CN115081645A - Modern power supply system power failure first-aid repair method based on intelligent map - Google Patents
Modern power supply system power failure first-aid repair method based on intelligent map Download PDFInfo
- Publication number
- CN115081645A CN115081645A CN202210444078.7A CN202210444078A CN115081645A CN 115081645 A CN115081645 A CN 115081645A CN 202210444078 A CN202210444078 A CN 202210444078A CN 115081645 A CN115081645 A CN 115081645A
- Authority
- CN
- China
- Prior art keywords
- power failure
- fault
- map
- emergency repair
- user
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000008439 repair process Effects 0.000 title claims abstract description 59
- 238000000034 method Methods 0.000 title claims abstract description 15
- 238000012423 maintenance Methods 0.000 claims abstract description 15
- 238000009877 rendering Methods 0.000 claims abstract description 4
- 230000002159 abnormal effect Effects 0.000 claims description 3
- 238000004140 cleaning Methods 0.000 claims description 3
- 230000015556 catabolic process Effects 0.000 claims 3
- 230000010354 integration Effects 0.000 claims 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Health & Medical Sciences (AREA)
- Data Mining & Analysis (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
The invention discloses a modern power supply system power failure emergency repair method based on an intelligent map, which comprises the steps that a data server integrates power failure related business flow data of all manufacturers in a cross-domain real-time manner; then, the map APP reads the service flow data, and the specific color rendering is carried out on the power failure area at the front end of the map APP; when the power is off, a user fills in and submits fault reporting information through a user terminal; map APP intelligence reads the report trouble information that the user submitted, generates the work trouble list: a maintenance department arranges fault maintenance, and emergency repair personnel rush to a fault site for maintenance, and update the emergency repair progress to a fault report sheet in real time in the whole emergency repair process; and the map APP background generates an emergency repair progress in real time according to the fault list to form a real-time fault maintenance condition of an emergency repair track, and feeds the fault maintenance condition back to the power consumer. The method and the system can enable a user to clearly see the power failure event information of the positioning position, quickly inquire the detailed information of the emergency repair progress, and accurately check the emergency repair track circuit of emergency repair personnel in real time.
Description
Technical Field
The invention relates to the technical field of power failure emergency repair, in particular to a modern power supply system power failure emergency repair method based on an intelligent map.
Background
At present, in the field of power grids, when planned power failure or emergency power failure occurs, a power failure area and a fault emergency repair condition are informed to a user through a power grid internet platform in a structured address mode.
There are two pain points in this way:
1. the power consumer needs to accurately position the power according to the power failure structured address information by additionally using a third-party map.
2. The third party map itself does not include outage information.
The two points above cannot be fused together in an intuitive manner.
Disclosure of Invention
The invention aims to solve the defects in the prior art, and provides a modern power supply system power failure emergency repair method based on an intelligent map.
In order to achieve the purpose, the invention adopts the following technical scheme: a modern power supply system power failure emergency repair method based on an intelligent map comprises the following steps:
step 1: the data server integrates the power failure related service flow data of each manufacturer in real time in a cross-domain manner; and 2. step 2.
The map APP reads the business flow data, and power failure is carried out at the front end of the map APP
Performing explicit color rendering on the region;
step 3, a user registers and logs in a map APP through a user terminal, inquires a power supply state, and fills and submits fault report information if the area where the user is located has an abnormal power utilization state;
step 4, the map APP intelligently reads fault reporting information submitted by a user and generates a working fault list;
step 5, the maintenance department rapidly arranges fault maintenance through the map APP background, and the emergency repair personnel receive the maintenance notice through the map APP and rapidly arrive at the fault site for maintenance, so that the emergency repair personnel can update the emergency repair progress to an obstacle-reporting list in real time in the whole emergency repair process;
and 6, acquiring the emergency repair progress of the fault list in real time by the background of the map APP, generating structured data, dotting on the map, forming a line by dots, and feeding back the real-time fault repair condition of an emergency repair track to the power consumer.
Preferably, the data server integrates service flow data related to power failure of each manufacturer in real time across domains, which is service flow data obtained by performing a series of data cleaning on the position, the location, the area, the content of power failure information, whether power failure occurs, and the related range by using the real-time computing capacity of big data.
Preferably, the map APP is a smart view map.
The invention has the following beneficial effects:
the method can enable a user to clearly see the power failure event information of the positioning position, quickly inquire the detailed information of the emergency repair progress, and accurately check the emergency repair track circuit of emergency repair personnel in real time; finally, the first-aid repair information is transparent and visual, so that the probability of wrong report and wrong report of a client is reduced, the waiting time of the client is reduced, the urgency degree of the client is relieved, and meanwhile, the high-efficiency information intercommunication capacity between a power consumer and a power grid company is improved to a certain extent.
Drawings
FIG. 1 is a flow chart of a modern power supply system power failure emergency repair method based on an intelligent map;
FIG. 2 is a view of a user reporting an obstacle interface on an intelligent aerial view map according to the present invention;
FIG. 3 is a diagram showing a user searching and reporting fault detail interface on an intelligent aerial view map;
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention.
Referring to fig. 1-3, one embodiment of the present invention is provided: a modern power supply system power failure emergency repair method based on an intelligent map comprises the following steps:
step 1: the data server integrates the power-off related business flow data of each manufacturer in real time in a cross-domain manner, and performs a series of data cleaning on the power-off information contents of the position, the affiliated place and the area, whether power-off faults exist and the related range by utilizing the real-time computing capacity of big data;
step 2, reading the business flow data by the intelligent aerial view map APP, and performing explicit color rendering on a blackout area at the front end of the intelligent aerial view map APP, wherein if the blackout area is rendered in an obvious red tone, if the xxx area displays red, the area is proved to be in a blackout state;
step 3, a user registers and logs in the intelligent aerial view map APP through a user terminal, inquires the power supply state, and fills and submits fault report information if the area where the user is located has an abnormal power utilization state;
therefore, the intelligent aerial view map needs to collect user and address data of each transformer, the longitude and latitude are transmitted to the intelligent aerial view map through an interface according to the longitude and latitude positioned by the user, the longitude and latitude are converted into virtual power utilization addresses by the intelligent aerial view map, the power failure time near the longitude and latitude is returned according to the power failure state and type mode, and the front end renders and marks the power failure time on the map through returned events and state information;
step 4, intelligently reading fault reporting information submitted by a user through an intelligent aerial view map APP, studying and judging by the system through a current positioning point and returned power failure information when the user fills the fault reporting information, and reporting faults if no event occurs in power failure to generate a working fault list;
step 5, the emergency repair department rapidly arranges fault emergency repair through the background of the intelligent aerial view map APP, emergency repair personnel carry a mobile terminal to receive emergency repair notification through the intelligent aerial view map APP, and go to a fault location for emergency repair according to the fault reporting address of a client, and the emergency repair personnel can update the emergency repair progress to a fault reporting list in real time in the whole emergency repair process;
and 6, acquiring the emergency repair progress of the fault list in real time by the APP background of the intelligent aerial view map, generating structured data, dotting on the map to form a point-to-line real-time fault emergency repair condition of an emergency repair track, and feeding the fault emergency repair condition back to the power consumer.
The following is a specific operation procedure of modern power supply system power failure emergency repair based on an intelligent aerial view map:
a. inquiring power failure events within 1000 meters near the current positioning position, namely, according to the longitude and latitude of the current positioning position, inquiring power failure event information with the current longitude and latitude as the center and the radius of 1000 meters, and displaying different power failure events on a map page in different states; events in blackouts use red markers, planned blackout events use blue markers, and recovered power events use green markers, as in fig. 2.
b. Whether the current positioning point has an event in the power failure or not is judged, namely whether the current positioning point (longitude and latitude) of the user has the event in the power failure or not is judged, and if the event in the power failure exists, the current positioning point of the client is prompted to be in the power failure, so that the client can know the event without reporting the fault, or the user is guided to enable a user number to report the fault; and if the current positioning point (longitude and latitude) of the user has no event in power failure, the user continues to carry out the next step, fills in fault reporting information and carries out one-key fault reporting operation.
c. Filling in the power failure information content, namely, the customer can select the information such as the power failure type, the power failure time, the contact person mode and the like and submit the information;
d. submitting fault reporting information, submitting the information after a user fills in complete fault reporting information, sending a fault reporting work order submitted by the user to an emergency repair team by a system, and arranging emergency repair personnel to carry out emergency repair after the emergency repair team personnel sign in the work order;
e. checking the emergency repair progress information, wherein after the emergency repair personnel start emergency repair, a client can check the emergency repair progress information in real time and check the emergency repair track of the emergency repair personnel; as shown in fig. 3.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.
Claims (3)
1. A modern power supply system power failure emergency repair method based on an intelligent map comprises the following steps:
step 1: the data server integrates the power failure related service flow data of each manufacturer in real time in a cross-domain manner;
step 2: reading the business flow data by the map APP, and carrying out power failure at the front end of the map APP
Performing explicit color rendering on the region;
and step 3: a user registers and logs in a map APP through a user terminal, inquires a power supply state, and fills and submits fault reporting information if the area where the user is located has an abnormal power utilization state;
and 4, step 4: the map APP intelligently reads fault reporting information submitted by a user and generates a working fault list;
and 5: a maintenance department rapidly arranges fault maintenance through a map APP background, first-aid repair personnel receive a maintenance notice through the map APP and rapidly arrive at a fault site for maintenance, and the first-aid repair personnel update the first-aid repair progress to a fault report sheet in real time in the whole first-aid repair process;
step 6: the map APP background collects the breakdown order rush-repair progress in real time to generate structured data, and points are formed on the map to form a point-to-line real-time breakdown maintenance condition of a rush-repair track and feed the breakdown maintenance condition back to the power consumer.
2. The intelligent map-based modern power supply system power failure emergency repair method according to claim 1, characterized in that: the cross-domain real-time integration of the service flow data related to the power failure of each manufacturer by the data server refers to service flow data obtained by performing a series of data cleaning on the power failure information content, the power failure fault content and the related range of the position, the location and the area by the data server through cross-domain real-time integration of the power failure related information of each manufacturer by utilizing the real-time computing capacity of big data.
3. The modern power supply system power failure emergency repair method based on the intelligent map as claimed in claim 1, wherein the method comprises the following steps: the map APP is an intelligent aerial view map.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210444078.7A CN115081645A (en) | 2022-04-25 | 2022-04-25 | Modern power supply system power failure first-aid repair method based on intelligent map |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210444078.7A CN115081645A (en) | 2022-04-25 | 2022-04-25 | Modern power supply system power failure first-aid repair method based on intelligent map |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115081645A true CN115081645A (en) | 2022-09-20 |
Family
ID=83247328
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210444078.7A Pending CN115081645A (en) | 2022-04-25 | 2022-04-25 | Modern power supply system power failure first-aid repair method based on intelligent map |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115081645A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116647443A (en) * | 2023-06-28 | 2023-08-25 | 广东昆仑信息科技有限公司 | Method and system for rapidly positioning network fault equipment in steel plant |
-
2022
- 2022-04-25 CN CN202210444078.7A patent/CN115081645A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116647443A (en) * | 2023-06-28 | 2023-08-25 | 广东昆仑信息科技有限公司 | Method and system for rapidly positioning network fault equipment in steel plant |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103837796B (en) | The transmission line malfunction visualization report method of a kind of sing on web and GIS and system | |
CN107682412A (en) | A kind of wisdom vehicle washing system and wisdom car-washing method | |
CN108960857A (en) | A kind of after-sale service management method, system and device | |
CN108053042A (en) | A kind of outage information is reported and submitted and delivery system | |
CN105915441A (en) | WeChat repair method based on distribution network emergency repair command system | |
CN103150598B (en) | Processing system and method for sudden failure of power transmission network | |
WO2023098375A1 (en) | Operation sheet processing method and device, storage medium, and electronic device | |
CN115081645A (en) | Modern power supply system power failure first-aid repair method based on intelligent map | |
CN112308246A (en) | Power failure notification method and system | |
CN107635080A (en) | Report processing method and equipment for repairment | |
CN106685075A (en) | Power supply fault monitoring method and device | |
CN111310969A (en) | Unmanned repair analysis and order distribution method based on GIS map | |
CN102523597A (en) | Method for monitoring power generation of oil engine at location of communication base station | |
CN104181415B (en) | Managing and monitoring system for direct current of transformer neutral point | |
CN202904354U (en) | Wireless remote transmission real-time monitoring system of polyethylene pipeline welding procedure based on Internet of Things | |
CN111666504A (en) | Method and system for rapidly declaring fault | |
CN107196295A (en) | Low voltage power distribution network powers off intelligent alarm system | |
CN112288281A (en) | Distribution network fault first-aid repair command processing system and method | |
CN109872129A (en) | A kind of line reports the closed-loop management method, device and terminal device of thing declaration form | |
CN113780595B (en) | Method for first-aid repair of base station in power failure and data analysis server | |
CN110278578B (en) | Management system for battery power and signal strength of public network interphone | |
CN212965235U (en) | Distribution network fault positioning and inspection management and control instrument | |
CN112990791B (en) | Scheduling work order flow monitoring method and system based on intelligent voice | |
CN108491314A (en) | A kind of system and method by intelligent tri coloured lantern remote monitor device state | |
CN105323280B (en) | Method for processing business, apparatus and system for electric system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |