CN115045558A CN202210864765.4A CN202210864765A CN115045558A CN 115045558 A CN115045558 A CN 115045558A CN 202210864765 A CN202210864765 A CN 202210864765A CN 115045558 A CN115045558 A CN 115045558A
Authority
CN
China
Prior art keywords
rod
holes
cross arm
pole
shaped clamp
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210864765.4A
Other languages
Chinese (zh)
Other versions
CN115045558B (en
Inventor
段浩宇
杨洪林
陈泊
温艳磊
徐阿娜
王欢
侯延飞
王靖雯
周永生
任雅雯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Henan Electric Power Co Ruyang County Power Supply Co
State Grid Corp of China SGCC
Original Assignee
State Grid Henan Electric Power Co Ruyang County Power Supply Co
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Henan Electric Power Co Ruyang County Power Supply Co, State Grid Corp of China SGCC filed Critical State Grid Henan Electric Power Co Ruyang County Power Supply Co
Priority to CN202210864765.4A priority Critical patent/CN115045558B/en
Publication of CN115045558A publication Critical patent/CN115045558A/en
Application granted granted Critical
Publication of CN115045558B publication Critical patent/CN115045558B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/24Cross arms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Suspension Of Electric Lines Or Cables (AREA)
  • Insulators (AREA)
  • Electric Cable Installation (AREA)

Abstract

A temporary telegraph pole easy to construct and install relates to a temporary telegraph pole, wherein two semicircular connecting seats (11) are arranged at intervals on the upper end face of one side of a lower pole (14), and a hidden groove (23) is arranged from the middle part of the other side of the lower pole to the position close to the lower end; the middle part of the end face of the lower end of one side of the upper rod (9) is provided with a connector (30), the lower part of the other side of the upper rod is provided with a hidden fixing groove (28), and the connector is inserted into a space (21) between two semicircle connecting seats of the lower rod and is connected by a shaft (13); the upper end of the control rod (12) is fixed in a hidden fixing groove of the upper rod, the lower part to the lower end of the control rod is fixed in the hidden groove through a connecting screw (16), and the upper end of the upper rod is provided with a cross arm; according to the invention, the upper rod and the lower rod are installed in advance, when the device is used, the lower end of the lower rod is deeply buried or connected with the basic cement pile connecting plate, the cross arm and the porcelain insulator can be installed on the ground, the upper rod is quickly lifted by the control rod, and the rush repair time is effectively saved.

Description

Interim wire pole of easy construction installation
Technical Field
The invention relates to a temporary telegraph pole, in particular to a temporary telegraph pole easy to construct and install.
Background
As is known, a telegraph pole is one of important infrastructures, and bears important tasks of local economic development and electricity utilization of urban residents, and the telegraph pole mainly comprises a wood telegraph pole, a cement telegraph pole and a steel pipe telegraph pole and is mainly erected in places such as fields, two sides of roads or streets; as society develops rapidly, the vehicle holding capacity of residents also rises rapidly; the accidents that the telegraph pole is collided frequently occur in the processes that trucks on the street wait for activities, the cars stop on sidewalks at night or sudden vehicle accidents and the like; the safety of the telegraph pole is endangered by many accidents of vehicles running fast on the road; so that accidents that vehicles hit the telegraph pole occur very much every year; the emergency repair requirement of the electric power department for the occurrence of vehicle impact on the telegraph pole is that the emergency time is as soon as possible to recover power supply so as to reduce the loss of customers as much as possible; the current telegraph pole is inconvenient to install.
Disclosure of Invention
In order to overcome the defects in the background art, the invention discloses a temporary telegraph pole easy to construct and install.
The technical scheme for realizing the invention is as follows: diaphysis fracture splint
A temporary telegraph pole easy to construct and install comprises a lower pole, an upper pole, a control rod and a cross arm, wherein two semicircular connecting seats are arranged at intervals on the upper end face of one side of the lower pole, and a hidden groove is formed from the middle part of the other side of the lower pole to the position close to the lower end of the other side of the lower pole; the middle part of the end face of the lower end of one side of the upper rod is provided with a connector, the lower part of the other side of the upper rod is provided with a hidden fixed groove, the connector of the upper rod is inserted into the space between the two semicircular connecting seats of the lower rod, and the connector of the upper rod is connected with a shaft hole B of the connector of the upper rod through a shaft and shaft holes A respectively arranged on the two semicircular connecting seats of the lower rod; the upper end of the control rod is fixed in a hidden fixing groove of the upper rod, the lower part to the lower end of the control rod are fixed in the hidden groove through a connecting screw, and the upper end of the upper rod is provided with a cross arm.
The temporary telegraph pole easy to construct and install is characterized in that a connecting flange is arranged at the lower end of the lower pole.
The temporary telegraph pole easy to construct and install is characterized in that two through holes are formed in the lower portion of the lower pole hiding groove at intervals, two locking holes are formed in the lower portion of the control rod at intervals, and two connecting screws sequentially penetrate through the two through holes in the lower pole hiding groove and the two locking holes in the control rod and are locked by nuts.
The temporary telegraph pole easy to construct and install is characterized in that two through holes A are formed in the lower portion of the other side of the upper pole and correspond to the two sides of the hidden fixing groove respectively; two through holes B are arranged at the upper part of the control rod at intervals; the two locking screws respectively pass through the two through holes A of the upper rod and the two through holes B of the control rod and then are locked by nuts.
The temporary telegraph pole easy to construct and install is characterized in that a handle ring is arranged at the position, close to the locking hole, of the lower portion of the control rod.
The temporary telegraph pole easy to construct and install is provided with two cross arm holes at intervals at the upper end of the upper pole; one side of the middle part of the cross arm angle iron B is provided with a U-shaped clamp B; the U-shaped clamp B is buckled on one side of the upper end of the upper rod, and two fixing screws respectively penetrate through unthreaded holes of two side plates of the U-shaped clamp B and two cross arm holes of the upper rod and are locked by nuts; porcelain bottle holes are respectively formed in two sides of the cross arm angle iron B, and a penetrating rod at the lower end of a porcelain bottle is fixed on the porcelain bottle holes to form a telegraph pole with a single cross arm.
The temporary telegraph pole easy to construct and install is provided with two cross arm holes at intervals at the upper end of the upper pole; one side of the middle part of the cross arm angle iron B is provided with a U-shaped clamp B; a U-shaped clamp A is arranged on one side of the middle part of the cross arm angle iron A; the U-shaped clamp B is buckled on one side of the upper end of the upper rod, the U-shaped clamp A is buckled on the outer sides of two side plates of the U-shaped clamp B from the other side of the upper end of the upper rod, and two fixing screws respectively penetrate through unthreaded holes of the two side plates of the U-shaped clamp A, the unthreaded holes of the two side plates of the U-shaped clamp B and the two cross arm holes of the upper rod and are locked by nuts; porcelain bottle holes are respectively formed in the two sides of the cross arm angle iron B, and penetrating rods at the lower ends of porcelain bottles are fixed on the porcelain bottle holes; porcelain bottle holes are respectively formed in two sides of the cross arm angle iron A, and the penetrating rods at the lower ends of the porcelain bottles are fixed on the porcelain bottle holes to form the telegraph pole with the double cross arms.
The temporary telegraph pole easy to construct and install is characterized in that the lower pole, the upper pole and the control rod are of hollow structures, and the upper end of the upper pole is provided with an end plate.
Through the disclosure, the beneficial effects of the invention are as follows:
according to the temporary telegraph pole easy to construct and install, the original whole telegraph pole is split into the upper pole, the lower pole and the control rod, and the temporary telegraph pole is convenient to carry along with a vehicle during rush repair through splitting; the upper rod and the lower rod, and the upper rod and the control rod are installed in advance, when the device is used, the lower end of the lower rod is deeply buried or connected with a basic cement pile connecting plate, the cross arm angle iron A, the cross arm angle iron B and the porcelain insulator can be installed under the rods, after the device is installed, the upper rod can be pulled up and erected by using a rope, and the rush repair time is effectively saved; the invention can be used for power supply of temporary construction sites; the invention is convenient to assemble, disassemble and carry, and is beneficial to quickly repairing the damaged telegraph pole.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic perspective view of the lower stem of the present invention;
FIG. 3 is a view from the direction A of FIG. 2;
FIG. 4 is a schematic perspective view of the upper stem of the present invention;
FIG. 5 is a schematic perspective view of a control lever of the present invention;
FIG. 6 is a schematic diagram of a single cross arm embodiment of the present invention;
FIG. 7 is a schematic diagram of a dual cross arm embodiment of the present invention;
FIG. 8 is a schematic view of a fixing screw structure according to the present invention;
FIG. 9 is a schematic perspective view of a cross arm angle A of the present invention;
in the figure: 1. a porcelain bottle; 2. an electric wire; 3. an end plate; 4. cross arm angle iron A; 5. a U-shaped card A; 6. fixing screws; 7. a U-shaped card B; 8. cross arm angle iron B; 9. an upper rod; 10. locking screws; 11. a semicircular connecting seat; 12. a control lever; 13. a shaft; 14. a lower rod; 15. a handle ring; 16. a connecting screw; 17. fixing a nut; 18. a connecting flange; 19. connecting a foundation cement pile; 20. a ground surface; 21. spacing; 22. the shaft hole A; 23. hiding the groove; 24. connecting holes; 25. a through hole; 26. a cross arm hole; 27. punching a hole A; 28. hiding the fixed groove; 29. a shaft hole B; 30. a connector; 31. punching a hole B; 32. a locking hole; 33. a nut; 34. a porcelain bottle hole; 35. and (4) a light hole.
Detailed Description
The present invention will be further illustrated with reference to the following examples; the following examples are not intended to limit the present invention, and are only used as a support for the implementation of the present invention, and any equivalent structure replacement within the technical framework of the present invention is included in the protection scope of the present invention;
the temporary telegraph pole easy to construct and install and described in the attached drawings 1-9 comprises a lower rod 14, an upper rod 9, a control rod 12 and a cross arm, wherein the lower rod 14, the upper rod 9 and the control rod 12 are of hollow structures, an end plate 3 is arranged at the upper end of the upper rod 9, a connecting flange 18 is arranged at the lower end of the lower rod 14, two semicircular connecting seats 11 are arranged at intervals on the upper end surface of one side of the lower rod 14, and a hidden groove 23 is arranged from the middle part of the other side of the lower rod 14 to the position close to the lower end; the middle part of the end face of the lower end of one side of the upper rod 9 is provided with a connector 30, the lower part of the other side of the upper rod 9 is provided with a hidden fixing groove 28, the connector 30 of the upper rod 9 is inserted into the interval 21 between the two semicircular connecting seats 11 of the lower rod 14, and a shaft hole B29 of the connector 30 of the upper rod 9 and a shaft hole A22 respectively arranged on the two semicircular connecting seats 11 of the lower rod 14 are connected by a shaft 13; the upper end of the control rod 12 is fixed in the hidden fixing groove 28 of the upper rod 9, the lower part to the lower end of the control rod 12 is fixed in the hidden groove 23 through the connecting screw 16, and the upper end of the upper rod 9 is provided with a cross arm.
With reference to fig. 1, 2, 3, 4 or 5, two through holes a27 are respectively formed at two sides of the lower portion of the other side of the upper rod 9 corresponding to the hidden fixing groove 28; two through holes B31 are arranged at the upper part of the control rod 12 at intervals; the two locking screws 10 are locked by nuts after respectively passing through the two through holes A27 of the upper rod 9 and the two through holes B31 of the control rod 12, the two through holes 25 are arranged at intervals at the lower part of the hidden groove 23 of the lower rod 14, the two locking holes 32 are arranged at intervals at the lower part of the control rod 12, the two connecting screws 16 are locked by nuts after sequentially passing through the two through holes 25 of the hidden groove 23 of the lower rod 14 and the two locking holes 32 of the control rod 12, and a handle ring 15 is arranged at the lower part of the control rod 12 close to the locking holes 32.
With reference to fig. 1, 4, 6, 7, 8 or 9, two cross arm holes 26 are provided at intervals at the upper end of the upper rod 9; one side of the middle part of the cross arm angle iron B8 is provided with a U-shaped clip B7; the U-shaped clamp B7 is buckled on one side of the upper end of the upper rod 9, and the two fixing screws 6 are locked by nuts 33 after respectively passing through unthreaded holes 35 of two side plates of the U-shaped clamp B7 and two cross arm holes 26 of the upper rod 9; porcelain bottle holes 34 are respectively formed in two sides of the cross arm angle iron B8, and a penetrating rod at the lower end of the porcelain bottle 1 is fixed on the porcelain bottle holes 34 to form a telegraph pole with a single cross arm; two cross arm holes 26 are arranged at the upper end of the upper rod 9 at intervals; one side of the middle part of the cross arm angle iron B8 is provided with a U-shaped clip B7; one side of the middle part of the cross arm angle iron A4 is provided with a U-shaped clamp A5; the U-shaped clamp B7 is buckled on one side of the upper end of the upper rod 9, the U-shaped clamp A5 is buckled on the outer sides of two side plates of the U-shaped clamp B7 from the other side of the upper end of the upper rod 9, and the two fixing screws 6 are locked by nuts 33 after respectively passing through unthreaded holes 35 of the two side plates of the U-shaped clamp A5, the unthreaded holes 35 of the two side plates of the U-shaped clamp B7 and the two cross arm holes 26 of the upper rod 9; porcelain bottle holes 34 are respectively formed in two sides of the cross arm angle iron B8, and a penetrating rod at the lower end of the porcelain bottle 1 is fixed on the porcelain bottle holes 34; porcelain bottle holes 34 are respectively formed in two sides of the cross arm angle iron A4, and a penetrating rod at the lower end of the porcelain bottle 1 is fixed on the porcelain bottle holes 34 to form a telegraph pole with double cross arms.
According to the temporary telegraph pole easy to construct and install, with the help of the attached drawings 1 to 9, the upper pole 9, the lower pole 14 and the control pole 12 can be made of square steel pipes, quadrangle steel pipes, hexagon steel pipes or round steel pipes, the quadrangle steel pipes are preferably used in the application, and the height ranges of the upper pole 9, the lower pole 14 and the control pole 12 are three meters to four meters which are convenient for a vehicle to carry by an electric emergency vehicle; wherein the lower end of the lower pole 14 is provided as an attachment flange 18 depending on the local utility pole practice; or when the cement telegraph pole is rush-repaired, the bottom of the lower pole 14 is provided with a cement casing plate with a middle casing hole, namely the cement casing plate can utilize the original cement telegraph pole; the cross arm angle iron A4U-shaped clamp A5 and the cross arm angle iron B8-shaped clamp B7 which are integrally structured are also carried along with the vehicle, but the porcelain bottles 1 on the cross arm angle iron A4 and the cross arm angle iron B8 can be installed in advance.
When in use, the control rod 12 is connected with the upper rod 9 by using two locking screws 10, the connector 30 of the upper rod 9 is connected with the semicircular connecting seat 11 of the lower rod 14 by using the shaft 13, the connecting hole 24 of the connecting flange 18 of the lower rod 14 is sleeved on the screw rod of the original steel pipe rod foundation cement pile connecting plate 19, and then the control rod is fixed by using the fixing nut 17; or digging out the original cement telegraph pole, penetrating the lower pole 14 into the hole of the cement sheathing board, and then burying, and tamping the buried soil; at this moment, the upper end of the upper rod 9 is attached to the ground 20, some mounting cross arm angle iron A4, cross arm angle iron B8 and the porcelain insulator 1 are lifted, the control rod 12 is pulled down by sleeving the rope on the handle ring 15, the control rod 12 enters the hidden groove 23 of the lower rod 14 at this moment, the two connecting screws 16 and the nuts are used for fixing, and the upper rod 9 climbing the application can fix the electric wire 2 and the porcelain insulator 1.
When the utility model is disassembled, the electric wires 2 are cut off by other telegraph poles, the ropes are controlled by the other side after penetrating into the handle ring 15, then the two connecting screws 16 are taken down and the handle ring 15 is pulled outside, at this time, the upper rod 9 is slowly laid down, the electric wires 2, the porcelain bottles 1, the cross arm angle iron A4 and the cross arm angle iron B8 are taken down, then the control rod 12 and the upper rod 9 are detached, and the lower rod 14 is pulled out for loading.
The present invention is not described in detail in the prior art.

Claims (8)

1. A temporary telegraph pole easy to construct and install comprises a lower pole (14), an upper pole (9), a control rod (12) and a cross arm, and is characterized in that: the upper end face of one side of the lower rod (14) is provided with two semicircular connecting seats (11) at intervals, and the middle part of the other side of the lower rod (14) to the position close to the lower end is provided with a hidden groove (23); the middle part of the end face of the lower end of one side of the upper rod (9) is provided with a connector (30), the lower part of the other side of the upper rod (9) is provided with a hidden fixing groove (28), the connector (30) of the upper rod (9) is inserted into a space (21) between two semicircular connecting seats (11) of the lower rod (14), and a shaft hole B (29) of the connector (30) of the upper rod (9) and a shaft hole A (22) which is respectively arranged on the two semicircular connecting seats (11) of the lower rod (14) are connected through a shaft (13); the upper end of the control rod (12) is fixed in a hidden fixing groove (28) of the upper rod (9), the lower part to the lower end of the control rod (12) is fixed in a hidden groove (23) through a connecting screw (16), and the upper end of the upper rod (9) is provided with a cross arm.
2. A temporary utility pole of claim 1, easy to construct and install, wherein: a connecting flange (18) is provided at the lower end of the lower rod (14).
3. A temporary utility pole of claim 1, easy to construct and install, wherein: two through holes (25) are arranged at the lower part of the hidden groove (23) of the lower rod (14) at intervals, two locking holes (32) are arranged at the lower part of the control rod (12) at intervals, and two connecting screws (16) are locked by nuts after sequentially penetrating through the two through holes (25) of the hidden groove (23) of the lower rod (14) and the two locking holes (32) of the control rod (12).
4. A temporary utility pole of claim 1, easy to construct and install, wherein: two through holes A (27) are respectively arranged at the lower part of the other side of the upper rod (9) corresponding to the two sides of the hidden fixing groove (28); two through holes B (31) are arranged at the upper part of the control rod (12) at intervals; the two locking screws (10) are locked by nuts after passing through the two through holes A (27) of the upper rod (9) and the two through holes B (31) of the control rod (12) respectively.
5. The temporary utility pole of claim 4, easy to construct and install, wherein: a handle ring (15) is arranged at the lower part of the control rod (12) close to the locking hole (32).
6. A temporary utility pole of claim 1, easy to construct and install, wherein: two cross arm holes (26) are arranged at the upper end of the upper rod (9) at intervals; one side of the middle part of the cross arm angle iron B (8) is provided with a U-shaped clamp B (7); the U-shaped clamp B (7) is buckled on one side of the upper end of the upper rod (9), and the two fixing screws (6) are locked by nuts (33) after respectively penetrating through unthreaded holes (35) of two side plates of the U-shaped clamp B (7) and two cross arm holes (26) of the upper rod (9); porcelain insulator holes (34) are respectively formed in two sides of the cross arm angle iron B (8), and a penetrating rod at the lower end of the porcelain insulator (1) is fixed on the porcelain insulator holes (34) to form a telegraph pole with a single cross arm.
7. A temporary utility pole of claim 1, easy to construct and install, wherein: two cross arm holes (26) are arranged at the upper end of the upper rod (9) at intervals; one side of the middle part of the cross arm angle iron B (8) is provided with a U-shaped clamp B (7); one side of the middle part of the cross arm angle iron A (4) is provided with a U-shaped clamp A (5); the U-shaped clamp B (7) is buckled on one side of the upper end of the upper rod (9), the U-shaped clamp A (5) is buckled on the outer sides of two side plates of the U-shaped clamp B (7) through the other side of the upper end of the upper rod (9), and the two fixing screws (6) are locked by nuts (33) after respectively penetrating through unthreaded holes (35) of the two side plates of the U-shaped clamp A (5), unthreaded holes (35) of the two side plates of the U-shaped clamp B (7) and two cross arm holes (26) of the upper rod (9); porcelain bottle holes (34) are respectively formed in two sides of the cross arm angle iron B (8), and a penetrating rod at the lower end of the porcelain bottle (1) is fixed on the porcelain bottle holes (34); porcelain insulator holes (34) are respectively formed in two sides of the cross arm angle iron A (4), and a penetrating rod at the lower end of the porcelain insulator (1) is fixed on the porcelain insulator holes (34) to form a telegraph pole with double cross arms.
8. A temporary utility pole of claim 1, easy to construct and install, wherein: the lower rod (14), the upper rod (9) and the control rod (12) are of hollow structures, and the upper end of the upper rod (9) is provided with an end plate (3).
CN202210864765.4A 2022-07-22 2022-07-22 Temporary telegraph pole easy to construct and install Active CN115045558B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210864765.4A CN115045558B (en) 2022-07-22 2022-07-22 Temporary telegraph pole easy to construct and install

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210864765.4A CN115045558B (en) 2022-07-22 2022-07-22 Temporary telegraph pole easy to construct and install

Publications (2)

Publication Number Publication Date
CN115045558A true CN115045558A (en) 2022-09-13
CN115045558B CN115045558B (en) 2024-03-12

Family

ID=83166548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210864765.4A Active CN115045558B (en) 2022-07-22 2022-07-22 Temporary telegraph pole easy to construct and install

Country Status (1)

Country Link
CN (1) CN115045558B (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200357685Y1 (en) * 2004-04-27 2004-07-30 양희성 A
CN204012562U (en) * 2014-06-11 2014-12-10 国家电网公司 A kind of New-style electrical wire bar distribution line gold utensil
CN104671091A (en) * 2015-02-15 2015-06-03 中国石油集团西部钻探工程有限公司 Hoisting draw stay bar
CN105421868A (en) * 2015-10-29 2016-03-23 国网山东临朐县供电公司 Low-voltage glass fiber reinforced plastic overhead circuit cross arm
JP3204989U (en) * 2016-04-13 2016-06-30 敏雄 森田 Temporary utility pole installation collection device
CN106193757A (en) * 2016-08-26 2016-12-07 汤巴斯科技有限公司 Compound first-aid repairing rod
KR20170013066A (en) * 2015-07-27 2017-02-06 주식회사 삼은통신 Prefabricated steel pole for optical cable
TWM540887U (en) * 2017-01-09 2017-05-01 Long Sight Wire Duct Co Ltd Connection structure for bracket and oblique support
CN106786138A (en) * 2016-12-08 2017-05-31 国家电网公司 High-voltage power transmission tower overhead ground wire rotates arm elevator apparatus
CN108321563A (en) * 2018-03-01 2018-07-24 国网湖北省电力公司宜昌供电公司 A kind of ground connection collet easy to use
CN110847684A (en) * 2019-11-28 2020-02-28 安徽省徽源电杆有限公司 Folding wire pole
CN211229749U (en) * 2019-11-29 2020-08-11 河南固强电力器材有限公司 Fixing piece for preventing cross arm from falling off
CN213274038U (en) * 2020-11-27 2021-05-25 王智福 Measuring device for rail transit construction

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200357685Y1 (en) * 2004-04-27 2004-07-30 양희성 A
CN204012562U (en) * 2014-06-11 2014-12-10 国家电网公司 A kind of New-style electrical wire bar distribution line gold utensil
CN104671091A (en) * 2015-02-15 2015-06-03 中国石油集团西部钻探工程有限公司 Hoisting draw stay bar
KR20170013066A (en) * 2015-07-27 2017-02-06 주식회사 삼은통신 Prefabricated steel pole for optical cable
CN105421868A (en) * 2015-10-29 2016-03-23 国网山东临朐县供电公司 Low-voltage glass fiber reinforced plastic overhead circuit cross arm
JP3204989U (en) * 2016-04-13 2016-06-30 敏雄 森田 Temporary utility pole installation collection device
CN106193757A (en) * 2016-08-26 2016-12-07 汤巴斯科技有限公司 Compound first-aid repairing rod
CN106786138A (en) * 2016-12-08 2017-05-31 国家电网公司 High-voltage power transmission tower overhead ground wire rotates arm elevator apparatus
TWM540887U (en) * 2017-01-09 2017-05-01 Long Sight Wire Duct Co Ltd Connection structure for bracket and oblique support
CN108321563A (en) * 2018-03-01 2018-07-24 国网湖北省电力公司宜昌供电公司 A kind of ground connection collet easy to use
CN110847684A (en) * 2019-11-28 2020-02-28 安徽省徽源电杆有限公司 Folding wire pole
CN211229749U (en) * 2019-11-29 2020-08-11 河南固强电力器材有限公司 Fixing piece for preventing cross arm from falling off
CN213274038U (en) * 2020-11-27 2021-05-25 王智福 Measuring device for rail transit construction

Also Published As

Publication number Publication date
CN115045558B (en) 2024-03-12

Similar Documents

Publication Publication Date Title
KR100876127B1 (en) Street light foundation
CN102733640B (en) Base used for fixedly installing light pole, telegraph pole and high-tension wire tower and installation method thereof
KR100945561B1 (en) Method and apparatus for constructing pole of tower-type facilities
CN105298205B (en) A kind of power network electric pole reinforces heightening device and its construction method
CN111795212B (en) Suspension method and suspension structure for pipeline crossing foundation pit
CN105350816A (en) Power grid telegraph pole strengthening and heightening device and construction method thereof
CN115045558A (en) Interim wire pole of easy construction installation
KR200433150Y1 (en) upholder for street lamppost
CN210031489U (en) Stool type bracket capping beam support
CN116517016A (en) Traffic facility foundation fixing device with embedded bolts
CN208266866U (en) A kind of wind resistance steady type guy anchor
KR100523556B1 (en) A structure for supporting a electric light plate
CN211572817U (en) Low-voltage distribution line supporting rod
CN209179594U (en) For low-voltage distributing line temporary repair electric pole
CN210530504U (en) Multifunctional protective railing for construction site
CN107642102B (en) A kind of damping electric pole
CN102957113B (en) Decoration construction temporary power construction system
CN201649003U (en) Active powder concrete column and steel pipe combination rail structure
CN221298819U (en) Windproof fence
CN114221276B (en) Bury high tension cable protection device that passes a bridge
CN213734639U (en) Intelligent parking area is with filling electric pile protection component
CN217106405U (en) High-stability transmission line iron tower
CN210517719U (en) Large-gradient cable truss structure
CN218540431U (en) Safety protection platform equipment suitable for construction of pier column in water
CN212063439U (en) Municipal works road laying structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant