferdam construction files based on a cofferdam BIM submodel and compiling main bridge construction files based on a main bridge BIM submodel; and respectively inputting the bridge structure framework and a foundation framework construction file corresponding to the bridge structure framework, a trestle BIM sub-model and a trestle construction file corresponding to the trestle BIM sub-model, a cofferdam BIM sub-model and a cofferdam construction file corresponding to the cofferdam BIM sub-model, a main bridge BIM sub-model and a main bridge BIM sub-model main bridge construction file into a simulation model for simulation, and performing construction simulation according to the simulation model based on the foundation parts constructed by the large temporary facility model.
Further, the basic skeleton building module comprises:
the Midas Civil software is used for establishing a structural framework in the Midas Civil software based on a construction drawing, and performing stress analysis in the Midas Civil software based on the structural framework to verify the structural framework;
the deriving unit is used for deriving the structural skeleton and skeleton parameters corresponding to the structural skeleton from the Midas Civil software;
and the importing unit is used for converting the format of the structural framework and the framework parameters corresponding to the structural framework to form a basic framework and framework parameters accepted by the BIM model and importing the basic framework and the framework parameters into the BIM model.
In the application, the design and construction integration application based on the BIM is adopted, the BIM design standard and the construction application standard are determined, and the refined BIM model of the whole structure is established. A BIM model of a design end is carried from a construction end, BIM modeling is adopted for auxiliary design, modeling simulation construction is carried out on six functional areas such as a reinforcing steel bar processing area, a binding area, a beam manufacturing area (a long and short line method is combined with a pedestal), a maintenance area, a beam storage area (128 sections), a beam lifting area and the like of a beam yard according to the construction requirements of continuous beams, and the spatial structure relation and the time flow relation of each functional area are visually analyzed.
The invention also provides a method for constructing a bridge model based on the BIM technology, which comprises the following steps:
step 1): establishing a temporary facility model by adopting Revit software, and setting the spatial structure relationship and the time flow relationship of each functional area in the temporary facility model to construct the continuous construction auxiliary design of the bridge; the method comprises the following steps of carrying out auxiliary design by adopting BIM modeling, carrying out modeling simulation construction on six functional areas such as a steel bar processing area, a binding area, a beam manufacturing area (a long and short line method is combined with a pedestal), a maintenance area, a beam storage area (128 sections), a beam lifting area and the like of a beam yard according to the construction requirements of continuous beams, and visually analyzing the spatial structure relationship and the time flow relationship of each functional area;
step 2): building a bridge structure framework by using Midas Civil software based on a construction drawing, and performing stress analysis in the Midas Civil software based on the bridge structure framework to verify the structure framework; exporting a bridge structure framework and bridge structure parameters, carrying out format conversion, and inputting the converted parameters into a BIM (building information modeling) model as a basic framework and framework parameters;
step 3): building a trestle BIM submodel based on the bridge structure skeleton in a BIM model, building a cofferdam BIM submodel based on the trestle BIM submodel, performing solid modeling on a cofferdam structure, and measuring the size and the spatial position of a detail component in the cofferdam BIM submodel; constructing a main bridge BIM sub-model on the upper part of the bridge structure framework based on the bridge structure framework;
the engineering main bridge spans two banks of the yellow river, wherein the pier 248# is positioned on the south bank of the yellow river, the pier 249# is positioned in the river channel of the yellow river, and the piers 250#, 251#, and 252# are positioned on the north bank of the yellow river. In order to ensure the traffic of construction vehicles, a trestle passage crossing the yellow river needs to be built for auxiliary construction. And (4) building a BIM (building information modeling) model of the trestle by adopting Dasuo software, and carrying out engineering calculation and construction guidance. And (4) compiling a safe construction scheme of the trestle by comprehensive analysis and guiding field construction.
The main bridge 249# underwater pier is located in the main river channel of the yellow river, the excavation depth is 16m, the water flow change is influenced by upstream water and sand adjustment and flood season, the short-time water level and flow rate change is obvious, and the river bed is scoured greatly. The 5m range of the bottom of the cofferdam is hard plastic, medium powder clay in dry strength. The pier lower structure is difficult to construct and tight in construction period, and is a control node of the whole pipe section. And (4) establishing a BIM sub-model of the steel cofferdam by adopting Dasuo software, and comparing and selecting the scheme. And analyzing the advantages and disadvantages of the double-wall steel cofferdam and the lock catch steel pipe pile cofferdam from the aspects of safety, technology and economy, and finally selecting the lock catch steel pipe pile cofferdam for construction. The cofferdam is successfully bottomed, so that the cost is saved, and the construction period is shortened. Plays a key role in engineering construction. And (4) adopting a steel cofferdam BIM submodel to guide construction. The cofferdam structure is subjected to solid modeling, the size and the spatial position of detail components can be visually measured in the cofferdam BIM submodel, and the site construction can be conveniently and rapidly guided.
And step 4): compiling a foundation framework construction file based on a foundation framework and framework parameters, a trestle bridge construction file based on a trestle BIM submodel, a cofferdam construction file based on a cofferdam BIM submodel and a main bridge construction file based on a main bridge BIM submodel; and respectively inputting the bridge structure framework and foundation framework construction files corresponding to the bridge structure framework, trestle BIM submodels and trestle construction files corresponding to the trestle BIM submodels, cofferdam BIM submodels and cofferdam construction files corresponding to the cofferdam BIM submodels, main bridge BIM submodels and main bridge BIM submodels into a simulation model for simulation, and performing construction simulation according to the simulation model based on foundation parts constructed by a large temporary facility model.
A geometrical model and a construction process model of the main bridge are established through a BIM technology, so that real-time, interactive and vivid simulation is carried out on a construction scheme, and the construction scheme is verified, optimized and perfected. In the three-dimensional simulation operation of the construction process, the problems possibly encountered in the actual construction process are predicted, the phenomena of rework and resource waste are avoided and reduced in advance, the construction scheme is optimized, construction resources are reasonably configured, the construction cost is saved, the construction progress is accelerated, the construction quality is controlled, and the purpose of improving the construction efficiency is achieved.
In the method, the whole bridge splicing continuous beam construction process guidance animation is manufactured through simulation, the 4D bottom crossing of the whole bridge is realized, the construction process of section beam erection is simulated, the construction process is transparent, the progress is visual, the scene is vivid, and the key steps and the specific control key points of section beam erection are integrated.
In the step 4), the foundation framework construction file, the trestle construction file, the cofferdam construction file and the main bridge construction file correspond to the time flow relation in the step 1).
Having described embodiments of the present invention, the foregoing description is intended to be exemplary, not exhaustive, and not limited to the embodiments disclosed. Many modifications and variations will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments. The terminology used herein was chosen in order to best explain the principles of the embodiments, the practical application, or technical improvements to the market, or to enable others of ordinary skill in the art to understand the embodiments disclosed herein.
Claims (5)
1. The method for constructing the bridge model based on the BIM technology is characterized by comprising the following steps:
step 1): establishing a temporary facility model by adopting Revit software, and setting the spatial structure relationship and the time flow relationship of each functional area in the temporary facility model to construct the continuous construction auxiliary design of the bridge;
step 2): building a bridge structure framework by using Midas Civil software based on a construction drawing, and performing stress analysis in the Midas Civil software based on the bridge structure framework to verify the structure framework; exporting a bridge structure framework and bridge structure parameters, carrying out format conversion, and inputting the converted parameters into a BIM (building information modeling) model as a basic framework and framework parameters;
step 3): building a trestle BIM submodel based on the bridge structure skeleton in a BIM model, building a cofferdam BIM submodel based on the trestle BIM submodel, performing solid modeling on a cofferdam structure, and measuring the size and the spatial position of a detail component in the cofferdam BIM submodel; constructing a main bridge BIM sub-model on the upper part of the bridge structure framework based on the bridge structure framework;
step 4): compiling a foundation framework construction file based on a foundation framework and framework parameters, a trestle bridge construction file based on a trestle BIM submodel, a cofferdam construction file based on a cofferdam BIM submodel and a main bridge construction file based on a main bridge BIM submodel; and respectively inputting the bridge structure framework and foundation framework construction files corresponding to the bridge structure framework, trestle BIM submodels and trestle construction files corresponding to the trestle BIM submodels, cofferdam BIM submodels and cofferdam construction files corresponding to the cofferdam BIM submodels, main bridge BIM submodels and main bridge BIM submodels into a simulation model for simulation, and performing construction simulation according to the simulation model based on foundation parts constructed by a large temporary facility model.
2. The method for constructing the bridge model based on the BIM technology as claimed in claim 1, wherein in step 1), modeling simulation construction is performed on the steel bar processing area, the binding area, the beam making area, the maintenance area, the beam storage area and the beam lifting area of the beam yard in the temporary facility model according to the continuous beam construction requirements, and the spatial structure relationship and the time flow relationship of the processing area, the binding area, the beam making area, the maintenance area, the beam storage area and the beam lifting area are determined.
3. The method for constructing a bridge model based on the BIM technology as claimed in claim 1, wherein in step 4), the infrastructure construction file, the trestle construction file, the cofferdam construction file and the main bridge construction file are corresponded to the time flow relationship in step 1).
4. System based on BIM technique founds bridge model, its characterized in that includes:
setting a temporary facility model for establishing the temporary facility model by adopting Revit software, and setting the spatial structure relationship and the time flow relationship of each functional area in the temporary facility model to construct the continuous construction auxiliary design of the bridge;
the basic framework construction module is used for establishing a bridge structure framework on a construction drawing by adopting Midas Civil software, and carrying out stress analysis in the Midas Civil software based on the bridge structure framework so as to verify the structure framework; exporting a bridge structure framework and bridge structure parameters, carrying out format conversion, and inputting the converted parameters into a BIM (building information modeling) model as a basic framework and framework parameters;
the bridge BIM submodel is established in the BIM model on the basis of the bridge structure framework;
the cofferdam BIM sub-model is constructed based on the trestle BIM sub-model; carrying out solid modeling on the cofferdam structure, and measuring the size and the spatial position of a detail component in a cofferdam BIM submodel;
the main bridge BIM submodel is constructed on the upper part of the bridge structure framework based on the bridge structure framework;
the simulation module is used for compiling foundation framework construction files based on a foundation framework and framework parameters, compiling trestle construction files based on a trestle BIM submodel, compiling cofferdam construction files based on a cofferdam BIM submodel and compiling main bridge construction files based on a main bridge BIM submodel; and respectively inputting the bridge structure framework and foundation framework construction files corresponding to the bridge structure framework, trestle BIM submodels and trestle construction files corresponding to the trestle BIM submodels, cofferdam BIM submodels and cofferdam construction files corresponding to the cofferdam BIM submodels, main bridge BIM submodels and main bridge BIM submodels into a simulation model for simulation, and performing construction simulation according to the simulation model based on foundation parts constructed by a large temporary facility model.
5. The BIM technology-based bridge model building system of claim 4, wherein the basic skeleton building module comprises:
the Midas Civil software is used for establishing a structural framework in the Midas Civil software based on a construction drawing, and performing stress analysis in the Midas Civil software based on the structural framework to verify the structural framework;
the deriving unit is used for deriving the structural skeleton and skeleton parameters corresponding to the structural skeleton from the Midas Civil software;
and the importing unit is used for converting the format of the structural framework and the framework parameters corresponding to the structural framework to form a basic framework and framework parameters accepted by the BIM model and importing the basic framework and the framework parameters into the BIM model.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210854411.1A CN115186349B (en) | 2022-07-20 | 2022-07-20 | Method and system for constructing bridge model based on BIM technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210854411.1A CN115186349B (en) | 2022-07-20 | 2022-07-20 | Method and system for constructing bridge model based on BIM technology |
Publications (2)
Publication Number | Publication Date |
---|---|
CN115186349A true CN115186349A (en) | 2022-10-14 |
CN115186349B CN115186349B (en) | 2024-03-15 |
Family
ID=83518867
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210854411.1A Active CN115186349B (en) | 2022-07-20 | 2022-07-20 | Method and system for constructing bridge model based on BIM technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115186349B (en) |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150248504A1 (en) * | 2014-03-01 | 2015-09-03 | Benjamin F. GLUNZ | Method and system for creating composite 3d models for building information modeling (bim) |
CN106934163A (en) * | 2017-03-17 | 2017-07-07 | 河南省交通规划设计研究院股份有限公司 | Bridge 3 D model construction method based on BIM |
CN108304631A (en) * | 2018-01-22 | 2018-07-20 | 北京市公路桥梁建设集团锐诚工程试验检测有限公司 | A kind of BIM parameterization design methods of bridge superstructure |
CN109753753A (en) * | 2019-01-21 | 2019-05-14 | 广东星层建筑科技股份有限公司 | A kind of bridge mould base intelligent design method based on BIM |
CN109783851A (en) * | 2018-12-10 | 2019-05-21 | 中国铁路设计集团有限公司 | Railway bowstring arch bridge Construction simulation system and method based on 3DGIS and BIM technology |
CN110414136A (en) * | 2019-07-29 | 2019-11-05 | 中国建筑第七工程局有限公司 | A kind of bridge fast modeling method based on BIM |
CN110804955A (en) * | 2019-11-27 | 2020-02-18 | 江西省公路桥梁工程有限公司 | Bridge construction method based on BIM |
CN111967081A (en) * | 2020-08-20 | 2020-11-20 | 广西路桥工程集团有限公司 | Bridge construction management system based on BIM |
CN111985040A (en) * | 2020-09-01 | 2020-11-24 | 中国铁路设计集团有限公司 | Bridge design and construction integrated application method based on BIM and GIS technology |
KR20210071151A (en) * | 2019-12-05 | 2021-06-16 | 한국철도기술연구원 | Automated bim construction system and method of railway bridge |
CN114329740A (en) * | 2022-01-14 | 2022-04-12 | 林同棪国际工程咨询(中国)有限公司 | BIM-based three-dimensional forward design method for large-span through-put type beam-arch combined rigid frame bridge |
CN114662189A (en) * | 2022-03-11 | 2022-06-24 | 深圳宏业基岩土科技股份有限公司 | Construction method of steel-concrete structure foundation pit trestle based on BIM |
-
2022
- 2022-07-20 CN CN202210854411.1A patent/CN115186349B/en active Active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150248504A1 (en) * | 2014-03-01 | 2015-09-03 | Benjamin F. GLUNZ | Method and system for creating composite 3d models for building information modeling (bim) |
CN106934163A (en) * | 2017-03-17 | 2017-07-07 | 河南省交通规划设计研究院股份有限公司 | Bridge 3 D model construction method based on BIM |
CN108304631A (en) * | 2018-01-22 | 2018-07-20 | 北京市公路桥梁建设集团锐诚工程试验检测有限公司 | A kind of BIM parameterization design methods of bridge superstructure |
CN109783851A (en) * | 2018-12-10 | 2019-05-21 | 中国铁路设计集团有限公司 | Railway bowstring arch bridge Construction simulation system and method based on 3DGIS and BIM technology |
CN109753753A (en) * | 2019-01-21 | 2019-05-14 | 广东星层建筑科技股份有限公司 | A kind of bridge mould base intelligent design method based on BIM |
CN110414136A (en) * | 2019-07-29 | 2019-11-05 | 中国建筑第七工程局有限公司 | A kind of bridge fast modeling method based on BIM |
CN110804955A (en) * | 2019-11-27 | 2020-02-18 | 江西省公路桥梁工程有限公司 | Bridge construction method based on BIM |
KR20210071151A (en) * | 2019-12-05 | 2021-06-16 | 한국철도기술연구원 | Automated bim construction system and method of railway bridge |
CN111967081A (en) * | 2020-08-20 | 2020-11-20 | 广西路桥工程集团有限公司 | Bridge construction management system based on BIM |
CN111985040A (en) * | 2020-09-01 | 2020-11-24 | 中国铁路设计集团有限公司 | Bridge design and construction integrated application method based on BIM and GIS technology |
CN114329740A (en) * | 2022-01-14 | 2022-04-12 | 林同棪国际工程咨询(中国)有限公司 | BIM-based three-dimensional forward design method for large-span through-put type beam-arch combined rigid frame bridge |
CN114662189A (en) * | 2022-03-11 | 2022-06-24 | 深圳宏业基岩土科技股份有限公司 | Construction method of steel-concrete structure foundation pit trestle based on BIM |
Non-Patent Citations (6)
Title |
---|
何祥平, 王浩, 郜辉等: "高铁连续梁桥BIM参数化建模及其工程应用", 哈尔滨工程大学学报, vol. 43, no. 03, 31 March 2022 (2022-03-31), pages 311 - 317 * |
刘孟, 王金鹏, 孙宸等: "BIM技术在基础设施项目管理中的应用研究", 工程管理学报, vol. 30, no. 06, 31 December 2016 (2016-12-31), pages 78 - 82 * |
刘孟;张文全;黄国鑫;张毅凯;: "BIM技术在黄河特大桥项目施工管理中的应用", 施工技术, no. 2, 31 December 2016 (2016-12-31), pages 596 - 599 * |
向聃: "BIM技术在道路桥梁施工管理中的应用研究", 湖南交通科技, vol. 43, no. 03, 30 September 2017 (2017-09-30), pages 165 - 170 * |
王碧军;王明慧;陈艳芳;杜康;张桥;: "BIM技术在桥梁钢围堰施工中的应用", 国防交通工程与技术, no. 04, 16 July 2020 (2020-07-16), pages 78 - 80 * |
薛洲: "BIM技术在铁路桥梁建设中的应用", 运输经理世界, no. 2021, 31 December 2021 (2021-12-31), pages 115 - 117 * |
Also Published As
Publication number | Publication date |
---|---|
CN115186349B (en) | 2024-03-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107761765B (en) | Fully assembled subway station double-column main body structure and construction method thereof | |
CN110566223B (en) | Deep-buried PBA subway station section design method | |
CN101280549A (en) | Construction method of mobile type bracket subsection cast-in-situ continuous beam | |
CN110700248A (en) | Miniature steel pipe pile for grouting small and medium-sized span bridge, pile foundation and construction method | |
CN111794774A (en) | Rapid entering protection structure of half cut single-pressure open cut tunnel and construction method | |
CN113622316A (en) | Steel truss girder multipoint traction type pushing construction system and construction method thereof | |
CN109577212A (en) | A kind of pretensioned prestressing Precasting Pedestal Construction method | |
CN102493472B (en) | Deepwater soft soil foundation reverse construction method low pile cap composite foundation construction process for bridge | |
CN112813983B (en) | Cantilever beam-column system implemented synchronously with pit depth in pit and construction method | |
CN115186349B (en) | Method and system for constructing bridge model based on BIM technology | |
CN207597914U (en) | Add the construction stress structure for building multi-layer underground space under a kind of existing building group | |
CN114197477B (en) | Construction method for zero-distance crossing of high-speed rail viaduct under construction deep foundation pit | |
Haugerud et al. | The lake lugano crossing-technical solutions | |
CN115928798B (en) | Method for passing through existing underground structure of rail transit through ultra-small clear distance long-distance oblique crossing | |
CN116451310B (en) | Method for ultra-small clear distance long-distance oblique crossing of existing U-shaped groove structure of rail transit | |
CN113699895B (en) | Construction method for overhead jacking of frame-structured bridge into existing line of multiple tracks | |
CN111851507B (en) | Construction method of pile-arch conversion structure system | |
Hui | Recent development and challenges of long-span railway cable-stayed bridges in China | |
Heggade | An engineering marvel in the capital of India | |
Yang et al. | Analysis on Deformation Control Technology for Large-Span Subway Tunnels from High-Narrow Channel | |
Liu et al. | Design and construction control of single tower cable-stayed bridge without backstays | |
Wang | Development of Plane Rotating Traction System: Based on the High-speed Rail (72+ 128+ 72) m Continuous Prestressed Concrete Beam Bridge | |
Rojas et al. | Structural design and construction of the Carouge-Bachet underground railway station in Switzerland | |
Han et al. | Research on Swivel Construction Technology of 22,400 Tons in Zoucheng Thirty Meter Bridge | |
Hernando et al. | The design of the Alto Tâmega dam in Portugal. A 106 m high double curvature arch dam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |