CN115075545A - Construction method of composite heat-insulation formwork - Google Patents

Construction method of composite heat-insulation formwork Download PDF

Info

Publication number
CN115075545A
CN115075545A CN202210696094.5A CN202210696094A CN115075545A CN 115075545 A CN115075545 A CN 115075545A CN 202210696094 A CN202210696094 A CN 202210696094A CN 115075545 A CN115075545 A CN 115075545A
Authority
CN
China
Prior art keywords
template
heat
composite heat
building
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210696094.5A
Other languages
Chinese (zh)
Inventor
周广升
王利锋
张焱
靳伟通
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Beijing Tianrun Construction Co Ltd
Original Assignee
China 22MCC Group Corp Ltd
Beijing Tianrun Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd, Beijing Tianrun Construction Co Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN202210696094.5A priority Critical patent/CN115075545A/en
Publication of CN115075545A publication Critical patent/CN115075545A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G9/00Forming or shuttering elements for general use
    • E04G9/10Forming or shuttering elements for general use with additional peculiarities such as surface shaping, insulating or heating, permeability to water or air
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • E04B2/8611Walls made by casting, pouring, or tamping in situ made in permanent forms with spacers being embedded in at least one form leaf
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/001Corner fastening or connecting means for forming or stiffening elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/007Plugs to close openings in forms' surface

Abstract

The invention belongs to the technical field of heat preservation construction of constructional engineering, and discloses a construction method of a composite heat preservation template, which comprises the following specific steps: s100, arranging an outer cantilever plate at each floor of a building; s200, building an internal support system; s300, typesetting of a heat preservation template; s400, transferring the steel bars and the heat preservation template downwards from the top of the building; s500, erecting an outer wall framework system; s600, installing a heat preservation template; and S700, building an outer wall body. The construction method of the composite heat-insulation template is suitable for the construction of the composite heat-insulation template of the super-high layer, provides enough space for the assembly of the heat-insulation template, reduces overhead operation, is beneficial to improving the construction efficiency, ensures the assembly effect of the heat-insulation template and reduces the potential safety hazard of operation.

Description

Construction method of composite heat-insulation formwork
Technical Field
The invention relates to the technical field of heat preservation construction of constructional engineering, in particular to a construction method of a composite heat preservation template.
Background
The height of the house building is continuously increased, however, along with the increase of the building height, the construction and the heat insulation performance of the outer wall heat insulation project are seriously tested. At present, super high-rise buildings are all shear wall structures, an outer wall structure and an outer heat insulation layer are respectively constructed, and then the outer wall structure and the outer heat insulation layer are combined through bonding. The cohesiveness of the outer wall structure and the outer heat-insulating layer is reduced along with the time, and the problem that the outer heat-insulating layer falls off can occur, so that safety accidents are caused.
In order to avoid bonding failure of an outer wall structure and an outer heat-insulating layer, the prior art provides a composite heat-insulating template cast-in-place concrete heat-insulating system, namely a heat-insulating structure integrated construction technology, wherein the composite heat-insulating template is a permanent outer template, concrete is poured on the inner side of the composite heat-insulating template, a leveling layer is further arranged on the outer side of the composite heat-insulating template, and then construction of an anti-cracking layer and a decorative surface layer is carried out. Finally, the composite heat-insulating template is firmly connected with the concrete through a connecting piece.
Compared with the traditional external heat-insulating layer, the composite heat-insulating template cast-in-place concrete heat-insulating system is firmly connected through the wall-through connecting piece, is constructed synchronously, forms a whole and effectively solves the problem that the traditional external heat-insulating layer is easy to bond and lose efficacy. However, in the construction of super high-rise buildings, the story height of a standard story is higher, the width of the composite heat-insulating template is 600mm, the maximum length of the composite heat-insulating template is 3000mm, the thickness of the composite heat-insulating template is 12-15mm, and the composite heat-insulating template is heavy in weight, large in size and difficult to install and construct. The installation engineering of the composite heat-insulation template mainly has the following problems: firstly, when the composite heat-insulation template is installed on an ultra-high layer with the height of more than 3m, at least two composite heat-insulation templates are needed for assembling each layer of vertical heat-insulation layer, the composite heat-insulation template is heavy, and the labor intensity of manual carrying is too high, so that the engineering progress is influenced. Secondly, need set up operation platform alone when carrying out the construction of compound incubation template, and receive the restriction of building outer protection frame, lead to operation platform space narrow and small, increased the construction degree of difficulty. In addition, when two vertical composite heat-insulating templates are transversely spliced, a splicing seam is generated, and meanwhile, a cold bridge phenomenon is generated when each layer of composite heat-insulating template is spliced, so that the construction quality is difficult to ensure. The cold bridge phenomenon mainly means that when the building outer enclosure structure conducts heat with the outside, because the heat transfer coefficient of some parts in the enclosure structure is obviously larger than that of other parts, the heat is intensively and quickly transferred from the parts, and thus the air conditioning, heating load and energy consumption of the building are increased. And finally, the constructors have great potential safety hazards when working at high heights outside the super high-rise building, and the construction difficulty is increased along with the increase of the floor height.
Therefore, a construction method of a composite heat-insulating template is needed to solve the above problems.
Disclosure of Invention
The invention aims to provide a construction method of a composite heat-insulation template, which is suitable for the construction of the composite heat-insulation template of a super high-rise building, provides enough space for the assembly of the heat-insulation template, reduces overhead operation, is beneficial to improving the construction efficiency, ensures the assembly effect of the heat-insulation template and reduces the potential safety hazard of operation.
In order to achieve the purpose, the invention adopts the following technical scheme:
a construction method of a composite heat-insulation template comprises the following specific steps:
s100, arranging an outer cantilever plate at each floor of a building;
s200, building an internal support system;
s300, typesetting of a heat preservation template;
s400, transferring the steel bars and the heat preservation template downwards from the top of the building;
s500, erecting an outer wall framework system;
s600, installing a heat preservation template;
and S700, building an outer wall body.
Alternatively, the installation of the building roof panel formwork is performed while the step S200 is performed.
Optionally, in step S200, an internal supporting system is built on the floor slab of the working floor, the internal supporting system includes a supporting rod portion and a working platform, the supporting rod portion is built on the floor slab of the working floor, the working platform is mounted on the supporting rod portion, and the working platform is used for providing a construction platform for the heat preservation formwork.
Optionally, in step S300, the method specifically includes the following steps:
s310, determining a typesetting scheme of the heat preservation template according to the size of the building outer wall, and drawing a typesetting pattern;
and S320, cutting the heat preservation template.
Optionally, the following steps are performed before step S600:
forming a plurality of reserved through holes in the heat-insulating template;
and (4) installing anchoring pieces in the reserved through holes, wherein the number of the anchoring pieces on each square meter of the heat-preservation template is not less than 8.
Optionally, in step S500, the following steps are specifically performed:
step S510, binding steel bars to form a steel bar framework;
and step S520, binding cushion blocks on two sides of the steel reinforcement framework.
Optionally, in step S600, the following steps are specifically performed:
s610, binding and positioning the anchoring piece and the outer wall framework system;
and S620, installing split bolts.
Optionally, in step S700, the following steps are specifically performed:
step S710, mounting an inner side template;
step S720, installing an outer template;
step S730, pouring concrete;
step S740, removing the inner side template and the outer side template;
and S750, plugging bolt holes of the outer wall body.
Optionally, in step S720, the outer side template is disposed flush with the outer edge of the outer cantilever plate.
Optionally, before step S200, the following steps are performed:
and erecting an external protection scaffold outside the operation layer.
The invention has the beneficial effects that:
according to the construction method of the composite heat-insulation template, the outer cantilever plate is arranged at each floor of the building, so that the cold bridge phenomenon at the joint of the heat-insulation templates between every two floors is prevented, the unloading function can be realized, the heat-insulation templates on each floor can root smoothly, and the installation quality of the heat-insulation templates is improved. Through setting up inside support system, for the heat preservation template provides construction platform, the concatenation installation of two or more heat preservation templates when being convenient for carry out super high floor construction has reduced the live time that the tower crane was taken in the heat preservation template installation, has improved the utilization efficiency of tower crane, can improve the quality of heat preservation template concatenation installation simultaneously, has reduced high altitude construction volume simultaneously, reduces high altitude construction's potential safety hazard. By typesetting the heat preservation templates, the reasonable arrangement of the usage of the heat preservation templates is realized, and the materials are saved to the maximum extent. The construction method of the composite heat-insulation template is suitable for the construction of the composite heat-insulation template of the super high-rise building, is beneficial to improving the construction efficiency, ensuring the construction effect, reducing the safety risk of high-place operation and reducing the potential safety hazard.
Drawings
FIG. 1 is a flow chart of a construction method of a composite heat-insulating formwork according to an embodiment of the present invention;
FIG. 2 is a schematic structural diagram of an outer suspension plate according to an embodiment of the present invention;
FIG. 3 is a schematic diagram of the layout of the heat preservation template according to the embodiment of the present invention;
fig. 4 is a schematic structural diagram of an anchor for installing a heat preservation formwork provided by the embodiment of the invention.
In the figure:
1. a floor slab; 2. an outer cantilever plate;
10. a heat preservation template; 11. and (4) an anchoring piece.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the invention and are not limiting of the invention. It should be further noted that, for the convenience of description, only some of the structures related to the present invention are shown in the drawings, not all of the structures.
In the description of the present invention, unless expressly stated or limited otherwise, the terms "connected," "connected," and "fixed" are to be construed broadly, e.g., as meaning permanently connected, removably connected, or integral to one another; can be mechanically or electrically connected; either directly or indirectly through intervening media, either internally or in any other relationship. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
In the present invention, unless otherwise expressly stated or limited, "above" or "below" a first feature means that the first and second features are in direct contact, or that the first and second features are not in direct contact but are in contact with each other via another feature therebetween. Also, the first feature being "on," "above" and "over" the second feature includes the first feature being directly on and obliquely above the second feature, or merely indicating that the first feature is at a higher level than the second feature. "beneath," "under" and "beneath" a first feature includes the first feature being directly beneath and obliquely beneath the second feature, or simply indicating that the first feature is at a lesser elevation than the second feature.
In the description of the present embodiment, the terms "upper", "lower", "right", "left", and the like are used based on the orientations and positional relationships shown in the drawings only for convenience of description and simplification of operation, and do not indicate or imply that the referred device or element must have a specific orientation, be configured and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used only for descriptive purposes and are not intended to have a special meaning.
Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the accompanying drawings are illustrative only for the purpose of explaining the present invention, and are not to be construed as limiting the present invention.
Fig. 1 shows a flow chart of a construction method of a composite heat-insulating formwork provided in an embodiment of the present invention. Referring to fig. 1, the present embodiment provides a construction method of a composite heat insulation template, and the construction method of the composite heat insulation template specifically includes the steps of:
s100, arranging an outer cantilever plate 2 at each floor 1 of the building;
s200, building an internal support system;
s300, typesetting the heat preservation template 10;
s400, transferring the steel bars and the heat preservation template 10 from the top of the building downwards;
s500, erecting an outer wall framework system;
s600, installing a heat preservation template 10;
and S700, building an outer wall body.
Fig. 2 is a schematic structural diagram of an outer cantilever plate according to an embodiment of the present invention. Referring to fig. 2, in step S100, the outer cantilever panel 2 has the same thickness as the floor slab 1, and is integrally constructed with the floor slab 1 by the slab-following reinforcing bars built in the floor slab 1. The width of the outer cantilever plate 2 is 25mm less than the thickness of the heat preservation template 10, namely the gap width between the outer edge of the outer cantilever plate 2 and the outer edge line of the building target is 25 mm. After the heat preservation templates 10 are installed, heat preservation mortar is filled in the gaps to prevent cold bridge phenomenon, and meanwhile, the unloading function is achieved, so that rooting of each layer of heat preservation templates 10 is guaranteed, and the installation quality is guaranteed.
Specifically, before step S200, the following steps are performed: and erecting an external protection scaffold outside the operation layer. This outer protection scaffold can guarantee construction safety, and its structure is prior art, and this embodiment is no longer repeated here.
More specifically, the installation of the building roof panel is performed simultaneously with the step S200. After the top plate formwork is installed, the top plate formwork is used as the installation root of the heat preservation formwork 10 on the top layer of the building.
More specifically, in step S200, an internal support system is built on the floor slab 1 on the working floor, the internal support system includes a support rod portion and a working platform, the support rod portion is built on the floor slab 1 on the working floor, the working platform is mounted on the support rod portion, and the working platform is used for providing a construction platform for the heat preservation formwork 10. This bracing piece portion is formed by the alternately ligature of a plurality of steel pipes, forms the stable support frame that has a take the altitude, guarantees the stability of inside support system. The operation platform can be made of wood plates or steel plates and is arranged on the upper end face of the supporting rod part in a binding and other fixing mode. Utilize the tower crane to transfer heat preservation template 10 to the operation layer after from building top, constructor can accomplish assembling of heat preservation template 10 on this internal support system, need not to occupy the tower crane for a long time, has improved the utilization efficiency of tower crane in whole building engineering. And constructors do not need to carry out long-time high-altitude outdoor operation, so that the potential safety hazard of high-altitude operation is reduced. Meanwhile, the internal support system has enough construction space, so that the assembling quality of the heat-insulating template 10 can be improved, and the operation is convenient. And this inside braced system can raise the installation basis of heat preservation template 10, is convenient for constructor to carry out the installation of the great heat preservation template 10 of size.
FIG. 3 is a schematic diagram of layout of heat preservation templates provided by the embodiment of the invention. In step S300, the method specifically includes the following steps: step S310, determining a typesetting scheme of the heat preservation template 10 according to the size of the building outer wall, and drawing a typesetting pattern; and step S320, cutting the heat preservation template 10.
Specifically, the heat preservation formwork 10 is designed and typeset in advance according to the size of the outer wall before formal installation, so that the using amount of the heat preservation formwork 10 with the standard specification is increased, and the heat preservation effect is improved. The positions where the heat preservation templates 10 of the standard plate specification cannot be used for installation, such as the structural modeling position and the narrow wall position, are specially typeset and numbered, and the heat preservation templates 10 of the standard specification are cut into specification sizes meeting the requirements by a cutting saw according to the typesetting requirements on a construction site, so that the installation quality is improved, and the reworking is reduced. In this embodiment, in order to ensure the heat preservation effect, the minimum width of the cutting and forming of the heat preservation template 10 should not be less than 200 mm.
More specifically, in step S500, the following steps are specifically performed: step S510, binding steel bars to form a steel bar framework; and step S520, binding cushion blocks on two sides of the steel reinforcement framework. After the binding of the external wall, the column and the beam steel bars is qualified and accepted, cushion blocks with the same strength as the wall body are bound on the inner side and the outer side of the steel bar framework, and 3 or 4 cushion blocks are arranged on each square meter of the steel bar framework. The cushion block is a cement mortar cushion block in the prior art, and the cushion block can ensure the section thickness and the strength of the composite heat-insulating template after construction is finished.
More specifically, the following steps are performed before step S600: forming a plurality of reserved through holes in the heat-insulating template 10; and (3) installing anchoring pieces 11 in the reserved through holes, wherein the number of the anchoring pieces 11 on each square meter of the heat-preservation template 10 is not less than 8. According to the requirements of typesetting patterns, the anchoring piece 11 and the steel reinforcement framework are bound and positioned by the binding steel wire.
More specifically, in step S600, the following steps are specifically performed: s610, binding and positioning the anchoring piece 11 and the outer wall framework system; and S620, installing split bolts.
Optionally, in step S700, the following steps are specifically performed:
step S710, mounting an inner side template;
step S720, installing an outer template;
step S730, pouring concrete;
step S740, removing the inner side template and the outer side template;
and S750, plugging bolt holes of the outer wall body.
Specifically, in step S710, holes are formed in the inner mold plate with reference to the positions of the split bolts, PVC sleeves are inserted into the holes, and the split bolts are screwed in, thereby preliminarily adjusting the split bolts.
Preferably, in step S720, the outer side form is disposed flush with the outer edge of the outer cantilever panel 2. With the outer board of overhanging of one deck on the operation layer as the root, outside template utilizes the outer board 2 of overhanging of operation layer to fix, should guarantee during the installation that outside template and outer edge of overhanging board 2 are level and smooth seamless, avoid producing the hourglass thick liquid phenomenon.
More specifically, in step S730, the vibrating rod is prevented from being directly vibrated to the heat-insulating formwork 10 during the concrete pouring so as to prevent the heat-insulating formwork 10 from being damaged. Meanwhile, the phenomenon that the vibrating rod is directly vibrated to the outer side template to cause damage to the outer side template and influence on the bonding force is avoided. When concrete is poured, galvanized iron sheets or protective covers are buckled on the upper edge of the heat preservation template 10 to form protection, so that the heat preservation template 10 is prevented from being polluted by the concrete. The building outer wall body needs to be vibrated compactly and uniformly, and the defects of flatness, no holes, rib leakage, ash residues and the like of the wall body are guaranteed. And after the outer side template is removed, the surface of the composite heat-insulation template is cleaned in time if cement slurry exists, and the flatness of the surface of the composite heat-insulation template is checked.
And finishing the basic construction of the composite heat-insulation formwork, then removing the inner side formwork, and immediately carrying out water spraying maintenance on the outer wall body, wherein the maintenance time is not less than 14 days.
And then, after the inner template and the outer template are removed, plugging bolt holes of the outer wall body, plugging the bolt holes into the bolt holes from the outer side of the outer wall body by using expansion waterproof mortar, wherein the depth of the bolt holes is 50mm, and tamping and leveling the bolt holes with round steel with the diameter of 10 mm. And after the expansion waterproof mortar reaches a certain strength every other day, the foam rubber pipe is deeply inserted into the bottom of the bolt hole from the inner side of the outer wall body for foaming and pouring. After the mortar outside the outer wall body is dried, the polyurethane coating waterproof material is coated to the split bolt hole, in order to facilitate acceptance and prevent brush leakage, polyurethane with 3 different colors is utilized for coating, white coating is adopted for the first time to form a circular mark with the diameter of 150mm, red coating is adopted for the second time to form a circular mark with the diameter of 130mm, and black coating is adopted for the third time to form a circular mark with the diameter of 110 mm. The total thickness of the coating film is not less than 1.8 mm.
And finally, performing the joint splicing and the anti-cracking treatment of the internal and external corners, which comprises the following specific steps: and (3) plastering and pressing crack-resistant mortar at the joints of the composite heat-insulating template, the intersection of the internal corner and the external corner and the like, and paving alkali-resistant mesh cloth to enhance the crack resistance.
It should be understood that the above-described embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. Numerous obvious variations, adaptations, and substitutions will occur to those skilled in the art without departing from the scope of the present invention. And are neither required nor exhaustive of all embodiments. Any modification, equivalent replacement, and improvement made within the spirit and principle of the present invention should be included in the protection scope of the claims of the present invention.

Claims (10)

1. The construction method of the composite heat-insulation template is characterized by comprising the following specific steps:
s100, arranging an outer cantilever plate (2) at each floor (1) of the building;
s200, building an internal support system;
s300, typesetting by using a heat preservation template (10);
s400, transferring the steel bars and the heat preservation template (10) from the top of the building downwards;
s500, erecting an outer wall framework system;
s600, installing a heat preservation template (10);
s700, building an outer wall body.
2. The method of constructing a composite heat-insulating formwork according to claim 1, wherein the step S200 is performed simultaneously with the installation of the building ceiling formwork.
3. The construction method of a composite heat-insulating formwork according to claim 1, wherein in step S200, an internal support system is built on the floor (1) of the working floor, the internal support system includes a support rod portion and a working platform, the support rod portion is built on the floor (1) of the working floor, the working platform is mounted on the support rod portion, and the working platform is used for providing a construction platform for the heat-insulating formwork (10).
4. The construction method of the composite heat preservation formwork of claim 1, characterized in that in the step S300, the method specifically comprises the following steps:
s310, determining a typesetting scheme of the heat preservation template (10) according to the size of the building outer wall, and drawing a typesetting pattern;
s320, cutting the heat preservation template (10).
5. The construction method of a composite heat-insulating formwork according to claim 1, wherein the following steps are further performed before step S600:
a plurality of reserved through holes are formed in the heat-insulating template (10);
and (3) installing anchoring pieces (11) in the reserved through holes, wherein the number of the anchoring pieces (11) on each square meter of the heat-preservation template (10) is not less than 8.
6. The construction method of a composite heat-insulating formwork according to claim 1, wherein in step S500, the following steps are specifically performed:
s510, binding steel bars to form a steel bar framework;
and S520, binding cushion blocks on two sides of the steel reinforcement framework.
7. The construction method of a composite heat-insulating formwork according to claim 1, wherein in step S600, the following steps are specifically performed:
s610, binding and positioning the anchoring piece (11) and the outer wall framework system;
and S620, installing split bolts.
8. The construction method of a composite heat-insulating formwork according to claim 1, wherein in step S700, the following steps are specifically performed:
s710, installing an inner side template;
s720, installing an outer template;
s730, pouring concrete;
s740, removing the inner side template and the outer side template;
and S750, plugging bolt holes of the outer wall body.
9. The construction method of a composite heat-insulating formwork according to claim 8, wherein in step S720, the outer formwork is disposed flush with the outer edge of the outer cantilever panel (2).
10. The construction method of a composite heat-insulating formwork according to claim 1, wherein before the step S200, the following steps are performed:
and erecting an external protection scaffold outside the operation layer.
CN202210696094.5A 2022-06-20 2022-06-20 Construction method of composite heat-insulation formwork Pending CN115075545A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210696094.5A CN115075545A (en) 2022-06-20 2022-06-20 Construction method of composite heat-insulation formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210696094.5A CN115075545A (en) 2022-06-20 2022-06-20 Construction method of composite heat-insulation formwork

Publications (1)

Publication Number Publication Date
CN115075545A true CN115075545A (en) 2022-09-20

Family

ID=83252702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210696094.5A Pending CN115075545A (en) 2022-06-20 2022-06-20 Construction method of composite heat-insulation formwork

Country Status (1)

Country Link
CN (1) CN115075545A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU7943301A (en) * 2000-10-16 2002-04-18 John Kralic A walling system
JP2003003594A (en) * 2001-06-21 2003-01-08 Tesuku:Kk External wall building up method and metal thereof for exterior insulating structure with reinforced concrete bearing wall structure
CN101245620A (en) * 2008-03-25 2008-08-20 河南国基建设集团有限公司 Non-net polyphenyl plate cast-in-place concrete exterior wall heat-preserving construction method
CN101914961A (en) * 2009-03-19 2010-12-15 吴淑环 Exterior wall external insulation composite wall body with support
CN107143141A (en) * 2017-07-19 2017-09-08 上海宝冶集团有限公司 External wall of high-rise building warming plate construction
CN109138227A (en) * 2018-10-19 2019-01-04 青岛建集团有限公司 Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU7943301A (en) * 2000-10-16 2002-04-18 John Kralic A walling system
JP2003003594A (en) * 2001-06-21 2003-01-08 Tesuku:Kk External wall building up method and metal thereof for exterior insulating structure with reinforced concrete bearing wall structure
CN101245620A (en) * 2008-03-25 2008-08-20 河南国基建设集团有限公司 Non-net polyphenyl plate cast-in-place concrete exterior wall heat-preserving construction method
CN101914961A (en) * 2009-03-19 2010-12-15 吴淑环 Exterior wall external insulation composite wall body with support
CN107143141A (en) * 2017-07-19 2017-09-08 上海宝冶集团有限公司 External wall of high-rise building warming plate construction
CN109138227A (en) * 2018-10-19 2019-01-04 青岛建集团有限公司 Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology

Similar Documents

Publication Publication Date Title
CN106013811A (en) Mounting method of prefabricated building
CN101736701B (en) Bridge steel and concrete mixing section constructing method
CN112854745A (en) Construction process of assembled building aluminum alloy template
CN111926910A (en) Installation method of fabricated building
CN104947846B (en) A kind of prefabricated integral frame light filling lining and preparation method thereof
CN105672664A (en) Integral heat insulation wallboard building system
CN110409860A (en) A kind of reconstruction structure and its remodeling method in old house
CN111042392A (en) Construction method of SDHH type disassembly-free formwork foam concrete partition wall
CN112482559A (en) Assembled steel structure building system and construction method
CN210369292U (en) Cast-in-place coincide mould shell integral structure of assembled building
CN218374567U (en) Can fix a position ALC wallboard reinforced structure that can exempt from to plaster
CN115075545A (en) Construction method of composite heat-insulation formwork
CN111379337B (en) Secondary structure anti-seepage and anti-leakage construction method
CN210369293U (en) Integrated structure of assembled building heat preservation formwork
CN111535339B (en) Construction process of concrete dam body of refuse landfill
CN210105005U (en) Ultralow energy consumption steel construction heat preservation building system
CN112761245A (en) Assembled reinforced concrete building main body structure and installation construction method thereof
CN112746704A (en) Arch type steel-concrete combined ceiling structure of large-span giant underground workshop and construction method
CN112127501A (en) Combined wall structure and construction method thereof
CN211774519U (en) Node structure for fixedly mounting assembly type prefabricated part wire feet
CN201236416Y (en) Prefabricated component for denizen house and prefabricated component house
CN112282145B (en) Manufacturing process of light concrete light steel frame PC embedded cast-in-place wall
CN115419190B (en) Construction method of cast-in-place concrete combined structure of superposed wall
CN219569340U (en) Assembled building element and building structure
CN216787893U (en) Prefabricated shear wall positioner

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination