CN114961214A CN202210618748.2A CN202210618748A CN114961214A CN 114961214 A CN114961214 A CN 114961214A CN 202210618748 A CN202210618748 A CN 202210618748A CN 114961214 A CN114961214 A CN 114961214A
Authority
CN
China
Prior art keywords
guide rail
alloy steel
support
aluminum alloy
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210618748.2A
Other languages
Chinese (zh)
Inventor
黎泽盛
黎鹏
林维钧
叶浩康
黎龙
黎战
林天生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Jingtong Kelide Engineering Technology Co ltd
Original Assignee
Guangxi Jingtong Kelide Engineering Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Jingtong Kelide Engineering Technology Co ltd filed Critical Guangxi Jingtong Kelide Engineering Technology Co ltd
Priority to CN202210618748.2A priority Critical patent/CN114961214A/en
Publication of CN114961214A publication Critical patent/CN114961214A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/001Safety or protective measures against falling down relating to scaffoldings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/16Struts or stiffening rods, e.g. diagonal rods
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)

Abstract

The invention relates to the technical field of building construction protection, and discloses an aluminum alloy steel combined attached lifting scaffold which comprises a scaffold system, an attached guide unloading and anti-falling system, a power lifting system and a construction protection system, wherein the scaffold system comprises a guide rail, a vertical rod, a walkway plate, a net frame, a triangular support and a Z-shaped support, the guide rail, the vertical rod, the walkway plate, the net frame, the triangular support and the Z-shaped support are connected through bolts, and the attached guide unloading and anti-falling system comprises an attached wall support, an adjustable unloading support, an anti-falling star wheel, a guide wheel set and a guide rail crosspiece. This aluminium alloy steel combination inserted lift scaffold can avoid the protection network and walk the too big easy high altitude of taking place of gap between the guidance tape and fall the thing, and support body intensity promotes greatly, eliminates current steel and climbs the potential safety hazard that the frame brought because of walking the guidance tape corrosion to reduce current steel and climb the environmental pollution and the manpower resources waste that the frame too much caused because of the accessory that needs the spraying.

Description

Aluminum alloy steel combined attached lifting scaffold
Technical Field
The invention relates to the technical field of building construction protection, in particular to an aluminum alloy steel combined attached lifting scaffold.
Background
The attached lifting scaffold (climbing frame) is erected at a certain height and attached to an engineering structure, can climb or descend along with the engineering structure layer by depending on self lifting equipment and devices, has an anti-overturning and anti-falling device, changes suspended operation into frame body internal operation, and has the characteristics of remarkable low carbon property, high technological content, economy, safety, convenience and the like.
However, with the increase of the use amount of the climbing frame, the problems of environmental pollution, manpower resource waste and the like are gradually highlighted due to the fact that the existing steel climbing frame is heavy in weight, inconvenient to construct, high-altitude falling risk caused by overlarge gaps and the fact that the steel climbing frame needs to be painted and renovated every use period.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides an aluminum alloy steel combined attached lifting scaffold, which has the advantages of light weight, high strength, one-step forming, difficulty in corrosion, high safety, convenience in transportation, construction time saving and the like, and solves the problems of large self weight, inconvenience in construction, low safety, environmental pollution and manpower resource waste of the existing steel scaffold.
(II) technical scheme
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides an aluminum alloy steel combination attached lift scaffold, includes frame system, adheres to direction off-load and anti-falling system, power lift system and construction protection system, frame system includes guide rail, pole setting, walks guidance tape, net frame, triangular supports and Z word and props, guide rail, pole setting, walk guidance tape, net frame, triangular supports and all through bolted connection between the Z word props, it includes attaches wall support, adjustable off-load ejector retainer, guide pulley group, prevents weighing down star wheel and guide rail crosspiece to adhere to direction off-load and anti-falling system, power lift system includes the hoisting point truss, hangs down the point truss, attaches the wall hoisting point, hangs down ring chain electric block and intelligence control system, construction protection system is including punching a hole the flute net piece, turning over board and interior ram.
Preferably, the guide rail is arranged on one side of the vertical rod, the wall attaching support is arranged on the other side of the guide rail, and the frame body is lifted in a remote control mode, so that the bottom wall attaching support is eight meters to one meter away from the zero point of the first layer of walkway plate.
Preferably, one side of attaching the wall support is provided with the floor of having built, one side of having built the floor is provided with promotes and hangs the seat, and the floor of having built quantity has three, and three floor of having built all is provided with attaches the wall support, promotes to hang the seat and installs by the wall support is attached to the second floor.
Preferably, one side of guide rail is provided with interim drawknot, the other end of interim drawknot and the top fixed mounting of having built the floor, the top of guide rail one side is provided with the floor of waiting to build, and interim drawknot is the rigidity, and the support body promotes the back that targets in place, and the support body is fixed to interim drawknot, prevents heavy wind blowing, and the interim drawknot need be demolishd when the support body is promoted.
Preferably, the guide rail is provided with a horizontal supporting truss, and the top end and the bottom end of the guide rail are respectively provided with a top cross rod and a pocket bottom cross rod, so that the strength of the frame body is improved.
Preferably, one side of the inner cantilever plate is fixedly provided with a turning plate connecting piece, one side of the turning plate, which is far away from the built floor, is rotatably connected with the top of the turning plate connecting piece, the walkway plate is fixedly provided with a net frame, the punched corrugated net piece is fixedly installed with the net frame through a pin, the turning plate is packed up, lifting obstacles are eliminated, an anti-falling component is checked, and the phenomenon that objects fall from high altitude due to overlarge gaps between the protective net and the walkway plate is avoided.
Compared with the prior art, the invention provides an aluminum alloy steel combined attached lifting scaffold, which has the following beneficial effects:
1. this aluminium alloy steel combination inserted lift scaffold can avoid the protection network and walk the too big easy high altitude of taking place of gap between the guidance tape and fall the thing, and support body intensity promotes greatly, eliminates current steel and climbs the potential safety hazard that the frame brought because of walking the guidance tape corrosion to reduce current steel and climb the environmental pollution and the manpower resources waste that the frame too much caused because of the accessory that needs the spraying.
2. This aluminum alloy steel combination inserted lift scaffold, support body one shot forming, the manufacturing procedure that production needs is few and light in weight, solves current steel and climbs the problem that the frame was constructed because of weight is too big inconvenience, reduces the support body and uses with the construction because of the burden of dead weight overweight to newly-built building main structure, convenient transportation, saves the engineering time.
Drawings
FIG. 1 is a schematic view of a main frame structure according to the present invention;
FIG. 2 is a schematic axial view of the frame of the present invention;
FIG. 3 is a schematic view of the fall arrest system of the present invention;
FIG. 4 is a schematic view of the wall attachment support of the present invention;
FIG. 5 is an enlarged view of the triangular brace mounting structure of the present invention;
FIG. 6 is an enlarged view of the Z-shaped stay mounting structure of the present invention;
FIG. 7 is an enlarged view of the pocket bottom mounting structure of the present invention;
FIG. 8 is a schematic view of the protection system of the present invention;
FIG. 9 is an enlarged view of the lower suspension point structure of the present invention;
FIG. 10 is an enlarged view of the upper suspension point structure of the present invention;
FIG. 11 is a schematic view of the circular guide rail structure of the present invention;
figure 12 is a cross-sectional view of the circular track configuration of the present invention.
Wherein: 1. a guide rail; 2. erecting a rod; 3. a walkway plate; 4. a triangular support; 5. a Z-shaped support; 6. a wall-attached support; 7. an adjustable unloading jack; 8. a guide wheel group; 9. anti-dropping star wheels; 10. a rail crosspiece; 11. an upper hoisting point truss; 12. a lower hoisting point truss; 13. hanging the electric chain hoist upside down; 14. punching a corrugated net sheet; 15. turning over a plate; 16. an inner cantilever plate; 17. a built floor; 18. lifting the hanging seat; 19. temporary pulling knots; 20. a horizontal lattice support; 21. a top cross bar; 22. a bottom cross rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-12, an aluminum alloy steel combined attached lifting scaffold comprises a frame system, an attached guiding unloading and anti-falling system, a power lifting system and a construction protection system, which can avoid the phenomenon that a gap between a protective screen and a walkway plate is too large and the possibility of falling objects from high altitude is high, greatly improve the strength of the frame, eliminate the potential safety hazard caused by corrosion of the walkway plate of the existing steel climbing frame, and reduce the environmental pollution and the waste of manpower resources caused by excessive parts needing to be sprayed on the existing steel climbing frame, wherein the frame system comprises a guide rail 1, a vertical rod 2, a walkway plate 3, a net frame, a triangular support 4 and a Z-shaped support 5, the guide rail 1, the vertical rod 2, the walkway plate 3, the net frame, the triangular support 4 and the Z-shaped support 5 are all connected through bolts, the attached guiding unloading and anti-falling system comprises an attached wall support 6, an adjustable unloading support 7, a guide wheel group 8, an anti-falling star wheel 9 and a guide rail crosspiece 10, the guide rail 1 is arranged on one side of the upright rod 2, the wall-attached support 6 is arranged on the other side of the guide rail 1, one side of the wall-attached support 6 is provided with a built floor 17, one side of the built floor 17 is provided with a lifting hanging seat 18, the number of the built floors 17 is three, the three built floors 17 are provided with the wall-attached support 6, the lifting hanging seats 18 are arranged beside the wall-attached support 6 on the second floor, one side of the guide rail 1 is provided with a temporary pull knot 19, the other end of the temporary pull knot 19 is fixedly arranged with the top of the built floor 17, the temporary pull knot 19 is rigid, after the frame body is lifted in place, the temporary pull knot 19 fixes the frame body, the large wind blow is prevented, the temporary pull knot 19 needs to be removed when the frame body is lifted, the top of one side of the guide rail 1 is provided with the floor to be built, the power lifting system comprises an upper lifting point truss 11, a lower lifting point truss 12, a wall-attached lifting point, an inverted ring chain electric hoist 13 and an intelligent control system, the guide rail 1 is provided with a horizontal support truss 20, guide rail 1's top and bottom are provided with horizontal pole 21 at the bottom of top horizontal pole and the pocket respectively, construction protection system is including punching a hole flute net piece 14, turn over board 15 and interior board 16 of choosing, one side fixed mounting who chooses board 16 in has the board connecting piece that turns over, turn over board 15 and keep away from one side of building floor 17 and turn over the top rotation of board connecting piece and be connected, it is provided with the reel to walk to fix on the board 3, the flute net piece 14 that punches a hole passes through pin and reel fixed mounting, support body one shot forming, the manufacturing process of production needs is few and light in weight, solve current steel and climb the problem of the frame because of weight is too big inconvenient construction, reduce the support body because of the burden of dead weight overweight to newly-built building main structure, convenient transportation and construction use, save the engineering time.
The intelligent control system is electrified to prepare and an electric hoist is pre-tightened to prepare, the turning plate is packed up and lifting obstacles are eliminated, an anti-falling component is checked, a lifting frame body is remotely controlled, a bottom wall-attached support is enabled to be eight meters to one meter away from a zero point of a first layer of walkway plate, an unloading supporting device always abuts against a guide rail to realize anti-falling in the lifting process, an anti-falling star wheel, a swinging block and the unloading supporting device realize double anti-falling simultaneously, the bottom wall-attached support is dismantled, the turning plate is closed after being continuously lifted in place, the guide rail is tightly supported by an adjustable unloading supporting device, the bottom wall-attached support is arranged on the uppermost layer, the wall-attached lifting point is circularly arranged to reach the height of one floor, the chain node of the electric hoist is reversely linked to the wall-attached lifting point to be fixed, the chain is enabled to be in a chain loosening state, the lifting is finished, the wall-attached lifting scaffold is gradually climbed to the top sealing along with the increase of the floor, and the aluminum alloy steel combined attached lifting scaffold has the characteristics of light weight, high strength, few processing procedures required by production and one-step forming, avoid the protection network and walk the too big problem that easily takes place the object that falls from high place in gap between the guidance tape, solve current steel and climb the frame because of weight is too big, the problem of inconvenient construction, reduce the support body because of the dead weight overweight to newly-built building main structure's burden, promote support body intensity, eliminate the potential safety hazard that current steel climbs the frame and brings because of walking the guidance tape corrosion, reduce the environmental pollution and the manpower resources waste that current steel climbs the frame and cause because of the accessory of needs spraying is too much.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides an attached lift scaffold of aluminum alloy steel combination, includes framework system, adheres to direction off-load and anti-falling system, power lift system and construction protection system, its characterized in that: the frame system includes that guide rail (1), pole setting (2), guidance tape (3), screen frame, three corner brace (4) and Z word prop (5), all through bolted connection between guide rail (1), pole setting (2), guidance tape (3), screen frame, three corner brace (4) and the Z word prop (5), it includes attaching wall support (6), adjustable off-load roof-supporting ware (7), guide pulley group (8), prevents weighing star wheel (9) and guide rail crosspiece (10) to adhere to direction off-load and anti-falling system, power hoisting system includes hoisting point truss (11), lower hoisting point truss (12), attaches wall hoisting point, inverted link chain electric block (13) and intelligence control system, construction protection system is including flute net piece (14), turns over board (15) and interior ram (16) that punches a hole.
2. The aluminum alloy steel combined attached lifting scaffold as claimed in claim 1, wherein: the guide rail (1) is arranged on one side of the vertical rod (2), and the wall-attached support (6) is arranged on the other side of the guide rail (1).
3. The aluminum alloy steel combined attached lifting scaffold as claimed in claim 1, wherein: one side of the wall-attached support (6) is provided with a built floor (17), and one side of the built floor (17) is provided with a lifting hanging seat (18).
4. The aluminum alloy steel combined attached lifting scaffold as claimed in claim 3, wherein: one side of the guide rail (1) is provided with a temporary tie (19), the other end of the temporary tie (19) is fixedly installed with the top of the built floor (17), and the top of one side of the guide rail (1) is provided with a floor to be built.
5. The aluminum alloy steel combined attached lifting scaffold as claimed in claim 1, wherein: the guide rail (1) is provided with a horizontal supporting truss (20), and the top end and the bottom end of the guide rail (1) are respectively provided with a top cross rod (21) and a pocket bottom cross rod (22).
6. The aluminum alloy steel combined attached lifting scaffold as claimed in claim 3, wherein: a turning plate connecting piece is fixedly installed on one side of the inner cantilever plate (16), one side, far away from the built floor (17), of the turning plate (15) is rotatably connected with the top of the turning plate connecting piece, a net frame is fixedly arranged on the walkway plate (3), and the punching corrugated net piece (14) is fixedly installed with the net frame through a pin.
CN202210618748.2A 2022-06-01 2022-06-01 Aluminum alloy steel combined attached lifting scaffold Pending CN114961214A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210618748.2A CN114961214A (en) 2022-06-01 2022-06-01 Aluminum alloy steel combined attached lifting scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210618748.2A CN114961214A (en) 2022-06-01 2022-06-01 Aluminum alloy steel combined attached lifting scaffold

Publications (1)

Publication Number Publication Date
CN114961214A true CN114961214A (en) 2022-08-30

Family

ID=82970715

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210618748.2A Pending CN114961214A (en) 2022-06-01 2022-06-01 Aluminum alloy steel combined attached lifting scaffold

Country Status (1)

Country Link
CN (1) CN114961214A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09144327A (en) * 1995-11-28 1997-06-03 Takenaka Komuten Co Ltd Outside protection system in construction of multistoried building
CN106481061A (en) * 2016-11-28 2017-03-08 湖南玖安模架工程技术有限公司 Climbing frame
CN108979118A (en) * 2017-06-05 2018-12-11 深圳市特辰科技股份有限公司 A kind of rotary-type positioning anti-fall device
CN208518310U (en) * 2018-07-10 2019-02-19 宁夏天鹰同创建筑技术有限公司 All steel type attachment type raise scaffold
CN210086788U (en) * 2019-05-17 2020-02-18 山东新活新材料科技有限公司 Anti-falling mechanism of aluminum alloy climbing frame
CN113137051A (en) * 2021-04-14 2021-07-20 中建铝新材料成都有限公司 Aluminum alloy climbing frame

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09144327A (en) * 1995-11-28 1997-06-03 Takenaka Komuten Co Ltd Outside protection system in construction of multistoried building
CN106481061A (en) * 2016-11-28 2017-03-08 湖南玖安模架工程技术有限公司 Climbing frame
CN108979118A (en) * 2017-06-05 2018-12-11 深圳市特辰科技股份有限公司 A kind of rotary-type positioning anti-fall device
CN208518310U (en) * 2018-07-10 2019-02-19 宁夏天鹰同创建筑技术有限公司 All steel type attachment type raise scaffold
CN210086788U (en) * 2019-05-17 2020-02-18 山东新活新材料科技有限公司 Anti-falling mechanism of aluminum alloy climbing frame
CN113137051A (en) * 2021-04-14 2021-07-20 中建铝新材料成都有限公司 Aluminum alloy climbing frame

Similar Documents

Publication Publication Date Title
CN100590277C (en) High-altitude bridge type cantilever scaffold
CN212614037U (en) Device for preventing small animals from climbing on electric pole
CN111395728B (en) Aluminum alloy attached lifting scaffold
CN220376298U (en) Hanging basket lifting device
CN214195484U (en) All-steel attached lifting scaffold
CN212836630U (en) All-steel integrated operation scaffold
CN111608382A (en) Temporary attachment device for climbing frame in free area
CN209369277U (en) A kind of lighting roof Construction of Steel Structure mounting platform
CN210002838U (en) Device for mounting steel structure vestibule color plate
CN114961214A (en) Aluminum alloy steel combined attached lifting scaffold
CN209145256U (en) The dedicated climbing frame of assembled architecture
CN206487129U (en) Safety hanging cradle for industrial premises Construction of Steel Structure
CN216109994U (en) Communication tower with lifting system
CN210888040U (en) Concrete building template for building
CN105152052A (en) Glass curtain wall component lifting device and glass curtain wall component installing method
CN214424055U (en) Attached lifting scaffold platform of unloading
CN208525688U (en) A kind of steel I-beam spraying safety belt suspension protective device
CN103977512A (en) Building climbing rescue vehicle
CN202899720U (en) Steel pole provided with foot treadles and used for high-tension transmission line iron tower
CN2276046Y (en) Divided multistage automatic climbing external scaffold
CN220954529U (en) Scaffold for building engineering
CN216109635U (en) Climbing frame lifting system
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN217418120U (en) Novel practical tower crane passageway of going to people device
CN216406098U (en) Movable construction platform for workshop construction of factory building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination