CN115110511A - Automatic monitoring devices is subsided on breakwater shore protection foundation top layer and layering - Google Patents

Automatic monitoring devices is subsided on breakwater shore protection foundation top layer and layering Download PDF

Info

Publication number
CN115110511A
CN115110511A CN202210719759.XA CN202210719759A CN115110511A CN 115110511 A CN115110511 A CN 115110511A CN 202210719759 A CN202210719759 A CN 202210719759A CN 115110511 A CN115110511 A CN 115110511A
Authority
CN
China
Prior art keywords
settlement
layered
magnetic
pipe
sedimentation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210719759.XA
Other languages
Chinese (zh)
Inventor
张红亮
羊小云
范传敬
李继广
杨鸿钧
徐文强
李学艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbour Consultants Co Ltd
Original Assignee
CCCC First Harbour Consultants Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbour Consultants Co Ltd filed Critical CCCC First Harbour Consultants Co Ltd
Priority to CN202210719759.XA priority Critical patent/CN115110511A/en
Publication of CN115110511A publication Critical patent/CN115110511A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • E02D1/02Investigation of foundation soil in situ before construction work
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • E02D1/08Investigation of foundation soil in situ after finishing the foundation structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C5/00Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Chemical & Material Sciences (AREA)
  • Soil Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Testing Or Calibration Of Command Recording Devices (AREA)
  • Geophysics And Detection Of Objects (AREA)

Abstract

The invention provides an automatic monitoring device for the surface layer and the layered settlement of a breakwater revetment foundation, which comprises a settlement plate, a drill hole below a water bottom mud surface, a sensor fixing piece, a plurality of settlement magnetic rings and an automatic data acquisition and transmission mechanism, wherein the sensor fixing piece is arranged on the bottom mud surface; the depth of the drill hole is larger than the influence depth of foundation deformation caused by load on a mud surface, the sedimentation magnetic rings are fixed on the inner wall of the drill hole at intervals from top to bottom, one of the sedimentation magnetic rings is positioned below the influence depth of the foundation deformation in the drill hole, and the sedimentation magnetic ring is used as a reference magnetic ring; the settling plate covers the orifice of the drilled hole; the upper end of the sensor fixing piece is connected with the settlement plate, the lower end of the sensor fixing piece extends into the bottom of the drilled hole, a plurality of magnetic displacement sensors are arranged on the sensor fixing piece at intervals and correspond to the settlement magnetic rings one to one, and the magnetic displacement sensors are electrically connected with the automatic data acquisition and transmission mechanism. The invention has the advantages of being suitable for settlement monitoring of soil bodies below the water surface on the offshore breakwater revetment, reasonable in structural design and high in monitoring precision.

Description

Automatic monitoring devices is subsided on breakwater shore protection foundation top layer and layering
Technical Field
The invention relates to the technical field of layered settlement monitoring of a foundation soil surface layer and a deep part in geotechnical engineering, in particular to an automatic monitoring device for the layered settlement of the foundation surface layer and the deep part of a breakwater revetment.
Background
The method is very important for monitoring the foundation soil body settlement and the layered settlement of the deep soil body in the geotechnical engineering construction process and the operation period, and is also very common in application. In the offshore breakwater revetment construction process, the loading rate is controlled by monitoring the foundation settlement rate, the construction process safety is guaranteed, meanwhile, data support is provided for construction measurement, the soil layer consolidation condition is researched according to the settlement condition, the post-construction settlement is judged, the accuracy of theoretical calculation is verified, and the engineering design reserved height is guided.
The foundation soil body layered settlement monitoring is usually carried out by adopting an electromagnetic layered settlement instrument, the electromagnetic layered settlement instrument is designed according to the electromagnetic induction principle, the depth of a pre-buried settlement magnetic ring is measured by adopting a measuring ruler, the height of an orifice is measured every time, the height of the orifice is converted into the height change of the magnetic ring according to the depth of the magnetic ring, and the settlement amount of each soil layer is calculated. The layered settlement meter in the prior art is mostly used for detecting land soil layer settlement, and the method is manual monitoring, is influenced by personnel, weather and surrounding environment, and cannot ensure the measurement precision and the monitoring frequency.
At present, the automatic monitoring method for the layered settlement on land mainly comprises the following steps:
(1) displacement meter method: the multi-point displacement meters are buried in the monitoring positions in a drilling mode, the anchoring probes are buried in the layering positions in a burying mode, and when the soil layers are settled, the displacement meters are transmitted to the ground surface through the transmission rods to measure the settlement amount of the soil layers. The method is limited by the size of the drill hole, and when too many point positions are monitored simultaneously, the drill holes are required to be added and buried respectively; in addition, the position of the surface sensor needs to be measured by elevation.
(2) The improvement of the traditional electromagnetic type layered settlement meter is that a motor and a control program are additionally arranged on the electromagnetic type layered settlement meter, a measuring cable is regularly wound and unwound in a settlement pipe, and the depth of a magnetic ring is recorded. The method does not consider errors caused by sedimentation and bending deformation of the sedimentation pipe, needs to measure the elevation of the pipe orifice of the sedimentation pipe, is easy to clamp a cable, has high requirements on the surrounding environment, and is not suitable for the underwater environment.
(3) Before the present patent, a patent "layered settlement monitoring device for soil in deep water area" (publication number: CN 204418149U) discloses a layered settlement monitoring device for soil in deep water area, which is based on the principle that a reference pile is driven under the body, a plurality of magnetic displacement sensors are fixed in the reference pile, a magnetic ring is arranged on each measuring rod of the displacement sensors, and the settlement amount is monitored through the change of the magnetic ring. The method has the advantages that the reference pile is required to be stable, the settlement of the surface layer of the foundation cannot be monitored, a thick layer of stones or accumulated sand bags are thrown above the mud surface of the foundation of the breakwater revetment, and when loads are applied to the pile top of the reference pile, the reference pile is bound to be settled, so that the monitoring data are inaccurate.
In addition to the above problems, the breakwater revetment project has a difficulty completely different from land monitoring, for example, the breakwater revetment monitoring foundation is located underwater, and meanwhile, stone blocks or sand bags are required to be loaded above the foundation, so that the elevation of the settling pipe cannot be directly measured every time, and meanwhile, monitoring equipment is easily damaged in the upper load applying process. In addition, in the traditional breakwater bank protection monitoring, the surface layer settlement and the layered settlement are carried out separately, so that the burying workload is large, the instrument protection difficulty is large, and the like, and therefore the invention provides the automatic monitoring device for the surface layer and the layered settlement of the foundation, which is suitable for the characteristics of the breakwater bank protection, and has important significance.
Disclosure of Invention
The invention of the technical scheme is that the reference magnetic ring is arranged at the position which is not influenced by the soil layer settlement at the deep position of the soil layer, so that the advantages that the position of the reference magnetic ring is not influenced by the soil layer settlement and the measured data is more accurate are achieved, but the layered settling tube is used as the reference in the detection structure applied to the land surface in the prior art, the height of the layered settling tube is not changed according to the fact that the height of the position is changed along with the soil layer settlement, and therefore the height of the layered settling tube needs to be measured and corrected manually at regular intervals, or obvious errors are caused by the assumption that the layered settling tube is motionless; secondly, because the technical scheme of the invention is mainly applied to the water bottom, the reference height on the layered settling pipe can not be conveniently corrected like a detection structure applied to the land surface, and the technical scheme omits the step of correction.
In order to solve the technical problems, the invention adopts the technical scheme that: an automatic monitoring device for the surface layer and the layered settlement of a breakwater revetment foundation comprises a settlement plate, a drill hole below a water bottom mud surface, a sensor fixing piece, a plurality of settlement magnetic rings and an automatic data acquisition and transmission mechanism;
the depth of the drill hole is greater than the influence depth of foundation deformation caused by load on a mud surface, the sedimentation magnetic rings are fixed on the inner wall of the drill hole at intervals from top to bottom, one of the sedimentation magnetic rings is positioned below the influence depth of the foundation deformation in the drill hole, and the sedimentation magnetic ring is used as a reference magnetic ring;
the settling plate covers the orifice of the drilled hole;
the upper end of the sensor fixing piece is connected with the settlement plate, the lower end of the sensor fixing piece extends into the bottom of the drilled hole, a plurality of magnetic displacement sensors are arranged on the sensor fixing piece at intervals and correspond to the settlement magnetic rings one to one, and the magnetic displacement sensors are electrically connected with the automatic data acquisition and transmission mechanism.
In the structure, the layered settlement monitoring position is determined according to the design requirement and the geological survey data, then the deformation influence depth of the foundation is determined by theoretical calculation according to the geological survey data and the load at the mud surface, wherein the reference magnetic ring is arranged below the deformation influence depth of the foundation, the position of the reference magnetic ring can be kept relatively unchanged and is not influenced by the sedimentation of the soil layer, the installation height of the rest settlement magnetic rings is confirmed according to the position to be measured, then the installation height of each magnetic displacement sensor is reasonably selected according to the design requirement, the magnetic displacement sensor at the corresponding position of each settlement magnetic ring is ensured to have enough measuring range, when in measurement, the subsidence of the measuring reference magnetic ring is L1, namely the subsidence of the surface layer of the foundation, the subsidence of the layered subsidence magnetic ring measured by the magnetic displacement sensor corresponding to a certain layered subsidence monitoring point is L2, and the difference value (L1-L2) is the subsidence of the layered subsidence magnetic ring.
Optionally, the sensor mounting includes a plurality of connecting rods, the connecting rod with the magnetic sensor one-to-one, the connecting rod with magnetic sensor top-down sets up in turn, the superiors the upper end of connecting rod with the settlement plate can be dismantled and be connected, and the lower extreme and one magnetic sensor connects, and is all the other the upper end of connecting rod all is connected with a magnetic sensor through an adapter. The magnetic sensors are connected in series with each other through a connecting rod.
Optionally, after the wires connected to the automated data acquisition and transmission mechanism on each of the magnetic sensors are collected under the settlement plate to form a wire, the wire is led out from the side of the settlement plate to be connected to the automated data acquisition and transmission mechanism, and the wire harness is sleeved with a cable protection tube.
Optionally, a layered sedimentation tube is arranged in the drill hole, and the sensor fixing piece is located in the layered sedimentation tube.
Optionally, the layered settling tube is formed by connecting multiple sections of unit tube bodies in series, and the unit tube bodies are detachably connected.
Optionally, a corrugated pipe is arranged between the layered settling pipe and the settling plate, the upper end of the corrugated pipe is flush with the underwater mud surface, and the lower end of the corrugated pipe is connected with the layered settling pipe. The arrangement of the corrugated pipe plays a role in buffering, and the phenomenon that the load on the mud surface directly presses the layered settling pipe to cause deformation of the protective pipe is avoided, so that equipment in the layered settling pipe is damaged.
Optionally, the inner diameter of the corrugated pipe is larger than the outer diameter of the layered settling pipe, and the corrugated pipe and the layered settling pipe are sleeved with each other.
The invention has the advantages and positive effects that: 1. meanwhile, the surface layer and the layered settlement of the breakwater revetment foundation can be measured; 2. the problem that although the layered settling pipe or the embedded reference pile is embedded in a stable soil layer, the layered settling pipe or the reference pile is driven to sink due to upper loading and upper soil layer sedimentation to cause measurement errors, or the layered settling pipe or the reference pile is relatively stable in bottom and causes the settling pipe or the reference pile to bend and deform due to upper acting force to cause measurement errors, even deformation is too large, and an internal sensor is damaged is solved; 3. the problems of various defects of manual monitoring and high protection difficulty of other issuing equipment are solved, an automatic monitoring method is adopted to guide field information construction, and the safety of the breakwater revetment is ensured. The popularization and the application of the method have great practical significance and remarkable economic and social benefits.
Drawings
FIG. 1 is a schematic diagram of the overall structure of an embodiment of the present invention;
in the figure: 1-breakwater bank protection; 2-automatic data acquisition and transmission mechanism; 3-floats or other column devices; 4-cable protective pipe; 5-soil layer; 6-a layered settling tube; 7-a signal line; 8-settling magnetic rings; 9-a reference magnetic ring; 10-a dedicated magneto-displacement sensor; 11-an adapter; 12-a connecting rod; 13-a bellows; 14-a settling plate; 15-water.
Detailed Description
The present invention will be described in further detail with reference to specific examples. It should be understood that the specific embodiments described herein are merely illustrative of the invention and do not limit the invention. In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on those shown in the drawings, and are used only for convenience in describing the present invention and for simplicity in description, and do not indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and thus, are not to be construed as limiting the present invention. In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; the two components can be directly connected or indirectly connected through an intermediate medium, and the two components can be communicated with each other. The specific meaning of the above terms in the present invention can be understood by those of ordinary skill in the art through specific situations.
The concrete structure and implementation process of the foundation surface layer and the layered settlement automatic monitoring device are explained in detail by taking the offshore stone jetty as an example.
As shown in the figure, the invention provides an automatic monitoring device for the surface layer and the layered settlement of a breakwater revetment foundation, which comprises a settlement plate 14, a drill hole below a water bottom mud surface, a layered settlement pipe 6, a sensor fixing piece, a plurality of settlement magnetic rings 8 and an automatic data acquisition and transmission mechanism 2;
the depth of the drilled hole is larger than the influence depth of foundation deformation caused by load on a mud surface, the sedimentation magnetic rings 8 are fixed on the inner wall of the drilled hole at intervals from top to bottom, one sedimentation magnetic ring 8 is positioned below the influence depth of the foundation deformation in the drilled hole, and the sedimentation magnetic ring 8 is used as a reference magnetic ring 9;
the settlement plate 14 covers the orifice of the drilled hole;
the upper end of the sensor fixing piece is connected with the settlement plate 14, the lower end of the sensor fixing piece extends into the bottom of the drill hole, a plurality of magnetic displacement sensors 10 are arranged on the sensor fixing piece at intervals,
the sensor fixing piece comprises a plurality of connecting rods 12, the connecting rods 12 correspond to the magnetic sensors 10 one by one, the connecting rods 12 and the magnetic sensors 10 are alternately arranged from top to bottom, the upper end of the connecting rod 12 on the uppermost layer is detachably connected with the settling plate 14, the lower end of the connecting rod 12 on the uppermost layer is connected with one magnetic sensor 10, and the upper ends of the other connecting rods 12 are connected with one magnetic sensor 10 through an adapter 11. The individual magneto sensors 10 are connected in series to each other by a connecting rod 12.
The electric wire connected with the automatic data acquisition and emission mechanism 2 on each magnetic sensor 10 passes through the wire hole reserved on the adapter 11, after the electric wire is converged into a wire under the settlement plate 14, the electric wire is led out from the side surface of the settlement plate 14 and connected with the automatic data acquisition and emission mechanism 2, and the wire harness is sleeved with the cable protective tube 4.
The layered settling tube 6 is arranged in the drill hole, and the sensor fixing piece is located in the layered settling tube 6.
The layered settling tube 6 is formed by connecting a plurality of sections of unit tube bodies in series, and all the unit tube bodies are detachably connected.
A corrugated pipe 13 is arranged between the layered settling pipe 6 and the settling plate 14, and two ends of the corrugated pipe 13 are respectively connected with the settling plate 14 and the layered settling pipe 6. The arrangement of the corrugated pipe 13 plays a role in buffering, and the phenomenon that the layered settling tube 6 is deformed due to the fact that the load on a mud surface directly presses the layered settling protection tube 6 is avoided, so that the damage to equipment in the layered settling tube 6 is caused.
The inner diameter of the corrugated pipe 13 is larger than the outer diameter of the layered settling pipe 6, and the corrugated pipe 13 and the layered settling pipe 6 are sleeved with each other.
Firstly, determining a layered settlement monitoring position according to design requirements and geological survey data, and then determining the foundation deformation influence depth through theoretical calculation according to the geological survey data and the structure load of the breakwater, namely determining the embedding position of the lowermost reference magnetic ring 9. Then, according to the layered settlement monitoring position required by design, the length of the connecting rod 12 is reasonably selected, and the magnetic displacement sensor 10 at the position corresponding to each settlement magnetic ring 8 is ensured to have enough measuring range.
Then, before the breakwater revetment 1 is constructed, a position is drilled by using a drilling ship, and in consideration of the offshore operation condition, a hole protecting pipe is firstly drilled before drilling, and then hole forming operation is carried out. The drilling depth needs to be 1-2m deeper than the depth of the reference magnetic ring 9, and is determined according to the estimated settlement of the surface layer. After drilling, a settlement magnetic ring 8 and a reference magnetic ring 9 are embedded according to the traditional mode, and the connection of the layered settlement pipes 6 which are 1-2m below the mud surface adopts active detachable connection. After the layered settling pipe 6 is buried, a corrugated pipe 13 with the diameter slightly larger than that of the layered settling pipe 6 is placed in the drilling protective pipe, the length of the corrugated pipe 13 is preferably 2m, and the upper end of the corrugated pipe 13 is flush with the mud surface.
And then, after soft soil around the drilled hole is self-compacted, fine sand is backfilled around the layered settling tube 6, and when the layered settling tube 6 does not float upwards any more, the drilled hole protection tube is detached. After the drill hole protection pipe is disassembled, the magnetic displacement sensor 10 is placed in the layered settling pipe 6. The method comprises the steps that the magnetic displacement sensors 10 corresponding to the reference magnetic rings 9 are firstly arranged, then the upper ends of the magnetic displacement sensors 10 are connected with connecting rods 12 through reserved threaded screw threads, the connecting rods 12 are connected with adapters 11, the adapters 11 are connected with the bottoms of the magnetic displacement sensors 10 corresponding to the last sedimentation magnetic ring 8, the steps are repeated until all the magnetic displacement sensors 10 are connected in series, and wires of the magnetic displacement sensors 10 are led out through holes reserved in the side faces of the adapters 11.
And disassembling the layered settling tube 6 connected with the lower loose joint of the mud surface, after the disassembly is finished, connecting the uppermost connecting rod 12 with the settling tube 14, connecting the bottoms of the uppermost connecting rod and the settling tube together through threads, and simultaneously collecting and penetrating the signal wires 7 of the sensors into the cable protection tube 4. And slowly lowering the settlement plate 14 and the cable protection pipe 4 to the mud surface by using a lifting rope.
And finally, the cable protecting pipe 4 is transversely laid along the breakwater revetment 1 and is pulled to a buoy or other upright post devices 3 outside the construction influence range of the breakwater revetment 1, and the signal wire 7 is connected into the automatic data acquisition and transmission mechanism 2. After whole operation is accomplished, the construction is carried out the sand cushion and is laid, then whole equipment fixing is accomplished, if the project does not design sand cushion or other treatment, then need arrange the diver to carry out the protection work of burying underground of cable pillar 4, prevent to throw stone in-process and damage the cable.
After the installation of the automatic monitoring device for the surface layer and the layered settlement of the breakwater revetment foundation is completed, the basic monitoring principle is as follows:
when the breakwater revetment 1 is loaded, the settlement plate 14 sinks, all the magnetic displacement sensors 10 connected with the settlement plate sink synchronously, the magnetic displacement sensor 10 at the lowest end sinks, the subsidence measured by the reference magnetic ring 9 is L1, namely the subsidence of the surface layer of the foundation, the magnetic displacement sensor 10 corresponding to a certain layered settlement monitoring point is L2 measured by the layered settlement magnetic ring 8, and the difference value (L1-L2) is the subsidence of the layered settlement magnetic ring 8.
All monitoring data are transmitted to the monitoring platform through the automatic data acquisition and transmission mechanism 2, and the purpose of automatically monitoring the surface layer of the breakwater revetment and the layered settlement is achieved.
The embodiments of the present invention have been described in detail, but the description is only for the preferred embodiments of the present invention and should not be construed as limiting the scope of the present invention. All equivalent changes and modifications made within the scope of the present invention shall fall within the scope of the present invention.

Claims (7)

1. The utility model provides a breakwater shore protection foundation top layer and layering subside automatic monitoring devices which characterized in that: the underwater mud surface sedimentation device comprises a sedimentation plate, a drill hole below the underwater mud surface, a sensor fixing piece, a plurality of sedimentation magnetic rings and an automatic data acquisition and transmission mechanism;
the depth of the drill hole is greater than the influence depth of foundation deformation caused by load on a mud surface, the sedimentation magnetic rings are fixed on the inner wall of the drill hole at intervals from top to bottom, one of the sedimentation magnetic rings is positioned below the influence depth of the foundation deformation in the drill hole, and the sedimentation magnetic ring is used as a reference magnetic ring;
the settling plate covers the orifice of the drilled hole;
the upper end of the sensor fixing piece is connected with the settlement plate, the lower end of the sensor fixing piece extends into the bottom of the drilled hole, a plurality of magnetic displacement sensors are arranged on the sensor fixing piece at intervals and correspond to the settlement magnetic rings one to one, and the magnetic displacement sensors are electrically connected with the automatic data acquisition and transmission mechanism.
2. The automatic monitoring devices of breakwater revetment foundation top layer and layering settlement of claim 1, characterized in that: the sensor fixing piece comprises a plurality of connecting rods, the connecting rods correspond to the magnetic sensors one by one, the connecting rods are alternately arranged from top to bottom, the uppermost layer is formed by the upper ends of the connecting rods, the settlement plates can be detachably connected, the lower ends of the connecting rods are connected with the magnetic sensors, and the connecting rods are connected with the magnetic sensors through adapters.
3. The automatic monitoring devices of breakwater shore protection foundation top layer and layering settlement of claim 2, characterized in that: and after the electric wires connected with the automatic data acquisition and emission mechanisms on the magnetic sensors are converged to form a wire below the settlement plate, the wire is led out from the side surface of the settlement plate and is connected with the automatic data acquisition and emission mechanisms, and the wire harness is sleeved with a cable protective pipe.
4. The automatic monitoring device of breakwater revetment foundation surface layer and layered settlement according to any one of claims 1-3, wherein: a layered sedimentation pipe is arranged in the drill hole, and the sensor fixing piece is located in the layered sedimentation pipe.
5. The automatic monitoring devices of breakwater revetment foundation top layer and layering settlement of claim 4, characterized in that: the layered settling pipe is formed by connecting multiple sections of unit pipe bodies in series, and all the unit pipe bodies are detachably connected.
6. The automatic monitoring devices of breakwater revetment foundation top layer and layering settlement of claim 5, characterized in that: the layered settling pipe and the settling plate are provided with corrugated pipes, the upper ends of the corrugated pipes are flush with the water bottom mud surface, and the lower ends of the corrugated pipes are connected with the layered settling pipe.
7. The automatic monitoring devices of breakwater shore protection foundation top layer and layering settlement of claim 6, characterized in that: the inner diameter of the corrugated pipe is larger than the outer diameter of the layered sedimentation pipe, and the corrugated pipe is sleeved with the layered sedimentation pipe.
CN202210719759.XA 2022-06-23 2022-06-23 Automatic monitoring devices is subsided on breakwater shore protection foundation top layer and layering Pending CN115110511A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210719759.XA CN115110511A (en) 2022-06-23 2022-06-23 Automatic monitoring devices is subsided on breakwater shore protection foundation top layer and layering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210719759.XA CN115110511A (en) 2022-06-23 2022-06-23 Automatic monitoring devices is subsided on breakwater shore protection foundation top layer and layering

Publications (1)

Publication Number Publication Date
CN115110511A true CN115110511A (en) 2022-09-27

Family

ID=83329268

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210719759.XA Pending CN115110511A (en) 2022-06-23 2022-06-23 Automatic monitoring devices is subsided on breakwater shore protection foundation top layer and layering

Country Status (1)

Country Link
CN (1) CN115110511A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115613540A (en) * 2022-11-11 2023-01-17 上海勘察设计研究院(集团)有限公司 Soil layered settlement testing device and burying method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115613540A (en) * 2022-11-11 2023-01-17 上海勘察设计研究院(集团)有限公司 Soil layered settlement testing device and burying method

Similar Documents

Publication Publication Date Title
CN105350509B (en) Filing layered sedimentation monitoring device and method
CN101078220B (en) Soft soil roadbed settlement monitoring method and device
CN104831762A (en) Dynamic monitoring system and monitoring method of deep foundation pit confined water drawdown
CN103644892A (en) Measuring device and method for layered settlement of soil body of deep foundation pit
CN113265998A (en) Combined foundation monitoring method for dynamic compaction reinforcement
CN109989433A (en) A kind of device and its detection method of the superfilled height of real-time detection cast-in-situ bored pile
CN102877447B (en) Shallow stratum multi-point settlement real-time monitoring device and method
CN105350488A (en) Test device for novel sheet-pile wharf and manufacturing method and test method of test device
CN115110511A (en) Automatic monitoring devices is subsided on breakwater shore protection foundation top layer and layering
CN107100213A (en) Soil disturbance monitoring system and monitoring method of the bridge construction of pile groups to adjacent piles
CN114016489A (en) Datum point fixing device for settlement monitoring
CN109443310A (en) A kind of subgrade settlement automated watch-keeping facility and construction technology
CN114894155B (en) Embankment or port yard filling layered settlement monitoring device and construction method
CN217517534U (en) Automatic monitoring devices is subsided on breakwater shore protection foundation top layer and layering
CN210341868U (en) In-situ soil body layered settlement monitoring device
CN102102358A (en) Method for measuring deep sedimentation deformation of foundation by using wireless conduction water pressure meter
CN109682347B (en) Method for measuring expansion amount at different depths in water meeting process of expansive soil
CN111854688A (en) Automatic change layering settlement appearance
CN116592938A (en) Multifunctional observation tube for earth and rockfill dam
CN107063178B (en) Concrete leveling markstone with displacement sensor and elevation observation and calculation method thereof
CN105649120A (en) Method for testing neutral point of negative friction of cast-in-place pile in deep backfilled soil
CN207277308U (en) Bridge construction of pile groups monitors system to the soil disturbance of adjacent piles
CN202850007U (en) Shallow stratum multipoint settlement real-time monitoring device
CN115450267A (en) Earth and rock dam settling pipe relay installation and embedding structure and method thereof
CN112197806B (en) Method for installing equipment for monitoring movement deformation, hydrology and stress of coal mining subsidence area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination