CN115031521A CN202210549107.6A CN202210549107A CN115031521A CN 115031521 A CN115031521 A CN 115031521A CN 202210549107 A CN202210549107 A CN 202210549107A CN 115031521 A CN115031521 A CN 115031521A
Authority
CN
China
Prior art keywords
movable
spring
shell
support frame
air
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210549107.6A
Other languages
Chinese (zh)
Other versions
CN115031521B (en
Inventor
段米英
夏琪
倪兵怀
吴志坚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Kesen Construction Technology Co ltd
Original Assignee
Jiangxi Kesen Construction Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Kesen Construction Technology Co ltd filed Critical Jiangxi Kesen Construction Technology Co ltd
Priority to CN202210549107.6A priority Critical patent/CN115031521B/en
Publication of CN115031521A publication Critical patent/CN115031521A/en
Application granted granted Critical
Publication of CN115031521B publication Critical patent/CN115031521B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F26DRYING
    • F26BDRYING SOLID MATERIALS OR OBJECTS BY REMOVING LIQUID THEREFROM
    • F26B21/00Arrangements or duct systems, e.g. in combination with pallet boxes, for supplying and controlling air or gases for drying solid materials or objects
    • F26B21/004Nozzle assemblies; Air knives; Air distributors; Blow boxes
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F26DRYING
    • F26BDRYING SOLID MATERIALS OR OBJECTS BY REMOVING LIQUID THEREFROM
    • F26B25/00Details of general application not covered by group F26B21/00 or F26B23/00

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Drying Of Solid Materials (AREA)

Abstract

The invention relates to an air drying device, in particular to an integrally-formed cement slurry air drying device for wall pouring. The invention aims to provide an integrally-formed wall body pouring cement slurry air-drying device which can reduce waiting time and prevent a wall body from cracking. The invention provides an integrally-formed cement slurry air-drying device for wall pouring, which comprises a support frame, universal wheels, handles, a shell, a cover plate and the like, wherein the left side and the right side of the bottom of the support frame are respectively connected with the universal wheels for moving in a front-back symmetrical and rotating mode, the rear side of the top of the support frame is connected with the handles, the top of the support frame is connected with the shell, and the cover plate is arranged on the top of the shell. According to the invention, the first movable rod is pulled to rotate, so that the movable plate does not block the air outlet groove any more, and the fan can blow cold air to the wall body by opening the refrigeration pipe and the fan, so that the wall body is dried, the wall body is dried quickly, and the waiting time of people is reduced.

Description

Integrated into one piece formula wall body is pour and is air-dried device with cement paste
Technical Field
The invention relates to an air drying device, in particular to an integrally-formed cement slurry air drying device for wall pouring.
Background
At present, the main mode of adopting when the wall body of building is built has the building block to pile up and the integral casting, and wherein the efficiency of construction, wholeness, result of use etc. of integral casting wall body all will be superior to the mode that the building block was piled up for people are when building the wall body, and the major part all can adopt integrated into one piece formula wall body, accelerates the time limit for a project progress with this.
At present, people need wait for longer time usually to make grout accomplish natural air drying after accomplishing integrated into one piece formula wall body and pour, lead to whole process longer, in the air-dry process, the crack appears easily in the wall body moreover, leads to the wall body unstable, and the follow-up wall body that arouses easily collapses.
Therefore, aiming at the defects, the integrally-formed wall body pouring cement slurry air-drying device capable of reducing waiting time and preventing the wall body from cracking is provided.
Disclosure of Invention
In order to overcome the defects that people need to wait for a long time for natural air drying after the integrally-formed wall is poured and cracks are easy to appear on the wall in the air drying process, the invention aims to provide the integrally-formed wall pouring cement paste air drying device which can reduce the waiting time and prevent the wall from cracking.
The invention is realized by the following technical approaches:
the utility model provides an integrated into one piece formula wall body is pour and is air-dried device with cement mortar, which comprises a supporting rack, the universal wheel, the handle, a housing, the apron, the fan, refrigerating mechanism, chucking mechanism and the mechanism that waters, the equal front and back symmetry rotary type in support frame bottom left and right sides is connected with the universal wheel that is used for removing, support frame top rear side is connected with the handle, the support frame top is connected with the shell, the apron has been placed at the shell top, the anterior interval connection of shell has six fans that are used for blowing, the inside refrigerating mechanism that is used for air cooling that is equipped with of shell, the shell bottom is equipped with the chucking mechanism that is used for blocking the effect, the inside mechanism that waters that is used for the wall body water spray that is equipped with of shell.
Further, refrigerating mechanism is including the refrigeration pipe, a supporting plate, first pivot, the fly leaf, first movable rod and torsional spring, the equal interval connection in both sides has the refrigeration pipe about the shell is inside, both sides all are connected with the backup pad around the inside right side of shell, it has three air outlet groove all to separate on the backup pad, equal rotary type is connected with first pivot in the backup pad, equal interval connection has three fly leaf in the first pivot, the fly leaf all blocks adjacent air outlet groove, first pivot downside all is connected with first movable rod, all be connected with the torsional spring between first movable rod top and the shell, left torsional spring is around in left first pivot, the torsional spring on right side is around in the first pivot on right side.
Further, the clamping mechanism comprises support columns, movable buckles and first springs, the support columns are connected to the front sides of the left side and the right side of the bottom of the shell, the movable buckles are connected to the lower portions of the support columns in a sliding mode, the first movable rods can be in contact with the movable buckles when rotating, and the bottoms of the movable buckles on the left side and the right side are respectively connected with the first springs between the support columns on the left side and the right side.
It is further explained that the mechanism of watering includes the water pipe, the shower nozzle, the storage water tank, first spacing post, adjustable shelf and second spring, the inside upside front portion of shell is connected with the water pipe, shell front side middle part upside is connected with the shower nozzle, water pipe upper end and shower nozzle intercommunication, bottom rear side middle part is connected with the storage water tank in the shell, open at the storage water tank top has two intake troughs, the equal sliding type in both sides of the left and right sides of shell lower part rear side is connected with first spacing post, be connected with the adjustable shelf between the first spacing post rear side, adjustable shelf and shell sliding type are connected, the adjustable shelf front portion is connected with the inside sliding type of storage water tank, all around having the second spring on the first spacing post, the one end of second spring all is connected with the shell, the other end of second spring all is connected with the adjustable shelf.
Further explaining, still including being used for fixed brake mechanism, brake mechanism is including the spacing post of second, movable block and third spring, and the left and right sides of support frame lower part rear side all is connected with the spacing post of second, and the slidingtype is connected with the movable block between the spacing post of second, and the movable block is connected with the support frame slidingtype, and the spacing post upside of second all is around having the third spring, and the one end of third spring all is connected with the movable block, and the other end of third spring all is connected with the support frame.
Further, the lifting mechanism is used for enabling the movable block to move upwards, and comprises a third limiting column, a second movable rod, a fourth spring, a second rotating shaft and a third movable rod, wherein the left side and the right side of the rear side of the bottom of the support frame are both connected with the third limiting column, the third limiting column is connected with the second movable rod in a sliding mode, the fourth spring is connected between the second movable rod and the rear side of the bottom of the support frame, the left fourth spring is wound on the left third limiting column, the right fourth spring is wound on the right third limiting column, the upper side of the second movable rod is connected with the second rotating shaft in a rotating mode, the third movable rod is connected between the two second rotating shafts in a sliding mode, and the third movable rod is in contact with the support frame.
Further explaining, the device also comprises a prying mechanism used for moving the movable frame, the prying mechanism comprises a supporting block, a fourth limit column and a U-shaped rod, the fourth spring is wound on the fourth limiting column on the right side, the support frame is connected with the fourth movable rod in a rotating mode in the middle of the left side and the right side in a rotating mode, the upper side of the fourth movable rod is in contact with the movable frame, the left side and the right side of the U-shaped rod are in rotating mode, the third rotating shaft is connected with the left movable rod and the right movable rod in a rotating mode, and the lower side of the fourth movable rod on the left side and the right side is in sliding mode connection with the third rotating shaft on the left side and the right side.
Further, the bottoms of the first movable rods are provided with grooves.
The invention provides an integrally-formed cement slurry air-drying device for wall pouring, which has the advantages that:
1. according to the invention, the first movable rod is pulled to rotate, so that the movable plate does not block the air outlet groove any more, and the fan can blow cold air to the wall body by opening the refrigeration pipe and the fan, so that the wall body is dried, the wall body is dried quickly, and the waiting time of people is reduced.
2. According to the invention, clear water is added into the middle part of the shell, and the movable frame is loosened, so that the movable frame can extrude clear water in the water storage tank to flow into the spray head through the water pipe, and the clear water is sprayed on the wall body through the spray head, and further, the crack of the wall body due to over-drying can be prevented.
3. Under the action of the movable block, the movable block is in contact with the ground, so that the friction force between the movable block and the ground can be increased, and the integrally-formed cement paste air-drying device for wall pouring is fixed.
4. According to the invention, the fourth movable rod can extrude the movable frame to move backwards by kicking the U-shaped rod to move forwards, so that the operation of people is facilitated.
Drawings
Fig. 1 is a schematic perspective view of the present invention.
Fig. 2 is a partial perspective view of the present invention.
Fig. 3 is a schematic sectional perspective view of the refrigeration mechanism of the present invention.
Fig. 4 is an enlarged schematic perspective view of the invention at a.
Fig. 5 is a schematic perspective view of the chucking mechanism of the present invention.
Fig. 6 is a schematic cross-sectional three-dimensional structure diagram of the chucking mechanism of the present invention.
Fig. 7 is an enlarged schematic perspective view of the position B of the present invention.
Fig. 8 is a schematic perspective view of the watering mechanism of the present invention.
Fig. 9 is a schematic sectional three-dimensional structure of the watering mechanism of the present invention.
Fig. 10 is an enlarged perspective view of the present invention at C.
Fig. 11 is a schematic perspective view of the brake mechanism of the present invention.
Fig. 12 is a schematic partial perspective view of the brake mechanism of the present invention.
Fig. 13 is an enlarged schematic perspective view of the invention at D.
FIG. 14 is a schematic view of a first partial structure of the lifting mechanism of the present invention.
FIG. 15 is a schematic diagram of a second partial structure of the lifting mechanism of the present invention.
Fig. 16 is a schematic view of a first partially assembled structure of the prying mechanism of the present invention.
Fig. 17 is a schematic view of a second partially separated body structure of the prying mechanism of the invention.
Reference numbers in the figures: 1: support frame, 2: universal wheel, 3: handle, 4: a housing, 401: cover plate, 5: a fan, 6: refrigeration mechanism, 61: refrigeration pipe, 62: support plate, 63: first rotating shaft, 64: a movable plate, 65: first movable bar, 66: torsion spring, 67: air outlet groove, 7: chucking mechanism, 71: support column, 72: movable buckle, 73: first spring, 74: groove, 8: watering mechanism, 81: water pipe, 82: head, 83: water storage tank, 84: water inlet tank, 85: first stopper post, 86: movable frame, 87: second spring, 9: brake mechanism, 91: second limit post, 92: movable block, 93: third spring, 10: lifting mechanism, 101: third limit post, 102: second movable bar, 103: fourth spring, 104: second rotation shaft, 105: third movable bar, 11: prying mechanism, 111: support block, 112: fourth limit post, 113: u-shaped bar, 114: fifth spring, 115: third shaft, 116: and a fourth movable rod.
Detailed Description
The invention is further explained by combining the drawings in the specification, and the embodiments of the invention are given by combining the drawings in the specification.
Example 1
An integrally formed cement mortar air-drying device for wall pouring comprises a support frame 1, universal wheels 2, a handle 3, a shell 4, a cover plate 401, a fan 5, a refrigerating mechanism 6, a clamping mechanism 7 and a watering mechanism 8, wherein the universal wheels 2 are rotationally connected on the left side and the right side of the bottom of the support frame 1 in a front-back symmetrical manner as shown in figures 1-10, under the action of the universal wheels 2, the integrally formed cement slurry air-drying device for wall pouring can be conveniently moved, the rear side of the top of the support frame 1 is connected with a handle 3, the top of the support frame 1 is connected with a shell 4, the top of the shell 4 is provided with a cover plate 401, the front part of the shell 4 is bolted with six fans 5 at intervals, open through fan 5, can blow cold air to the wall body, the inside refrigerating mechanism 6 that is equipped with of shell 4, shell 4 bottom is equipped with chucking mechanism 7, and the inside mechanism 8 that waters that is equipped with of shell 4.
The refrigerating mechanism 6 includes a refrigerating pipe 61, a support plate 62, a first rotating shaft 63, a flap plate 64, a first movable lever 65, and a torsion spring 66, as shown in fig. 3 and 4, the refrigerating pipe 61 is bolted at intervals on both left and right sides inside the housing 4, open through refrigeration pipe 61, can refrigerate the air, both sides all are connected with backup pad 62 around the inside right side of shell 4, equal spaced apart has three play air groove 67 on two backup pads 62, equal rotary type is connected with first pivot 63 on two backup pads 62, equal spaced connection has three fly leaf 64 on two first pivots 63, six fly leaf 64 all block adjacent play air groove 67, two first pivot 63 downside all are connected with first movable rod 65, all be connected with torsional spring 66 between two first movable rod 65 tops and the shell 4, left torsional spring 66 is around on left first pivot 63, torsional spring 66 on right side is around on the first pivot 63 on right side.
The clamping mechanism 7 comprises supporting columns 71, movable buckles 72 and first springs 73, as shown in fig. 5, 6 and 7, the supporting columns 71 are welded on the front sides of the left side and the right side of the bottom of the shell 4, the movable buckles 72 are connected on the lower portions of the two supporting columns 71 in a sliding mode, the first movable rods 65 are clamped through the movable buckles 72 and can be fixed, the first movable rods 65 can be in contact with the movable buckles 72 when rotating, the first springs 73 are connected between the bottoms of the movable buckles 72 on the left side and the right side and the supporting columns 71 on the left side and the right side respectively, and grooves 74 are formed in the bottoms of the two first movable rods 65.
The watering mechanism 8 comprises a water pipe 81, a spray head 82, a water storage tank 83, a first limit column 85, a movable frame 86 and a second spring 87, as shown in fig. 8, 9 and 10, the water pipe 81 is connected with the front part of the upper side in the shell 4, the spray head 82 is bolted on the upper side of the middle part of the front side of the shell 4, clear water is sprayed on the wall body through the spray head 82, the wall body can be prevented from cracking due to over drying, the upper end of the water pipe 81 is communicated with the spray head 82, the water storage tank 83 is connected with the middle part of the rear side of the bottom in the shell 4, two water inlet grooves 84 are arranged at the top of the water storage tank 83, the first limit column 85 is connected with the left side and the right side of the rear side of the lower part of the shell 4 in a sliding way, the movable frame 86 is connected with the shell 4 in a sliding way, the front part of the movable frame 86 is connected with the inner part of the water storage tank 83 in a sliding way, the second spring 87 is wound on the two first limit columns 85, one ends of the two second springs 87 are connected to the housing 4, and the other ends of the two second springs 87 are connected to the movable frame 86.
When people need to use the integrally formed cement paste air-drying device for wall pouring, firstly, the handle 3 is pushed to move, under the action of the universal wheel 2, the integrally formed cement paste air-drying device for wall pouring is driven to move to a specified position, the fan 5 faces to a wall body, then the handle 3 is loosened, the cover plate 401 is taken down, then clean water is added into the middle of the shell 4, the clean water flows into the water storage tank 83 through the water inlet groove 84, then the cover plate 401 is put back to the original position, then the first movable rod 65 is pulled to rotate, so that the first rotating shaft 63 and the movable plate 64 are driven to rotate, the torsion spring 66 deforms, the movable plate 64 no longer blocks the air outlet groove 67, when the first movable rod 65 is in contact with the movable buckle 72, the first movable rod 65 extrudes the movable buckle 72 to move downwards, the first spring 73 is compressed, and when the movable buckle 72 is aligned with the groove 74, the first spring 73 restores to the original state, the first spring 73 drives the movable buckle 72 to move upwards to reset, so that the movable buckle 72 is clamped on the first movable rod 65, the first movable rod 65 is loosened, then the refrigerating pipe 61 and the fan 5 are opened, the refrigerating pipe 61 refrigerates air in the shell 4, the fan 5 draws out cold air through the air outlet groove 67 and blows the cold air to the wall, and then the wall is air-dried, during the period, people can pull the movable frame 86 to move backwards, the second spring 87 stretches, when the movable frame 86 moves to the rear lower part of the front side water inlet groove 84, clean water in the shell 4 flows into the front part of the inner side of the water storage tank 83 through the front side water inlet groove 84, then the movable frame 86 is loosened, the second spring 87 restores the original state, the second spring 87 drives the movable frame 86 to move forwards to reset, so that the movable frame 86 extrudes clean water in the front part of the inner side of the water storage tank 83 to flow into the spray head 82 through the water pipe 81, and clean water is sprayed on the wall through the spray head 82, and further preventing the wall from cracking due to over-drying, after the wall is air-dried, closing the cooling pipe 61 and the fan 5, and then pushing the first movable rod 65 to rotate reversely, so as to drive the first rotating shaft 63 and the movable plate 64 to rotate reversely, so that the first movable rod 65 extrudes the movable buckle 72 to move downwards, compressing the first spring 73, so as to enable the movable buckle 72 to loosen the first movable rod 65, then loosen the first movable rod 65, restoring the torsion spring 66 to the original state, driving the first movable rod 65, the first rotating shaft 63 and the movable plate 64 to rotate reversely and restore by the torsion spring 66, so as to enable the movable plate 64 to block the air outlet groove 67 again, when the first movable rod 65 is separated from the movable buckle 72, restoring the first spring 73 to the original state, driving the movable buckle 72 to move upwards and restore by the first spring 73, and then pushing the integrally-formed wall pouring cement slurry air-drying device from the designated position.
Example 2
On the basis of embodiment 1, the integrated wall body casting cement slurry air-drying device further comprises a brake mechanism 9, wherein the brake mechanism 9 comprises a second limiting column 91, a movable block 92 and a third spring 93, as shown in fig. 1, fig. 2, fig. 11, fig. 12 and fig. 13, the second limiting columns 91 are welded on the left side and the right side of the rear side of the lower portion of the support frame 1, the movable block 92 is connected between the two second limiting columns 91 in a sliding mode, the movable block 92 is in contact with the ground through the movable block 92, the integrated wall body casting cement slurry air-drying device can be fixed, the movable block 92 is connected with the support frame 1 in a sliding mode, the third spring 93 is wound on the upper sides of the two second limiting columns 91, one ends of the two third springs 93 are connected with the movable block 92, and the other ends of the two third springs 93 are connected with the support frame 1.
The lifting mechanism 10 comprises third limiting columns 101, second movable rods 102, fourth springs 103, second rotating shafts 104 and third movable rods 105, as shown in fig. 2, 14 and 15, the third limiting columns 101 are welded on the left and right sides of the rear side of the bottom of the support frame 1, the second movable rods 102 are connected on the two third limiting columns 101 in a sliding manner, the fourth springs 103 are connected between the two second movable rods 102 and the rear side of the bottom of the support frame 1, the fourth springs 103 on the left side are wound on the third limiting columns 101 on the left side, the fourth springs 103 on the right side are wound on the third limiting columns 101 on the right side, the second rotating shafts 104 are connected on the upper sides of the two second movable rods 102 in a rotating manner, and the third movable rods 105 are connected between the two second rotating shafts 104 in a sliding manner, the movable block 92 can be moved upward by pulling the third movable bar 105 to rotate, and the third movable bar 105 is in contact with the support frame 1.
In the initial state, the movable block 92 contacts the ground, when people need to move the integrally formed wall body pouring cement slurry air-drying device, the third movable rod 105 is firstly pulled to rotate, the third movable rod 105 pulls the second rotating shaft 104 to move upwards, so as to drive the second movable rod 102 to move upwards, the fourth spring 103 is compressed, the second movable rod 102 extrudes the movable block 92 to move upwards, the third spring 93 is compressed, so as to separate the movable block 92 from the ground, then the third movable rod 105 is pushed to move forwards, so that the third movable rod 105 is clamped on the support frame 1 in a horizontal state, then the third movable rod 105 is released, then people can move the integrally formed wall body pouring cement slurry air-drying device, when the integrally formed wall body pouring cement slurry air-drying device stops moving, the third movable rod 105 is pulled to move backwards, and then the third movable rod 105 is pulled to rotate reversely to reset, then, the third movable rod 105 is loosened, the fourth spring 103 is restored, the fourth spring 103 drives the second movable rod 102 and the second rotating shaft 104 to move downwards to reset, when the second movable rod 102 is separated from the movable block 92, the third spring 93 is restored, the third spring 93 drives the movable block 92 to move downwards to reset, the movable block 92 is in contact with the ground, and therefore friction force between the movable block and the ground is increased, and the integrally-formed wall body pouring cement mortar air-drying device is further fixed to prevent the integrally-formed wall body pouring cement mortar air-drying device from moving.
The lifting mechanism 11 further comprises a lifting mechanism 11, the lifting mechanism 11 comprises a supporting block 111, a fourth limiting column 112, a U-shaped rod 113, a fifth spring 114, a third rotating shaft 115 and a fourth movable rod 116, as shown in fig. 2, 16 and 17, the supporting block 111 is welded on the left side and the right side of the rear side of the bottom of the support frame 1, the supporting block 111 is located on the front side of the second movable rod 102, the fourth limiting column 112 is connected on the two supporting blocks 111 in a sliding manner, the U-shaped rod 113 is connected between the two fourth limiting columns 112, the movable frame 86 can move backwards by kicking the U-shaped rod 113, the fifth spring 114 is connected between the rear sides of the two supporting blocks 111 and the U-shaped rod 113, the fifth spring 114 on the left side is wound on the fourth limiting column 112 on the left side, the fifth spring 114 on the right side is wound on the fourth limiting column 112 on the right side, the left side and the right side of the middle part of the support frame 1 are rotatably connected with the fourth movable rod 116, the upper sides of the two fourth movable rods 116 are both in contact with the movable frame 86, the left and right sides of the front side of the U-shaped rod 113 are both rotatably connected with third rotating shafts 115, and the lower sides of the left and right fourth movable rods 116 are respectively slidably connected with the left and right third rotating shafts 115.
When people need to pull the movable frame 86 to move backwards, the U-shaped rod 113 can be kicked to move forwards, the fifth spring 114 is compressed, so that the third rotating shaft 115 is driven to move forwards, the third rotating shaft 115 is driven to extrude the fourth movable rod 116 to rotate, the fourth movable rod 116 is driven to extrude the movable frame 86 to move backwards, and further the operation of people is facilitated.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention.

Claims (8)

1. An integrally formed cement slurry air drying device for wall pouring comprises a support frame (1), universal wheels (2), handles (3), a shell (4), a cover plate (401) and fans (5), wherein the left side and the right side of the bottom of the support frame (1) are respectively connected with the universal wheels (2) used for moving in a front-back symmetrical and rotating mode, the rear side of the top of the support frame (1) is connected with the handles (3), the top of the support frame (1) is connected with the shell (4), the cover plate (401) is placed at the top of the shell (4), the front part of the shell (4) is connected with six fans (5) used for blowing at intervals, the integrally formed cement slurry air drying device is characterized by further comprising a refrigerating mechanism (6), a clamping mechanism (7) and a watering mechanism (8), the refrigerating mechanism (6) used for refrigerating air is arranged inside the shell (4), the clamping mechanism (7) used for clamping is arranged at the bottom of the shell (4), a watering mechanism (8) for spraying water to the wall body is arranged in the shell (4).
2. The cement mortar air drying device for pouring the integrally formed wall body as claimed in claim 1, wherein the refrigerating mechanism (6) comprises refrigerating pipes (61), a support plate (62), a first rotating shaft (63), movable plates (64), a first movable rod (65) and a torsion spring (66), the refrigerating pipes (61) are connected to the left side and the right side of the inside of the casing (4) at intervals, the support plates (62) are connected to the front side and the rear side of the right side of the inside of the casing (4), three air outlet grooves (67) are formed in the support plates (62) at intervals, the first rotating shaft (63) is rotatably connected to the support plates (62), the three movable plates (64) are connected to the first rotating shaft (63) at intervals, the adjacent air outlet grooves (67) are blocked by the movable plates (64), the first movable rod (65) is connected to the lower side of the first rotating shaft (63), the torsion spring (66) is connected between the top of the first movable rod (65) and the casing (4), the left torsion spring (66) is wound on the left first rotating shaft (63), and the right torsion spring (66) is wound on the right first rotating shaft (63).
3. The cement mortar air-drying device for pouring the integrally-formed wall body as claimed in claim 2, wherein the clamping mechanism (7) comprises a support column (71), movable buckles (72) and first springs (73), the support column (71) is connected to the front sides of the left side and the right side of the bottom of the shell (4), the movable buckles (72) are connected to the lower portions of the support columns (71) in a sliding mode, the first movable rods (65) can be in contact with the movable buckles (72) when rotating, and the first springs (73) are connected between the bottoms of the movable buckles (72) on the left side and the bottom of the support columns (71) on the left side and the right side respectively.
4. The cement slurry air-drying device for integrally formed wall pouring as claimed in claim 3, wherein the watering mechanism (8) comprises a water pipe (81), a spray head (82), a water storage tank (83), a first limit column (85), a movable frame (86) and a second spring (87), the water pipe (81) is connected to the front part of the upper side inside the shell (4), the spray head (82) is connected to the upper side of the middle part of the front side of the shell (4), the upper end of the water pipe (81) is communicated with the spray head (82), the water storage tank (83) is connected to the middle part of the rear side of the bottom inside the shell (4), two water inlet grooves (84) are formed in the top of the water storage tank (83), the first limit column (85) is connected to the left side and the right side of the rear side of the lower part of the shell (4) in a sliding manner, the movable frame (86) is connected between the rear sides of the first limit columns (85), and the movable frame (86) is connected with the shell (4) in a sliding manner, the front part of the movable frame (86) is connected with the inside of the water storage tank (83) in a sliding manner, a first limiting column (85) is wound with a second spring (87), one end of the second spring (87) is connected with the shell (4), and the other end of the second spring (87) is connected with the movable frame (86).
5. The cement slurry air-drying device for the integrally-formed wall body pouring as claimed in claim 4, wherein the device further comprises a brake mechanism (9) for fixing, the brake mechanism (9) comprises a second limiting column (91), a movable block (92) and a third spring (93), the second limiting column (91) is connected to the left side and the right side of the rear side of the lower portion of the support frame (1), the movable block (92) is connected between the second limiting columns (91) in a sliding manner, the movable block (92) is connected with the support frame (1) in a sliding manner, the third spring (93) is wound on the upper side of the second limiting column (91), one end of the third spring (93) is connected with the movable block (92), and the other end of the third spring (93) is connected with the support frame (1).
6. The grout air-drying device for pouring the integrally formed wall body according to claim 5, which is characterized by further comprising a lifting mechanism (10) for enabling the movable block (92) to move upwards, wherein the lifting mechanism (10) comprises a third limiting column (101), a second movable rod (102), a fourth spring (103), a second rotating shaft (104) and a third movable rod (105), the left side and the right side of the rear side of the bottom of the support frame (1) are respectively connected with the third limiting column (101), the third limiting column (101) is respectively connected with the second movable rod (102) in a sliding manner, the fourth spring (103) is respectively connected between the second movable rod (102) and the rear side of the bottom of the support frame (1), the fourth spring (103) on the left side is wound on the third limiting column (101) on the left side, the fourth spring (103) on the right side is wound on the third limiting column (101) on the right side, and the second rotating shaft (104) is respectively connected with the upper side of the second movable rod (102), a third movable rod (105) is connected between the two second rotating shafts (104) in a sliding manner, and the third movable rod (105) is in contact with the support frame (1).
7. The cement mortar air-drying device for pouring the integrally formed wall body as claimed in claim 6, characterized by further comprising a prying mechanism (11) for moving the movable frame (86), wherein the prying mechanism (11) comprises a supporting block (111), a fourth limiting column (112), a U-shaped rod (113), a fifth spring (114), a third rotating shaft (115) and a fourth movable rod (116), the supporting block (111) is connected to the left and right sides of the rear side of the bottom of the supporting frame (1), the supporting block (111) is positioned at the front side of the second movable rod (102), the fourth limiting column (112) is connected to the supporting block (111) in a sliding manner, the U-shaped rod (113) is connected between the fourth limiting columns (112), the fifth spring (114) is connected between the rear side of the supporting block (111) and the U-shaped rod (113), the fifth spring (114) on the left side is wound on the fourth limiting column (112) on the left side, the fifth spring (114) on the right side is wound on the fourth limiting column (112) on the right side, the left side and the right side of the middle of the support frame (1) are connected with a fourth movable rod (116) in a rotating mode, the upper side of the fourth movable rod (116) is in contact with the movable frame (86), the left side and the right side of the front side of the U-shaped rod (113) are connected with a third rotating shaft (115) in a rotating mode, and the lower sides of the fourth movable rods (116) on the left side and the right side are connected with the third rotating shafts (115) on the left side and the right side in a sliding mode respectively.
8. A unit for drying grout for casting of walls as claimed in claim 3 wherein the first movable bar (65) is recessed (74) at its bottom.
CN202210549107.6A 2022-05-20 2022-05-20 Cement paste air-dries device for integrated into one piece formula wall body pouring Active CN115031521B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210549107.6A CN115031521B (en) 2022-05-20 2022-05-20 Cement paste air-dries device for integrated into one piece formula wall body pouring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210549107.6A CN115031521B (en) 2022-05-20 2022-05-20 Cement paste air-dries device for integrated into one piece formula wall body pouring

Publications (2)

Publication Number Publication Date
CN115031521A true CN115031521A (en) 2022-09-09
CN115031521B CN115031521B (en) 2023-06-06

Family

ID=83120685

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210549107.6A Active CN115031521B (en) 2022-05-20 2022-05-20 Cement paste air-dries device for integrated into one piece formula wall body pouring

Country Status (1)

Country Link
CN (1) CN115031521B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3164068U (en) * 2010-08-31 2010-11-11 東北自興株式会社 Curing room for secondary concrete products
CN107289761A (en) * 2017-07-25 2017-10-24 苏州宸浩纺织科技有限公司 A kind of woven cotton yarn drying plant
CN107639728A (en) * 2017-11-07 2018-01-30 佛山市达普光机电科技有限公司 A kind of concrete water seasoning device
CN108412170A (en) * 2018-03-07 2018-08-17 谢晓辉 Apparatus for drying after a kind of wall plaster
CN211876243U (en) * 2020-03-13 2020-11-06 深圳市科瑞昌机电设备有限公司 Multifunctional air conditioner with energy saving and environmental protection functions
CN212771223U (en) * 2020-05-29 2021-03-23 青岛华尊机械股份有限公司 Yarn storage rack of water-jet loom
CN214537309U (en) * 2021-04-13 2021-10-29 广东鑫泰洋实业有限公司 Quick drying device of concrete wall
CN114452423A (en) * 2022-02-21 2022-05-10 郭良明 Comprehensive disinfection device for body-worn isolation clothes
CN114482471A (en) * 2022-01-19 2022-05-13 深圳市爱善天使电子商务有限公司 Wall paint smearing equipment for building construction

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3164068U (en) * 2010-08-31 2010-11-11 東北自興株式会社 Curing room for secondary concrete products
CN107289761A (en) * 2017-07-25 2017-10-24 苏州宸浩纺织科技有限公司 A kind of woven cotton yarn drying plant
CN107639728A (en) * 2017-11-07 2018-01-30 佛山市达普光机电科技有限公司 A kind of concrete water seasoning device
CN108412170A (en) * 2018-03-07 2018-08-17 谢晓辉 Apparatus for drying after a kind of wall plaster
CN211876243U (en) * 2020-03-13 2020-11-06 深圳市科瑞昌机电设备有限公司 Multifunctional air conditioner with energy saving and environmental protection functions
CN212771223U (en) * 2020-05-29 2021-03-23 青岛华尊机械股份有限公司 Yarn storage rack of water-jet loom
CN214537309U (en) * 2021-04-13 2021-10-29 广东鑫泰洋实业有限公司 Quick drying device of concrete wall
CN114482471A (en) * 2022-01-19 2022-05-13 深圳市爱善天使电子商务有限公司 Wall paint smearing equipment for building construction
CN114452423A (en) * 2022-02-21 2022-05-10 郭良明 Comprehensive disinfection device for body-worn isolation clothes

Also Published As

Publication number Publication date
CN115031521B (en) 2023-06-06

Similar Documents

Publication Publication Date Title
US2902705A (en) Pool cleaner
CN115031521A (en) Integrated into one piece formula wall body is pour and is air-dried device with cement paste
CN110425169A (en) A kind of intelligent pipeline blower
CN107521457B (en) A kind of new automobile windscreen wiper system
CN114213152B (en) Building concrete maintenance sprinkler
CN110864218A (en) Efficient air-intake anti-blocking natural gas storage tank
CN108941068B (en) Special cleaning device for automobile foot pad
CN213523564U (en) Municipal garden afforestation protector
CN108939467B (en) Table tennis circulating collector
CN217858721U (en) Aluminum cooling fin die-casting equipment with cleaning function
CN112588626B (en) Belt cleaning device for automobile wheel hub
CN207242562U (en) A kind of tourie
CN114029290B (en) Vertical inside earth cleaning equipment of nozzle stub for building industry
CN109758843A (en) A kind of purification device for administering haze
CN113102341B (en) A plantain seed cleaning device for medicinal material is handled
CN114440595A (en) Rotary drying device convenient for improving filling performance of sausage casings
CN109990393B (en) Corrosion-resistant air conditioner outdoor unit
CN209449351U (en) A kind of pest killing machine for crops
CN109157167B (en) Artificial intelligence electronic robot capable of networking for home use
CN117450282B (en) Ultra-high pressure gate valve
CN202875009U (en) Cold drink machine
CN215742607U (en) Intelligent building site dust device
CN216174903U (en) Quick cleaning device of debris under water
CN214686033U (en) Casting shot blasting machine
CN219926081U (en) Production line tongs

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant