CN115030533A - Green building construction process and green building assembly type wall - Google Patents
Green building construction process and green building assembly type wall Download PDFInfo
- Publication number
- CN115030533A CN115030533A CN202210109296.5A CN202210109296A CN115030533A CN 115030533 A CN115030533 A CN 115030533A CN 202210109296 A CN202210109296 A CN 202210109296A CN 115030533 A CN115030533 A CN 115030533A
- Authority
- CN
- China
- Prior art keywords
- green building
- wall body
- wall
- glue
- fixedly connected
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 16
- 238000009435 building construction Methods 0.000 title claims abstract description 13
- 239000003292 glue Substances 0.000 claims abstract description 32
- 238000007789 sealing Methods 0.000 claims abstract description 17
- 238000003780 insertion Methods 0.000 claims abstract description 11
- 230000037431 insertion Effects 0.000 claims abstract description 11
- 238000004321 preservation Methods 0.000 claims abstract description 4
- 238000007599 discharging Methods 0.000 claims description 13
- 238000007664 blowing Methods 0.000 claims description 10
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 8
- 238000001035 drying Methods 0.000 claims description 7
- 239000004568 cement Substances 0.000 claims description 4
- 229910052742 iron Inorganic materials 0.000 claims description 4
- 239000011248 coating agent Substances 0.000 claims description 3
- 238000000576 coating method Methods 0.000 claims description 3
- 238000012545 processing Methods 0.000 claims description 3
- 230000000694 effects Effects 0.000 abstract description 14
- 230000008595 infiltration Effects 0.000 abstract description 4
- 238000001764 infiltration Methods 0.000 abstract description 4
- 238000010276 construction Methods 0.000 abstract 1
- 239000012528 membrane Substances 0.000 description 7
- 238000013461 design Methods 0.000 description 2
- 239000011440 grout Substances 0.000 description 2
- 239000012466 permeate Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012856 packing Methods 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 230000031068 symbiosis, encompassing mutualism through parasitism Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/24—Safety or protective measures preventing damage to building parts or finishing work during construction
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/61—Connections for building structures in general of slab-shaped building elements with each other
- E04B1/6108—Connections for building structures in general of slab-shaped building elements with each other the frontal surfaces of the slabs connected together
- E04B1/612—Connections for building structures in general of slab-shaped building elements with each other the frontal surfaces of the slabs connected together by means between frontal surfaces
- E04B1/6125—Connections for building structures in general of slab-shaped building elements with each other the frontal surfaces of the slabs connected together by means between frontal surfaces with protrusions on the one frontal surface co-operating with recesses in the other frontal surface
- E04B1/6137—Connections for building structures in general of slab-shaped building elements with each other the frontal surfaces of the slabs connected together by means between frontal surfaces with protrusions on the one frontal surface co-operating with recesses in the other frontal surface the connection made by formlocking
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
- E04B1/6801—Fillings therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C2/00—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
- E04C2/30—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the shape or structure
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A20/00—Water conservation; Efficient water supply; Efficient water use
- Y02A20/108—Rainwater harvesting
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mechanical Engineering (AREA)
- Finishing Walls (AREA)
Abstract
The invention relates to the technical field of building construction, in particular to a green building construction process, which comprises the following steps: s1, preparing, namely treating a foundation and preparing a green building assembly wall and a floor slab; s2, assembling the green building assembled wall, aligning the two walls, inserting the insertion block into the containing cavity, extruding the sealing glue of the containing cavity from the discharge channel, and filling the glue into the gap at the whole joint; s3, after the wall of the first floor is completely installed; s4, repeating the steps S2-S3 according to the height of the built floor, and installing the roof after finishing the steps; s5, installing a rainwater collecting mechanism on the roof, performing waterproof heat preservation treatment on the roof, and installing a pipeline between the rainwater collecting mechanism and the construction flower bed. The invention has the function of repairing and sealing the gap, prevents the infiltration of rainwater and enhances the waterproof effect of the wall joint.
Description
Technical Field
The invention relates to the technical field of building construction, in particular to a green building construction process and a green building assembly type wall body.
Background
In the whole life cycle, the method saves resources, protects the environment, reduces pollution, provides healthy, applicable and efficient use space for people, and realizes the high-quality building harmony and symbiosis between people and nature to the maximum extent. When setting up green building, generally adopt the mode of assembled, assemble each part of building, when carrying out wall body assembled joint, the wall body adopts the mode of concatenation, can lead to the junction to produce a gap, even scribble grout and carry out sealing treatment externally, but grout is difficult to the infiltration gap, do not repair the gap, although can play sealed effect in the short time, the weather of blowing can lead to droing of cement, the rainwater is hit on the wall when raining, lead to the rainwater to permeate from the gap easily, flow into in the room, the water-proof effects of wall has been influenced.
Disclosure of Invention
The invention aims to solve the defects that gaps are contained at the joints of walls in the prior art, so that rainwater is easy to permeate, and the waterproof effect of the walls is influenced, and provides a green building construction process and a green building assembled wall.
In order to achieve the purpose, the invention adopts the following technical scheme:
a green building construction process is designed, and comprises the following steps:
s1, preparing, namely treating a foundation and preparing a green building assembly wall and a floor slab;
s2, assembling the green building assembled wall, aligning the two walls, inserting the insertion block into the containing cavity, extruding the sealing glue in the containing cavity from the discharge channel, filling the glue in the gap of the whole joint, blowing the glue at the joint of the walls for 30-45min by using a blowing device, drying and solidifying the glue in the gap of the joint of the walls, and leveling the gap after drying and solidifying;
s3, after the wall body on the first floor is completely installed, installing a floor slab, and meanwhile, smearing cement paste at the joint of the wall body and the joint of the wall body and the floor slab;
s4, repeating the steps S2-S3 according to the height of the built floor, and installing the roof after finishing the steps;
s5, installing a rainwater collection mechanism on the roof, performing waterproof heat preservation treatment on the roof, and installing a pipeline between the rainwater collection mechanism and the building flower bed.
Preferably, when the flattening treatment is performed, the method comprises the following steps:
a1, processing and shoveling the glue solidified by the leaked glue;
and A2, coating the concave parts in the gaps with glue, and drying by using a blowing device.
The invention also provides a green building assembly type wall body which comprises a wall body, wherein one side of the wall body is fixedly connected with the inserting part, the other side of the wall body is provided with a connecting groove, the connecting groove is internally provided with the accommodating cavity, the inserting part is fixedly connected with an inserting block, the inserting block is matched with the accommodating cavity for use, the inner wall of the accommodating cavity is fixedly connected with a first sealing film, the accommodating cavity is communicated with the connecting groove through a conduction mechanism, and a fixing mechanism is arranged between the inserting part and the connecting groove.
Preferably, the conduction mechanism comprises a discharge channel and a second sealing film, the discharge channel is communicated with the accommodating cavity, the second sealing film is fixedly connected to the inner wall of the discharge channel, and the discharge port of the discharge channel is located at the upper end of the connecting groove.
Preferably, the fixing mechanism comprises mounting grooves, stand columns, limiting blocks and magnets, the mounting grooves are formed in the inner walls of the two sides of each connecting groove, the stand columns and the stand columns can be inserted into the mounting grooves in an inserting mode, the inner sides of the stand columns are fixedly connected with the magnets, the opposite surfaces of the magnets are magnetic surfaces of the same polarity, fixing holes are formed in the two surfaces of the inserting portion, iron blocks are fixedly connected to the inner walls of the fixing holes, and the stand columns can be inserted into the fixing holes.
Preferably, two the equal fixedly connected with stopper in the relative outside of stand, the stopper is right the stand is spacing.
Preferably, the upper end and the lower end of the insertion part are fixedly connected with two connecting blocks, and the two connecting blocks can be inserted into the connecting grooves.
The invention provides a green building construction process and a green building assembly wall body, which have the beneficial effects that: through carrying out the wall body installation, when splicing, extrude the inside sealed glue of wall body, make sealed glue be full of in the gap, play the sealed effect of repairing to the gap, prevent the infiltration of rainwater, strengthened the water-proof effects of wall body junction.
Drawings
FIG. 1 is a schematic structural diagram of a green building fabricated wall according to the present invention;
FIG. 2 is a perspective view of a green building fabricated wall according to the present invention;
FIG. 3 is a cross-sectional view of a front view of a green building fabricated wall in accordance with the present invention;
FIG. 4 is a side view of a green building fabricated wall according to the present invention;
fig. 5 is an enlarged view of a portion a of fig. 4 of a green building fabricated wall according to the present invention.
In the figure: wall body 1, connecting block 2, grafting portion 3, insert piece 4, fixed orifices 5, hold chamber 6, first seal membrane 7, discharging channel 8, second seal membrane 9, spread groove 10, mounting groove 11, stand 12, stopper 13, magnet 14.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Example 1
Referring to fig. 1 to 5, a green building construction process includes the following steps:
s1, preparing, namely treating a foundation and preparing a green building assembly wall and a floor slab;
s2, assembling the green building assembled wall, aligning two walls 1 to enable the insertion block 4 to be inserted into the containing cavity 6, extruding the sealing glue of the containing cavity 6 from the discharging channel 8 to enable the glue to fill the gap of the whole joint, blowing the glue at the joint of the walls for 30-45min by adopting a blowing device to dry and solidify the glue in the gap of the joint of the walls, and leveling the gap after the drying and solidification are finished;
s3, after the wall body on the first floor is completely installed, installing a floor slab, and meanwhile, smearing cement paste at the joint of the wall body and the joint of the wall body and the floor slab;
s4, repeating the steps S2-S3 according to the height of the built floor, and installing the roof after finishing the steps;
s5, installing a rainwater collection mechanism on the roof, performing waterproof and heat preservation treatment on the roof, installing a pipeline between the rainwater collection mechanism and the flower bed of the building, and watering plants planted in the flower bed by rainwater by collecting the rainwater, so that a water source is saved and the concept of green building is met.
2. A green building construction process according to claim 1, wherein the leveling process comprises the steps of:
a1, processing and removing the glue solidified by the leaked glue;
and A2, coating the concave parts in the gaps with glue, and drying by using a blowing device.
The invention also provides a green building assembled wall body, which comprises a wall body 1, wherein one side of the wall body 1 is fixedly connected with an inserting part 3, the other side of the wall body 1 is provided with a connecting groove 10, a containing cavity 6 is arranged in the connecting groove 10, an inserting block 4 is fixedly connected on the inserting part 3, the inserting block 4 is matched with the containing cavity 6 for use, a first sealing film 7 is fixedly connected on the inner wall of the containing cavity 6, the containing cavity 6 is communicated with the connecting groove 10 through a conducting mechanism, a fixing mechanism is arranged between the inserting part 3 and the connecting groove 10, when the wall body is connected, the inserting part 3 is inserted into the connecting groove 10, the inserting block 4 enters the containing cavity 6, the inserting block 4 punctures the first sealing film 7 to play a role of extruding the sealing glue in the containing cavity 6, the sealing glue flows into the connecting groove 10 from the conducting mechanism, a gap between the connecting groove 10 and the inserting part 3 is filled, thereby play the sealed effect of packing to the gap, get rid of the gap, prevent the infiltration of rainwater, strengthened the water-proof effects of wall body junction.
Conduction mechanism includes discharging channel 8, second seal membrane 9, discharging channel 8 is linked together with holding chamber 6, fixedly connected with second seal membrane 9 on the 8 inner walls of discharging channel, discharging channel 8's discharge gate department is located the upper end position of spread groove 10, play sealed effect to sealed glue through second seal membrane 9 and first seal membrane 7, when inserting piece 4 and inserting and holding in the chamber 6, play extruded effect to sealed glue, to make sealed glue break second seal membrane 9, make sealed glue flow out from discharging channel 8, glue flows downwards under the effect of gravity, be full of whole gap.
Two connecting blocks 2 of the equal fixedly connected with in both ends about grafting portion 3, two connecting blocks 2 all can be pegged graft into spread groove 10, through the design that adopts connecting block 2, play sealed effect to the both ends of spread groove 10, make to be favorable to preventing that sealing glue from flowing out from both ends.
Example 2
Referring to fig. 4-5, as another preferred embodiment of the present invention, the difference from embodiment 1 is that the fixing mechanism includes mounting grooves 11, vertical columns 12, limiting blocks 13, and magnets 14, the mounting grooves 11 are respectively disposed on the inner walls of the two sides of the connecting groove 10, the vertical columns 12 can be inserted into the two mounting grooves 11, the magnets 14 are respectively fixedly connected to the inner sides of the two vertical columns 12, the opposite surfaces of the two magnets 14 are like magnetic surfaces, the two surfaces of the inserting portion 3 are respectively disposed with fixing holes 5, the inner walls of the two fixing holes 5 are respectively and fixedly connected with iron blocks, the vertical columns 12 can be inserted into the fixing holes 5, when the inserting portion 3 is inserted, when the fixing holes 5 are aligned with the vertical columns 12, the attraction between the magnets 14 and the iron blocks will cause the vertical columns 12 to be inserted into the fixing holes 5, thereby fixing the wall 1, and compared with other fixing methods, the situation that is not easy to fall off, the connecting effect between the wall bodies 1 is ensured, and the opposite surfaces of the two magnets 14 are the same-polarity magnetic surfaces, so that repulsive force is generated, and the blocking condition is avoided when the inserting part 3 is inserted.
The equal fixedly connected with stopper 13 in the relative outside of two stands 12, stopper 13 is spacing to stand 12, through the design that adopts stopper 13, plays spacing effect to stand 12, prevents that stand 12 from breaking away from mounting groove 11.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered as the technical solutions and the inventive concepts of the present invention within the technical scope of the present invention.
Claims (7)
1. A green building construction process is characterized by comprising the following steps:
s1, preparing, namely treating a foundation and preparing a green building assembly type wall body and a floor slab;
s2, assembling the green building assembly type wall body, aligning two wall bodies (1), inserting the insertion block (4) into the containing cavity (6), extruding the sealing glue of the containing cavity (6) from the discharging channel (8), filling the glue in the gap of the whole joint, blowing the glue at the joint of the wall bodies for 30-45min by using a blowing device, and leveling the gap after the drying;
s3, after the wall body on the first floor is completely installed, installing a floor slab, and meanwhile, smearing cement paste at the joint of the wall body and the joint of the wall body and the floor slab;
s4, repeating the steps S2-S3 according to the height of the built floor, and installing the roof after finishing the steps;
s5, installing a rainwater collection mechanism on the roof, performing waterproof heat preservation treatment on the roof, and installing a pipeline between the rainwater collection mechanism and the building flower bed.
2. The green building construction process of claim 1, wherein the leveling process comprises the following steps:
a1, processing and shoveling the glue solidified by the leaked glue;
and A2, coating the concave parts in the gaps with glue, and drying by using a blowing device.
3. The green building assembly type wall body according to any one of claims 1-2, comprising a wall body (1), wherein the insertion part (3) is fixedly connected to one side of the wall body (1), the connection groove (10) is formed in the other side of the wall body (1), the accommodating cavity (6) is formed in the connection groove (10), an insertion block (4) is fixedly connected to the insertion part (3), the insertion block (4) is matched with the accommodating cavity (6) for use, a first sealing film (7) is fixedly connected to the inner wall of the accommodating cavity (6), the accommodating cavity (6) is communicated with the connection groove (10) through a conduction mechanism, and a fixing mechanism is arranged between the insertion part (3) and the connection groove (10).
4. A green building assembled wall according to claim 3, wherein the conducting mechanism comprises a discharging channel (8) and a second sealing film (9), the discharging channel (8) is communicated with the accommodating cavity (6), the second sealing film (9) is fixedly connected to the inner wall of the discharging channel (8), and the discharging port of the discharging channel (8) is located at the upper end position of the connecting groove (10).
5. The green building assembly wall body as claimed in claim 3, wherein the fixing mechanism comprises mounting grooves (11), upright posts (12), limiting blocks (13) and magnets (14), the mounting grooves (11) are formed in the inner walls of the two sides of the connecting groove (10), the upright posts (12) can be inserted into the two mounting grooves (11), the magnets (14) are fixedly connected to the inner sides of the two upright posts (12), the opposite surfaces of the two magnets (14) are like magnetic surfaces, the fixing holes (5) are formed in the two surfaces of the inserting portion (3), the iron blocks are fixedly connected to the inner walls of the two fixing holes (5), and the upright posts (12) can be inserted into the fixing holes (5).
6. A green building assembled wall according to claim 5, wherein a limiting block (13) is fixedly connected to the opposite outer sides of the two upright posts (12), and the limiting block (13) limits the upright posts (12).
7. A green building assembled wall according to claim 3, wherein two connecting blocks (2) are fixedly connected to both upper and lower ends of the insertion part (3), and both of the connecting blocks (2) can be inserted into the connecting grooves (10).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210109296.5A CN115030533A (en) | 2022-01-28 | 2022-01-28 | Green building construction process and green building assembly type wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210109296.5A CN115030533A (en) | 2022-01-28 | 2022-01-28 | Green building construction process and green building assembly type wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115030533A true CN115030533A (en) | 2022-09-09 |
Family
ID=83119945
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210109296.5A Pending CN115030533A (en) | 2022-01-28 | 2022-01-28 | Green building construction process and green building assembly type wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115030533A (en) |
Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0843056A2 (en) * | 1996-11-13 | 1998-05-20 | Premark RWP Holdings, Inc. | Articles with tongue and groove joint and method of making such a joint |
CN1380926A (en) * | 2000-06-06 | 2002-11-20 | M·凯恩德尔 | Panel with glue and covering, and method and device for producing thereof |
CN2783078Y (en) * | 2005-01-21 | 2006-05-24 | 洪镇忠 | Valve rod limiter |
CN201713953U (en) * | 2010-03-30 | 2011-01-19 | 闫振甲 | Composite sandwich foam concrete wallboard and its seam sealing construction |
CN204485532U (en) * | 2015-02-11 | 2015-07-22 | 重庆阳正环保科技有限公司 | Granular activated carbon web plate |
CN205112275U (en) * | 2015-11-28 | 2016-03-30 | 申雅密封件(淮安)有限公司 | Injection of car door frame sealing strip connects lower bolster |
CN205474609U (en) * | 2016-01-21 | 2016-08-17 | 中铁第四勘察设计院集团有限公司 | A joggle formula support rail girder construction that is arranged in low circuit of putting of low -speed maglev traffic engineering |
CN107447852A (en) * | 2017-08-30 | 2017-12-08 | 河北建筑工程学院 | Integral prefabricated balcony filling wall and its construction method |
CN107558626A (en) * | 2017-09-01 | 2018-01-09 | 蔡岗 | A kind of prefabricated assembled wall structure and the method using this structure building house |
CN207301643U (en) * | 2017-08-29 | 2018-05-01 | 珠海摩丽电子科技有限公司 | A kind of toner cartridge positioner |
CN207377017U (en) * | 2017-11-06 | 2018-05-18 | 王林芳 | A kind of indoor design decorative wall panels convenient for assembling |
CN209779895U (en) * | 2019-01-23 | 2019-12-13 | 宿迁德威新材料有限公司 | flame-retardant portland cement wallboard |
KR20200038829A (en) * | 2018-10-04 | 2020-04-14 | 이종하 | the block for a building with the binding structure |
CN111206707A (en) * | 2020-02-12 | 2020-05-29 | 珠海市联港中投建筑装饰工程有限公司 | Metal covering composite curtain wall plate assembly for constructional engineering |
CN211421448U (en) * | 2019-09-28 | 2020-09-04 | 海盐宝仕龙塑业股份有限公司 | Anti-aging PVC (polyvinyl chloride) wallboard |
CN211873373U (en) * | 2020-03-16 | 2020-11-06 | 尤璐 | Building energy-saving heat-insulating structure |
CN214295995U (en) * | 2021-01-21 | 2021-09-28 | 浙江博昇滑动轴承科技股份有限公司 | A transfer car (buggy) for bearing production |
CN214657690U (en) * | 2021-02-04 | 2021-11-09 | 广西安业建设集团有限公司 | Energy-saving environment-friendly green building structure |
-
2022
- 2022-01-28 CN CN202210109296.5A patent/CN115030533A/en active Pending
Patent Citations (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0843056A2 (en) * | 1996-11-13 | 1998-05-20 | Premark RWP Holdings, Inc. | Articles with tongue and groove joint and method of making such a joint |
CN1380926A (en) * | 2000-06-06 | 2002-11-20 | M·凯恩德尔 | Panel with glue and covering, and method and device for producing thereof |
CN1466646A (en) * | 2000-06-06 | 2004-01-07 | M�������չ�˾ | Arrangement for connecting planar components |
CN2783078Y (en) * | 2005-01-21 | 2006-05-24 | 洪镇忠 | Valve rod limiter |
CN201713953U (en) * | 2010-03-30 | 2011-01-19 | 闫振甲 | Composite sandwich foam concrete wallboard and its seam sealing construction |
CN204485532U (en) * | 2015-02-11 | 2015-07-22 | 重庆阳正环保科技有限公司 | Granular activated carbon web plate |
CN205112275U (en) * | 2015-11-28 | 2016-03-30 | 申雅密封件(淮安)有限公司 | Injection of car door frame sealing strip connects lower bolster |
CN205474609U (en) * | 2016-01-21 | 2016-08-17 | 中铁第四勘察设计院集团有限公司 | A joggle formula support rail girder construction that is arranged in low circuit of putting of low -speed maglev traffic engineering |
CN207301643U (en) * | 2017-08-29 | 2018-05-01 | 珠海摩丽电子科技有限公司 | A kind of toner cartridge positioner |
CN107447852A (en) * | 2017-08-30 | 2017-12-08 | 河北建筑工程学院 | Integral prefabricated balcony filling wall and its construction method |
CN107558626A (en) * | 2017-09-01 | 2018-01-09 | 蔡岗 | A kind of prefabricated assembled wall structure and the method using this structure building house |
CN207377017U (en) * | 2017-11-06 | 2018-05-18 | 王林芳 | A kind of indoor design decorative wall panels convenient for assembling |
KR20200038829A (en) * | 2018-10-04 | 2020-04-14 | 이종하 | the block for a building with the binding structure |
CN209779895U (en) * | 2019-01-23 | 2019-12-13 | 宿迁德威新材料有限公司 | flame-retardant portland cement wallboard |
CN211421448U (en) * | 2019-09-28 | 2020-09-04 | 海盐宝仕龙塑业股份有限公司 | Anti-aging PVC (polyvinyl chloride) wallboard |
CN111206707A (en) * | 2020-02-12 | 2020-05-29 | 珠海市联港中投建筑装饰工程有限公司 | Metal covering composite curtain wall plate assembly for constructional engineering |
CN211873373U (en) * | 2020-03-16 | 2020-11-06 | 尤璐 | Building energy-saving heat-insulating structure |
CN214295995U (en) * | 2021-01-21 | 2021-09-28 | 浙江博昇滑动轴承科技股份有限公司 | A transfer car (buggy) for bearing production |
CN214657690U (en) * | 2021-02-04 | 2021-11-09 | 广西安业建设集团有限公司 | Energy-saving environment-friendly green building structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203499340U (en) | Prefabricated assembled enclosure | |
CN105064553A (en) | Flexible prefabricated and assembled shear wall-external window integrated construction system and method | |
CN203640113U (en) | Unit curtain wall system | |
CN115030533A (en) | Green building construction process and green building assembly type wall | |
CN110939213A (en) | Waterproof outer wall of building | |
CN211597267U (en) | Energy-saving waterproof curtain wall | |
CN204898903U (en) | Waterproof structure sealing layer in outer wall split bolt hole | |
CN114382186B (en) | Low-energy-consumption building foundation heat-insulation bridge heat-insulation structure and construction method | |
CN206902665U (en) | Hydraulic asphalt concrete coring deep hole integrally loads recovery instrument | |
CN106522166A (en) | Construction method for concrete engineering cavity mould with bulges and reinforcing fibers | |
CN206111016U (en) | Window attaches splicing apparatus of frame | |
CN213927284U (en) | Assembled dampproofing floor with embedded assembly structure | |
CN211007513U (en) | Flue pipe pre-buried formula shutoff bears device | |
CN211597100U (en) | Concrete outer wall draws seam structure | |
CN210369467U (en) | Glass curtain wall easy to splice | |
CN208105523U (en) | A kind of fabricated structure waterproof construction | |
CN108999047B (en) | Landscaping brick | |
CN110966025A (en) | Shield tunnel segment crack plugging device and construction method | |
CN201605691U (en) | Single track sealing structure of unit type curtain wall | |
CN204919894U (en) | Flexible prefabricated assembly shear force wall - exterior window integration construction system | |
CN219754533U (en) | Subway tunnel contact channel deep groove protection device | |
CN116770889A (en) | Prefabricated city utility tunnel of assembled | |
CN211973940U (en) | Waterproof construction of glass curtain wall and stone material curtain tie point | |
CN203640112U (en) | Transverse beam structure of unit curtain wall | |
CN218814437U (en) | Concrete outer wall anti-seepage structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |