CN114997030A - Temporary support unloading sequence and unloading amount determining method - Google Patents

Temporary support unloading sequence and unloading amount determining method Download PDF

Info

Publication number
CN114997030A
CN114997030A CN202210925259.1A CN202210925259A CN114997030A CN 114997030 A CN114997030 A CN 114997030A CN 202210925259 A CN202210925259 A CN 202210925259A CN 114997030 A CN114997030 A CN 114997030A
Authority
CN
China
Prior art keywords
unloading
temporary support
temporary
support
formula
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210925259.1A
Other languages
Chinese (zh)
Other versions
CN114997030B (en
Inventor
李鑫奎
张其林
姜海西
黄玉林
伍小平
况中华
严再春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Smi Highway Group Co ltd
Tongji University
Shanghai Construction Group Co Ltd
Original Assignee
Shanghai Smi Highway Group Co ltd
Tongji University
Shanghai Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Smi Highway Group Co ltd, Tongji University, Shanghai Construction Group Co Ltd filed Critical Shanghai Smi Highway Group Co ltd
Priority to CN202210925259.1A priority Critical patent/CN114997030B/en
Publication of CN114997030A publication Critical patent/CN114997030A/en
Application granted granted Critical
Publication of CN114997030B publication Critical patent/CN114997030B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/23Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F17/00Digital computing or data processing equipment or methods, specially adapted for specific functions
    • G06F17/10Complex mathematical operations
    • G06F17/16Matrix or vector computation, e.g. matrix-matrix or matrix-vector multiplication, matrix factorization
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Physics (AREA)
  • Computational Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Mathematical Analysis (AREA)
  • Pure & Applied Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Data Mining & Analysis (AREA)
  • Evolutionary Computation (AREA)
  • Civil Engineering (AREA)
  • Computing Systems (AREA)
  • Architecture (AREA)
  • Algebra (AREA)
  • Structural Engineering (AREA)
  • Databases & Information Systems (AREA)
  • Software Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention belongs to the technical field of construction of constructional engineering structures, and particularly relates to a temporary support unloading sequence and unloading amount determining method, aiming at solving the problem of determining an optimal unloading sequence and unloading levels under the condition of asynchronous unloading of temporary supports. The method comprises the following steps: firstly, unloading temporary supports one by one in sequence by using finite element analysis software, unloading 1 unit each time, calculating the reaction variation of the rest temporary supports caused by unloading of the temporary supports in sequence, and establishing a temporary support unloading influence matrix according to the calculation result; determining the maximum allowable support counterforce and the maximum allowable single unloading amount of the temporary support by combining the finite element model and the relevant specifications, and determining an unloading control value; thirdly, establishing a temporary supporting and unloading sequence determining principle; fourthly, establishing an unloading sequence determining method; and fifthly, determining the single unloading amount. The temporary support unloading sequence and the single unloading amount can be more reasonably determined, the unloading efficiency is improved, and the safety risk of unloading construction is reduced.

Description

Temporary support unloading sequence and unloading amount determining method
Technical Field
The invention belongs to the technical field of construction of constructional engineering structures, and particularly relates to a method for determining temporary support unloading sequence and unloading amount.
Background
A certain number of temporary supports are required to be arranged in the processes of assembling components or parts and pouring concrete in the large-scale space structure and the bridge structure, the components or parts are assembled and poured on the temporary supports for molding, the temporary supports are unloaded after the structure construction is finished, and the load is transferred to the structure or a permanent support from the temporary supports. The unloading of temporary supports results in adjustment of structural boundaries, load shifting, and structural architecture changes. Due to the fact that structural system conversion is involved, in the asynchronous unloading process, unloading of a certain temporary support or a plurality of temporary supports can cause changes of other temporary support loads, and the situation that certain temporary support forces are greatly increased can occur.
Generally, most projects cannot adopt a synchronous unloading scheme and only can adopt asynchronous unloading from the aspects of economy, construction convenience and the like. To control safety in the unloading process, a reasonable unloading order, unloading classification, and unloading amount per stage must be determined. Currently, the temporary support unloading sequence, the unloading classification and the unloading amount of each stage are determined by trial calculation, namely, according to engineering experience and simple calculation, a plurality of schemes are preliminarily set and combined, then each scheme is calculated in detail, and the final unloading grouping and classification are determined according to the calculation result. The method usually depends on the experience of technicians, the workload is large, the randomness of scheme combination is large, theoretical support is lacked, and standardization and unification cannot be realized.
Therefore, how to provide a temporary supporting unloading sequence and an unloading amount determining method to improve the safety of unloading construction is a technical problem that needs to be solved by those skilled in the art.
The information disclosed in this background section is only for enhancement of understanding of the general background of the invention and should not be taken as an acknowledgement or any form of suggestion that this information is prior art that is known to a person skilled in the art.
Disclosure of Invention
The invention provides a temporary support unloading sequence and unloading amount determining method, which is used for solving the problems of optimal unloading sequence and unloading classification under the condition of asynchronous unloading of temporary supports, reducing the influence of overlarge temporary support counter force on the temporary support safety and the structure body quality in the unloading process and improving the safety of unloading construction.
In order to solve the technical problems, the invention comprises the following technical scheme:
a method for determining unloading sequence and unloading amount of temporary supports is provided, and the number of the temporary supports is assumed to be n, and the method comprises the following steps:
step S1, unloading the temporary supports one by using finite element analysis software, unloading 1 unit each time, calculating the variation of the reaction force of the rest temporary supports caused by unloading the temporary supports in sequence, and establishing a temporary support unloading influence matrix according to the calculation result
Figure 77980DEST_PATH_IMAGE001
Figure 421237DEST_PATH_IMAGE002
Formula (1);
step S2, determining the maximum allowable support counterforce and the maximum allowable single unloading amount of the temporary support by combining finite element calculation, relevant specifications, unloading equipment specifications and actual conditions of a construction site, calculating the corresponding unloading amount according to the maximum allowable support counterforce of the temporary support, comparing the unloading amount with the maximum allowable single unloading amount, and selecting a smaller value as an unloading control value;
step S3, establishing a temporary supporting and unloading sequence determination principle: the maximum allowable support counterforce and the maximum allowable single unloading amount in the unloading process do not exceed the unloading control value; the temporary support counter force changes uniformly in the unloading process, and sudden changes are reduced;
step S4, preparing an unloading order determination method: arranging the sum of the reaction variation of all other supports corresponding to each temporary support after unloading in a descending order, wherein the order is the temporary support unloading order, and after unloading the temporary supports according to the order, the self-weight load of the structure is transferred to the permanent support or the structure per se most quickly;
step S5, determining the single unload amount: after the temporary support is unloaded, all temporary support counter forces do not exceed the unloading control value, when the unloading amount of a certain temporary support exceeds the unloading control value, the actual unloading amount of the temporary support is the unloading control value, and n is an integer greater than 2.
Further, the temporary support unloading influence matrix in the step S1
Figure 640735DEST_PATH_IMAGE001
The establishment method comprises the following steps:
firstly, establishing a structure finite element model to calculate related parameters:
firstly, a structure main body and a temporary support model are established, a simulation working condition is established according to the construction process, the support counter force of each temporary support before unloading is obtained,
Figure 448154DEST_PATH_IMAGE003
representing the support reaction force of the ith temporary support before unloading, and establishing a support reaction force vector of all temporary supports through a formula (2)
Figure 25897DEST_PATH_IMAGE004
Figure 918766DEST_PATH_IMAGE005
Formula (2);
secondly, establishing a matrix of influence of unloading of the single temporary support on other temporary supports according to the finite element model
Figure 364791DEST_PATH_IMAGE001
: starting from the first support, reducing 1 unit length, calculating the support reaction force variation of other temporary supports after the temporary support is unloaded through a finite element model,
Figure 541563DEST_PATH_IMAGE006
the 1 st temporary supporting and unloading unit is represented, and the ith temporary supporting reaction force variation is represented;
Figure 539475DEST_PATH_IMAGE007
representing 1 unit of unloading of the ith temporary support, and variation of reaction force of the jth temporary support (i, j =1,2,3 … … n); 1 unit of temporary supporting and unloading is marked as-1, the temporary supporting counter force is increased to be plus, and the counter force is reduced to be-;
sequentially calculating influence data of reaction variation of all temporary supports on other temporary supports to obtain temporary support unloading influence matrix
Figure 404794DEST_PATH_IMAGE001
Further, the unloading control value determining method in step S2 includes:
determining maximum allowable support counter force of each temporary support by combining finite element calculation and relevant specifications
Figure 982406DEST_PATH_IMAGE008
(i =1,2,3 … n), and then the maximum support reaction force vector is established by equation (3)
Figure 702100DEST_PATH_IMAGE009
Figure 57864DEST_PATH_IMAGE010
Formula (3);
Calculating the unloading value of each temporary support in the state according to the determined maximum allowable support counter force by adopting finite element calculation
Figure 722064DEST_PATH_IMAGE011
Determining the maximum allowable single unloading amount of each temporary support by combining the specification of unloading equipment and actual conditions of a construction site
Figure 322941DEST_PATH_IMAGE012
(i=1,2,3…n);
Will be provided with
Figure 897141DEST_PATH_IMAGE012
And
Figure 174539DEST_PATH_IMAGE013
and comparing, and selecting a smaller value as a temporary support unloading control value:
Figure 840881DEST_PATH_IMAGE014
then, a temporary support unloading control value vector is established through a formula (4)
Figure 229137DEST_PATH_IMAGE015
Figure 923424DEST_PATH_IMAGE016
Equation (4).
Further, the principle that the temporary support unloading is required to follow includes: the unloading efficiency is improved while the safety is considered, the single unloading amount is increased as much as possible, the unloading times are reduced, and the transfer of the self-weight load of the structure from the temporary support to the permanent support or the structure is completed through the unloading steps as few as possible.
Further, the step S4 includes:
Figure 122455DEST_PATH_IMAGE017
formula (5);
if the 2 nd temporary support is unloaded by 1 unit, an unloading vector is established by the formula (6):
Figure 761247DEST_PATH_IMAGE018
formula (6);
and (3) if the ith temporary support is unloaded by 1 unit, establishing an unloading vector through a formula (7):
Figure 468041DEST_PATH_IMAGE019
formula (7);
after the 1 st temporary support is unloaded by 1 unit, all temporary support reaction force change vectors are established through a formula (8):
Figure 79151DEST_PATH_IMAGE020
Figure 370455DEST_PATH_IMAGE021
=
Figure 247275DEST_PATH_IMAGE022
formula (8);
at this time, after the 1 st temporary support is unloaded, the sum of the variation of all temporary support reaction forces is equal to
Figure 508492DEST_PATH_IMAGE023
Figure 646212DEST_PATH_IMAGE023
Calculated by equation (9):
Figure 951161DEST_PATH_IMAGE024
formula (9);
after the ith temporary support is unloaded, allThe sum of the variation of the temporary support reaction force is
Figure 502228DEST_PATH_IMAGE025
Figure 114606DEST_PATH_IMAGE025
Calculated by equation (10):
Figure 700308DEST_PATH_IMAGE026
equation (10);
as can be seen from the formula (10), the sum of the variation of all temporary support reaction forces after the ith temporary support unloading is the influence matrix
Figure 910578DEST_PATH_IMAGE027
The sum of the ith column;
according to the influence matrix
Figure 886624DEST_PATH_IMAGE027
And calculating the sum of each row, arranging the sum in a numerical sequence from large to small, wherein the sequence is a temporary support unloading sequence, and after the temporary support is unloaded according to the sequence, the self-weight load of the structure is transferred to the permanent support or the structure per se most quickly.
Further, the step S5 includes:
(1) setting the ith temporary support single unloading amount as
Figure 224065DEST_PATH_IMAGE028
Then, a temporary support unload vector is established by equation (11):
Figure 211744DEST_PATH_IMAGE029
formula (11);
(2) after the ith temporary support is unloaded, each temporary support just reaches the maximum allowable value, n analytic solutions can be calculated, and the formula (12):
Figure 609227DEST_PATH_IMAGE030
formula (12);
then:
Figure 806990DEST_PATH_IMAGE031
it is thus possible to calculate:
Figure 197389DEST_PATH_IMAGE032
n pieces are obtained by solving
Figure 288842DEST_PATH_IMAGE033
Is given as
Figure 873538DEST_PATH_IMAGE034
So that the minimum value is used as the ith temporary support unloading amount
Figure 620914DEST_PATH_IMAGE033
Written as formula (13):
Figure 237840DEST_PATH_IMAGE035
formula (13)
Namely, it is
Figure 659767DEST_PATH_IMAGE036
The calculated temporary support unloading amount
Figure 461370DEST_PATH_IMAGE033
And unload control value
Figure 368146DEST_PATH_IMAGE037
Comparing, and when a certain temporary support unloading amount
Figure 601812DEST_PATH_IMAGE033
Exceeding the unload control value
Figure 871119DEST_PATH_IMAGE037
The actual unloading amount of the temporary support is determined as the unloading control value of the temporary support
Figure 92891DEST_PATH_IMAGE037
Compared with the prior art, the invention has the beneficial technical effects that:
the invention provides a temporary support unloading sequence and an unloading amount determining method, which comprises the steps of utilizing finite element analysis software to sequentially unload temporary supports one by one, unloading 1 unit each time, sequentially calculating the reaction variation of the rest temporary supports caused by unloading of the temporary supports, and establishing a temporary support unloading influence matrix according to the calculation result; determining the maximum allowable support counterforce and the maximum allowable single unloading amount of the temporary support by combining the finite element model and the relevant specifications, and determining an unloading control value; thirdly, establishing a temporary supporting and unloading sequence determining principle; fourthly, establishing an unloading sequence determining method; and fifthly, determining the single unloading amount. The temporary support unloading sequence and the single unloading amount can be more reasonably determined, the unloading efficiency is improved, and the safety risk of unloading construction is reduced.
Detailed Description
The temporary support unloading sequence and the unloading amount determining method proposed by the present invention will be further described in detail with reference to the following embodiments. The advantages and features of the present invention will become more apparent from the following description.
Example one
The temporary support unloading can be divided into synchronous unloading and non-synchronous unloading. The synchronous unloading is that hydraulic jacks are arranged on all temporary supports, the hydraulic jacks descend simultaneously according to the calculated unloading amount under the control of a control system, the temporary supports descend synchronously by adopting a synchronous unloading method, and the temporary support counterforce is always in a reduction trend, so that the temporary supports and the main structure are not damaged, and the unloading safety is high. However, most projects cannot adopt a synchronous unloading scheme and only adopt asynchronous unloading from the aspects of economy, construction convenience and the like. The temporary support unloading is mainly to determine a reasonable unloading sequence and single unloading amount. The conventional temporary supporting and unloading are often based on experience, so that the efficiency is low and scientific support is lacked.
To control safety in the unloading process, a reasonable unloading order, unloading classification, and unloading amount per stage must be determined.
The embodiment provides a method for determining temporary support unloading sequence and unloading amount, which comprises the following specific steps:
assuming that the number of temporary supports is n, n is an integer greater than 2.
Step S1, using finite element analysis software to sequentially unload the temporary supports one by one, unloading 1 unit each time, sequentially calculating the variation of the reaction force of the rest temporary supports caused by unloading of the temporary supports, and establishing a temporary support unloading influence matrix according to the calculation result
Figure 814859DEST_PATH_IMAGE038
Figure 773588DEST_PATH_IMAGE039
Formula (1);
step S2, determining the maximum allowable support counterforce and the maximum allowable single unloading amount of the temporary support by combining finite element calculation, relevant specifications, unloading equipment specifications and actual conditions of a construction site, calculating the corresponding unloading amount according to the maximum allowable support counterforce of the temporary support, comparing the unloading amount with the maximum allowable single unloading amount, and selecting a smaller value as an unloading control value;
step S3, establishing a temporary supporting and unloading sequence determination principle: the maximum allowable support counterforce and the maximum allowable single unloading amount in the unloading process do not exceed the unloading control value; the temporary support counter force changes uniformly in the unloading process, and sudden changes are reduced;
step S4, formulating an unloading order determining method: arranging the sum of the reaction variation of all other supports corresponding to each temporary support after unloading in a descending order, wherein the order is the temporary support unloading order, and after unloading the temporary supports according to the order, the self-weight load of the structure is transferred to the permanent support or the structure per se most quickly;
step S5, determining the single unload amount: after temporary support unloading, all temporary support counterforces do not exceed the unloading control value, and when the unloading amount of a certain temporary support exceeds the unloading control value, the actual unloading amount of the temporary support is the unloading control value.
In this embodiment, it is more preferable that the unloading influence matrix is temporarily supported in the step S1
Figure 648134DEST_PATH_IMAGE040
The establishment method comprises the following steps:
firstly, establishing a structure finite element model to calculate related parameters:
firstly, a structure main body and a temporary support model are established, a simulation working condition is established according to the construction process, the support counter force of each temporary support before unloading is obtained,
Figure 525961DEST_PATH_IMAGE041
representing the support reaction force of the ith temporary support before unloading, and establishing a support reaction force vector of all temporary supports through a formula (2)
Figure 984493DEST_PATH_IMAGE042
Figure 746912DEST_PATH_IMAGE043
Formula (2);
secondly, establishing a matrix of influence of unloading of the single temporary support on other temporary supports according to the finite element model
Figure 725233DEST_PATH_IMAGE044
: reducing 1 unit length from the first support, calculating the support reaction variation of other temporary supports after the temporary support is unloaded by a finite element model,
Figure 790272DEST_PATH_IMAGE045
the 1 st temporary supporting and unloading unit is represented, and the ith temporary supporting reaction force variation is represented;
Figure 486832DEST_PATH_IMAGE046
representing the ith temporary support unloading by 1 unit, and the jth temporary support reaction force variation (i, j =1,2,3 … … n); 1 unit of temporary support unloading is marked as-1, the temporary support counterforce is increased to be plus, and the counterforce is reduced to be minus;
sequentially calculating the influence data of the reaction variation of all temporary supports on other temporary supports to obtain a temporary support unloading influence matrix
Figure 98948DEST_PATH_IMAGE044
Further, the unloading control value determining method in step S2 includes:
determining maximum allowable support counter force of each temporary support by combining finite element calculation and relevant specifications
Figure 135037DEST_PATH_IMAGE047
Then, the maximum allowable support reaction force vector is established by the formula (3)
Figure 557928DEST_PATH_IMAGE048
Figure 289255DEST_PATH_IMAGE049
Formula (3);
calculating the unloading value of each temporary support in the state according to the determined maximum allowable support counter force by adopting finite element calculation
Figure 721373DEST_PATH_IMAGE050
Determining the maximum allowable single unloading amount of each temporary support by combining the specification of unloading equipment and actual conditions of a construction site
Figure 189133DEST_PATH_IMAGE051
(i=1,2,3…n);
Will be provided with
Figure 782925DEST_PATH_IMAGE051
And
Figure 126182DEST_PATH_IMAGE052
and comparing, and selecting a smaller value as a temporary support unloading control value:
Figure 581565DEST_PATH_IMAGE053
then, a temporary support unloading control value vector is established through a formula (4)
Figure 451301DEST_PATH_IMAGE054
Figure 465262DEST_PATH_IMAGE055
Equation (4).
In this embodiment, more preferably, the principle that the temporary support unloading is required to follow further includes: the unloading efficiency is improved while the safety is considered, the single unloading amount is increased as much as possible, the unloading times are reduced, the unloading steps are reduced as few as possible, and the self-weight load of the structure is transferred to the permanent support or the structure.
In this embodiment, more preferably, the step S4 includes:
in terms of unloading efficiency, after a certain temporary support is unloaded, the smaller the sum of all temporary support counter-forces indicates that the load is transferred to the permanent support or the structure per se, and the higher the unloading efficiency is. For convenience of calculation, the calculation is carried out according to 1 unit of unloading of each temporary support:
and (3) if the 1 st temporary support is unloaded by 1 unit, establishing an unloading vector through a formula (5):
Figure 295815DEST_PATH_IMAGE056
formula (5);
assuming that the 2 nd temporary support is unloaded by 1 unit, an unloading vector is established by the formula (6):
Figure 804157DEST_PATH_IMAGE057
formula (6);
and (3) if the ith temporary support is unloaded by 1 unit, establishing an unloading vector through a formula (7):
Figure 279131DEST_PATH_IMAGE058
formula (7);
after the 1 st temporary support is unloaded by 1 unit, all temporary support reaction force change vectors are established through a formula (8):
Figure 214726DEST_PATH_IMAGE059
Figure 532575DEST_PATH_IMAGE060
=
Figure 93875DEST_PATH_IMAGE061
formula (8);
at this time, after the 1 st temporary support is unloaded, the sum of the variation of all temporary support reaction forces is equal to
Figure 672624DEST_PATH_IMAGE062
Figure 529853DEST_PATH_IMAGE062
Calculated by equation (9):
Figure 334998DEST_PATH_IMAGE063
formula (9);
after the ith temporary support is unloaded, the sum of the variable quantities of all temporary support reaction forces is equal to
Figure 185142DEST_PATH_IMAGE064
Figure 133244DEST_PATH_IMAGE064
Calculated by equation (10):
Figure 410642DEST_PATH_IMAGE065
equation (10);
as can be seen from the formula (10), after the ith temporary support is unloaded, the sum of the variation of all temporary support reaction forces is the influence matrix
Figure 703083DEST_PATH_IMAGE066
The sum of the ith column;
according to the influence matrix
Figure 842072DEST_PATH_IMAGE066
And calculating the sum of each row, and then arranging the sum in a numerical sequence from large to small, wherein the sequence is a temporary supporting and unloading sequence, and the self-weight load of the structure is transferred to a permanent support or the structure per se most quickly according to the unloading sequence.
In this embodiment, more preferably, the step S5 includes:
(1) setting the ith temporary support single unloading amount as
Figure 395413DEST_PATH_IMAGE067
Then, a temporary support unload vector is established by equation (11):
Figure 624138DEST_PATH_IMAGE068
formula (11);
(2) after the ith temporary support is unloaded, each temporary support just reaches the maximum allowable value, n analytic solutions can be calculated, and the formula (12):
Figure 200612DEST_PATH_IMAGE069
formula (12);
then:
Figure 64663DEST_PATH_IMAGE070
it is thus possible to calculate:
Figure 488822DEST_PATH_IMAGE071
n numbers are obtained by solving
Figure 373602DEST_PATH_IMAGE072
Is given as
Figure 686640DEST_PATH_IMAGE073
So that the minimum value is used as the ith temporary support unloading amount
Figure 619961DEST_PATH_IMAGE072
Expressed as formula (13):
Figure 85578DEST_PATH_IMAGE074
formula (13)
Namely, it is
Figure 688728DEST_PATH_IMAGE075
The calculated temporary support unloading amount
Figure 239796DEST_PATH_IMAGE072
And unload control value
Figure 711228DEST_PATH_IMAGE076
Comparing, and when a certain temporary support unloading amount
Figure 280619DEST_PATH_IMAGE072
Exceeding the unload control value
Figure 569517DEST_PATH_IMAGE076
The actual unloading amount of the temporary support is determined as the unloading control value of the temporary support
Figure 358613DEST_PATH_IMAGE076
The temporary support unloading sequence and the single unloading amount can be accurately determined through the steps. In this embodiment, more preferably, in order to ensure safer construction, in the actual construction process, the selection of the support reaction force and the single unloading amount may be reduced according to the actual engineering, that is, the actual unloading amount of the temporary support is obtained by the temporary support unloading sequence and the unloading amount determining method, and then 80% of the value of the actual unloading amount is selected for the actual engineering application.
The above examples are preferred embodiments of the present invention, but the present invention is not limited to the above examples. The above-mentioned embodiments only express several embodiments of the present invention, and the description thereof is more specific and detailed, but not construed as limiting the scope of the invention. It should be noted that, for a person skilled in the art, several variations and modifications can be made without departing from the inventive concept, which falls within the scope of the present invention. Therefore, the protection scope of the present patent shall be subject to the appended claims.

Claims (5)

1. A method for determining unloading sequence and unloading amount of temporary supports is characterized in that the number of the temporary supports is assumed to be n, and the method comprises the following steps:
step S1, unloading the temporary supports one by using finite element analysis software, unloading 1 unit each time, calculating the variation of the reaction force of the rest temporary supports caused by unloading the temporary supports in sequence, and establishing a temporary support unloading influence matrix according to the calculation result
Figure 459687DEST_PATH_IMAGE001
Figure 947825DEST_PATH_IMAGE002
Formula (1);
step S2, determining the maximum allowable support counterforce and the maximum allowable single unloading amount of the temporary support by combining finite element calculation, relevant specifications, unloading equipment specifications and actual conditions of a construction site, calculating the corresponding unloading amount according to the maximum allowable support counterforce of the temporary support, comparing the unloading amount with the maximum allowable single unloading amount, and selecting a smaller value as an unloading control value;
step S3, establishing a temporary supporting and unloading sequence determination principle: the maximum allowable support counterforce and the maximum allowable single unloading amount in the unloading process do not exceed the unloading control value; the temporary support counter force changes uniformly in the unloading process, and sudden changes are reduced;
step S4, preparing an unloading order determination method: arranging the sum of the reaction variation of all other supports corresponding to each temporary support after unloading in a descending order, wherein the order is the temporary support unloading order, and after unloading the temporary supports according to the order, the self-weight load of the structure is transferred to the permanent support or the structure per se most quickly;
step S5, determining the single unload amount: after the temporary support is unloaded, all temporary support counter forces do not exceed the unloading control value, when the unloading amount of a certain temporary support exceeds the unloading control value, the actual unloading amount of the temporary support is the unloading control value, and n is an integer greater than 2.
2. The temporary support unloading sequence and unloading amount determining method according to claim 1, wherein the temporary support unloading influence matrix in step S1
Figure 240003DEST_PATH_IMAGE001
The establishment method comprises the following steps:
firstly, establishing a structure finite element model to calculate related parameters:
firstly, a structure main body and a temporary support model are established, a simulation working condition is established according to the construction process, the support counter force of each temporary support before unloading is obtained,
Figure 16330DEST_PATH_IMAGE003
representing the support reaction force of the ith temporary support before unloading, and establishing a support reaction force vector of all temporary supports through a formula (2)
Figure 110187DEST_PATH_IMAGE004
Figure 346390DEST_PATH_IMAGE005
Formula (2);
secondly, establishing a matrix of influence of unloading of the single temporary support on other temporary supports according to the finite element model
Figure 892909DEST_PATH_IMAGE001
: reducing 1 unit length from the first support, calculating the support reaction variation of other temporary supports after the temporary support is unloaded by a finite element model,
Figure 4085DEST_PATH_IMAGE006
the 1 st temporary supporting and unloading unit is represented, and the ith temporary supporting reaction force variation is represented;
Figure 952449DEST_PATH_IMAGE007
representing the ith temporary support unloading by 1 unit, and the jth temporary support reaction force variation (i, j =1,2,3 … … n); 1 unit of temporary supporting and unloading is marked as-1, the temporary supporting counter force is increased to be plus, and the counter force is reduced to be-;
sequentially calculating influence data of reaction variation of all temporary supports on other temporary supports to obtain temporary support unloading influence matrix
Figure 356623DEST_PATH_IMAGE001
3. The temporary support unloading sequence and unloading amount determining method according to claim 1, wherein the unloading control value determining method in step S2 includes:
determining maximum allowable support counter force of each temporary support by combining finite element calculation and relevant specifications
Figure 390438DEST_PATH_IMAGE008
(i =1,2,3 … n), and then the maximum allowable support reaction force direction is established by the formula (3)Measurement of
Figure 39726DEST_PATH_IMAGE009
Figure 842596DEST_PATH_IMAGE010
Formula (3);
calculating the unloading value of each temporary support in the state according to the determined maximum allowable support counter force by adopting finite element calculation
Figure 104424DEST_PATH_IMAGE011
Determining the maximum allowable single unloading amount of each temporary support by combining the specification of unloading equipment and actual conditions of a construction site
Figure 625536DEST_PATH_IMAGE012
(i=1,2,3…n);
Will be provided with
Figure 812934DEST_PATH_IMAGE012
And
Figure 532629DEST_PATH_IMAGE013
and comparing, and selecting a smaller value as a temporary support unloading control value:
Figure 622813DEST_PATH_IMAGE014
then, a temporary support unloading control value vector is established through a formula (4)
Figure 335948DEST_PATH_IMAGE015
:
Figure 733562DEST_PATH_IMAGE016
Equation (4).
4. The temporary support unloading sequence and unloading amount determining method of claim 1, wherein the step S4 includes:
assuming that the 1 st temporary support is unloaded by 1 unit, an unloading vector is established through a formula (5):
Figure 743981DEST_PATH_IMAGE018
formula (5);
assuming that the 2 nd temporary support is unloaded by 1 unit, an unloading vector is established by the formula (6):
Figure 37691DEST_PATH_IMAGE020
formula (6);
and (3) if the ith temporary support is unloaded by 1 unit, establishing an unloading vector through a formula (7):
Figure 254433DEST_PATH_IMAGE022
formula (7);
after the 1 st temporary support is unloaded by 1 unit, all temporary support reaction force change vectors are established through a formula (8):
Figure 518055DEST_PATH_IMAGE024
Figure 946762DEST_PATH_IMAGE026
=
Figure 270427DEST_PATH_IMAGE028
formula (8);
at this time, after the 1 st temporary support is unloaded, the sum of the variation of all temporary support reaction forces is equal to
Figure 743173DEST_PATH_IMAGE030
Figure 76065DEST_PATH_IMAGE030
Calculated by equation (9):
Figure 562541DEST_PATH_IMAGE032
formula (9);
after the ith temporary support is unloaded, the sum of the variation of all temporary support counter forces is equal to
Figure 385004DEST_PATH_IMAGE034
Figure 291518DEST_PATH_IMAGE034
Calculated by equation (10):
Figure 428101DEST_PATH_IMAGE036
equation (10);
according to the formula (10), the sum of the variable quantities of all temporary support reaction forces after the i-th temporary support is unloaded is an influence matrix
Figure 769084DEST_PATH_IMAGE038
The sum of the ith column;
according to an influence matrix
Figure 965710DEST_PATH_IMAGE038
And calculating the sum of each column, then arranging the sum in the numerical sequence from large to small, wherein the sequence is a temporary support unloading sequence, and after the temporary support is unloaded according to the sequence, the self-weight load of the structure is transferred to a permanent support or the structure per se at the fastest speed.
5. The temporary support unloading sequence and unloading amount determining method of claim 1, wherein the step S5 includes:
(1) setting the ith temporary support single unloading amount as
Figure 955925DEST_PATH_IMAGE040
Then a temporary support unload vector is established by equation (11):
Figure 630620DEST_PATH_IMAGE042
formula (11);
(2) after the ith temporary support is unloaded, each temporary support just reaches the maximum allowable value, n analytic solutions can be calculated, and the formula (12):
Figure 91688DEST_PATH_IMAGE044
formula (12);
then:
Figure 459216DEST_PATH_IMAGE046
it is thus possible to calculate:
Figure 871480DEST_PATH_IMAGE048
n numbers are obtained by solving
Figure 349866DEST_PATH_IMAGE050
Is given as
Figure 931020DEST_PATH_IMAGE052
So that the minimum value is used as the ith temporary support unloading amount
Figure 203869DEST_PATH_IMAGE050
Written as formula (13):
Figure 371939DEST_PATH_IMAGE054
formula (13);
the calculated temporary support unloading amount
Figure 388437DEST_PATH_IMAGE050
And unload control value
Figure 27359DEST_PATH_IMAGE056
Comparing, when a certain temporary support unloading amount
Figure 471110DEST_PATH_IMAGE050
Exceeding the unload control value
Figure 123546DEST_PATH_IMAGE056
The actual unloading amount of the temporary support is determined as the unloading control value of the temporary support
Figure 943735DEST_PATH_IMAGE056
CN202210925259.1A 2022-08-03 2022-08-03 Temporary support unloading sequence and unloading amount determining method Active CN114997030B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210925259.1A CN114997030B (en) 2022-08-03 2022-08-03 Temporary support unloading sequence and unloading amount determining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210925259.1A CN114997030B (en) 2022-08-03 2022-08-03 Temporary support unloading sequence and unloading amount determining method

Publications (2)

Publication Number Publication Date
CN114997030A true CN114997030A (en) 2022-09-02
CN114997030B CN114997030B (en) 2022-10-21

Family

ID=83021157

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210925259.1A Active CN114997030B (en) 2022-08-03 2022-08-03 Temporary support unloading sequence and unloading amount determining method

Country Status (1)

Country Link
CN (1) CN114997030B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116127554A (en) * 2022-11-22 2023-05-16 中交建筑集团有限公司 Intelligent unloading construction method and system for large-span structure capable of reducing unloading mutation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2581511A1 (en) * 1985-05-10 1986-11-14 Poitou Mecanique Chaudronnerie Method and device for dismembering an animal carcass
CN102644386A (en) * 2012-04-28 2012-08-22 上海建工集团股份有限公司 Unloading control method for steel structure temporary bracing
CN108681343A (en) * 2018-04-19 2018-10-19 浙江精工钢结构集团有限公司 A kind of sandbox unloading automatic control system and construction method
US20200290270A1 (en) * 2019-03-15 2020-09-17 Ricoh Company, Ltd. Jettable Temporary Binders to Create Removable Support Materials
CN112482579A (en) * 2020-12-14 2021-03-12 北京市机械施工集团有限公司 Bidirectional large-rigidity large-span conversion truss system and unloading method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2581511A1 (en) * 1985-05-10 1986-11-14 Poitou Mecanique Chaudronnerie Method and device for dismembering an animal carcass
CN102644386A (en) * 2012-04-28 2012-08-22 上海建工集团股份有限公司 Unloading control method for steel structure temporary bracing
CN108681343A (en) * 2018-04-19 2018-10-19 浙江精工钢结构集团有限公司 A kind of sandbox unloading automatic control system and construction method
US20200290270A1 (en) * 2019-03-15 2020-09-17 Ricoh Company, Ltd. Jettable Temporary Binders to Create Removable Support Materials
CN112482579A (en) * 2020-12-14 2021-03-12 北京市机械施工集团有限公司 Bidirectional large-rigidity large-span conversion truss system and unloading method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JIANHUA SHAO 等: "Research on the Unloading Process of Long-Span Steel Roof and the Design of Temporary Bracing Structure", 《ADVANCED MATERIALS RESEARCH VOLS 163-167 (2011)》 *
叶芳芳 等: "重庆大剧院大悬挑结构卸载分析", 《建筑科学与工程学报》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116127554A (en) * 2022-11-22 2023-05-16 中交建筑集团有限公司 Intelligent unloading construction method and system for large-span structure capable of reducing unloading mutation
CN116127554B (en) * 2022-11-22 2023-08-08 中交建筑集团有限公司 Intelligent unloading construction method and system for large-span structure capable of reducing unloading mutation

Also Published As

Publication number Publication date
CN114997030B (en) 2022-10-21

Similar Documents

Publication Publication Date Title
CN114997030B (en) Temporary support unloading sequence and unloading amount determining method
De Donato et al. Mathematical programming methods for the inelastic analysis of reinforced concrete frames allowing for limited rotation capacity
CN105787183A (en) Synthesis algorithm for determining reasonable finished-bridge cable force of cable-stayed bridge
CN110932281B (en) Multi-section cooperative correction method and system based on quasi-steady-state sensitivity of power grid
CN107142835A (en) The ribbed arch bridge rib-lifting section point rib installation control method of stress-free state method
CN106934179B (en) Method for processing data of main node tensile test of angle steel of power transmission tower
CN107895083A (en) A kind of cable-supported bridge based on the long influence matrix of rope adjusts Suo Fangfa
TWI737497B (en) Quality designing method and electrical device
CN109977442A (en) A kind of method for numerical simulation of super thick slab multi- pass rolling technique
CN109193807A (en) A kind of Economic Dispatch method and system
CN101763450B (en) Titanium alloy component quantifying design method
KR100773395B1 (en) Preflex composite girder and its manufacturing method
CN109610339B (en) Assembled type unbalanced load preventing pushing device for concrete continuous rigid frame bridge and construction method thereof
CN111092440A (en) Method and system for coordinated control of primary frequency modulation and AGC of hydroelectric generating set
CN101767287A (en) Part processing deformation control method based on blank predeformation
CN111272326B (en) Method for solving single-end under-ice-cover unbalanced tension of continuous overhead transmission line
CN101397773A (en) Method for large-range adjusting stay cable force or suspender force
CN112380750A (en) Stress coupling simulation method for continuous heat treatment and machining
CN109241560B (en) Treatment method of steel structure fiber model
CN110220784B (en) Method and system for representing martensite phase transformation strength increment of transformation induced plasticity steel
CN112685861A (en) Lightweight design optimization method suitable for building framework
CN113361071B (en) Method for calculating ultimate strength of thin-wall beam under bending and torsion combined load effect
Farshi et al. Buckling analysis of structural steel frames with inelastic effects according to codes
CN118461555A (en) Ocean platform transformation method capable of adjusting rod stress
CN114861254B (en) Calculation method of bending stiffness of steel tube steel fiber reinforced concrete structure for bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant