CN108053042A - A kind of outage information is reported and submitted and delivery system - Google Patents
A kind of outage information is reported and submitted and delivery system Download PDFInfo
- Publication number
- CN108053042A CN108053042A CN201711476303.0A CN201711476303A CN108053042A CN 108053042 A CN108053042 A CN 108053042A CN 201711476303 A CN201711476303 A CN 201711476303A CN 108053042 A CN108053042 A CN 108053042A
- Authority
- CN
- China
- Prior art keywords
- power failure
- outage information
- information
- outage
- power
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 claims abstract description 16
- 230000008439 repair process Effects 0.000 claims abstract description 16
- 230000010365 information processing Effects 0.000 claims abstract description 9
- 230000015556 catabolic process Effects 0.000 claims abstract description 8
- 238000012795 verification Methods 0.000 claims description 19
- 238000001514 detection method Methods 0.000 claims description 13
- 230000005540 biological transmission Effects 0.000 claims description 10
- 238000010295 mobile communication Methods 0.000 claims description 8
- 238000012423 maintenance Methods 0.000 claims description 7
- 230000008569 process Effects 0.000 abstract description 4
- 238000012545 processing Methods 0.000 description 4
- 230000004888 barrier function Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 235000013399 edible fruits Nutrition 0.000 description 2
- 238000007689 inspection Methods 0.000 description 2
- 238000012360 testing method Methods 0.000 description 2
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 238000007619 statistical method Methods 0.000 description 1
- 230000001960 triggered effect Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04W—WIRELESS COMMUNICATION NETWORKS
- H04W4/00—Services specially adapted for wireless communication networks; Facilities therefor
- H04W4/12—Messaging; Mailboxes; Announcements
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02D—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
- Y02D30/00—Reducing energy consumption in communication networks
- Y02D30/70—Reducing energy consumption in communication networks in wireless communication networks
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Economics (AREA)
- Theoretical Computer Science (AREA)
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- General Physics & Mathematics (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Primary Health Care (AREA)
- Water Supply & Treatment (AREA)
- Public Health (AREA)
- General Health & Medical Sciences (AREA)
- Entrepreneurship & Innovation (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Computer Networks & Wireless Communication (AREA)
- Signal Processing (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of outage information report and submit with delivery system and method, including:Have a power failure plan typing subsystem, for receiving the scheduled outage information of typing;Distribution Network Failure reports subsystem for repairment, for receiving the fault repairing information of user, generates breakdown repair work order;Distribution detects subsystem automatically, for detecting the power-off event of distribution network, generates outage information, above-mentioned outage information is sent to server;Server, for outage information processing, outage information reports, power distribution rush-repair is dispatched, customer interrupted determines and outage information issue.The present invention incorporates scheduled outage and the outage information of accidental power failure is generated, reported and submitted, overhauling distribution and outage information issuing process, effectively provides efficiency and accuracy rate that power grid tackles various power-off events.
Description
Technical field
The invention belongs to outage information Intelligent statistical analysis fields more particularly to a kind of outage information to report and submit and issue system
System.
Background technology
Current outage information is reported and submitted and issue there is problems:
Since fault outage is more, data message amount is big, and dispatcher is less efficient during outage information is counted, and wrong
Rate is higher by mistake.According to statistics, when the power failure (outage information is more than 20/day) of larger area occurs, outage information reports the used time
Will be longer, and easily there is mistake, outage information content is inaccurate, reports and submits of poor quality.
The power failure range that department is reported to provide that has a power failure is inaccurate, causes the outage information that outage information issuing unit announces not
Accurately.Outage information notify it is in the form of a single, scheduled outage mainly with newspaper, put up based on power failure bulletin is single, network is announced, failure
Have a power failure based on mainly being reported with 95598TST, although having begun the mobile phone used notice, due to Client handset number more
Newly, cause many users that cannot timely receive outage information, outage information is caused to be informed not in place.
Since the power-off event that client reports for repairment may belong to the scope of scheduled outage, such as some clients are not received by meter
Draw have a power failure message, reported for repairment in the range of the scheduled outage, since the scope is being overhauled, if in addition into
Row service personnel allotment will cause personnel to waste.
Therefore, outage information generation and issue accuracy rate how are effectively improved, is that those skilled in the art need to solve at present
Certainly the technical issues of.
The content of the invention
To overcome above-mentioned the deficiencies in the prior art, the present invention provides a kind of outage informations to report and submit and delivery system and side
Method plans typing subsystem by having a power failure respectively, and Distribution Network Failure reports subsystem and distribution for repairment and detects subsystem acquisition power failure automatically
Event, generates outage information, and above-mentioned outage information is sent to server;Outage information processing is carried out by server, is had a power failure
Information reporting, power distribution rush-repair scheduling, customer interrupted determines and outage information issue.The present invention incorporates scheduled outage and accident
The outage information of power failure is generated, reported and submitted, overhauling distribution and outage information issuing process, is effectively provided power grid and is tackled various power failures
The efficiency and accuracy rate of event.
To achieve the above object, the present invention adopts the following technical scheme that:
A kind of outage information is reported and submitted and delivery system, including:
Have a power failure plan typing subsystem, for receiving the scheduled outage information of typing and being sent to server;
Distribution Network Failure reports subsystem for repairment, for receiving the fault repairing information of user, generates breakdown repair work order and sends
To server;
Distribution detects subsystem automatically, for detecting the power-off event of distribution network, generates outage information and is sent to clothes
Business device;
Server, for outage information processing, outage information reports, power distribution rush-repair is dispatched, customer interrupted determines and is stopped
Power information is issued.
Further, the outage information processing specifically includes:
(1) automatic Verification is carried out to the outage information and breakdown repair work order of reception according to default constraints, if school
It tests not by then reporting work order reception system for repairment to the power failure plan input system, Distribution Network Failure or the automatic examination and repair system of distribution is anti-
Miscue is presented, if verification passes through, performs next step.
(2) outage information merger is carried out according to power off time and power failure position.
Further, the relation constraint of data type of the constraints including field, option and interfield.
Further, the step (2) includes:
For the data that the plan typing subsystem that has a power failure is sent, power failure range is matched with map datum, generation stops
Electric scheduled outage scope;
It reports the data of subsystem transmission for repairment for Distribution Network Failure, power failure position is matched with map datum, generation event
Barrier reports power failure range for repairment;
It detects the data of subsystem transmission automatically for distribution, based on the abort situation and distribution line network, judges
Power failure range in circuit network matches the circuit network of power failure with map datum, generates automatic detection power failure range;
To the power failure scheduled outage scope of identical power off time, troublshooting power failure range and automatic detection power failure range into
Row compares, if troublshooting power failure range or automatic detection power failure range are judged as in the range of the power failure scheduled outage
Outage information is carried out merger by same power-off event;
Wherein, the map datum is map vector, distribution line network and the map datum rigid registrations.
Further, the power distribution rush-repair scheduling specifically includes:
(1) according to the geography information of power failure range, related service personnel is distributed;
(2) it is that related service personnel carries out path planning based on map datum;
(3) the maintenance situation of service personnel's feedback is received.
Further, the customer interrupted determines to specifically include:
(1) power grid customer database based on customer address with map datum is associated, obtains client's distribution map;
(2) client's distribution map is had a power failure respectively with power failure scheduled outage scope, troublshooting power failure range and automatic detection
Scope carries out spatial overlay analysis, obtains the client of power failure scheduled outage scope, the client of troublshooting power failure range and automatic
Detect the client of power failure range.
Further, the outage information issue specifically includes:
(1) contact method verification is carried out to the client that customer interrupted determining module obtains;
(2) for the successful client of authentication, outage information is sent to former registration number;The outage information includes stopping
Electric reason, power failure range and power failure starting and termination time.
Further, the step (1) includes:By customer name, identification card number and cell-phone number by network interface and
Mobile communications network sends real name verification request to the module of subscriber authentication;
The device of subscriber authentication searches corresponding mobile phone in subscriber identity information database according to the identification card number
Number, and by the cell-phone number found and receive cell-phone number compare, if comparing result unanimously if real name verification success, such as
The failure of fruit comparing result inconsistent then real name verification, wherein, it user is stored in subscriber identity information database handles mobile phone and open
The personal information including user's real name, identification card number and phone number registered during family to mobile communication carrier.
Further, the step (2) further includes:For the unsuccessful client of authentication, subscriber identity information is extracted
Corresponding cell-phone number in database sends outage information;Or its place place is determined by client geographic location, according to
Outage information is announced based on its property contact method of internet checking, notice property in the place.
Second purpose according to the present invention, the present invention also provides a kind of outage informations based on the system to report and submit and send out
Cloth method, comprises the following steps:
Receive the power failure plan typing subsystem, Distribution Network Failure reports subsystem and distribution for repairment and detects subsystem transmission automatically
Outage information and outage information is verified, if verify pass through if trigger outage information and report;After examination & approval pass through, root
Repairing distribution is carried out according to the location information of outage information, and receives the line maintenance situation of related personnel's feedback;
Data and outage information determine power failure range according to the map;
Target customer is determined according to power grid customer database and power failure range;
Outage information is sent to the target user.
Beneficial effects of the present invention
1st, the present invention incorporates scheduled outage and the outage information of accidental power failure is generated, reported and submitted, overhauling distribution and have a power failure and believe
Issuing process is ceased, effectively provides the efficiency and accuracy rate of power grid reply power-off event.
2nd, the present invention is made a report on for repair personnel outage information, the work order for reporting generation for repairment have carried out data check, into one
Specification data format and content are walked, data accuracy is improved, the burden of rechecking is alleviated for the personnel of making a report on.
3rd, since the power-off event that client reports for repairment may belong to the scope of scheduled outage, such as some clients are not received by
The message of scheduled outage is reported for repairment when having a power failure and occurring.The power-off event of same time is carried out merger by the present invention, is avoided
The repetition of outage information repeats to overhaul caused by reporting.
4th, due to being registered when the customer data in power grid is opened an account, contact method may change, and the present invention passes through
Interface is verified using the authentication means of mobile communication business business, ensures outage information notice in place.
Description of the drawings
The accompanying drawings which form a part of this application are used for providing further understanding of the present application, and the application's shows
Meaning property embodiment and its explanation do not form the improper restriction to the application for explaining the application.
Fig. 1 reports the frame diagram with delivery system for outage information of the present invention.
Specific embodiment
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.It is unless another
It indicates, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field
The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root
According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative
It is also intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " bag
Include " when, indicate existing characteristics, step, operation, device, component and/or combination thereof.
In the case where there is no conflict, the feature in the embodiment and embodiment in the application can be mutually combined.
Embodiment one
It is reported present embodiment discloses a kind of outage information and delivery system, including:Have a power failure plan typing subsystem, distribution
Subsystem and server are overhauled in troublshooting work order receiving subsystem, distribution automatically, wherein,
Have a power failure plan typing subsystem, for receiving the scheduled outage information of typing and being sent to server, the power failure
When plan information includes power failure type (scheduled overhaul has a power failure, ad hoc inspection and repair has a power failure and temporary derangement has a power failure), safety at power cut, has a power failure
Between, power failure range, dead line title, power failure taiwan area and the circuit powered etc. by which electric substation (tower).
Distribution Network Failure reports subsystem for repairment, for receiving the fault repairing information of user, generates breakdown repair work order and sends
To server;The breakdown repair work order includes power failure address, power failure time of origin and user contact details.
Distribution detects subsystem automatically, for detecting the power-off event of distribution network, generates outage information and is sent to clothes
Business device;The outage information includes power off time and abort situation.Specifically, receive switch changed position information that DMS main websites send,
The variation of protection act information and telemetry judges generation and the abort situation of power-off event.
Server is used including outage information processing module, outage information reporting module, power failure range determining module, power failure
Family determining module and outage information release module, wherein,
The outage information processing module reception power failure plan typing subsystem, Distribution Network Failure report subsystem and distribution for repairment certainly
The outage information and verified to outage information that dynamic detection subsystem is sent, are triggered if in outage information if verifying
Report module;
Outage information reporting module, reporting and submitting and feed back for outage information;
Power distribution rush-repair scheduler module, for carrying out repairing distribution according to outage information and receiving what related personnel fed back
Line maintenance situation, including safety at power cut, power off time, power failure range and recovery time etc.;
Customer interrupted determining module, for determining customer interrupted;
Outage information release module, for sending outage information to customer interrupted.
Specifically, the outage information processing module specifically carries out following processing:
(1) automatic Verification is carried out to the outage information and breakdown repair work order of reception according to default constraints, if school
It tests not by then reporting work order reception system for repairment to the power failure plan input system, Distribution Network Failure or the automatic examination and repair system of distribution is anti-
Miscue is presented, if verification passes through, performs next step.
The relation constraint of data type of the constraints including field, option and interfield, such as:In each column
Specific keyword can only be filled in, power failure type is only capable of filling in scheduled overhaul power failure, ad hoc inspection and repair power failure and temporary derangement power failure;
The relation constraint of interfield such as power failure range, dead line title, power failure taiwan area and the circuit are by which electric substation (tower)
Power supply, information above is related to geographical location, according to the geography information and line information to prestore in database, can determine whether above-mentioned
It is whether conflicting between information, it is verified mutually accordingly.
(2) outage information merger is carried out according to power off time and power failure position.Specifically,
For the data that the plan typing subsystem that has a power failure is sent, power failure range is matched with map datum, generation stops
Electric scheduled outage scope;
It reports the data of subsystem transmission for repairment for Distribution Network Failure, power failure position is matched with map datum, generation event
Barrier reports power failure range for repairment;
It detects the data of subsystem transmission automatically for distribution, based on the abort situation and distribution line network, judges
Power failure range in circuit network matches the circuit network of power failure with map datum, generates automatic detection power failure range;
To the power failure scheduled outage scope of identical power off time, troublshooting power failure range and automatic detection power failure range into
Row compares, if troublshooting power failure range or automatic detection power failure range are judged as in the range of the power failure scheduled outage
Outage information is carried out merger by same power-off event;
Wherein, the map datum is map vector, and the map vector is accurate to cell, and records its attribute information;
Distribution line network and the map datum are based on identical map projection and coordinate system, and rigid registrations.The distribution line
The attribute information of network and electric network information database association, the electric network information data-base recording substation, circuit level-one branch line,
The information such as two level branch line ..., bar number.
The power distribution rush-repair scheduler module specifically carries out following processing:
(1) according to the geography information of power failure range, related service personnel is distributed;
(2) it is that related service personnel carries out path planning based on map datum;
(3) the maintenance situation of service personnel's feedback is received.
The customer interrupted determining module specifically carries out following processing:
(1) power grid customer database based on customer address with map datum is associated, obtains client's distribution map;
(2) client's distribution map is had a power failure respectively with power failure scheduled outage scope, troublshooting power failure range and automatic detection
Scope carries out spatial overlay analysis, obtains the client of power failure scheduled outage scope, the client of troublshooting power failure range and automatic
Detect the client of power failure range.
The outage information release module specifically carries out following processing:
(1) contact method verification is carried out to the client that customer interrupted determining module obtains;
By customer name, identification card number and cell-phone number by network interface and mobile communications network to subscriber authentication
Module send real name verification request;
The device of subscriber authentication searches corresponding mobile phone in subscriber identity information database according to the identification card number
Number, and by the cell-phone number found and receive cell-phone number compare, if comparing result unanimously if real name verification success, such as
The inconsistent then real name verification failure of fruit comparing result.
Wherein, user is stored in subscriber identity information database to handle when mobile phone is opened an account to mobile communication carrier's registration
The personal information including user's real name, identification card number and phone number.
(2) for the successful client of authentication, outage information is sent to former registration number;
For the unsuccessful client of authentication, the corresponding cell-phone number extracted in subscriber identity information database sends power failure
Information;Or
Place (such as cell, office building or factory) where determining it by client geographic location, according to the field
Internet checking its property contact method is based on, notice property announces outage information;The outage information includes stopping
Electric reason, power failure range and have a power failure starting and termination time etc..
Preferably due to overhauling may fulfil ahead of schedule, the opportunity for sending outage information is further included when recovering power transmission the last period
Between, prior notice client.
Embodiment two
The outage information that the purpose of the present embodiment is to provide system described in embodiment one is reported and submitted and dissemination method, including
Following steps:
Receive the power failure plan typing subsystem, Distribution Network Failure reports subsystem and distribution for repairment and detects subsystem transmission automatically
Outage information and outage information is verified, if verify pass through if trigger outage information and report;After examination & approval pass through, root
Repairing distribution is carried out according to the location information of outage information, and receives the line maintenance situation of related personnel's feedback;
Data and outage information determine power failure range according to the map;
Target customer is determined according to power grid customer database and power failure range;
Outage information is sent to the target user.
Beneficial effects of the present invention:
1st, the present invention incorporates scheduled outage and the outage information of accidental power failure is generated, reported and submitted, overhauling distribution and have a power failure and believe
Issuing process is ceased, effectively provides the efficiency and accuracy rate of power grid reply power-off event.
2nd, the present invention is made a report on for repair personnel outage information, the work order for reporting generation for repairment have carried out data check, into one
Specification data format and content are walked, data accuracy is improved, the burden of rechecking is alleviated for the personnel of making a report on.
3rd, since the power-off event that client reports for repairment may belong to the scope of scheduled outage, such as some clients are not received by
The message of scheduled outage is reported for repairment when having a power failure and occurring.The power-off event of same time is carried out merger by the present invention, is avoided
The repetition of outage information repeats to overhaul caused by reporting.
4th, due to being registered when the customer data in power grid is opened an account, contact method may change, and the present invention passes through
Interface is verified using the authentication means of mobile communication business business, ensures outage information notice in place.
It will be understood by those skilled in the art that each module or each step of the invention described above can be filled with general computer
It puts to realize, optionally, they can be realized with the program code that computing device can perform, it is thus possible to which they are stored
In the storage device by computing device come perform either they are fabricated to respectively each integrated circuit modules or by they
In multiple modules or step be fabricated to single integrated circuit module to realize.The present invention is not limited to any specific hardware and
The combination of software.
Above-mentioned, although the foregoing specific embodiments of the present invention is described with reference to the accompanying drawings, not protects model to the present invention
The limitation enclosed, those skilled in the art should understand that, based on the technical solutions of the present invention, those skilled in the art are not
Need to make the creative labor the various modifications or changes that can be made still within protection scope of the present invention.
Claims (10)
1. a kind of outage information is reported and submitted and delivery system, which is characterized in that including:
Have a power failure plan typing subsystem, for receiving the scheduled outage information of typing and being sent to server;
Distribution Network Failure reports subsystem for repairment, for receiving the fault repairing information of user, generates breakdown repair work order and is sent to clothes
Business device;
Distribution detects subsystem automatically, for detecting the power-off event of distribution network, generates outage information and is sent to server;
Server, for outage information processing, outage information reports, power distribution rush-repair is dispatched, customer interrupted determines and the letter that has a power failure
Breath issue.
2. a kind of outage information as described in claim 1 is reported and submitted and delivery system, which is characterized in that the outage information processing
It specifically includes:
(1) automatic Verification is carried out to the outage information and breakdown repair work order of reception according to default constraints, if verification is not
By then reporting work order reception system or the automatic examination and repair system feedback mistake of distribution for repairment to the power failure plan input system, Distribution Network Failure
It prompts by mistake, if verification passes through, performs next step.
(2) outage information merger is carried out according to power off time and power failure position.
3. a kind of outage information as claimed in claim 2 is reported and submitted and delivery system, which is characterized in that the constraints includes
The relation constraint of the data type of field, option and interfield.
4. a kind of outage information as claimed in claim 2 is reported and submitted and delivery system, which is characterized in that the step (2) includes:
For the data that the plan typing subsystem that has a power failure is sent, power failure range is matched with map datum, generation power failure meter
Draw power failure range;
It reports the data of subsystem transmission for repairment for Distribution Network Failure, power failure position is matched with map datum, generate failure report
Repair power failure range;
It detects the data of subsystem transmission automatically for distribution, based on the abort situation and distribution line network, judges circuit
Power failure range in network matches the circuit network of power failure with map datum, generates automatic detection power failure range;
The power failure scheduled outage scope of identical power off time, troublshooting power failure range and automatic detection power failure range are compared
It is right, if troublshooting power failure range or automatic detection power failure range are judged as same in the range of the power failure scheduled outage
Outage information is carried out merger by power-off event;
Wherein, the map datum is map vector, distribution line network and the map datum rigid registrations.
5. a kind of outage information as described in claim 1 is reported and submitted and delivery system, which is characterized in that the power distribution rush-repair scheduling
It specifically includes:
(1) according to the geography information of power failure range, related service personnel is distributed;
(2) it is that related service personnel carries out path planning based on map datum;
(3) the maintenance situation of service personnel's feedback is received.
6. a kind of outage information as described in claim 1 is reported and submitted and delivery system, which is characterized in that the customer interrupted determines
It specifically includes:
(1) power grid customer database based on customer address with map datum is associated, obtains client's distribution map;
(2) by client's distribution map respectively with power failure scheduled outage scope, troublshooting power failure range and detecting power failure range automatically
Spatial overlay analysis is carried out, obtains the client of power failure scheduled outage scope, the client of troublshooting power failure range and automatic detection
The client of power failure range.
7. a kind of outage information as described in claim 1 is reported and submitted and delivery system, which is characterized in that the outage information issue
It specifically includes:
(1) contact method verification is carried out to the client that customer interrupted determining module obtains;
(2) for the successful client of authentication, outage information is sent to former registration number;The outage information includes having a power failure former
Cause, power failure range and power failure starting and termination time.
8. a kind of outage information as claimed in claim 7 is reported and submitted and delivery system, which is characterized in that the step (1) includes:
Customer name, identification card number and cell-phone number are sent out by network interface and mobile communications network to the module of subscriber authentication
Real name verification is sent to ask;
The device of subscriber authentication searches corresponding cell-phone number in subscriber identity information database according to the identification card number, and
By the cell-phone number found and receive cell-phone number compare, if comparing result unanimously if real name verification success, if right
The failure of more inconsistent than result then real name verification, wherein, when user is stored in subscriber identity information database handling mobile phone and open an account
The personal information including user's real name, identification card number and phone number registered to mobile communication carrier.
9. a kind of outage information as claimed in claim 7 is reported and submitted and delivery system, which is characterized in that the step (2) is also wrapped
It includes:For the unsuccessful client of authentication, the corresponding cell-phone number extracted in subscriber identity information database sends outage information;
Or its place place is determined by client geographic location, according to the place based on its property correspondent party of internet checking
Formula, notice property announce outage information.
10. a kind of outage information based on any one of the claim 1-9 systems is reported and submitted and dissemination method, including following step
Suddenly:
Receive the power failure plan typing subsystem, Distribution Network Failure reports subsystem and distribution for repairment and detects stopping for subsystem transmission automatically
Power information and outage information is verified, if verify pass through if trigger outage information and report;After examination & approval pass through, according to stopping
The location information of power information carries out repairing distribution, and receives the line maintenance situation of related personnel's feedback;
Data and outage information determine power failure range according to the map;
Target customer is determined according to power grid customer database and power failure range;
Outage information is sent to the target user.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711476303.0A CN108053042A (en) | 2017-12-29 | 2017-12-29 | A kind of outage information is reported and submitted and delivery system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711476303.0A CN108053042A (en) | 2017-12-29 | 2017-12-29 | A kind of outage information is reported and submitted and delivery system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108053042A true CN108053042A (en) | 2018-05-18 |
Family
ID=62129393
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711476303.0A Pending CN108053042A (en) | 2017-12-29 | 2017-12-29 | A kind of outage information is reported and submitted and delivery system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108053042A (en) |
Cited By (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108875975A (en) * | 2018-06-27 | 2018-11-23 | 国网甘肃省电力公司金昌供电公司 | A kind of excellent dress system of wisdom precisely informed based on client's outage information |
CN109255729A (en) * | 2018-11-06 | 2019-01-22 | 国网山东省电力公司泰安供电公司 | Outage information management method, apparatus and system |
CN109525740A (en) * | 2018-10-12 | 2019-03-26 | 成都北科维拓科技有限公司 | A kind of event-handling method and system |
CN109829646A (en) * | 2019-01-30 | 2019-05-31 | 深圳供电局有限公司 | Written notice sending method and device |
CN110069538A (en) * | 2019-04-19 | 2019-07-30 | 国网湖北省电力有限公司咸宁供电公司 | A method of user's outage information is inquired with cell-phone number |
CN110263112A (en) * | 2019-05-31 | 2019-09-20 | 上海电力学院 | A kind of outage information delivery system based on graphicalization |
CN110363422A (en) * | 2019-07-10 | 2019-10-22 | 国网山东省电力公司临沂供电公司 | One kind stopping power transmission information management system, method and electronic equipment |
CN110445245A (en) * | 2019-08-02 | 2019-11-12 | 珠海和一科技有限公司 | It is a kind of have a power failure, power down active reporting method |
CN110879867A (en) * | 2019-11-20 | 2020-03-13 | 云南电网有限责任公司电力科学研究院 | Information publishing method and system based on LED advertisement function power distribution cabinet |
CN110889524A (en) * | 2019-11-06 | 2020-03-17 | 深圳供电局有限公司 | Power failure reservation application processing method and device, computer equipment and medium |
CN110929903A (en) * | 2019-11-06 | 2020-03-27 | 深圳供电局有限公司 | Power failure reservation method, device, computer equipment and medium |
CN110969829A (en) * | 2019-10-18 | 2020-04-07 | 国网浙江省电力有限公司电力科学研究院 | Power failure data sharing method based on cloud platform computing and message bus technology |
CN111178551A (en) * | 2019-12-10 | 2020-05-19 | 国网浙江桐乡市供电有限公司 | Power protection system intelligent decision method based on power protection big data |
CN111178685A (en) * | 2019-12-10 | 2020-05-19 | 国网浙江桐乡市供电有限公司 | Power protection system intelligent decision method based on power protection big data |
CN111552904A (en) * | 2020-04-17 | 2020-08-18 | 贵州电网有限责任公司 | Intelligent power grid operation information issuing system |
CN112381245A (en) * | 2020-11-16 | 2021-02-19 | 国网山东省电力公司临沂供电公司 | Join in marriage automatic pushing means of net fault power failure information |
CN112557802A (en) * | 2021-02-24 | 2021-03-26 | 国网江西省电力有限公司电力科学研究院 | Accurate analysis method and system for power outage of transformer area |
CN114282694A (en) * | 2021-12-23 | 2022-04-05 | 北京东土拓明科技有限公司 | Power maintenance control method and device, computing equipment and computer readable storage medium |
CN114495462A (en) * | 2021-12-28 | 2022-05-13 | 深圳供电局有限公司 | Alarm message processing method and device, computer equipment and storage medium |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102055809A (en) * | 2011-01-20 | 2011-05-11 | 中国联合网络通信集团有限公司 | Method, devices and system for ordering teleservice based on browser/server (B/S) structure |
CN104766180A (en) * | 2015-04-24 | 2015-07-08 | 国家电网公司 | Method for improving power failure information submission accuracy |
CN105139118A (en) * | 2015-08-19 | 2015-12-09 | 国网山东省电力公司东营供电公司 | Distribution network fault first-aid repair power failure information reporting system and method |
CN105469149A (en) * | 2015-11-21 | 2016-04-06 | 国网山东滨州市沾化区供电公司 | Service system for electric power fault reporting and repairing |
CN105809373A (en) * | 2016-04-27 | 2016-07-27 | 国网山东省电力公司济南市长清区供电公司 | Distribution network fault information comprehensive collection and management platform |
US9424729B2 (en) * | 2013-03-15 | 2016-08-23 | Vivint, Inc. | Security system tracking of remote items using reduced power |
CN105894172A (en) * | 2015-11-17 | 2016-08-24 | 国家电网公司 | Joint outage judging method based on marketing and distribution fusion |
CN105915551A (en) * | 2016-06-22 | 2016-08-31 | 武汉青禾科技有限公司 | Real-name system verification method and communication operator real-name system verification method based on mobile terminal bottom layer |
CN106875114A (en) * | 2017-02-10 | 2017-06-20 | 国家电网公司 | The SMS platform optimization system and method for distribution repairing maneuvering platform |
-
2017
- 2017-12-29 CN CN201711476303.0A patent/CN108053042A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102055809A (en) * | 2011-01-20 | 2011-05-11 | 中国联合网络通信集团有限公司 | Method, devices and system for ordering teleservice based on browser/server (B/S) structure |
US9424729B2 (en) * | 2013-03-15 | 2016-08-23 | Vivint, Inc. | Security system tracking of remote items using reduced power |
CN104766180A (en) * | 2015-04-24 | 2015-07-08 | 国家电网公司 | Method for improving power failure information submission accuracy |
CN105139118A (en) * | 2015-08-19 | 2015-12-09 | 国网山东省电力公司东营供电公司 | Distribution network fault first-aid repair power failure information reporting system and method |
CN105894172A (en) * | 2015-11-17 | 2016-08-24 | 国家电网公司 | Joint outage judging method based on marketing and distribution fusion |
CN105469149A (en) * | 2015-11-21 | 2016-04-06 | 国网山东滨州市沾化区供电公司 | Service system for electric power fault reporting and repairing |
CN105809373A (en) * | 2016-04-27 | 2016-07-27 | 国网山东省电力公司济南市长清区供电公司 | Distribution network fault information comprehensive collection and management platform |
CN105915551A (en) * | 2016-06-22 | 2016-08-31 | 武汉青禾科技有限公司 | Real-name system verification method and communication operator real-name system verification method based on mobile terminal bottom layer |
CN106875114A (en) * | 2017-02-10 | 2017-06-20 | 国家电网公司 | The SMS platform optimization system and method for distribution repairing maneuvering platform |
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108875975A (en) * | 2018-06-27 | 2018-11-23 | 国网甘肃省电力公司金昌供电公司 | A kind of excellent dress system of wisdom precisely informed based on client's outage information |
CN109525740B (en) * | 2018-10-12 | 2021-01-26 | 成都北科维拓科技有限公司 | Event processing method and system |
CN109525740A (en) * | 2018-10-12 | 2019-03-26 | 成都北科维拓科技有限公司 | A kind of event-handling method and system |
CN109255729A (en) * | 2018-11-06 | 2019-01-22 | 国网山东省电力公司泰安供电公司 | Outage information management method, apparatus and system |
CN109829646A (en) * | 2019-01-30 | 2019-05-31 | 深圳供电局有限公司 | Written notice sending method and device |
CN110069538A (en) * | 2019-04-19 | 2019-07-30 | 国网湖北省电力有限公司咸宁供电公司 | A method of user's outage information is inquired with cell-phone number |
CN110263112A (en) * | 2019-05-31 | 2019-09-20 | 上海电力学院 | A kind of outage information delivery system based on graphicalization |
CN110363422A (en) * | 2019-07-10 | 2019-10-22 | 国网山东省电力公司临沂供电公司 | One kind stopping power transmission information management system, method and electronic equipment |
CN110445245A (en) * | 2019-08-02 | 2019-11-12 | 珠海和一科技有限公司 | It is a kind of have a power failure, power down active reporting method |
CN110969829A (en) * | 2019-10-18 | 2020-04-07 | 国网浙江省电力有限公司电力科学研究院 | Power failure data sharing method based on cloud platform computing and message bus technology |
CN110889524B (en) * | 2019-11-06 | 2023-03-24 | 深圳供电局有限公司 | Power failure reservation application processing method and device, computer equipment and medium |
CN110889524A (en) * | 2019-11-06 | 2020-03-17 | 深圳供电局有限公司 | Power failure reservation application processing method and device, computer equipment and medium |
CN110929903A (en) * | 2019-11-06 | 2020-03-27 | 深圳供电局有限公司 | Power failure reservation method, device, computer equipment and medium |
CN110879867A (en) * | 2019-11-20 | 2020-03-13 | 云南电网有限责任公司电力科学研究院 | Information publishing method and system based on LED advertisement function power distribution cabinet |
CN111178551A (en) * | 2019-12-10 | 2020-05-19 | 国网浙江桐乡市供电有限公司 | Power protection system intelligent decision method based on power protection big data |
CN111178685A (en) * | 2019-12-10 | 2020-05-19 | 国网浙江桐乡市供电有限公司 | Power protection system intelligent decision method based on power protection big data |
CN111552904A (en) * | 2020-04-17 | 2020-08-18 | 贵州电网有限责任公司 | Intelligent power grid operation information issuing system |
CN112381245A (en) * | 2020-11-16 | 2021-02-19 | 国网山东省电力公司临沂供电公司 | Join in marriage automatic pushing means of net fault power failure information |
CN112381245B (en) * | 2020-11-16 | 2023-01-10 | 国网山东省电力公司临沂供电公司 | Join in marriage automatic pushing tools of net fault power failure information |
CN112557802A (en) * | 2021-02-24 | 2021-03-26 | 国网江西省电力有限公司电力科学研究院 | Accurate analysis method and system for power outage of transformer area |
CN114282694A (en) * | 2021-12-23 | 2022-04-05 | 北京东土拓明科技有限公司 | Power maintenance control method and device, computing equipment and computer readable storage medium |
CN114495462A (en) * | 2021-12-28 | 2022-05-13 | 深圳供电局有限公司 | Alarm message processing method and device, computer equipment and storage medium |
CN114495462B (en) * | 2021-12-28 | 2024-03-22 | 深圳供电局有限公司 | Alarm message processing method, device, computer equipment and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108053042A (en) | A kind of outage information is reported and submitted and delivery system | |
CN107368898B (en) | Intelligent fault reporting and maintenance monitoring method | |
CN107886446A (en) | A kind of distribution network failure rushes to repair workform management system | |
CN104036348A (en) | Electronic mobile operation order system | |
CN106875114A (en) | The SMS platform optimization system and method for distribution repairing maneuvering platform | |
CN109859829A (en) | A kind of wechat public platform based Medical Devices repair reporting system and its operation method | |
CN104636868A (en) | Application management system for nuclear power station equipment maintenance information and application method thereof | |
CN105915441A (en) | WeChat repair method based on distribution network emergency repair command system | |
CN110647567B (en) | Power failure plan auxiliary decision system based on end data fusion | |
CN105225039A (en) | Based on independently reporting the floating population's management method with Community Watch | |
CN101459925A (en) | Complaint management system and method for telecommunication network | |
CN108171339B (en) | Mobile interconnection-based distribution network integrated service management system and emergency repair method thereof | |
CN104657841A (en) | Express item delivery method, delivery processing method, express cabinet terminal and service system | |
CN112217672B (en) | Service processing system for CDN platform | |
CN106384312A (en) | Tour group service management platform | |
CN108712392A (en) | A kind of cloud data managing method and cloud system | |
CN109598640A (en) | A kind of user power utilization information query system and its application method based on wechat public platform | |
CN108366176A (en) | A kind of charging method of terminal applies, apparatus and system | |
CN109709917A (en) | A kind of fault handling method and system of intelligence production line | |
CN106301893B (en) | Information interacting method and system for BTS management maintenance | |
CN109726999A (en) | A kind of household services card management system | |
CN106056776A (en) | NFC mobile terminal based public bike intelligent management system | |
CN116503021A (en) | Digital tool system and method for on-site rush repair of power base unit | |
CN106384159A (en) | Judge meeting appointment method and device applied to court system | |
CN112446619B (en) | Power distribution network rush-repair processing method and device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||